Basketball Court Estimate

This document provides an estimation of costs for constructing a basketball court. It includes three main items: 1) Providing and placing reinforced concrete (RCC) for structures like the roof, beams, columns, foundations, etc. Totaling Rs. 4,488,600 2) Providing and placing steel reinforcement including cutting, bending and binding, totaling Rs. 2,709,604 3) Cement concrete flooring 40mm thick, totaling Rs. 2,179,350. The gross total estimated cost is Rs. 13,379,489 or 13.38 lacs including contingencies, labor welfare costs, and a 20% addition to the tender rate.

Uploaded by

Lokesh Mundra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
3K views4 pages

Basketball Court Estimate

This document provides an estimation of costs for constructing a basketball court. It includes three main items: 1) Providing and placing reinforced concrete (RCC) for structures like the roof, beams, columns, foundations, etc. Totaling Rs. 4,488,600 2) Providing and placing steel reinforcement including cutting, bending and binding, totaling Rs. 2,709,604 3) Cement concrete flooring 40mm thick, totaling Rs. 2,179,350. The gross total estimated cost is Rs. 13,379,489 or 13.38 lacs including contingencies, labor welfare costs, and a 20% addition to the tender rate.

Uploaded by

Lokesh Mundra
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Estimation of BasketBall court

S. No. Item

Nos.

D/H

Qty

Unit

Rate

Amount

425 Providing and placing in position RCC for roof,


beams, columns column footing lintels chhajjas,
balcony, stairs etc, excluding cost of reinforcement
but including centring, shuttering, proping,
finishing &curing etc.complete. 1:2:4

904b Providing and placing in position tested steel for


R.C.C. work including cutting, bending, binding etc.
as per drawings and placing in position complete
up to floor two level including cost of binding wire
and all wastage etc. complete.
reinforcement

29

15

130.5

78.5

29

15

0.15

130.5 cum.

0.5 5122.125 Kg

4488.6

585762.3

52.9

270960.4

250.5

217935.0

1220 Cement concrete flooring 1:2:4 (1cement, 2sand,


4graded stone aggregate, 20mm nominal size) laid
in one layer and finished with floating coat of neat
cement. 40 mm thick finishing in floor
1

870
Total =

20 % above tender rate =


1 % for labour welfare =
3.5 % for contingencies =
Gross Total =

1074657.7

214931.5
10746.6
37613.0
1337948.9
13.38 lacs