Allaboutconstruction - Blogspot.qa-Construction Sequence of MEP Works in Buildings

The document outlines the typical construction sequence of MEP (mechanical, electrical, and plumbing) works in buildings. It discusses 4 main stages: 1) MEP first fix of all concealed items and pipe sleeves, 2) MEP second fix stage 1 of high-level works above false ceilings, 3) MEP second fix stage 2 for clearances and connections below false ceilings, and 4) MEP final fix of air terminals, wiring, and other fixtures. External MEP works like connections to utility lines and external piping are also addressed. Coordination between trades is emphasized, especially during false ceiling installation.

Uploaded by

Humaid Shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views1 page

Allaboutconstruction - Blogspot.qa-Construction Sequence of MEP Works in Buildings

The document outlines the typical construction sequence of MEP (mechanical, electrical, and plumbing) works in buildings. It discusses 4 main stages: 1) MEP first fix of all concealed items and pipe sleeves, 2) MEP second fix stage 1 of high-level works above false ceilings, 3) MEP second fix stage 2 for clearances and connections below false ceilings, and 4) MEP final fix of air terminals, wiring, and other fixtures. External MEP works like connections to utility lines and external piping are also addressed. Coordination between trades is emphasized, especially during false ceiling installation.

Uploaded by

Humaid Shaikh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

allaboutconstruction.blogspot.

qa
http://allaboutconstruction.blogspot.qa/2013/09/construction-sequence-of-mep-works-in.html

Construction Sequence of MEP works in Buildings


Grouping of MEP Fixes like PVC Electrical conduits in Slabs :
1. MEP 1st Fix - All Concealed Items/Pipe Sleeves in Verticals/Horizontals (Column/Slab)
2. MEP 2nd Fix - Stage 1: High Level MEP Works at False Ceiling
i) Fixing supports, installation of Firefighting, Chilled Water piping, drainage pipes, water supply(hot & cold), rain
water, cable ladders, G.I Conduiting, AC ducting
ii) Pressure tests and insulations
iii) Installation of FCUs, water heaters
(Note: False Ceiling people will fix runners after the Stage 1 of MEP 2nd Fix)
3. MEP 2nd Fix - Stage 2: Clearance for False Ceiling People
i) Sprinkler droppers, AC duct droppers, flexible cable for light fixtures, fire stopping and identification works etc.
(Note: False Ceiling people will close ceiling tiles and MEP people will connect their diffusers in position on the
ceiling tiles - too much coordination is required at this stage)
MEP 2nd Fix: Other Areas
Installation of all equipments like AHUs(Floor mounted), all pumps, heat exchangers(if any), bus bars,
generators, water tanks etc.,
4. MEP Final Fix
Installation of Air terminals, sprinkler heads, wiring accessories, low current devices, CCTV, Public Address
System (PAS), Isolators, fire fighting equipments(Hydrants), Sanitaryware, DBs, SMDBs & Dressing, SMA TVs,
Structured Cabling, All Switch Points
External and other MEP works
i) Connections to Main lines of Govt. Authority, water supply, drainage, ETISALAT
ii) LV Room installations (MDBs, SMDBs, DBs)
iii) Installation of external piping, Manhole construction
iv) Installation of lightning protection, Backup System, Intercom System etc.,