Design of Slow Sand Filter Final
Design of Slow Sand Filter Final
3600
Cum / day
Since slow sand filters work for 24 hrs a day the quantity to be filter per hour
=
3600
24
150
150
0.150
1000
Sqm
2A
+
(n
1)
Where
l
=
b
=
A
=
n
=
2n
A
Therefore,
l
2
8
x
+
l =
Say =
Therefore, A =
1000
b =
b =
Say b
Length of wall
breadth of wall
Total surface area of filter bed
Nos of filter beds
But provide
8 Nos.
b
1000
2000
=
9
14.90711985
15.00
8
x
l
=
222.22222222
M
x
x
15.00
1000
15
x
8
8.3333333333
8.5
M
b
x
Niketan Consultants
Therefore,Area provided is
15.00
x
8.5
Therefore, Each bed will have Length
breadth
=
8.5
m
=
No of Beds
M
8
15
127.5
bed
Sqm
127.5
1020
>
1000 Sqm
Hence Ok
Cheak for Over loading
Let us assume
1 Filter bed is Washed at a time
Filteration capacity of each filter
=
15
150
8.5
= .2 Cum /hr
Hence Ok
The schematic lay out of slow sand filter bed be as under
Design of Filter Bed
Let filter bed be as under with over all depth of filter bed =
2.70 mt
0.40 mt Gravel
Sand Spcification
Size of sand
= 0.2- 0.3 mm
Uniformity co-eff =
= 2.0 mm 40 mm
Size of garval i
= 2.0
5 10
depth in mm
= 80
80
20
40
80 80
80
Niketan Consultants
15.00 x
8.5
127.5
Sq Mts
0.15% to 0.3 %
0.19125
Sqm
1912.5 Sqcm
=
=
1.5
1.5
1913
2868.8 Sqcmt
2868.75
4303.125 Sqcmt
4303 Cm
58.1 mm
28.6875
110 Nos.
0.785x0.05812
Spacing of Laterals=
15
55
Length of Laterals on each side =
0.273 m
Say
250mm C/C
8.5 -
0.75
3.875m
2
Which is Less Than 3.78(60x.063=3.78m)
Hence Ok
0.2
15
8.5
100
=
0.19125
Sqm
3.875
=
No. of Orifice = 0.1913
110
Diameter of Orifice d=
0.19125
100
387.5 Cm
100 x
x
100
9 Nos.
2
x
0.49 Cm
3.142
Niketan Consultants
Niketan Consultants
=
=
=
Detention provide =
3600 Cum/Day
180 Cum/Day
3
Hrs
3X
180
= 540 Cum
540
2
= 270
Cum
with average water depth in tank as 3.0 mts, Surface area of tank
270
3
= 90
Sqm
3B2
= 90 Sqm
B
=
5.48
Say
5.5 M
L = 3 x 5.50 = 16.5Mts
So, Provide 16.5 Mts X 5.5 Mts of each unit
Total Area Provided = 90.75 Sqm > 90 Sqm Ok
Total area provided = 2 (16.5 x 5.5 x 3.0) = 544.5cum > 540 Cum
Hence, OK
16.5 Mts
Unit 1
5.5 Mts
Unit 2
5.5 Mts
16.5 Mts
3600
90.75 x 2.0
19.840
Cum/Sqm/Day
<
36 Cum/Sqm/Day
Hence Ok
Overall Depth of each Unit with 3.0 mts standing water depth (SWD)
=
=
0.3 m/sec
1/2 x
0.3 m
0.05 Cum/sec
0.05
0.3 x 0.3
50 cmt
=
0.28 Mts
Say 30 cmt
Niketan Consultants
6.5 Mts
14.0 Mts
For uniform dispersal of flow of water provide perforated baffle wall in front of inlet pipe at 1.2 M away
from the wall.
0.15
= 0.333 Sqm
3
0.15
Opening below baffle wall for movement of sludge and water, provided 45
cm considering sludge deposit of 25 cm before flushed one.
Therefore opening available below for flow of water (45-25)_ 20 Cm
The baffle wall is supported over 20 x 20 Cm columns 3 Nos.
Hence length of opening available
Area of opening available
= 6.25 - (0.2x3)
=
5.65 M
5.65 x 0.2 = 1.13 Sqm.
Niketan Consultants
Niketan Consultants
49094 mm2
0.63
0.0625
0.54
Design Of interconnecting From Distribution tank(Inlet Equidistrbution Retangular Weir) For Slow sand Filters
Since Separate pipes Are Tobe Give From Distribution Tank to SSF
Dischage In each Filter=
0.00521
Cum/Sec
Assuming the Velocity of flow In the pipe as=
0.5 M/sec
Dia of pipe=
0.00521
x
4
0.5
x 3.142
0.1152
=
Provide
100
mm Dia CI Pipe
Now, Velocity in pipe
V=Q/A
V=
0.00521
0.785
X
0.1 X
0.1
0.66
=
Hence Ok
Calculation Of Head Losses in pipe:
For SSF 1,SSF 4 on either side
Length of pipe=
30 m
Hazen Willam Constant=
100
Area of Cross Section in pipe A=
3.142 X
100 X
100 =
7855 mm2
4
Wetted perimeter =
3.142
x
100
314.2
mm
=
Hydraulic Mean Radius r =
25
mm
0.025
m
=
V= Q/A=0.854XCX r.63xS0.54
Now, Accroding to Hazen Willams Formula
0.63
0.54
0.66
0.854
x
100
x
0.025
x
S
=
S
0.00498
m/m
=
Frictional Losses=
0.16434 m
Out let RL at Distribution Box=
595.03 M
inlet RL at Distribution Chamber=
594.86566 M
Niketan Consultants
100
3.142 X
100 X
100
4
Wetted perimeter =
3.142
x
100
314.2
mm
=
Hydraulic Mean Radius r =
25
mm
0.025
m
=
Now, Accroding to Hazen Willams Formula
V= Q/A=0.854XCX r.63xS0.54
M
0.854
x
100
x
=
S
0.00498
m/m
=
Frictional Losses=
0.08217 m
Out let RL at Distribution Box=
595.03 M
inlet RL at Distribution Chamber=
594.948 M
7855 mm2
0.63
0.025
0.54
Design Of interconnecting From Slow sand Filters Out let to Rure Water Sump
One of Slow Sand Filter =
8 Nos.
Qty of water to be Treated=
143.75
Cum/Hr
Qty of water to be Treated by each pipe=
17.9688 Cum/Hr
0.00499 Cum/Sec
=
a. From SSF 1 to Junction SSF2
Since pipes Are inter connceted from SSF 1 to SSF2
Discharge in pipe =
0.0049913 Cum/Sec
Assuming the Velocity of flow In the pipe as=
0.5 M/sec
Dia of pipe=
0.00499
x
4
0.5
x 3.142
0.1127
=
Provide
100 mm Dia CI Pipe
Now, Velocity in pipe
V=Q/A
V=
0.00499
0.785
X
0.1 X
0.1
0.636
M/sec
=
Hence Ok
Calculation Of Head Losses in pipe:
Length of pipe=
15 m
Hazen Willam Constant=
Area of Cross Section in pipe A=
100
3.142 X
100 X
100
4
Wetted perimeter =
3.142
x
100
314.2
mm
=
Hydraulic Mean Radius r =
25
mm
0.025
m
=
.63
0.54
Now, Accroding to Hazen Willams Formula
V= Q/A=0.854XCX r xS
0.64
0.854
x
100
x
=
S
0.00498
m/m
=
Frictional Losses=
0.08217 m
Out let RL at Slow Sand Filter =
593.88 M
RL at Outlet of SSF 2 =
593.798 M
0.5 M/sec
0.00998
0.5
0.1594
x
x
7855 mm2
0.63
0.025
0.54
4
3.142
Niketan Consultants
Provide
150 mm Dia CI Pipe
Now, Velocity in pipe
V=Q/A
V=
=
0.00998
0.785
X
0.15
0.565
M/sec
Hence Ok
0.15
100
3.142 X
150 X
150
4
Wetted perimeter =
3.142
x
150
471.3
mm
=
Hydraulic Mean Radius r =
37.5
mm
0.0375
m
=
.63
0.54
Now, Accroding to Hazen Willams Formula
V= Q/A=0.854XCX r xS
0.57
0.854
x
100
x
=
S
0.00498
m/m
=
Frictional Losses=
0.08217 m
RL at Outlet of SSF 2 =
593.798 M
RL at Outlet of SSF 3=
593.716 M
c. From SSF 3 to Junction SSF4
Since pipes Are inter connceted from SSF3 to SSF4
Discharge in pipe =
0.014974 Cum/Sec
Assuming the Velocity of flow In the pipe as=
Dia of pipe=
=
0.5 M/sec
0.01497
0.5
0.1953
x
x
4
3.142
0.15
17674 mm2
0.63
0.0375
0.54
Provide
150 mm Dia CI Pipe
Now, Velocity in pipe
V=Q/A
V=
=
0.01497
0.785
X
0.15
0.848
M/sec
Hence Ok
100
3.142 X
150 X
150
4
Wetted perimeter =
3.142
x
150
471.3
mm
=
Hydraulic Mean Radius r =
37.5
mm
0.0375
m
=
.63
0.54
Now, Accroding to Hazen Willams Formula
V= Q/A=0.854XCX r xS
0.85
0.854
x
100
x
=
S
0.00498
m/m
=
Frictional Losses=
0.16434 m
Out let RL at Raw water Sump=
593.716 M
inlet RL at Distribution Chamber=
593.551 M
17674 mm2
0.63
0.0375
0.54
Niketan Consultants
0.5 M/sec
0.01997
0.5
0.2255
x
x
4
3.142
0.2
Provide
200 mm Dia CI Pipe
Now, Velocity in pipe
V=Q/A
V=
=
0.01997
0.785
X
0.2
0.636
M/sec
Hence Ok
100
3.142 X
200 X
200
4
Wetted perimeter =
3.142
x
200
628.4
mm
=
Hydraulic Mean Radius r =
50
mm
0.05
m
=
.63
0.54
V= Q/A=0.854XCX r xS
Now, Accroding to Hazen Willams Formula
0.64
0.854
x
100
x
=
S
0.00498
m/m
=
Frictional Losses=
0.16434 m
RL at Outlet of SSF 3 =
593.551 M
RL at inlet Level of Sump =
593.387 M
31420 mm2
0.63
0.05
0.54
Niketan Consultants