E-01 - Switchboard Procedure Maintenance PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

UNIVERSITY OF TOLEDO

FACILITIES AND CONSTRUCTION


Section:

Subject:

Electrical/Electronics

Procedure Number:

E-01

Preventive Maintenance Electric

Effective Date:

January, 1980

Revised Date:

August 2014

Reviewed Date:

e/i4-

Switchboards and3^ato^ontrol Centers

Facilities Officer:

Standard Operating Procedure

All electrical switchboards and motor control centers will be maintained in accordance with guidelines established in
NFPA70B and/or per manufacturer's specifications and recommendations.
Purpose

To ensure safety, cleanliness and proper operation.


Procedure

Annual:

1.
2.
3.
4.
5.
6.

Check for indications of overheating and loose or broken hardware.


Clean and visually inspect unit.
Take voltage readings.
Take reading of load in amperes.
Record all readings and submit to the Electrical Systems Director.
Report any unusual conditions to the Electrical Systems Director immediately.

Page 1 of 1

You might also like