SL - No Request Received Date Working Days Reqd For Processing Request

The document contains 15 entries listing request received dates, working days required for processing, request closed dates, and working days taken to complete requests for 15 different cases. It shows details like request received date, expected processing time, actual completion date and time taken for various requests.

Uploaded by

Anish Babu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views8 pages

SL - No Request Received Date Working Days Reqd For Processing Request

The document contains 15 entries listing request received dates, working days required for processing, request closed dates, and working days taken to complete requests for 15 different cases. It shows details like request received date, expected processing time, actual completion date and time taken for various requests.

Uploaded by

Anish Babu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Sl.

No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Request Received Date


11-Jan-12
10-Feb-12
2-Mar-12
5-Jun-12
12-Mar-12
25-Jan-12
18-Feb-12
17-Feb-12
19-Jan-12
20-Mar-12
20-Jan-12
20-Feb-12
22-Mar-12
11-Apr-12
18-Apr-12

Working Days Reqd For Processing Request


7
11
14
8
18
21
14
18
9
7
5
6
12
13
14

Date On Which Payment is Expected

1-Jan-12
14-Jan-12
25-Dec-12

Sl.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Request Received Date


11-Jan-12
10-Feb-12
2-Mar-12
5-Jun-12
12-Mar-12
25-Jan-12
18-Feb-12
17-Feb-12
19-Jan-12
20-Mar-12
20-Jan-12
20-Feb-12
22-Mar-12
11-Apr-12
18-Apr-12

Request Closed Date


21-Jan-12
18-Feb-12
4-Mar-12
9-Jun-12
18-Mar-12
28-Jan-12
25-Feb-12
20-Feb-12
2-Feb-12
29-Mar-12
28-Jan-12
25-Feb-12
29-Mar-12
19-Apr-12
22-Apr-12

Working Days Taken To Complete Request

Sl.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Client Registered
11-Jan-01
10-Feb-01
2-Mar-01
5-Jun-01
1-Mar-01
25-Jan-03
3-Feb-03
17-Feb-03
19-Jan-03
20-Mar-03
6-Jan-06
6-Feb-06
22-Mar-06
11-Apr-06
6-Apr-06

Years Completed

Sl.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Lease Expiry Date


11-Jan-16
10-Feb-16
2-Mar-16
5-Jun-16
1-Mar-16
25-Jan-15
3-Feb-15
17-Feb-15
19-Jan-15
20-Mar-15
19-May-15
18-Jul-15
16-Sep-15
15-Nov-15
14-Jan-16

Years Left

Months Completed

Days Completed
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.

Months Left

Days Left

yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs
yrs

Sl.No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Journey Date
1/11/2001
2/10/2001
3/2/2001
6/5/2001
3/1/2001
1/25/2003
2/3/2003
2/17/2003
1/19/2003
3/20/2003
1/6/2006
2/6/2006
3/22/2006
4/11/2006
4/6/2006

Airline
Spicejet
Air Asia
Spicejet
Indigo
Air Asia
Indigo
Air India
Indigo
Spicejet
Air India
Spicejet
Spicejet
Indigo
Spicejet
Air Asia

Schedule Status
Delayed
On Schedule
Delayed
On Schedule
On Schedule
Delayed
Delayed
On Schedule
Delayed
Delayed
On Schedule
On Schedule
Delayed
Delayed
Delayed