Scheduling

The document discusses scheduling techniques for projects. It describes network techniques like PERT for research and development projects using probabilistic times, and CPM for construction using deterministic times. It provides an example schedule with tasks, predecessors, and durations, and illustrates the activity on node and activity on arrow network diagrams and Gantt chart that can represent the schedule and critical path of task A-C-F.

Uploaded by

Das Apurbo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views6 pages

Scheduling

The document discusses scheduling techniques for projects. It describes network techniques like PERT for research and development projects using probabilistic times, and CPM for construction using deterministic times. It provides an example schedule with tasks, predecessors, and durations, and illustrates the activity on node and activity on arrow network diagrams and Gantt chart that can represent the schedule and critical path of task A-C-F.

Uploaded by

Das Apurbo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 6

Scheduling

A network of activity and event relationships that


graphically portrays the sequential relations between the
tasks in a project

Network Technique
PERT -- Program Evaluation and Review Technique
Probabilistic activity time
Research & Development
CPM

-- Critical Path Method


Deterministic activity time
Construction/Production

Scheduling
Task

Predecessor

Time

C, D

Activity on Node

C
F

A
D

Start
B

End

Activity on Arrow

5
E

5
5

A
0

Start
0

B
5

11

11

11

11

E
14

F
11

19

19

19

End

19

19

Critical Path
19

ACF

19

GANTT Chart

Task Pred Time 1


A

C, D

2 3 4 5 6 7 8 9 10111213141516171819