Method Statement of Sheet Piling Works
Method Statement of Sheet Piling Works
Method Statement of Sheet Piling Works
METHOD STATEMENT
For
Welsh Government
at
Northern Gateway
Document Reference: C11588/11.3/ MS002
Rev C0
Date
23/01/2015
Prepared by
Signature
S.Yates
Approval
R. Howarth
Signature
Date
23/01/2015
Approved By:
For:
Revision Status and Distribution
(For revisions refer to the addendum schedule attached)
Distribution: Volker Stevin/ Foreman / File 11.3
Page 1 of 33
Northern Gateway
Addendum Schedule
Addendum
Number
Date
Alterations
Signature
Date
The site Foreman/Supervisor may carry out hand written addendums to this Method
Statement only after discussions regarding the changes with the Author or Manager, and
that they agree with the proposed changes. Any such alterations will be referenced as the
latest issue number followed by a, b, c
The Method Statement will then be briefed to all personnel concerned and recorded on a
task briefing sheet.
Page 2 of 33
Northern Gateway
Contents
1.0
Introduction ...........................................................................................................................3
2.0
Purpose ................................................................................................................................4
3.0
Programme ...........................................................................................................................4
4.0
Responsibilities .....................................................................................................................4
5.0
Reference Documents ..........................................................................................................4
6.0
Working Hours ......................................................................................................................5
7.0
Pre-requisites to starting on site............................................................................................5
8.0
Mobilisation ...........................................................................................................................5
a) Deliveries ..............................................................................................................................5
b) Equipment ............................................................................................................................5
c) Labour and Small Tools ........................................................................................................ 6
Methodology. ........................................................................................................................6
9.0
a) Pitching and Driving Using Movax......................................................................................................6
b) Water Jetting (If required) ...................................................... .................................................6
c) Controls & Monitoring ...........................................................................................................7
10.0 Labour ..................................................................................................................................7
11.0 Safety and COSHH...............................................................................................................7
12.0 Housekeeping .......................................................................................................................8
13.0 Environmental Information ....................................................................................................8
d) Waste and Pollution ..............................................................................................................8
e) Noise & Vibration ..................................................................................................................8
f) Fuel & Oils ............................................................................................................................8
g) Water courses ......................................................................................................................8
14.0 Personal Protective Equipment .............................................................................................8
15.0 Lifting Equipment ..................................................................................................................8
16.0 Lighting .................................................................................................................................9
17.0 Emergency Procedures ........................................................................................................9
18.0 Third Parties .........................................................................................................................9
APPENDICES .................................................................................................................................9
Appendix A
Risk Assessments
Appendix B
Site layout/Installation
Appendix C
Appendix D
Appendix E
Appendix F
Completion Certificate
Impact Driving Records
COSHH Assessments
Page 3 of 33
Northern Gateway
1.0
Introduction
This method statement details the proposed works connected with the off loading, loading and
installation of sheet pile retaining wall using a 25tn excavator and Movax unit to construct a
retaining wall at the Northern Gateway project for Welsh Government. The work is to be
completed in one visit from 16/03/15. The scope of works is to install 180no AU14 sheet piles
throughout CH1350-CH1500 along an existing cycle path.
The site location of the works and delivery address is:
C/o Volker Stevin
Off Welsh Road
Deeside
Wales
CH5
2.0
Purpose
The purpose of this method statement is to identify potential hazards and to provide a safe and
considered method of work.
3.0
Programme
The works will be completed in accordance with the Volker Stevin programme of works.
Mobilisation of plant and personnel to site will be 16/03/15 with an anticipated programme
period of 2 weeks.
4.0
Responsibilities
Volker Stevin will be responsible for ensuring that all the FPS attendances are provided and in
place prior to the piling equipment mobilising to site.
The Piling Foreman will be responsible for ensuring that the operations completed by Volker
Stevin will be in accordance with this method statement.
The Operations Manager will be responsible for ensuring the Piling Foreman has the necessary
support for works.
The Operations Manager will be responsible for ensuring the Method Statement and Risk
assessments are in place and, together with the Piling Foreman that site conditions match those
envisaged for the works.
On this project the relevant staff are:
5.0
VGE Personnel
Position
Site Status
Robert Howarth
Martin Knight
Mark Curtis
Steven Yates
Construction Manager
Operations Manager
Piling Supervisor
Graduate Engineer
Piling Foreman
Movax operator
Piling Operative
Visiting
Visiting
Visiting
Visiting
On site full time
On site full time
On site full time
Contact
Numbers
07748 112 263
07968 480 891
07876 876 317
07914 784 073
Reference Documents
Sheet Pile layout
Sheet Piling RAMS
Sheet Piling Lift Plan
Page 4 of 33
Northern Gateway
6.0
Working Hours
Working hours will be 7.30am to 6.00pm.
Safety and task lighting will be required at the start and end of the shift during the winter months.
Lighting units will be positioned to ensure the lights do not shine directly onto the lower bund.
7.0
8.0
A site safety induction is to be provided by Volker Stevin which will include the site
emergency procedures and personnel authorised to give instructions.
All VS Piling personnel will be inducted into this Method Statement and Risk Assessment
and will be briefed by the Operations Manager/Piling Supervisor and a copy given to the
Volker Stevin Project Manager.
Clear and safe access and egress to and from the site for our personnel and adequate
demarcation from other operations (Site clearance etc).
Suitable haul road & access to all areas for the works, including stable and well maintained
piling platforms. This will be detailed in the VS Traffic Management Plan.
Removal of obstructions.
Adequate Welfare facilities.
Setting out of the pile line and levels.
A signed Permit to Work for pile installation operations (Appendix E).
Other permits as necessary (eg Hot Works permit for cutting/ burning operations).
Clear delineation and notification of any live overhead or underground services.
Mobilisation
a) Deliveries
The Piling Foreman will inspect the platform prior to the Movax setting up. If satisfactory, he will
get the certificate from Appendix C signed off by the Volker Stevin Project Manager prior to any
operations commencing.
Offloading of the plant and ancillary equipment will be carried out within the site boundary. The
low loader will reverse to the Queensferry Hotel Car park to the works area, the low loader will
then be tracked off by the rig operator and track onto the cycle path. A banksmen is to be
present at all times and the speed of the excavator is to be limited to a walking speed.
Goalposts will be erected under the cables to establish a minimum height..
All deliveries will be made to the main site compound.
No plant/materials are to be stored on the lower berm.
All delivery vehicles will arrive with suitable edge protection.
b) Equipment
The Operations Manager will make the necessary arrangements via Volker Brooks (i.e.
movement orders where necessary) for the delivery of the piling equipment to site. The
proposed plant to be used on this project will be as follows:
25tn excavator
50v Movax unit
Telehandler
Weld set
Trailer unit
Page 5 of 33
Northern Gateway
9.0
Methodology.
The Piling Foreman will liaise with VS and agree the setting out locations of the piles and
associated levels.
The Piling Foreman will inspect the platform provided by VS for the Movax unit. If
satisfactory he will obtain endorsement of the certificate within Appendix C by a
representative of VS before commencing any operations.
The sheet piles will be transported to the piling area by the trailer unit and offloaded using
the 25tn Excavator. The sheets will be stacked in bundles of three to allow the Movax to
manoeuvre them if required.
The AU14 (upto 8m long) single sheet pile will be picked up by the Movax side grip.
The pile will be placed on the track to allow the driver to manoeuvre the hammer over the
pile and grip the section on the side.
The pile will then be lifted and positioned onto the required line for the retaining wall. The
pile will then be driven using the side grips of the hammer as far as possible depending on
prevalent underlying ground conditions. The jaws of the hammer will then be released and
the hammer moved up the pile and re-gripped onto the section and driven further.
Page 6 of 33
Northern Gateway
This will continue until the pile is driven far enough to allow the hammer to be positioned on
top of the pile. Once the Movax is positioned on top of the pile and attached via the bottom
jaw of the hammer the pile will be driven to its final level or refusal, whichever shall be the
lesser. VS will provide a machine to remove any material to allow the piles to be driven to
finished level.
The next pile will be handled in a similar manner and pitched into the clutch of the previous
pile. The pile will be driven in the same manner as the first. The pile installation will be
continued in the same manner until the end of the pile line or a change in direction.
Pile installation records will be kept on a daily basis together with daily record sheets and
provided to VS at the end of each day for verification.
If sheet pile refuses due to obstructions, the what if table will be reviewed for a possible
solution. The Project Manager (Hyder) will be informed by VS.
b)
Backdriving Sequence
If the piles refuse during driving with the Movax, impact driving may be required to drive the
piles to final level to meet the project requirements.
An Impact hammer will be mobilised to site and attached to the excavator.
The hammer will commence driving under operation by the piling operative. The driving will
be monitored throughout the driving process.
Driving will stop upon the pile final level being reached or refusal of the pile under the
driving process.
10.0
Volker Stevin will be responsible for clearly marking the line and level of all pile wall
sections and confirming the levels prior to the rig moving to the next pile.
Each pile will be checked for verticality as work proceeds by the Piling Foreman using a
sprit level.
The Piling Foreman will ensure that the piles are installed in accordance with the pile
schedule and relevant drawings.
Records will be kept of any piles which fail to achieve the required drive depth.
Labour
Operatives engaged in the site works will be a piling foreman, Movax operator, and a piling
operative.
All operatives are trained and experienced in piling works. Training records of the operatives
involved in the works will be provided at the pre commencement induction. To ensure
compliance with this method statement a briefing will be held for all personnel involved. No
visitors will be allowed within the immediate working area unless they are deemed experienced
in this work.
All operatives are CSCS/ CPCS qualified for their appropriate role and carry their cards with
them.
11.0
Diesel
Hydraulic oil
Oxygen
Propane.
Grease
Page 7 of 33
Northern Gateway
12.0
Housekeeping
All vehicles and plant will be kept in a clean condition.
The working area will be kept clean and clear of trip hazards. Any spillages will be reported to
Volker Stevin and cleared immediately. All waste will be deposited into skips provided by Volker
Stevin for disposal.
All plant will carry a comprehensive spill kit.
13.0
Environmental Information
g) Water courses
The Rive Dee is located adjacent to the sheet pile line. Re fuelling will be carried out away from the
water course.
14.0
15.0
Additional PPE will be worn as required for activities such as burning and welding and as
required by the risk assessments.
Lifting Equipment
All craneage, chains, slings, shackles and shoes will have valid certification for inspection at
all times. Present colour of all in test lifting equipment is Red.
Page 8 of 33
Northern Gateway
16.0
Daily checks to be made on chain clamp / lock-nut pitching chain and component
connectors together with the standard daily rig check carried out by the operator.
Lighting
Safety and Task lighting will be provided as necessary by VS. Site lighting to allow safe
movement around the site if needed is also to be provided by VS. Lighting units will be
positioned to ensure the lights do not shine directly onto the lower bund.
17.0
Emergency Procedures
Emergency Procedures will be briefed by Volker Stevin as part of the site induction, including
the responsible person, contact numbers and hospital directions. The VS designated First Aider
for the project will be Mr Dave McCafferty the Piling Foreman.
18.0
Third Parties
Third party assets are the responsibility of VS as indicated on the Permit to Work.
The site works described above will be completed out in a secure working area provided by VS.
APPENDICES
Page 9 of 33
Northern Gateway
Appendix A
RISK ASSESSMENT
RISK ASSESSMENT
Form Ref:
HSP-004-01
Revision:
Rev Date:
Contract:
Activity/Operation:
1
HAZARD/RISK
Ref:
6
CONTROLS
All
All
All
All
C11588/RA02/Rev 0.
Sv
RISK ASSESSMENT
Form Ref:
HSP-004-01
Revision:
Rev Date:
Contract:
Activity/Operation:
1
HAZARD/RISK
Lifting of Piles
All
Ref:
6
CONTROLS
All
All
C11588/RA02/Rev 0.
Sv
RISK ASSESSMENT
Form Ref:
HSP-004-01
Revision:
Rev Date:
Contract:
Activity/Operation:
1
HAZARD/RISK
Ref:
6
CONTROLS
All
Cutting/burning Welding
All
All
C11588/RA02/Rev 0.
When operatives clutch pile hands to be kept free from any areas they
are likely to become trapped.
Operatives working in close proximity to Machinery to wear additional
PPE or Ear Protection when required.
Sheet Piles to be installed as per Design to the position and Toe levels
specified.
If Toe levels cannot be achieved or any onsite conditions differ to the
design, cease work immediately and contact VS and VGE designer.
Any deviation from Design to be approved by VS.
Piles to be clutched together to form a rigid wall and installed plum.
Piles to be installed prior to excavating to the structure formation level.
Cutting/Burning Welding of Sheet Piles to be controlled with a Hot
Works Permit.
Operative cutting to be trained & competent.
Additional PPE of Face Mask, Fire Retardent Gloves/Overalls to be
used.
Hot works area to be fenced off/shrouded at all times with warning
signs erected.
Sparks etc to be directed from other work activities.
When welding Support brackets excavator to lift/hold in position until
weld complete.
Fire Extinguisher to be available at all Hot Works Locations
Plant to carry spill kits at all times and plant working.
All re-fuelling to be undertaken within controlled areas.
Any spillages or leaks to be reported to the site supervisor immediately
and dealt with accordingly.
Drip trays to be used under all equipment
Volkerstevin to provide banksmen to control the traffic whilst crossing
Welsh Road.
Speed limit to be enforced and speed to be limit to walking pace.
VS to provide and manage exclusion zone from The Queensferry Hotel.
Vehicles to travel in forward gear at all times possible.
Page 3 of 6
Sv
RISK ASSESSMENT
Form Ref:
HSP-004-01
Revision:
Rev Date:
Contract:
Activity/Operation:
1
HAZARD/RISK
All
All
All
Ref:
C11588/RA02/Rev 0.
CONTROLS
When offloading trailer ensure that the trailer does not block the
road.
Sv
Steven Yates
Date Assessed: 23/01/2015
Page 4 of 6
Key:
L - Likelihood
Sv - Severity
R - Risk
RISK ASSESSMENT
Form Ref:
HSP-004-01
Revision:
Rev Date:
All Operatives to Sign to Acknowledge they have Read & Fully Understood the Risk Assessment : C11588/RA01/Rev 2.
Name
Signature
Page 5 of 6
Date
RISK ASSESSMENT
Form Ref:
HSP-004-01
Revision:
Rev Date:
Page 6 of 6
Northern Gateway
Appendix B
CH1350
CH1500
4
All traffic to be
managed and
exclusion zones
enforced. No
machinery is to
travel without a
banksmen.
CH 1500
Footpath 3m
wide
Footpath 3m
wide
Overhead Cable
CH 1350
CH 1500
Movax excavator
with slew
restrictor
U Pile Stacks
U Pile Stacks
CH 1500
U Pile Stacks
Direction of piling
U Pile Stacks
Footpath 3m
wide
Overhead Cable
Movax excavator
with slew
restrictor
Northern Gateway
Appendix C
Working Platform
Designer Name
Tel No.
Designer Organisation
Is Testing Specified?
Yes / No
Date
Organisation
Signature
The HSE has worked closely with the FPS to develop this initiative and supports the principle of reducing
accidents by the certification of properly designed, prepared and maintained working platforms
WPC/4 - October 2011
Date
Organisation
Signature
Comments
(include key details of alteration,
modification, maintenance, repair, date of
next inspection, and whether or not revised
drawing issued etc. as appropriate)
The HSWA 1974 and CDM Regulations 2007 require the Principal Contractor to appoint competent Designers in respect of
Working Platform design. This legislation explains how competence can be assessed by reference to professional qualifications or
professional memberships and by reference to practical experience of the design of working platforms. Principal Contractors must
be satisfied that a competent Designer has been appointed by them in accordance with the relevant legislation before they
complete and sign the WPC.
1.2.
The stability of tracked plant is fundamentally dependent upon the provision of a suitable and sufficient working platform. It must be
properly designed and installed to a recognised standard. Whilst the same type of rig may be operated by different companies, the
design bearing pressures may differ due to the specific operating configuration of the rig and/or any modifications. Details of the
plant to be used and bearing pressures will be provided by the specialist contractor in advance of work commencing.
1.3.
Working platform design is extremely sensitive to the bearing pressure and type of fill used in the platform. (For example, changing
the angle of friction of the fill from 35 degrees to 45 degrees can halve the platform thickness.) It is therefore advised that the
Designer may have to adopt conservative/cautious estimates of platform shear strength unless higher values can be demonstrated
by testing or with reference to appropriate published data.
1.4.
The working platform must be free draining to prevent the build up of water and slurry. In the case of fine-grained sub-grades, a
separation/filter membrane should be installed beneath the platform material to inhibit pumping and infiltration of the fine-grained
soils up into the platform material during wet weather (which can impair platform performance and increase maintenance costs).
1.5.
Proof testing of the platform can be carried out with a suitably sized circular plate subjected to the maximum design loading. Such
testing, as part of an appropriately designed testing regime, should highlight any gross inconsistencies in platform performance.
Potentially, significant savings in platform thickness and cost may be realised by adopting a more detailed testing strategy.
1.6.
The working platform must have a specified design life which starts before delivery of the piling equipment and ends on completion
of all piling works. This includes load testing, integrity testing, investigation of non conformances and any remedial works.
1.7.
The specialist contractor is to advise the Principal Contractor at the earliest practicable opportunity should the specialist contractor
become aware of any circumstances relating to the working platform that renders it unsafe.
2. Installation
2.1.
The FPS Working Platform Certificate is mandatory for all sites where a rig or attendant plant operates. It must be signed by an
authorised representative of the Principal Contractor. This signature confirms that the legal duties required under CDM have been
carried out.
2.2.
If the working platform is to be constructed or removed in phases while piling works are ongoing, then the extent of the platform
must be clearly defined on the certificate and, in accordance with good practice, physically on site. This is particularly important
where the platform material is removed from an area previously made available to the specialist contractor.
2.3.
The working platform provides access for all plant deliveries, sub-contractors and personnel associated with the specialist
operations. Properly designed and installed the working platform could also provide suitable and safe access for following trades for
the whole project.
2.4.
Poor definition of the edge of the working platform is a major cause of tracked plant instability. It is good practice that the working
platform should extend at least 2m beyond the pile position/edge of the building to ensure sufficient safe working area for the
specialists personnel and attendant plant. Where having to work within this 2m zone is unavoidable the Designer is to be informed
of the requirement to design the platform for working up to its edge.
2.5.
Where access ramps are used to move between working levels these must be of sufficient gradient and width to allow the plant to
move safely with the stability constraints of the machine. Ramps must be in a straight line between working areas.Rigs and cranes
cannot change direction on ramps. Where a change in direction is required, this must be on a flat level platform.
The working platform must be kept free draining. Water and slurry which is allowed to build up on the working platform can hide
such hazards as recently constructed piles, trip hazards, uneven or unstable ground, services and excavations. Slurry can be
transferred to work equipment which increases the risk of slips on steps as well as difficult handling of work tools.
3.2.
Obstructions encountered during installation of the piling works will generally require excavation to remove them. This can create a
soft spot which can result in the rig overturning. It is essential, therefore, that any excavations made in the working platform are
reinstated to the designed standard, including any reinforcement and separation filter/membrane.
3.3.
The working platform shall be subject to regular inspection by a competent individual appointed by the Principal Contractor (e.g. the
Temporary Works Co-ordinator) throughout its design life and after any reinstatement or any works which might have modified it.
Any damaged or inadequate areas identified must be reinstated to the designed standard. Following the regular inspection, the
Working Platform Regular Inspection Log shall be signed by an authorised representative of the Principal Contractor and issued to
the specialist contractor with a layout drawing of the working platform amended as appropriate.
Items that must be included and properly located on the working platform layout drawing and be notified by the Principal Contractor
to the specialist contractor would include: detail of platform edges and 2m delineation, trial pits, services or voids, areas of
backfilling, known underground basements; areas that are covered by the certificate or permit, test locations (if specified by the
Designer of the platform) and any other feature that may affect the safety of operations.
Northern Gateway
Appendix D
Piling Equipment
NB - Refer to
800mm
Grouser
Case CX235C SR
Excavator 25t zero swing - Tier 4i
Case CX235SR
2.4m dipper arm / 800mm grouser shoes
Additional spec
Bio-degradable Hydraulic Oil
LOLER compatible with ASLI and check valves
Slew and height restriction by motion cut
Camera assisted 360 vision
Double lock quick hitch
Dual circuit hydraulic function
Cab rock guarding
Movax SG50v & IH25d compatible with auto
alignment control system
Suitable piles
Technical data
Sheet piles
H-beams
Tubes
Piler type
Pipe clamps:
(which are fitted to sheet
pile jaws)
90 - 250 mm
Width 400-1200 mm
Size H180H500
Tube reducer:
(which are fitted to
tube jaws)
193.7 - 610.0 mm
Depth 265 mm
Weight
max. 1400 kg
Length up to 18 m
SG-60
Depth (mm)
1060 - 1383
Width (mm)
1192
23 - 30
28 - 38
350
Frequency (1/min)
2500 - 3000
Driving method
Swing / tilt angle (o)
SG-60V
2260 - 2680
2468
Length up to 18 m
SG-50V
Height (mm)
Ground vibration
Length
up to 18 m
SG-50
500
600
normal
low
normal
low
no
yes
no
yes
vibra
360 / 30
Movax Oy Ltd
Tlkkimentie 10, FI-13130 Hmeenlinna, Finland | www.movax.com, email: marketing(a)movax.fi
Northern Gateway
Appendix E
Standard Forms
Permit to Work
Completion Certificate
Pile Driving Record Sheet
Impact Driving Record Sheet
Northern Gateway
Project
Client
Commencement Date
We the client hereby acknowledge that we have undertaken all reasonable steps to
identify, locate, expose and protect where necessary any known utility service or third
party structure within the vicinity of the proposed piling works.
By signing this permit VS relieves VolkerGround Engineering of any liability for any direct
or consequential damage to health, safety, environment or third party property which is
attributable as a result of the clients failure to comply with the above in accordance with
VolkerGround Engineering Terms and Conditions.
We hereby give VolkerGround Engineering Ltd permission to commence piling operations
from the above date.
Signed:
Name:
for :
Date:
Northern Gateway
Project:
Client:
Date of Completion:
Comments:
VolkerGround Engineering
Representative Signature:
Date:
Clients Signature:
Date:
Northern Gateway
Appendix F
Northern Gateway
June 2013
June 2013
June 2013
June 2013
June 2013
June 2013
These Risk Assessments, and generic COSHH Assessments are applicable to all our works and
are available for review at any time. All site personnel will be briefed on these assessments in the
pre commencement induction.
Northern Gateway
IMC
Notes
71819
Diesel (Gas Oil)
Keyword
Data Sheet
Last Modified
Health Hazard
Env. Hazard
Pkg Group
Diesel Fuel
01
14/02/2007
MEDIUM HAZARD
HIGH HAZARD
III
Hazards
Considerations
Northern Gateway
First Aid
- INHALATION REMOVE TO FRESH AIR AND REST
- AFTER A SIGNIFICANT EXPOSURE CALL FOR MEDICAL ASSISTANCE
- INGESTION DO NOT INDUCE VOMITING
- INGESTION GIVE PLENTY OF WATER IN SIPS
- INGESTION GET IMMEDIATE MEDICAL ATTENTION
- EYE IRRIGATE WITH WATER FOR AT LEAST 15 MINUTES
- SKIN WASH WITH SOAP / CLEANSER AND RINSE WITH WATER
- IF IRRITATION PERSISTS CONSULT A DOCTOR
Fire
- ISOLATED SMALL SCALE FIRE:- WATER FOG CARBON DIOXIDE POWDER FOAM
- DO NOT USE WATER JET
- LARGE FIRE:- EVACUATE AREA, CALL FIRE BRIGADE OR FOLLOW SITE PROCEDURE
- WEAR SELF-CONTAINED BREATHING APPARATUS AND PROTECTIVE CLOTHING
- TOXIC FUMES ARE PRODUCED WHEN THIS SUBSTANCE IS INVOLVED IN A FIRE
- CONTACT WATER SERVICES CO. AND EA IF WATERCOURSES ARE CONTAMINATED
- AVOID CONTAMINATION OF WATERCOURSES BY FIREFIGHTING RUN-OFF
Handling Outside For up to Hour Daily
KEEP SKIN
COVERED
AVOID SKIN
CONTACT
IF SPLASH LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
IF HEAVILY
SOILED
EATING OR
DRINKING
WASH AFTER
CONTACT
IF HEAVILY
SOILED
KEEP SKIN
COVERED
AVOID SKIN
CONTACT
IF SPLASH LIKELY
Northern Gateway
IMC
Notes
863
Engine Oil - Generic
Mineral Oil 5mg/m3 8hTWA 10mg/m3
15mSTEL WEL
Various
LIQUID
None
Mineral Oil: 100%
Keyword
Data Sheet
Last Modified
Oil (Engine)
03
08/06/2007
Health Hazard
Env. Hazard
Pkg Group
MEDIUM HAZARD
LOW HAZARD
N/A
Discontinued
No
Hazards
Considerations
Northern Gateway
First Aid
- INHALATION REMOVE TO FRESH AIR AND REST
- AFTER A SIGNIFICANT EXPOSURE CALL FOR MEDICAL ASSISTANCE IMMEDIATELY
- INGESTION DO NOT INDUCE VOMITING
- INGESTION GIVE PLENTY OF WATER IN SIPS
- IF FEELING UNWELL CONSULT A DOCTOR IMMEDIATELY
- EYE IRRIGATE WITH WATER FPOR AT LEAST 15 MINUTES
- SKIN WASH WITH SOAP/CLEANSER AND RINSE WITH WATER
- IF IRRITATION PERSISTS THEN CONSULT A DOCTOR
Fire
- ISOLATED SMALL SCALE FIRE:- USE POWDER FOAM CARBON DIOXIDE (CO2)
- DO NOT USE WATER JET
- LARGE FIRE:- EVACUATE AREA, CALL FIRE BRIGADE OR FOLLOW SITE PROCEDURE
- WEAR SELF CONTAINED BREATHING APPARATUS AND PROECTIVE CLOTHING
- TOXIC FUMES ARE PRODUCED WHEN SUBSTANCE IS INVOLVED IN A FIRE
KEEP SKIN
COVERED
IF SOILED
NITRILE
IF SPLASH LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
Northern Gateway
IMC
Notes
867
Grease (Generic)
Mineral Oil 5mg/m3 8hTWA 10mg/m3
15mSTEL WEL
Various
LIQUID
N/A
Mineral Oil
Thickners & Additives
Keyword
Data Sheet
Last Modified
Grease
04
24/07/2008
Health Hazard
Env. Hazard
Pkg Group
MEDIUM HAZARD
LOW HAZARD
N/A
Discontinued
No
Hazards
Considerations
Northern Gateway
First Aid
- INHALATION REMOVE TO FRESH AIR AND REST
- AFTER A SIGNIFICANT EXPOSURE CALL FOR MEDICAL ASSISTANCE IMMEDIATELY
- INGESTION DO NOT INDUCE VOMITING
- INGESTION GIVE PLENTY OF WATER IN SIPS
- IF FEELING UNWELL CONSULT A DOCTOR IMMEDIATELY
- EYE IRRIGATE WITH WATER FOR AT LEAST 15 MINUTES
- SKIN WASH WITH SOAP / CLEANSER AND RINSE WITH WATER
- IF IRRITATION PERSISTS THEN CONSULT A DOCTOR
- HIGH PRESSURE INJECTION OF MATERIAL INTO SKIN GET IMMEDIATE MEDICAL ATTENTION
Fire
- ISOLATED SMALL SCALE FIRE:- USE POWDER FOAM CARBON DIOXIDE (CO2)
- DO NOT USE WATER JET
- LARGE FIRE:- EVACUATE AREA, CALL FIRE BRIGADE OR FOLLOW SITE PROCEDURE
- WEAR SELF CONTAINED BREATHING APPARATUS AND PROCTECTIVE CLOTHING
- TOXIC FUMES ARE PRODUCED WHEN SUBSTANCE IS INVOLVED INA FIRE
Gun Applying in Any Area (Not Confined) For up to 2 Hours Daily
KEEP SKIN
COVERED
NITRILE
IF SPLASH LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
IF SOILED
Northern Gateway
Keyword
14658
Data Sheet
Hydraulic Oils
500mg/m3 8hrTWA * EH40 Recommended Last Modified
Health Hazard
Various
Env. Hazard
LIQUID
Pkg Group
N/A
Hydrocarbon Oil (CAS: 64742-65-0) (<1% Benzene) (99 99.5%)
Addatives (0.5%)
IMC
Notes
Discontinued
Hazards
Considerations
Hydraulic Oil
05
06/07/2001
LOW HAZARD
LOW HAZARD
N/A
No
Northern Gateway
First Aid
- INHALATION REMOVE TO FRESH AIR AND REST
- AFTER A SIGNIFICANT EXPOSURE CALL FOR MEDICAL ASSISTANCE IMMEDIATELY
- INGESTION DO NOT INDUCE VOMITING
- INGESTION GIVE PLENTY OF WATER IN SIPS
- IF FEELING UNWELL CONSULT A DOCTOR IMMEDIATELY
- EYE IRRIGATE WITH WATER FOR AT LEAST 15 MINUTES
- SKIN WASH WITH SOAP/CLEANSER AND RINSE WITH WATER
- IF IRRITATION PERSISTS THEN CONSULT A DOCTOR
Fire
- ISOLATED SMALL SCALE FIRE:- USE POWDER FOAM CARBON DIOXIDE(CO2)
- DO NOT USE WATER JET
- LARGE FIRE:- EVACUATE AREA, CALL FIRE BRIGADE OR FOLLOW SITE PROCEDURE
- WEAR SELF CONTAINED BREATHING APPARATUS
- TOXIC FUMES ARE PRODUCED WHEN SUBSTANCE IS INVOLVED IN A FIRE
Hand Applying Inside a Well Ventilated Area For up to Hour Daily
AVOID SKIN
CONTACT
AFTER USE
NITRILE
IF SPLASH LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
IF HEAVILY
SOILED
Northern Gateway
CA 006 OXYGEN
Assessment
Material/Process
Exposure Limit
Supplier
Physical State
UN Number
Contents
IMC
Notes
19932
Oxygen
BOC Gases
Gas
1072
Oxygen: 99.5%
Keyword
Data Sheet
Last Modified
Health Hazard
Env. Hazard
Pkg Group
Gas
06
01/08/2008
MEDIUM HAZARD
LOW HAZARD
II
Discontinued
No
Hazards
Considerations
Northern Gateway
First Aid
- AVOID LEAKS AND DIRECT INHALATION
- INHALATION REMOVE TO FRESH AIR AND REST
- AFTER SIGNIFICANT EXPOSURE CALL FOR MEDICAL ASSISTANCE
- WEAR APPROPRIATE PPE WHEN USING OXYGEN, IF BURNT WITH FLAME SEEK MEDICAL ATTENTION
IMMEDIATELY
Fire
- ISOLATED SMALL SCALE FIRE:- IF POSSIBLE STOP FLOW OF PRODUCT
- MOVE AWAY FROM CONTAINER AND TRY TO COOL FROM A PROTECTED POSITION
- ALL KNOWN FIRE EXTINGUISHERS CAN BE USED ON OXYGEN CONTAINERS
- LARGE FIRE:- EVACUATE AREA, CALL FIRE BRIGADE OR FOLLOW SITE PROCEDURE
- KEEP CLEAR EXPOSURE TO FIRE MAY CAUSE CONTAINER TO RUPTURE OR EXPLODE
Connecting Oxygen Inside a Well Ventilated Space All Day
KEEP SKIN
IF CONTACT
LIKELY
IF CONTACT
LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
IF HEAVILY
SOILED
EATING OR
DRINKING
WASH AFTER
CONTACT
KEEP SKIN
COVERED
IF HEAVILY SOILED
IF CONTACT
LIKELY
AFTER USE
Northern Gateway
CA007 PROPANE
Assessment
Material/Process
Exposure Limit
Supplier
Physical State
UN Number
Contents
IMC
Notes
1153
Propane
BOC Ltd
Gas
1978
Propane 100%
Keyword
Data Sheet
Last Modified
Health Hazard
Env. Hazard
Pkg Group
Gas
07
12/08/2008
MEDIUM HAZARD
MEDIUM HAZARD
N/A
Discontinued
No
Hazards
Considerations
Northern Gateway
First Aid
- INHALATION REMOVE TO FRESH AIR AND REST
- AFTER A SIGNIFICANT EXPOSURE CALL FOR MEDICAL ASSISTANCE IMMEDIATELY
- EYE CONTACT IRRIGATE USING EYE WASH AND GET IMMEDIATE MEDICAL ATTENTION
- SKIN WARM EXPOSED AREA SLOWLY
- SKIN CONTACT RINSE WITH WATER AND GET IMMEDIATE MEDICAL ATTENTION
Fire
- ISOLATED SMALL SCALE FIRE:- ALL KNOWN EXTINGUISHERS CAN BE USED ON FIRE
- LARGE FIRE:- EVACUATE AREA, CALL FIRE BRIGADE OR FOLLOW SITE PROCEDURE
- WEAR SELF CONTAINED BREATHING APPARATUS AND PROTECTIVE CLOTHING
- TOXIC FUMES ARE PRODUCED WHEN SUBSTANCE IS INVOLVED IN A FIRE
- KEEP CONTAINERS COOL WITH WATER SPRAY
Handling Propane Cylinders in Any Areas (Not Confined) For up to Hour Daily
KEEP SKIN
COVERED
HEAVY DUTY
IF CONTACT
LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
IF HEAVILY
SOILED
Connecting Propane Inside Poorly Ventilated Areas For up to Hour, in a Well Ventilated Area For up to 8 Hours
and Outside All Day
KEEP SKIN
COVERED
HEAVY DUTY
IF CONTACT
LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
IF HEAVILY
SOILED
Northern Gateway
Changing Propane Inside in a Well Ventilated Area For up to 2 Hours Daily
KEEP SKIN
HEAVY DUTY
IF CONTACT
LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT
EATING OR
DRINKING
WASH AFTER
CONTACT
IF HEAVILY SOILED
KEEP SKIN
COVERED
HEAVY DUTY
IF HEAVILY SOILED
AFTER USE
IF CONTACT
LIKELY
Northern Gateway
Burning with Propane Inside and Outside All Day
KEEP SKIN
COVERED
IF HEAVILY SOILED
HEAT RESISTANT
IF CONTACT
LIKELY
EATING OR
DRINKING
WASH AFTER
CONTACT