Planning
Department
IFAH SDN. BHD.
•MOHD ZULFAIZ BIN ABDULLAH
Gazebo Project •MUHAMMAD GHAZALI BIN BURHANUUDDIN
1. Introduction
Inthis chapter, it shows the planning by
weeks. It also shows planning schedule
by Gantt Chart that shows project made
from begin until assembly.
2. Academic calendar 02/2010
Week/Job 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Measuring
Cutting
Fabricate
Joining
Cutting Awning
Pre – Assemble
Assemble
Painting
3. Project planning
3.1 Gantt Chart
Week/Job 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Measuring • •
Cutting • • •
Fabricate • • • • • • • •
Joining • • • • •
Cutting Awning •
Pre – Assemble •
Assemble •
Painting •
•
3.2 Explanation for each job.
3.2.1 Measuring
Measure all material that want to be
use. Tools that will be use are plate
square, measuring tape, engineer chalk
and scriber.
•Gantt Chart
3.2.2 Cutting
Machine that will be use are disk cutter
machine and shearing machine. When
cutting process have be done grinding
process take part to ensure the smooth
edge of material. Portable grinding
machine will be use.
•
3.2.3 Fabricate
Two process will take part.:-
Rolling – Rolling machine will be use
to roll square tube for make awning
support.
Drilling – Make a hole for gusset.
Drilling machine, Punching machine
and portable drilling machine can be
use.
•Gantt Chart
3.2.4 Joining
Type joints that be use are bolt and nut
and welding. Bolt and nut use for
gusset.
Welding be use for another part that
not use bolt and nut.
•
3.2.5 Cutting awning
When the awning support have done, awning
will be cut followed by structure.
•Gantt Chart
3.2.6 Pre-Assemble
Assemble all parts but not too tightly.
Inspection will be done.
•Gantt Chart
3.2.7 Assemble
Assemble all parts after inspected.
Finishing.
•
3.2.8 Painting
Use semi gloss black.
•Gantt Chart
4. Align man power
Week/Job 1 2 3 4 5 6 7 8 9 10 11 12 13 14
Measuring 5 5
Cutting 6 7 6
Fabricate 12 18 18 9 9 9 9 4
Joining 9 9 9 6 4
Cutting Awning 3
Pre – Assemble 10
Assemble 9
Painting 3