Ifah Sdn. Bhd. Gazebo Project: - Mohd Zulfaiz Bin Abdullah - Muhammad Ghazali Bin Burhanuuddin

This document contains a planning schedule in the form of a Gantt chart for a gazebo project. The Gantt chart shows the timeline over 14 weeks for key jobs in the project including measuring, cutting, fabricating, joining, cutting the awning, pre-assembly, assembly, and painting. Each job is explained in brief sections detailing the process and equipment used. The final section outlines the manpower aligned to each job and week. The Gantt chart and explanations provide a concise overview of the project schedule and responsibilities.

Uploaded by

swissdec_3004
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
122 views

Ifah Sdn. Bhd. Gazebo Project: - Mohd Zulfaiz Bin Abdullah - Muhammad Ghazali Bin Burhanuuddin

This document contains a planning schedule in the form of a Gantt chart for a gazebo project. The Gantt chart shows the timeline over 14 weeks for key jobs in the project including measuring, cutting, fabricating, joining, cutting the awning, pre-assembly, assembly, and painting. Each job is explained in brief sections detailing the process and equipment used. The final section outlines the manpower aligned to each job and week. The Gantt chart and explanations provide a concise overview of the project schedule and responsibilities.

Uploaded by

swissdec_3004
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 15

Planning

Department

IFAH SDN. BHD.


•MOHD ZULFAIZ BIN ABDULLAH
Gazebo Project •MUHAMMAD GHAZALI BIN BURHANUUDDIN
1. Introduction
 Inthis chapter, it shows the planning by
weeks. It also shows planning schedule
by Gantt Chart that shows project made
from begin until assembly.
2. Academic calendar 02/2010

Week/Job 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Measuring

Cutting

Fabricate

Joining

Cutting Awning

Pre – Assemble

Assemble

Painting
3. Project planning
3.1 Gantt Chart
Week/Job 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Measuring • •

Cutting • • •

Fabricate • • • • • • • •

Joining • • • • •

Cutting Awning •

Pre – Assemble •

Assemble •

Painting •

3.2 Explanation for each job.
3.2.1 Measuring

 Measure all material that want to be


use. Tools that will be use are plate
square, measuring tape, engineer chalk
and scriber.

•Gantt Chart
3.2.2 Cutting
 Machine that will be use are disk cutter
machine and shearing machine. When
cutting process have be done grinding
process take part to ensure the smooth
edge of material. Portable grinding
machine will be use.


3.2.3 Fabricate
 Two process will take part.:-
 Rolling – Rolling machine will be use
to roll square tube for make awning
support.
 Drilling – Make a hole for gusset.
Drilling machine, Punching machine
and portable drilling machine can be
use.
•Gantt Chart
3.2.4 Joining
 Type joints that be use are bolt and nut
and welding. Bolt and nut use for
gusset.
 Welding be use for another part that
not use bolt and nut.


3.2.5 Cutting awning
 When the awning support have done, awning
will be cut followed by structure.

•Gantt Chart
3.2.6 Pre-Assemble

 Assemble all parts but not too tightly.


Inspection will be done.

•Gantt Chart
3.2.7 Assemble
 Assemble all parts after inspected.
Finishing.


3.2.8 Painting
 Use semi gloss black.

•Gantt Chart
4. Align man power
Week/Job 1 2 3 4 5 6 7 8 9 10 11 12 13 14

Measuring 5 5

Cutting 6 7 6

Fabricate 12 18 18 9 9 9 9 4

Joining 9 9 9 6 4

Cutting Awning 3

Pre – Assemble 10

Assemble 9

Painting 3