Weight Calculations For Instrument Bulk: Project

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 36

WEIGHT CALCULATIONS FOR INSTRUMENT BULK

PROJECT: By:
Platform :
ESTIMATE CLASS: C (± 30%) Rev.: 0
Building Block:
D (± 20%) Date: 04.03..2005

A BULK MATERIAL FOR ACTUATED VALVES

Tag category: Description: No. off:


03 - tubing 04 - cable tray 07 - cable 09 - field instr.
EV_XV - 3SOV_HD Double acting, hydraulic w./accu. 0 0 0 0
EV_XV - 2SOV_HD Double acting, hydraulic w./accu. 0 0 0 0
XV - 2SOV_HS Single acting, hydraulic 0 0 0 0
XV - 1SOV_HS Single acting, hydraulic 0 0 0 0
EV_XV - 3SOV_PS Single acting, pneumatic w./accu. 0 0 0 0
EV_XV - 2SOV_PS Single acting, pneumatic w./accu. 0 0 0 0
XV - 1SOV_PS Single acting, pneumatic 0 0 0 0

HCV Choke valve, pneumatic stepping actuator 0 0 0 0


HIPPS Quick Shutoff Valve w/pneum., single acting actuator 0 0 0 0
PV_LV_TV Control valve, pneumatic 0 0 0 0

HV_E On/off valve, electrical 0 0 0 0


B BULKMATERIAL FOR FIELD INSTRUMENTS (close coupled or remote)

Tag category: Description: No. off:


03 - tubing 04 - cable tray 07 - cable 09 - field instr.

PT_PS Remote mounted pressure transmitter or switch 0 0 0 0


FT_PDT_PDS Remote mounted diff. press. transmitter or switch 0 0 0 0
TT Pt100 element with 4-20mA transmitter 0 0 0 0
LT_DISPL Level transmitter mounted in vertical standpipe 0 0 0 0
LT_FLG Level transmitter mounted directly to flange 0 0 0 0
LT_SEAL Level transmitter with sealed element(s) 0 0 0 0
Metering run (non-fiscal)
PT_PS Gas metering pressure transmitter 0 0 0 0
FT_PDT_PDS Gas metering diff. press. transmitter or switch 0 0 0 0
TT Gas metering Pt100 element with 4-20mA transmitter 0 0 0 0
DT Gas metering density transmitter 0 0 0 0

ESD handswitches 0 0 0 0
Man fire call pt. 0 0 0 0
Gas detectors, line 0 0 0 0
Gas detectors, pt 0 0 0 0
Flame IR 0 0 0 0
Deluge release 0 0 0 0
C INSTRUMENTS (not requiring hook-up, or valves <4")

Tag category: Description: No. off:


03 - tubing 04 - cable tray 07 - cable 09 - field instr.
PSV-CONV_1,5x2_L Safety relief valve (inlet=150-300#), conventional 0
PSV-CONV_1,5x2,5_M Safety relief valve (inlet=600-900#), conventional 0
PSV-CONV_2x3_M Safety relief valve (inlet=150-600#), conventional 0
PSV-CONV_2x3_H Safety relief valve (inlet=900-2500#), conventional 0
PSV-PIL_1x2_M Safety relief valve (inlet=150-600#), pilot operated 0
PSV-PIL_1x2_H Safety relief valve (inlet=900-2500#), pilot operated 0
PSV-PIL_2x3_M Safety relief valve (inlet=150-600#), pilot operated 0
PSV-PIL_2x3_H Safety relief valve (inlet=900-2500#), pilot operated 0

FE_FO Orifice plate (all sizes), or flow element/assembly <4" 0


PI_TI Pressure or temperature indicator, directly mounted 0
TW Thermowell 0
PSE Pressure safety element 2"
VLV_CON_2_M Control valve 2", pneumatic (150-600#/flanged) 0
VLV_CON_2_H Control valve 2", pneumatic (900-1500#/flanged) 0
VLV_CON_3_M Control valve 3", pneumatic (150-600#/flanged) 0
VLV_CON_3_H Control valve 3", pneumatic (900-1500#/flanged) 0

VLV_ACT_2BA_L Actuated on/off valve 2", pneum. (150-300#/flanged) 0


VLV_ACT_2BA_M Actuated on/off valve 2", pneum. (600-900#/flanged) 0
VLV_ACT_2BA_H Actuated on/off valve 2", pneum. (1500-2500#/flanged) 0
VLV_ACT_3BA_L Actuated on/off valve 3", pneum. (150-300#/flanged) 0
VLV_ACT_3BA_M Actuated on/off valve 3", pneum. (600-900#/flanged) 0
VLV_ACT_3BA_H Actuated on/off valve 3", pneum. (1500-2500#/flanged) 0

D BULK FOR INSTRUMENTED PACKAGE EQUIPMENT

Tag category: Description: No. off:


03 - tubing 04 - cable tray 07 - cable 09 - field instr.
FIREW Fire Water pump 0 0 0
SEAW_1M Sea Water pump 0 0 0
HPU_200 Hydraulic Power Unit, 200 Barg 1 0 43 88
FISCAL_USM_2X Fiscal Metering Skid, Ultrasonic, 2x100% 0 0 0
ANALYSE_GC Analyser Cabinet for fiscal metering 0 0 0
COMPR_GT_20MW Gas compressor, turbine driven, 20MW 0 0 0
COMPR_EL_8MW Gas compressor, electr. driven, 8MW (w./VORECON) 0 0 0

03 - tubing 04 - cable tray 07 - cable 09 - field instr.

SUM BULK MATERIAL A - VALVES H/U 0 0 0 0

SUM BULK MATERIAL B - FIELD INSTRUMENTS H/U 0 0 0 0

SUM BULK MATERIAL C - INSTRUMENTS (NO H/U) & VALVES<4" 0

SUM BULK MATERIAL D - PACKAGED INSTR. H/U 0 43 88

TOTAL 130 kg 0 43 88 0
NOTE: Discipline allowances (in %) are made directly in the MTO list !!!
Cost/weight estimate on-off valve - pneum./hydr. w./3 off solenoids and accum.
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 25 2.8 1.45 101.5 250 6250 2.4 60
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 28 0.7 1.45 28.42 200 5600 0.68 19
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 90 0.16 1.45 20.88 70 6300 0.29 26
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 6 1.42 1.45 12.354 50 300
9 IUA J0730010C00 KAB TEST 1X2X1 2 1.54 1.45 4.466 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 15 1 15 150 150
14 0

Total 230.151 21400 19 60 40 0

Hydraulic hook-up reference: C007-C-000-JH-403-01

Company: Statoil

Installation: Sleipner A

32319115.xls / EV_XV-3SOV_HD
Cost/weight estimate on-off valve - pneum./hydr. w./2 off solenoids and accum.
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 25 2.8 1.45 101.5 250 6250 1.7 43
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 28 0.7 1.45 28.42 200 5600 0.68 19
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 60 0.16 1.45 13.92 70 4200 0.29 17
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 6 1.42 1.45 12.354 50 300
9 IUA J0730010C00 KAB TEST 1X2X1 2 1.54 1.45 4.466 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 15 1 15 150 150
14 0

Total 223.191 19300 19 43 31 0

Hydraulic hook-up reference: C007-C-000-JH-403-01

Company: Statoil

Installation: Sleipner A

32319115.xls / EV_XV-2SOV_HD
Cost/weight estimate on-off valve - hydr. w./1 off solenoid
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 20 2.8 1.45 81.2 250 5000 1.7 34
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 20 0.7 1.45 20.3 200 4000 0.68 14
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1,5 60 0.16 1.45 13.92 70 4200 0.315 19
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1,5 6 1.42 1.45 12.354 50 300
9 IUA J0730010C00 KAB TEST 1X2X1,5 2 1.54 1.45 4.466 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 15 1 15 150 150
14 0

Total 194.771 16450 14 34 32 0

Hydraulic hook-up reference:


Company: Statoil

Installation: Sleipner A

32319115.xls / XV-2SOV_HS
Cost/weight estimate on-off valve - hydr. w./1 off solenoid
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 15 2.8 1.45 60.9 250 3750 1.7 26
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 20 0.7 1.45 20.3 200 4000 0.68 14
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 6 1.42 1.45 12.354 50 300
9 IUA J0730010C00 KAB TEST 1X2X1 2 1.54 1.45 4.466 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 15 1 15 150 150
14 0

Total 167.511 13100 14 26 22 0

Hydraulic hook-up reference: C007-C-000-JH-423-01

Company: Statoil

Installation: Sleipner A

32319115.xls / XV-1SOV_HS
Cost/weight estimate on-off valve - pneumatic w./3 off solenoids and accum.
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 13 2.8 1.45 52.78 250 3250 1.7 22
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 16 0.7 1.45 16.24 200 3200 0.68 11
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 90 0.16 1.45 20.88 70 6300 0.29 26
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 6 1.42 1.45 12.354 50 300
9 IUA J0730010C00 KAB TEST 1X2X1 2 1.54 1.45 4.466 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 15 1 15 150 150
14 0

Total 169.251 16000 11 22 40 0

Pneumatic hook-up reference: C007-C-000-JH-343-01

Company: Statoil

Installation: Sleipner A

32319115.xls / EV_XV-3SOV_PS
Cost/weight estimate on-off valve - pneumatic w./2 off solenoids and accum.
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 13 2.8 1.45 52.78 250 3250 1.7 22
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 16 0.7 1.45 16.24 200 3200 0.68 11
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 60 0.16 1.45 13.92 70 4200 0.29 17
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 6 1.42 1.45 12.354 50 300
9 IUA J0730010C00 KAB TEST 1X2X1 2 1.54 1.45 4.466 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 15 1 15 150 150
14 0

Total 162.291 13900 11 22 31 0

Pneumatic hook-up reference: C007-C-000-JH-344-01

Company: Statoil

Installation: Sleipner A

32319115.xls / EV_XV-2SOV_PS
Cost/weight estimate on-off valve - pneumatic w./1 off solenoid
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 10 2.8 1.45 40.6 250 2500 1.7 17
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 5 0.7 1.45 5.075 150 750 0.68 3
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 6 1.42 1.45 12.354 0
9 IUA J0730010C00 KAB TEST 1X2X1 2 1.54 1.45 4.466 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 12 1 12 150 150
14 0

Total 128.986 8300 3 17 22 0

Pneumatic hook-up reference: C007-C-000-JH-323-01

Company: Statoil

Installation: Sleipner A

32319115.xls / XV-1SOV_PS
Cost/weight estimate choke valve - pneumatic (stepping) w./pos. transm. and lim. sw.
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 10 2.8 1.45 40.6 250 2500 1.7 17
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 3 0.7 1.45 3.045 180 540 0.68 2
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 0 1.42 1.45 0 50 0
9 IUA J0730010C00 KAB TEST 1X2X1 0 1.54 1.45 0 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 60 0.16 1.45 13.92 90 5400 0.45 27
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 4 1.72 1.45 9.976 50 200
12 IUA J0730011C00 KAB TEST 2X2X1 2 1.54 1.45 4.466 0
13 DUMMY MARSH. CAB MODS 1 10 1 10 150 150
14 0

Total 122.317 10890 2 17 36 0

Pneumatic hook-up reference: C007-C-000-JH-319-01

Company: Statoil

Installation: Sleipner A

32319115.xls / HCV
Cost/weight estimate control valve - pneumatic
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 15 2.8 1.45 60.9 250 3750 1.7 26
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 8 0.7 1.45 8.12 180 1440 0.68 5
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 IEA J0940085A00 INSTALL I/P OMFORMER 1 5.38 1.45 7.801 0
5 IEB J0940090A00 INSTALL FILTERREGULATOR 1 1.5 1.45 2.175 0 40 40
6 ISA J0940090B00 KALIBRERE FILTERREGULATOR 1 0.5 1.45 0.725 0
7 ISA J0940085B00 KALIBRERE I/P OMFORMER 1 0.5 1.45 0.725 0
8 IMA J0940085C00 TESTE I/P OMFORMER 1 0.5 1.45 0.725 0
9 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1,5 30 0.16 1.45 6.96 70 2100 0.315 9
10 ITA J0730010B00 KAB GLAND & TERM 1X2X1,5 2 1.42 1.45 4.118 50 100
11 IUA J0730010C00 KAB TEST 1X2X1,5 1 1.54 1.45 2.233 0
12 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 30 0.16 1.45 6.96 90 2700 0.45 14
13 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
14 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
Marsh Cab mods 1 10 1 10 500 500
Total 130.263 10690 5 26 23 40

Pneumatic hook-up reference:


Company: Statoil

Installation: Sleipner A

32319115.xls / HIPPS
Cost/weight estimate control valve - pneumatic
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 8 2.8 1.45 32.48 250 2000 1.7 14
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 3 0.7 1.45 3.045 180 540 0.68 2
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 1 8 1.45 11.6 0
4 IEA J0940085A00 INSTALL I/P OMFORMER 1 5.38 1.45 7.801 0
5 IEB J0940090A00 INSTALL FILTERREGULATOR 1 1.5 1.45 2.175 0
6 ISA J0940090B00 KALIBRERE FILTERREGULATOR 1 0.5 1.45 0.725 0
7 ISA J0940085B00 KALIBRERE I/P OMFORMER 1 0.5 1.45 0.725 0
8 IMA J0940085C00 TESTE I/P OMFORMER 1 0.5 1.45 0.725 0
9 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
10 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
11 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
12 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 0 0.16 1.45 0 90 0
13 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
14 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
Marsh Cab mods 1 10 1 10 500 500
Total 89.808 5340 2 14 9 0

Pneumatic hook-up reference: C007-C-000-JH-312-01

Company: Statoil

Installation: Sleipner A

32319115.xls / PV_LV_TV
Cost/weight estimate on-off valve - electrical
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 5 2.8 1.45 20.3 250 1250 1.7 9
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 180 0 0.68 0
3 IIA J0330010C00 RR<= 1.0MMTEST PNEU <=12M/MB& 0 8 1.45 0 0
4 J0820010A00 STYRESKAP INSTALL 0 4 1.45 0 0
5 DUMMY STYRESKAP TEST 0 10 1.45 0 0
6 ISA J0940036C03 TESTE LIMIT SWITCH 2 0.5 1.45 1.45 0
7 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 15 0.16 1.45 3.48 70 1050 0.29 4
8 ITA J0730010B00 KAB GLAND & TERM 1X2X1 0 1.42 1.45 0 50 0
9 IUA J0730010C00 KAB TEST 1X2X1 0 1.54 1.45 0 0
10 IPA J0730011A00 KAB TREKK & INSTAL 2X2X1 0 0.16 1.45 0 90 0 0.45 0
11 ITA J0730011B00 KAB GLAND & TERM 2X2X1 2 1.72 1.45 4.988 50 100
12 IUA J0730011C00 KAB TEST 2X2X1 1 1.54 1.45 2.233 0
13 DUMMY MARSH. CAB MODS 1 10 1 10 150 150
14 0

Total 42.451 2550 0 9 4 0

Hook-up reference: NA

Company: Statoil

Installation: Sleipner A

32319115.xls / HV_E
Cost/weight estimate on-off valve - pressure transmitter/switch
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 9 2.8 1.45 36.54 250 2250 1.7 15
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 4 0.7 1.45 4.06 200 800 0.68 3
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 1 1 1.45 1.45 0
4 J1050010A00 INSTALL INSTRUMENTHUS 1 2.2 1.45 3.19 2500 2500
5 J0940060A00 INSTALLERE TRANSMITTER 1 5.75 1.45 8.3375 0 10 10
6 ISA J0940060B00 KALIBRERE TRANSMITTER 1 3 1.45 4.35 0
7 J0940060C00 TESTE TRANSMITTER 1 0.5 1.45 0.725 0
8 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
9 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
10 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
11 0
12 0
13 0
14 DUMMY MARSH. CAB MODS 1 5 1 5 150 150

Total 76.9635 7900 3 15 9 10

Process hook-up reference: C007-C-000-JH-126-01

Company: Statoil

Installation: Sleipner A

32319115.xls / PT_PS
Cost/weight estimate on-off valve - DP transmitter/switch
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 10 2.8 1.45 40.6 250 2500 1.7 17
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 10 0.7 1.45 10.15 200 2000 0.68 7
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 1 1 1.45 1.45 0
4 J1050010A00 INSTALL INSTRUMENTHUS 1 2.2 1.45 3.19 2500 2500
5 J0940060A00 INSTALLERE TRANSMITTER 1 5.75 1.45 8.3375 0 10 10
6 ISA J0940060B00 KALIBRERE TRANSMITTER 1 3 1.45 4.35 0
7 J0940060C00 TESTE TRANSMITTER 1 0.5 1.45 0.725 0
8 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
9 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
10 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
11 0
12 0
13 0
14 DUMMY MARSH. CAB MODS 1 5 1 5 150 150

Total 87.1135 9350 7 17 9 10

Process hook-up reference: C007-C-000-JH-134-01

Company: Statoil

Installation: Sleipner A

32319115.xls / FT_PDT_PDS
Cost/weight estimate on-off valve - temperature transmitter
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 5 2.8 1.45 20.3 250 1250 1.7 9
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 200 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0 0
4 J1050010A00 INSTALL INSTRUMENTHUS 1 2.2 1.45 3.19 2500 2500
5 J0940060A00 INSTALLERE TRANSMITTER 1 5.75 1.45 8.3375 0 10 10
6 ISA J0940060B00 KALIBRERE TRANSMITTER 1 3 1.45 4.35 0
7 J0940060C00 TESTE TRANSMITTER 1 0.5 1.45 0.725 0
8 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
9 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
10 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
11 0
12 0
13 0
14 DUMMY MARSH. CAB MODS 1 5 1 5 150 150

Total 55.2135 6100 0 9 9 10

Hook-up reference: NA

Company: Statoil

Installation: Sleipner A

32319115.xls / TT
Cost/weight estimate on-off valve - level transmitter (displacer type)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 10 2.8 1.45 40.6 250 2500 1.7 17
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 200 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0 0
4 J1050010A00 INSTALL INSTRUMENTHUS 0 2.2 1.45 0 2500 0
5 J0940060A00 INSTALLERE TRANSMITTER 1 5.75 1.45 8.3375 138500 138500 55 55
6 ISA J0940060B00 KALIBRERE TRANSMITTER 1 3 1.45 4.35 0
7 J0940060C00 TESTE TRANSMITTER 1 0.5 1.45 0.725 0
8 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
9 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
10 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
11 0
12 0
13 0
14 DUMMY MARSH. CAB MODS 1 5 1 5 150 150

Total 72.3235 143350 0 17 9 55

Process hook-up reference: C007-C-000-JH-

Company: Statoil

Installation: Sleipner A

32319115.xls / LT_DISPL
Cost/weight estimate on-off valve - level transmitter (flanged, direct mounted)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 10 2.8 1.45 40.6 250 2500 1.7 17
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 200 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 1 1 1.45 1.45 0
4 J1050010A00 INSTALL INSTRUMENTHUS 0 2.2 1.45 0 2500 0
5 J0940060A00 INSTALLERE TRANSMITTER 1 5.75 1.45 8.3375 40000 40000 20 20
6 ISA J0940060B00 KALIBRERE TRANSMITTER 1 3 1.45 4.35 0
7 J0940060C00 TESTE TRANSMITTER 1 0.5 1.45 0.725 0
8 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
9 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
10 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
11 0
12 0
13 0
14 DUMMY MARSH. CAB MODS 1 5 1 5 150 150

Total 73.7735 44850 0 17 9 20

Process hook-up reference: C007-C-000-JH-

Company: Statoil

Installation: Sleipner A

32319115.xls / LT_FLG
Cost/weight estimate on-off valve - level transmitter (sealed element type)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 15 2.8 1.45 60.9 250 3750 1.7 26
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 5 0.7 1.45 5.075 200 1000
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0 0
4 J1050010A00 INSTALL INSTRUMENTHUS 0 2.2 1.45 0 2500 0
5 J0940060A00 INSTALLERE TRANSMITTER 1 5.75 1.45 8.3375 40000 40000 40 40
6 ISA J0940060B00 KALIBRERE TRANSMITTER 1 3 1.45 4.35 0
7 J0940060C00 TESTE TRANSMITTER 1 0.5 1.45 0.725 0
8 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
9 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
10 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
11 0
12 0
13 0
14 DUMMY MARSH. CAB MODS 1 5 1 5 150 150

Total 97.6985 47100 0 26 9 40

Process hook-up reference: C007-C-000-JH-

Company: Statoil

Installation: Sleipner A

32319115.xls / LT_SEAL
Cost/weight estimate density transmitter
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. stk.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 10 2.8 1.45 40.6 250 2500 1.7 17
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 200 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 1 1 1.45 1.45 0
4 J1050010A00 INSTALL INSTRUMENTHUS 0 2.2 1.45 0 2500 0
5 J0940060A00 INSTALLERE TRANSMITTER 1 5.75 1.45 8.3375 40000 40000 20 20
6 ISA J0940060B00 KALIBRERE TRANSMITTER 1 3 1.45 4.35 0
7 J0940060C00 TESTE TRANSMITTER 1 0.5 1.45 0.725 0
8 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 30 0.16 1.45 6.96 70 2100 0.29 9
9 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.118 50 100
10 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.233 0
11 0
12 0
13 0
14 DUMMY MARSH. CAB MODS 1 5 1 5 150 150

Total 73.7735 44850 0 17 9 20

Process hook-up reference: C007-C-000-JH-

Company: Statoil

Installation: Sleipner A

32319115.xls / DT
Cost/weight estimate packaged equipment - fire water pump
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Cost Estimate - ANALYSER Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 0 2.8 1.45 0 250 0 1.7 0


2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 180 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0 0
4 J0820010A00 STYRESKAP INSTALL 0 4 1.45 0 0
5 DUMMY STYRESKAP TEST 0 10 1.45 0 0
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 0 0.16 1.45 0 70 0 0.29 0
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 0 1.42 1.45 0 50 0
8 IUA J0730010C00 KAB TEST 1X2X1 0 1.54 1.45 0 0
9 IPA KAB TREKK & INSTAL 4X2X1 0.575 0
10 ITA KAB GLAND & TERM 4X2X1 ,
11 IUA KAB TEST 4X2X1
12 IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 0 0.18 1.45 0 310 0 0.98 0
13 ITA J0730013B00 KAB GLAND & TERM 8X2X1 0 3.65 1.45 0 150 0
14 IUA J0730013C00 KAB TEST 8X2X1 0 2.08 1.45 0 0
15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 0 0.23 1.45 0 390 0 1.46 0
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 0 6.55 1.45 0 150 0
17 IUA J0730010C00 KAB TEST 16X2X1 0 2.65 1.45 0 0
18 IPA KAB TREKK & INSTAL 24X2X1 2.105 0
19 ITA KAB GLAND & TERM 24X2X1
20 IUA KAB TEST 24X2X1
21 E0210200B10 GJENNOMG ÅPNE 6x1 0 1.5 1.45 0 0
22 E0210200B00 GJENNOMG PAKKE 6x1 0 3 1.45 0 0
23 DUMMY INSTALL KOB BOKS 0 10 1.45 0 4000 0
24 DUMMY MARSH. CAB MODS 0 10 1 0 180 0

Total 0 0 0 0 0 0

32319115.xls / FIREW
Cost/weight estimate packaged equipment - sea water pump
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Cost Estimate - ANALYSER Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 0 2.8 1.45 0 250 0 1.7 0


2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 180 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0 0
4 J0820010A00 STYRESKAP INSTALL 0 4 1.45 0 0
5 DUMMY STYRESKAP TEST 0 10 1.45 0 0
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 0 0.16 1.45 0 70 0 0.29 0
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 0 1.42 1.45 0 50 0
8 IUA J0730010C00 KAB TEST 1X2X1 0 1.54 1.45 0 0
9 IPA KAB TREKK & INSTAL 4X2X1 0.575 0
10 ITA KAB GLAND & TERM 4X2X1 ,
11 IUA KAB TEST 4X2X1
12 IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 0 0.18 1.45 0 310 0 0.98 0
13 ITA J0730013B00 KAB GLAND & TERM 8X2X1 0 3.65 1.45 0 150 0
14 IUA J0730013C00 KAB TEST 8X2X1 0 2.08 1.45 0 0
15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 0 0.23 1.45 0 390 0 1.46 0
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 0 6.55 1.45 0 150 0
17 IUA J0730010C00 KAB TEST 16X2X1 0 2.65 1.45 0 0
18 IPA KAB TREKK & INSTAL 24X2X1 2.105 0
19 ITA KAB GLAND & TERM 24X2X1
20 IUA KAB TEST 24X2X1
21 E0210200B10 GJENNOMG ÅPNE 6x1 0 1.5 1.45 0 0
22 E0210200B00 GJENNOMG PAKKE 6x1 0 3 1.45 0 0
23 DUMMY INSTALL KOB BOKS 0 10 1.45 0 4000 0
24 DUMMY MARSH. CAB MODS 0 10 1 0 180 0

Total 0 0 0 0 0 0

32319115.xls / SEAW_1M
Cost/weight estimate packaged equipment - hydraulic power unit (200 Barg)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 25 2.8 1.45 101.5 250 6250 1.7 43
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 180 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0 0
4 J0820010A00 STYRESKAP INSTALL 0 4 1.45 0 0
5 DUMMY STYRESKAP TEST 0 10 1.45 0 0
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 50 0.16 1.45 11.6 70 3500 0.29 15
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 0 1.42 1.45 0 50 0
8 IUA J0730010C00 KAB TEST 1X2X1 0 1.54 1.45 0 0
9 IPA KAB TREKK & INSTAL 4X2X1 0.575 0
10 ITA KAB GLAND & TERM 4X2X1 ,
11 IUA KAB TEST 4X2X1
12 IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 0 0.18 1.45 0 310 0 0.98 0
13 ITA J0730013B00 KAB GLAND & TERM 8X2X1 0 3.65 1.45 0 150 0
14 IUA J0730013C00 KAB TEST 8X2X1 0 2.08 1.45 0 0
15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 50 0.23 1.45 16.675 390 19500 1.46 73
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 2 6.55 1.45 18.995 150 300
17 IUA J0730010C00 KAB TEST 16X2X1 1 2.65 1.45 3.8425 0
18 IPA KAB TREKK & INSTAL 24X2X1 2.105 0
19 ITA KAB GLAND & TERM 24X2X1
20 IUA KAB TEST 24X2X1
21 E0210200B10 GJENNOMG ÅPNE 6x1 0 1.5 1.45 0 0
22 E0210200B00 GJENNOMG PAKKE 6x1 0 3 1.45 0 0
23 DUMMY INSTALL KOB BOKS 0 10 1.45 0 4000 0
24 DUMMY MARSH. CAB MODS 0 10 1 0 180 0

Total 152.6125 29550 0 43 88 0


Cost/weight estimate packaged equipment - fiscal metering station (2x100%) w./ultrasonic flow elements
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 0 2.8 1.45 0 250 0 1.7 0


2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0 180 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0 0
4 J0820010A00 STYRESKAP INSTALL 0 4 1.45 0 0
5 DUMMY STYRESKAP TEST 0 10 1.45 0 0
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 0 0.16 1.45 0 70 0 0.29 0
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 0 1.42 1.45 0 50 0
8 IUA J0730010C00 KAB TEST 1X2X1 0 1.54 1.45 0 0
9 IPA KAB TREKK & INSTAL 4X2X1 0.575 0
10 ITA KAB GLAND & TERM 4X2X1 ,
11 IUA KAB TEST 4X2X1
12 IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 0 0.18 1.45 0 310 0 0.98 0
13 ITA J0730013B00 KAB GLAND & TERM 8X2X1 0 3.65 1.45 0 150 0
14 IUA J0730013C00 KAB TEST 8X2X1 0 2.08 1.45 0 0
15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 0 0.23 1.45 0 390 0 1.46 0
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 0 6.55 1.45 0 150 0
17 IUA J0730010C00 KAB TEST 16X2X1 0 2.65 1.45 0 0
18 IPA KAB TREKK & INSTAL 24X2X1 2.105 0
19 ITA KAB GLAND & TERM 24X2X1
20 IUA KAB TEST 24X2X1
21 E0210200B10 GJENNOMG ÅPNE 6x1 0 1.5 1.45 0 0
22 E0210200B00 GJENNOMG PAKKE 6x1 0 3 1.45 0 0
23 DUMMY INSTALL KOB BOKS 0 10 1.45 0 4000 0
24 DUMMY MARSH. CAB MODS 0 10 1 0 180 0

Total 0 0 0 0 0 0

Process hook-up reference: C007-C-000-JH-

Company: Statoil

Installation: Sleipner A
Cost/weight estimate packaged equipment - analyser cabinet w./gas chromatograph for fiscal metering
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Cost Estimate - ANALYSER Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 13 2.8 1.45 52.78 250 3250 2.4 31
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 10 0.7 1.45 10.15 180 1800 0.68 7
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 1 1 1.45 1.45 0
4 J0820010A00 STYRESKAP INSTALL 1 4 1.45 5.8 0
5 DUMMY STYRESKAP TEST 1 10 1.45 14.5 0
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 0 0.16 1.45 0 70 0 0.29 0
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 0 1.42 1.45 0 50 0
8 IUA J0730010C00 KAB TEST 1X2X1 0 1.54 1.45 0 0
9 IPA KAB TREKK & INSTAL 4X2X1 0.575 0
10 ITA KAB GLAND & TERM 4X2X1 ,
11 IUA KAB TEST 4X2X1
12 IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 120 0.18 1.45 31.32 310 37200 0.98 118
13 ITA J0730013B00 KAB GLAND & TERM 8X2X1 2 3.65 1.45 10.585 150 300
14 IUA J0730013C00 KAB TEST 8X2X1 1 2.08 1.45 3.016 0
15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 0 0.23 1.45 0 390 0 1.46 0
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 0 6.55 1.45 0 150 0
17 IUA J0730010C00 KAB TEST 16X2X1 0 2.65 1.45 0 0
18 IPA KAB TREKK & INSTAL 24X2X1 2.105 0
19 ITA KAB GLAND & TERM 24X2X1
20 IUA KAB TEST 24X2X1
21 E0210200B10 GJENNOMG ÅPNE 6x1 0 1.5 1.45 0 0
22 E0210200B00 GJENNOMG PAKKE 6x1 0 3 1.45 0 0
23 DUMMY INSTALL KOB BOKS 0 10 1.45 0 4000 0
24 DUMMY MARSH. CAB MODS 0 10 1 0 180 0

Total 129.601 42550 7 31 118 0

Process hook-up reference: C007-C-000-JH-224-01

Company: Statoil

Installation: Sleipner A
BLOCK DIAGRAM Date: 29.10.2003
Rev.: 0
GAS TURBINE DRIVEN COMPRESSOR (20MW)

FIELD ELECTR. ROOM LOCAL EQUIPMENT ROOM


35 m (Note 1) (Note 1)

60 m
WHRU 9 12 PRx1,0 MCC
45 1 PRx1,0
RIO
Profibus 3
100 m 19
1
10 m PCS 10
10 12 PRx1,0 1 PRx1,0 1
2 2 PRx1,5
G.T. 3 4 PRx1,0

PRx1,0

PRx1,0
DRIVER 39 CENTR. CONTR. ROOM
75 120 m

16
6 12 TRx1,0

8
12 PRx1,0 PSD 1 1 PRx1,5 + +
16 PRx1,0

PRx1,0

PRx1,0

PRx1,0

PRx1,0

PRx1,0
1 PRx1,0

10 m (average length)
8
4
1
4
1
GEAR 2

RELAY LOGIC

16 TRx1,0
16 PRx1,0 REMOTE I/O
27
8 PRx1,0 TCP
COMPR. 4 Profibus
16 PRx1,0 Hydr. start
(Stages: 2 ) 23 24 PRx1,0
4 TRx1,0 CCP

PRx1,0

PRx1,0
4 PRx1,0 12 PRx0,75 (Thermocouple, type K)
16 PRx1,5
1 PRx1,0

2
2
LUBE 7 1 PRx1,0 2
OIL 1 PRx1,0 FUEL CONTROL
2
4 PRx1,0

PRx1,0
8 PRx1,0 (i)

2
2
PROCESS 3 2 PRx1,0 (i) VIBR. MON.
12 PRx1,0 (i)
12 PRx1,0 (i)

32319115.xls/BLK. DIAGR. 20MW_GTCOMPR Note 1: Existing room, or part of new compressor module.
Cost/weight estimate packaged equipment - compressor, gas turbine driven (20MW)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 0 2.8 1.45 0.0 250 0 1.7 0


ED SS INST BROER 0 - 150 MM 0 2.8 1.45 0.0 250 0 1.7 0
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0.0 180 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0.0 0
4 J0820010A00 STYRESKAP INSTALL 0 4 1.45 0.0 0
5 DUMMY STYRESKAP TEST 0 10 1.45 0.0 0

FIELD - LER: 35 m (acc. to block diagram)


WHRU:
IPA KAB TREKK & INSTAL 12X2X1 35 0.22 1.45 11.2 360 12600 1.24 43
ITA KAB GLAND & TERM 12X2X1 2 4.91 1.45 14.2 150 300
IUA KAB TEST 12X2X1 1 2.38 1.45 3.5 0

GT DRIVER:
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 105 0.16 1.45 24.4 70 7350 0.29 30
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 6 1.42 1.45 12.4 50 300
8 IUA J0730010C00 KAB TEST 1X2X1 3 1.54 1.45 6.7 0
(cross sect. 1,5mm2) IPA KAB TREKK & INSTAL 2X2X1 35 0.16 1.45 8.1 200 7000 0.515 18
(cross sect. 1,5mm2) ITA KAB GLAND & TERM 2X2X1 2 1.73 1.45 5.0 50 100
(cross sect. 1,5mm2) IUA KAB TEST 2X2X1 1 1.54 1.45 2.2 0
9 IPA KAB TREKK & INSTAL 4X2X1 35 0.16 1.45 8.1 200 7000 0.575 20
10 ITA KAB GLAND & TERM 4X2X1 2 2.36 1.45 6.8 50 100
11 IUA KAB TEST 4X2X1 1 1.68 1.45 2.4 0
(individ. scr.) IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 35 0.19 1.45 9.6 380 13300 1.095 38
(individ. scr.) ITA KAB GLAND & TERM 8X2X1 2 4.20 1.45 12.2 150 300
(individ. scr.) IUA J0730013C00 KAB TEST 8X2X1 1 2.10 1.45 3.0 0
IPA KAB TREKK & INSTAL 12X2X1 35 0.22 1.45 11.2 360 12600 1.24 43
ITA KAB GLAND & TERM 12X2X1 2 4.91 1.45 14.2 150 300
IUA KAB TEST 12X2X1 1 2.38 1.45 3.5 0
15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 35 0.23 1.45 11.7 390 13650 1.46 51
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 2 6.07 1.45 17.6 150 300
17 IUA J0730010C00 KAB TEST 16X2X1 1 2.61 1.45 3.8 0
(cross sect. 1,5mm2) 15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 35 0.23 1.45 11.7 460 16100 1.72 60
(cross sect. 1,5mm2) 16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 2 6.07 1.45 17.6 150 300
(cross sect. 1,5mm2) 17 IUA J0730010C00 KAB TEST 16X2X1 1 2.61 1.45 3.8 0
18 IPA KAB TREKK & INSTAL 24X2X1 35 0.25 1.45 12.7 560 19600 2.105 74
19 ITA KAB GLAND & TERM 24X2X1 2 8.75 1.45 25.4 150 300
20 IUA KAB TEST 24X2X1 1 3.50 1.45 5.1 0
(thermocouple) IPA KAB TREKK & INSTAL 12X2X1 35 0.22 1.45 11.2 900 31500 0.94 33
(thermocouple) ITA KAB GLAND & TERM 12X2X1 2 4.91 1.45 14.2 150 300
(thermocouple) IUA KAB TEST 12X2X1 1 2.38 1.45 3.5 0
IPA KAB TREKK & INSTAL 4X3X1 35 0.19 1.45 9.6 200 7000 0.715 25
ITA KAB GLAND & TERM 4X3X1 2 3.02 1.45 8.8 50 100
IUA KAB TEST 4X3X1 1 1.96 1.45 2.8 0

GEAR:
(individ. scr.) IPA KAB TREKK & INSTAL 2X2X1 35 0.16 1.45 8.1 240 8400 0.48 17
(individ. scr.) ITA KAB GLAND & TERM 2X2X1 2 1.99 1.45 5.8 50 100
(individ. scr.) IUA KAB TEST 2X2X1 1 1.54 1.45 2.2 0

COMPR.:
(individ. scr.) IPA KAB TREKK & INSTAL 12X2X1 70 0.22 1.45 22.3 400 28000 1.475 103
(individ. scr.) ITA KAB GLAND & TERM 12X2X1 4 5.65 1.45 32.7 150 600
(individ. scr.) IUA KAB TEST 12X2X1 2 2.38 1.45 6.9 0

32319115.xls/COMPR_GT_20MW Page 30 of 36
Cost/weight estimate packaged equipment - compressor, gas turbine driven (20MW)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:
REM. I/O:
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 35 0.16 1.45 8.1 70 2450 0.29 10
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.1 50 100
8 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.2 0

FIELD - CCR: 100 m (acc. to block diagram)


COMPR.:
9 IPA KAB TREKK & INSTAL 4X2X1 200 0.16 1.45 46.4 200 40000 0.575 115
10 ITA KAB GLAND & TERM 4X2X1 4 2.36 1.45 13.7 50 200
11 IUA KAB TEST 4X2X1 2 1.68 1.45 4.9 0

FIELD - RIO: 10 m (acc. to block diagram)


GT DRIVER:
COMPR.:
15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 20 0.23 1.45 6.7 390 7800 1.46 29
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 4 6.07 1.45 35.2 150 600
17 IUA J0730010C00 KAB TEST 16X2X1 2 2.61 1.45 7.6 0
IPA KAB TREKK & INSTAL 16X3X1 20 0.25 1.45 7.3 480 9600 1.605 32
ITA KAB GLAND & TERM 16X3X1 4 8.73 1.45 50.6 50 200
IUA KAB TEST 16X3X1 2 3.48 1.45 10.1 0
LUBE OIL:
12 IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 10 0.19 1.45 2.8 310 3100 0.98 10
13 ITA J0730013B00 KAB GLAND & TERM 8X2X1 2 3.65 1.45 10.6 150 300
14 IUA J0730013C00 KAB TEST 8X2X1 1 2.10 1.45 3.0 0
PROCESS:
9 IPA KAB TREKK & INSTAL 4X2X1 10 0.16 1.45 2.3 200 2000 0.575 6
10 ITA KAB GLAND & TERM 4X2X1 2 2.36 1.45 6.8 50 100
11 IUA KAB TEST 4X2X1 1 1.68 1.45 2.4 0

MCC - LER: 60 m (acc. to block diagram)


REM. I/O:
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 60 0.16 1.45 13.9 70 4200 0.29 17
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.1 50 100
8 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.2 0

CCR - LER: 120 m (acc. to block diagram)


PSD:
(cross sect. 1,5mm2) 6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 120 0.16 1.45 27.8 70 8400 0.315 38
(cross sect. 1,5mm2) 7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.1 50 100
(cross sect. 1,5mm )
2
8 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.2 0

INTERNAL LER: 10 m (acc. to block diagram)


PCS:
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 20 0.16 1.45 4.6 70 1400 0.29 6
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 4 1.42 1.45 8.2 50 200
8 IUA J0730010C00 KAB TEST 1X2X1 2 1.54 1.45 4.5 0
(unarmoured cable) 9 IPA KAB TREKK & INSTAL 4X2X1 20 0.16 1.45 4.6 200 4000 0.325 7
10 ITA KAB GLAND & TERM 4X2X1 4 2.36 1.45 13.7 50 200
11 IUA KAB TEST 4X2X1 2 1.68 1.45 4.9 0
(unarmoured cable) 12 IPA J0730013A00 KAB TREKK & INSTAL 8X2X1 20 0.19 1.45 5.5 310 6200 0.59 12
13 ITA J0730013B00 KAB GLAND & TERM 8X2X1 4 3.65 1.45 21.2 150 600
14 IUA J0730013C00 KAB TEST 8X2X1 2 2.10 1.45 6.1 0
(unarmoured cable) 15 IPA J0730018A00 KAB TREKK & INSTAL 16X2X1 10 0.23 1.45 3.3 390 3900 0.98 10
16 ITA J0730018B00 KAB GLAND & TERM 16X2X1 2 6.55 1.45 19.0 150 300
17 IUA J0730010C00 KAB TEST 16X2X1 1 2.65 1.45 3.8 0

32319115.xls/COMPR_GT_20MW Page 31 of 36
Cost/weight estimate packaged equipment - compressor, gas turbine driven (20MW)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:
TCP:
(unarmoured cable) IPA KAB TREKK & INSTAL 2X2X1 20 0.16 1.45 4.6 200 4000 0.23 5
ITA KAB GLAND & TERM 2X2X1 4 1.73 1.45 10.0 50 200
IUA KAB TEST 2X2X1 2 1.54 1.45 4.5 0

VIBR.:
(unarmoured cable) IPA KAB TREKK & INSTAL 2X2X1 10 0.16 1.45 2.3 200 2000 0.23 2
ITA KAB GLAND & TERM 2X2X1 2 1.73 1.45 5.0 50 100
IUA KAB TEST 2X2X1 1 1.54 1.45 2.2 0

21 E0210200B10 GJENNOMG ÅPNE 6x1 0 1.5 1.45 0.0 0


22 E0210200B00 GJENNOMG PAKKE 6x1 0 3 1.45 0.0 0
23 DUMMY INSTALL KOB BOKS 0 10 1.45 0.0 4000 0
24 DUMMY MARSH. CAB MODS 0 10 1 0.0 180 0

Total 885 303650 0 0 899 0

= Cable estimate pending on number of compressor stages

Electrical hook-up reference: See block diagram on separate worksheet Total NOK/kg for bulk: 338
Company: Total Mhrs./tonn for bulk: 985
Installation:

32319115.xls/COMPR_GT_20MW Page 32 of 36
BLOCK DIAGRAM Date: 30.10.2003
Rev.: 0
ELECTRICAL (VSD) DRIVEN COMPRESSOR (8MW)

FIELD ELECTR. ROOM LOCAL EQUIPMENT ROOM


50 m (Note 1) (Note 1)

60 m

3 4 PRx1,0
PROCESS 3 4 PRx1,0 MCC
4 1 PRx1,0
RIO
Profibus 3
120 m
PCS

2 2 PRx1,0

ELECTR.
DRIVER CENTR. CONTR. ROOM
(FIXED
SPEED) 4
PSD

4 PRx1,0
8 TRx1,0
17 12

10 m
PRx1,0

VORECON
VARIABLE 11
GEAR

8 TRx1,0
28 24 PRx1,0 4 PRx1,0 (i)

COMPR. 4 4 PRx1,0 12 PRx1,0 (i) VIBR. MON.

(Stages: 1 ) 12 12 PRx1,0 (i)

32319115.xls/BLK. DIAGR. 8MW_ELCOMPR Note 1: Existing room, or part of new compressor module.
BLOCK DIAGRAM Date: 30.10.2003
Rev.: 0
ELECTRICAL (VSD) DRIVEN COMPRESSOR (8MW)

32319115.xls/BLK. DIAGR. 8MW_ELCOMPR Note 1: Existing room, or part of new compressor module.
Cost/weight estimate packaged equipment - compressor, electr. driven (8MW)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

1 ED E041010AA0S SS INST BROER 0 - 150 MM 0 2.8 1.45 0.0 250 0 1.7 0


ED SS INST BROER 0 - 150 MM 0 2.8 1.45 0.0 250 0 1.7 0
2 IHA J0330010A00 RR<= 1.0MMINSTALLER <=12M/MB& 0 0.7 1.45 0.0 180 0 0.68 0
3 IIA J0330010E00 RR<= 1.0MMTEST PROS <=12M/MB& 0 1 1.45 0.0 0
4 J0820010A00 STYRESKAP INSTALL 0 4 1.45 0.0 0
5 DUMMY STYRESKAP TEST 0 10 1.45 0.0 0

FIELD - LER: 50 m (acc. to block diagram)


ELECTR. DRIVER:
IPA KAB TREKK & INSTAL 2X2X1 50 0.16 1.45 11.6 180 9000 0.45 23
ITA KAB GLAND & TERM 2X2X1 2 1.73 1.45 5.0 50 100
IUA KAB TEST 2X2X1 1 1.54 1.45 2.2 0
(individ. scr.) IPA KAB TREKK & INSTAL 4X2X1 50 0.16 1.45 11.6 230 11500 0.64 32
(individ. scr.) ITA KAB GLAND & TERM 4X2X1 2 2.71 1.45 7.9 150 300
(individ. scr.) IUA KAB TEST 4X2X1 1 1.68 1.45 2.4 0

VORECON VAR.
GEAR:
(individ. scr.) IPA KAB TREKK & INSTAL 12X2X1 100 0.22 1.45 31.9 400 40000 1.475 148
(individ. scr.) ITA KAB GLAND & TERM 12X2X1 4 5.65 1.45 32.7 150 600
(individ. scr.) IUA KAB TEST 12X2X1 2 2.38 1.45 6.9 0
IPA KAB TREKK & INSTAL 12X2X1 50 0.22 1.45 16.0 360 18000 1.24 62
ITA KAB GLAND & TERM 12X2X1 2 4.91 1.45 14.2 150 300
IUA KAB TEST 12X2X1 1 2.38 1.45 3.5 0
IPA KAB TREKK & INSTAL 8X3X1 100 0.22 1.45 31.9 350 35000 1.205 121
ITA KAB GLAND & TERM 8X3X1 4 5.08 1.45 29.5 50 200
IUA KAB TEST 8X3X1 2 2.64 1.45 7.7 0

COMPR.:
(individ. scr.) IPA KAB TREKK & INSTAL 12X2X1 100 0.22 1.45 31.9 400 40000 1.475 148
(individ. scr.) ITA KAB GLAND & TERM 12X2X1 4 5.65 1.45 32.7 150 600
(individ. scr.) IUA KAB TEST 12X2X1 2 2.38 1.45 6.9 0
18 IPA KAB TREKK & INSTAL 24X2X1 50 0.25 1.45 18.1 560 28000 2.105 105
19 ITA KAB GLAND & TERM 24X2X1 2 8.75 1.45 25.4 150 300
20 IUA KAB TEST 24X2X1 1 3.50 1.45 5.1 0
IPA KAB TREKK & INSTAL 8X3X1 100 0.22 1.45 31.9 350 35000 1.205 121
ITA KAB GLAND & TERM 8X3X1 4 5.08 1.45 29.5 50 200
IUA KAB TEST 8X3X1 2 2.64 1.45 7.7 0

PROCESS:
9 IPA KAB TREKK & INSTAL 4X2X1 100 0.16 1.45 23.2 200 20000 0.575 58
10 ITA KAB GLAND & TERM 4X2X1 4 2.36 1.45 13.7 50 200
11 IUA KAB TEST 4X2X1 2 1.68 1.45 4.9 0

FIELD - CCR: 120 m (acc. to block diagram)


COMPR.:
9 IPA KAB TREKK & INSTAL 4X2X1 240 0.16 1.45 55.7 200 48000 0.575 138
10 ITA KAB GLAND & TERM 4X2X1 4 2.36 1.45 13.7 50 200
11 IUA KAB TEST 4X2X1 2 1.68 1.45 4.9 0

MCC - LER: 60 m (acc. to block diagram)


MCC/RIO:
6 IPA J0730010A00 KAB TREKK & INSTAL 1X2X1 60 0.16 1.45 13.9 70 4200 0.29 17
7 ITA J0730010B00 KAB GLAND & TERM 1X2X1 2 1.42 1.45 4.1 50 100
8 IUA J0730010C00 KAB TEST 1X2X1 1 1.54 1.45 2.2 0
9 IPA KAB TREKK & INSTAL 4X2X1 120 0.16 1.45 27.8 200 24000 0.575 69
10 ITA KAB GLAND & TERM 4X2X1 4 2.36 1.45 13.7 50 200
11 IUA KAB TEST 4X2X1 2 1.68 1.45 4.9 0

32319115.xls/COMPR_EL_8MW Page 35 of 36
Cost/weight estimate packaged equipment - compressor, electr. driven (8MW)
03 - rør 04 - kabelbrett 07 - kabel 09 - feltinstrument
Qty Norm Faktor Timer Unit price Cost Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt: Vekt pr. m.: Totalt:

INTERNAL LER: 10 m (acc. to block diagram)


VIBR.:
(unarmoured cable) 9 IPA KAB TREKK & INSTAL 4X2X1 10 0.16 1.45 2.3 200 2000 0.325 3
10 ITA KAB GLAND & TERM 4X2X1 2 2.36 1.45 6.8 50 100
11 IUA KAB TEST 4X2X1 1 1.68 1.45 2.4 0

21 E0210200B10 GJENNOMG ÅPNE 6x1 0 1.5 1.45 0.0 0


22 E0210200B00 GJENNOMG PAKKE 6x1 0 3 1.45 0.0 0
23 DUMMY INSTALL KOB BOKS 0 10 1.45 0.0 4000 0
24 DUMMY MARSH. CAB MODS 0 10 1 0.0 180 0

Total 598 318100 0 0 1043 0

= Cable estimate pending on number of compressor stages

Electrical hook-up reference: See block diagram on separate worksheet Total NOK/kg for bulk: 305
Company: Total Mhrs./tonn for bulk: 574
Installation:

32319115.xls/COMPR_EL_8MW Page 36 of 36