Glenfield Road Corridor Management Plan
Glenfield Road Corridor Management Plan
Glenfield Road Corridor Management Plan
IZ036400
Document title:
CMP
Document No.:
Revision:
Date:
10 August 2015
Client name:
Auckland Transport
Client no:
111-15-281-PS
Project manager:
Jeremy Hosking
Author:
Nic Grgec
File name:
:\ZBIFA\Projects\ZB01674\Deliverables (issued)\Reports\
Glenfield Road Corridor Management Plan Final 2015.docx
Date
Description
By
Review
Approved
19/06/2015
NG
JH
JH
10/08/2015
Final
NG
JH
JH
Copyright 2015 Jacobs New Zealand Limited. The concepts and information contained in this document are the property of Jacobs. Use or copying
of this document in whole or in part without the written permission of Jacobs constitutes an infringement of copyright.
Limitation: This report has been prepared on behalf of, and for the exclusive use of Jacobs Client, and is subject to, and issued in accordance with, the
provisions of the contract between Jacobs and the Client. Jacobs accepts no liability or responsibility whatsoever for, or in respect of, any use of, or
reliance upon, this report by any third party.
Table of Contents
1
Introduction 7
1.1
Study process
1.2
Corridor sections
1.3
11
1.3.1
General vehicles
11
1.3.2 Pedestrians
12
1.3.3 Cycling
14
1.3.4
Public transport
15
1.3.5
Neighbouring projects
16
1.4
17
Problems 19
4.1
26
4.2
30
4.3
32
4.4
34
4.5
36
4.6
38
4.7
42
25
4.8 Summary
45
4.8.1 Pedestrians
45
4.8.2
46
4.8.3 Cycling
46
4.8.4
Public transport
47
4.8.5
General vehicles
48
Implementation plan 49
5.1 Pedestrians
49
5.2 Cycling
49
5.3
Public transport
50
5.4
50
5.5
General vehicles
50
Appendices
Appendix A - Land use and transport file note
Appendix B - Problem definition file note
Appendix C - Options, priorities and points of tension file note
List of figures
Figure 1.1 : Glenfield Road corridor location
11
12
13
14
15
16
18
19
Figure 2.2 : Glenfield Road between Bentley Ave and Kaipatiki Road (looking south)
21
26
28
29
29
31
31
33
33
34
35
35
Figure 4.12 : Coronation Road / Glenfield Road bus and cycle priority
36
37
37
39
39
40
Figure 4.18 : Glenfield Road / Pupuke Road intersection - southbound bus priority
41
Figure 4.19 : Section 7 - eastern footpath and grass berm looking north
42
43
43
44
45
46
47
48
51
Executive Summary
Introduction
A Corridor Management Plan (CMP) is an important tool for planning and
implementing transport improvements for a corridor and is based on an
integrated assessment of both the transport and land uses within the
corridor. Auckland Transport is responsible for developing and reviewing
CMPs for arterial roads in the Auckland region.
Jacobs has been commissioned by Auckland Transport to develop
the Corridor Management Plan (CMP) for the Glenfield Road corridor.
The corridor is located on the North Shore of Auckland and includes
1
the sections of Glenfield Road and Birkenhead Road between Bentley
Avenue and Onewa Road (shown in red in Figure 1.1). The total length of
the corridor is in the order of 3.5 km and does not include the section of
Glenfield Road north of Bentley Ave as this has recently been upgraded.
Introduction
continued
The existing and future transport and land use contexts for the
corridor (refer Appendix A)
The identified problems and the ideal future state defined by the
technical stakeholders (refer Appendix B)
The study process undertaken for the Glenfield Road CMP is presented
in the flowchart in Figure 1.2. A number of file notes have been prepared
throughout the project to capture the outcomes of each of the CMP
steps. These include discussion on:
The following CMP collates and summarises the work to date and
presents the preferred long-term strategic vision for the corridor.
An implementation plan which includes short, medium and longterm projects to achieve this vision is presented. These projects will
subsequently be put forward for inclusion in the Auckland Regional Land
Transport Programme or may be implemented via other channels. The
CMP also provides strategic guidance to other projects not included in
the implementation plan.
Introduction
continued
RD
SUNNYFIEL
ME
LO
T
E
ID
CHIVA
EY
RL
W
AV
E
EY
AVE
E
AV
RD
EL
FI
ST
E
AV
Y CR ES
D
AV
E
N
EA
EIG
W
IE
HR
RAYMO ND TCE
RD
KAURI
GLEN
W PL
GLADSTONE
RD
ONEWA RD
HI
NE
S T MO
A
200
400
IRFAX AVE
V IE W
DR
Figure 1.3: Corridor
sections
BARLO
ZION RD
RD
PARK AVE
WARATAH ST
PL
ROSEBERRY
D
KE R
600 Meters
FA
CO
TILDE
N
HI
LL
PA
RK
IN
GL
RD
N
A
C
O
LYDIA AVE
TC E
AORAN G I
RD
E
AV
AY
SW
W
VIE
I
LV
R AL
TUI GLE N
ST
M AIN
N
TO
S
CE
K ST
U
PU P
SY
MO ORE ST
BAN
AV E
PA
AI
PASS
BY
PL
AC
IS
VERBENA RD
S
L L CRE
C IT
Y
UR
HB
HIG
WE
AY
VE
BY A
EN
N
TO
AL
Eskdale Reserve to
Pupuke Road
Section 7
AN
O
C
Section 6
Birkenhead Avenue
E
AV
L
EL
PL
MC D O
RD
EN
RC
EL
AW
AN
ST
N
LY
VE
N A
TE
BAT
NT
U
VE
RECREATION DR
BAL
T
HILLC R E S
AV
GL
E
ION P
OR
SP E E
RR
CHELS EA
D
R
ST
D
Y
MON
A
GRE
T
ST
MOKOIA RD
N RD
R
AW N
EL
TR
RO G
NAT IO
RD
RD
E
AV
EL
HOB
VANDELEUR AVE
ST
FI
N PL
L
HIWIHAU P
N TO
A IN
DOM
Section 5
VE
ST
N
LE
BR U
RD
Eskdale Reserve
N
LET O
IM
T
UR
O
CORO
C AS T
ER
LM
HE
AR
BEAT R I C
EN
C
AGI N
DR
BL
RD
DR
HI
GH
E
AV
RS
AE
UE
EQ
CH
YB
LE
E
ER
OODC OT
N
LI
RD
G
OU
R
LB O
RIE
AH
K
PAR
LE
SU
W O R TH
E
AV
W
PO
MA
ST
IT H
W
TL
ST
Section 3
Section 4RD
DA
LP
D OWNIN G
RT to
High RRoad
O BE
Coronation Road
ES
K
CE
EL
TW
AR
H RD
Downing Street to
ST
High Road
LRY R
D
ED
G
N
PL
COU RT
EN
WR
AR
AC
PE
BE
DIN PL
GE
AN
ST
M
TA
R
ES S A D
NT
CO
SEA
VIE
BR
AV
E
RD
EF
O
Section 2
Kaipatiki Avenue to
Downing Street
SE
LL
DR
CA
HI
L
MAYFIE D RD
OE
L
D CRES
KAIPAT IKI RD
AN
DI
RD
Bentley Avenue to
Kaipatiki Avenue
DR
EAL
RD
AV E
Section
1
N
N
EE
LI N
KA
SA
RO
U
AN
Introduction
continued
Section
10
Description
The section of Glenfield Road from Bentley Avenue to Kaipatiki Road passes through the Glenfield Town Centre with a mixture of
retail and small businesses either side of the corridor. The Westfield Shopping Mall is a significant land use which fronts this section of
the corridor. There is an on road cycle lane southbound.
The Kaipatiki Road to Downing Street section is a continuation of the town centre however it has less active retail and business
frontages, and currently primarily caters for vehicle movements at the Kaipatiki Road and Downing Street intersections. Currently
there is some provision for cyclists on and off road.
The Downing Street to High Road section is largely characterised by the Oruamo Reserve and a steep uphill section of Glenfield
Road (southbound) which currently has a wide carriageway with a crawler lane and no footpath on the eastern side.
The High Road to Coronation Road section is largely characterised by a steep downhill section of Glenfield Road (southbound) which
sits above some property boundary levels and below others. Access roads either side of Glenfield Road provide access to these
properties.
The Coronation Road to Eskdale Road section is largely characterised by a fairly straight section of road with a gradual downhill
slope in the southbound direction. The Eskdale Reserve is adjacent to the corridor on the west side and a residential neighbourhood
borders the corridor to the east. There is no footpath along the majority of the western side on the road.
This section connects the two signalised intersections at Eskdale Road and Pupuke Road. Some of the residential properties on the
western side are situated below the road level and at the Pupuke Road intersection some properties are above the road level. The
retaining walls on the western side of the road are a significant constraint for future options along this section.
The Birkenhead Avenue section is largely characterised by residential properties on both sides of the road with many private
driveways having access from Glenfield Road. Birkenhead Domain and playing fields are located on the west side of the corridor. At
the southern end of this section, the corridor intersects with Onewa Road and Birkenhead Town Centre is located to the south of the
intersection. The land adjacent to the corridor between Pupuke Road and Onewa Road is zoned for terrace housing and apartment
buildings in the Proposed Auckland Unitary Plan.
Introduction
SUNNYFIEL
AV
E
EY
RL
W
AV
E
RD
H
DR
CO
GL
ST
AV
T
UR
LE
I
NF
EL
R
D
Northcote
College
TILDE
N
ONEWA RD
HI
NE
FAI R
ADT
15,014 (4.5% HCV)
(2014)
ST
E
C
O
RAL
EIG
HR
D
AVE
H UKA R D
M AIN
Birkenhead
Primary
IEW
L RD
BAL
Y
YB
IE
E AV
C HE L SE
A VIE
W DR
BARLO
400
Meters
W P600
L
E
IT T A V
200
CO LON I A
RD
B
IG H
Kauri Glen
Reserve
VALLEY R D
UR
P OR R
S
PA
MOKOIA RD
ZION RD
AN
ADT
19,998 (3.0% HCV)
(2014)
PARK AVE
HI
LL
PA
R
K
D
R
AN
ROSEBERRY
ADT
11,612 (3.1% HCV)
(2015)
AV
ADT
17,726 (2.5% HCV)
(2015)
RD
PL
ST
WARATA H ST
E
AV
Secondary Arterial
TC E
Clearway
RECREATION DR
GLADSTONE RD
IP
W
VIE
RD
AORANG I
Primary Arterial/
Overdimension
Vehicle Route
Birkenhead War
Memorial Park
Y
CIT
BIRKENHEA D AVE
W
A
TO
AL
LYDIA AVE
ADT
21,370 (3% HCV)
(2014)
PUP
TUI GLE N
UK E
K ST
VE
BAN
ADT
1,961 (1.4% HCV)
(2014)
ST
MOORE
RD
AV
E
S
GL
I
CRES
TO
IA
Willow Park
School
AY
SW
IN
LL
WE
LV
SY
S
CE
AC
MC D O
ST
ADT
1,698 (1.5% HCV)
(2014)
PL
PL
FAX AVE
P
Y CR ES
AVE
VERBENA RD
BY
S
TON T
EL
P
M
HOB
E
VANDELEUR AV
T LE
O
C
GRE
T
ADT
10,302 (1.9% HCV)
(2014)
D
AN
AY
SP E E
LL
AW
E
AV
ADT
21,046 (3.0% HCV)
(2014)
EN
AW N
EL
TR
N
LY
RD
ADT
7,685 (2.5% HCV)
(2015)
AN
ST
N PL
ST
PO
HIG
S
ER
RD
CH
AR
McFetridge
Park
LM
NTO
CAS
RD
ADT
8,311 (2.4% HCV)
(2015)
Eskdale
Reserve
D
BR
EL
M AYFI D RD
E AL
OE
L
D D
R
HE
AT
H
FOR
TH
E
WI
RD
E D
RD
E
BEAT R I C
OODC OT
AG I N
ADT
470 (1.3% HCV)
(2012)
VE
BRU
RD
K
PAR
AIN
DOM
O RT
S RD
ERT
ADT
7,263 (2.1% HCV)
(2012)
DA
L
Marlborough
School
ADT
841 (3.6% HCV)
(2014)
!
ROB
ES
K
AV
ADT
4,586 (4.5% HCV)
(2012)
11
ED
G
LL
E
RI
RD
Windy Ridge
School
LRY R
D
ST
PL
COU RT
EN
RD
D
R
E
C
U
MA
PL
R C EL
LE
AN
ST
E
ER
Glenfield
Intermediate
TW
PEACH RD
ADT
2,893 (1.3% HCV)
(2014)
AH
SE
AV
IE
ADT
10,485
(2009)
YA
VE
AR
R
ES S A D
NT
TLE
TAM
CO
BE
N
IA
CHIVA
Glenfield
Primary
GEDIN PL
SE
CA
ME
LO
T
GL
HI
L LSIDE
D
R
D CRES
ADT
10,580 (3.4% HCV)
Glenfield
Kaipatiki
(2015)
College
Reserve
PL
EN
Currently Glenfield Road has a two hour, twoway peak volume in the order of 2,200 vehicles
which is forecast to increase to in the order of
3,000 vehicles by 2036. The corridor generally
has one lane in each direction with short
stretches of flush median, on-street parking and
clearways. In the five years from 2009 to 2013, 1
fatal and in the order of 60 injury crashes have
occurred along the corridor, with the majority
occurring at intersections. The crash history
for the corridor is discussed in greater detail in
Section 2.2 of Appendix B.
GL A D
AV E
KAIPAT IKI RD
N
EE
ND
AL I
KA
NU
MA
RD
ROS
Y S AVE
continued
Introduction
continued
1.3.2 Pedestrians
The footpaths along the corridor vary in width and are discontinuous
over some sections (refer Figure 1.6). Along the length of the corridor
there are six signalised crossings and three pedestrian refuge crossings
with long stretches without any crossing facilities. A number of
pedestrian crashes have occurred in close proximity to bus stops in
locations with no crossing facilities.
12
The Kaiptiki Local Board has developed a network plan which proposes
a number of walking and cycling connections within and between local
parks, open spaces and reserves within the local board area (refer Figure
1.5). This is discussed further in Section 4.3 of Appendix A.
Introduction
continued
ORD
U NNYFIELD
RO
AD
BE
W
!"
DRI
VE
KI
Kaipatiki
Reserve
EL
OT
PL A
"
W
NT
LE
EF
EW
RU
RO
O RTH
O
R
AD
AD
AD
ET
POWRIE STREET
LA
ELD RO
AD
GL ENFI
E
ZION ROAD
AD
RV
IC
SE
Kauri Glen
Reserve
L EN
Northcote
College
ON EWA RO AD
A X AV
EN UE
E
AV E NU
ROSE
PARK AVENUE
LE
HU KA RO A
AN
UE
HI
LL
PA
RK
OR
DE
T IL N AV
EN
S
LI
IN
G
RO
A
EL
UE
UE
ROAD
E
AV
N
AY
W
TO
AL
E
AV
ROA
KAURI G
R O AD
Birkenhead
Primary
ET
S
CE
ET
RE
VIEW D RIV E
Y
RY B PA SS
BU
RE
AC
MO KO
IA
AY
AW
AN
AN
EB
UE
W
"
W"
GH
HI
U KE
RO
"
W
No Crossing
200
PU P
ACE
AORA NGI PL
RR
BE
ST
TUI GLE N
"
W
Signalised Crossing
A
SE
EL
ESCENT
CR
EET
AVE
StudyCorridor
LL
Challenging pedestrian
crossing of side road
VI
YL
Willow Park
School
E
OR
MO
R
K ST
"
W
NU
Birkenhead War
Memorial Park
R
VE
Signalised
Crossings
VE
BAN
"
W
TR
E
UE
E
DO W
MC
"
W
AD
RO
Pedestrian Refuge
Crossings
RA
"
W
E
NU
N
OU
E
AV
EN
AT T
TB
MON
A
"
W
E RO AD
OG
IN G S
T REE T
N
AVE
STREET
No Footpath
Walkway
CE
"
W
ESKDAL
WN
LY
ND
EN
CH
R
"
W
DO
U
N
Y P
WN
ELA
TR
D
N ROA
"
W
E
AV
W
"
W"
O AD
NAT IO
ST
BY
Bus Stops
CORO
Small section of
bus stop / footpath
HOB
STREE
T
DR
OA
"
W
Eskdale
Reserve
ON
T LE T
NF
OA
R
LD
E
TR
ROA
A IN
DOM
"
W
I EL
IHAU P LA C
K
PAR
D
Incomplete
A
RO
A
crossing
V EL M
across
Westfield Rd
FAIRF
McFetridge
Park
FI E
G LE N
UR
CO
IN
IG
AG
RO
AD
OA
TS R
BER
HIW
VERBENA ROAD
"
W
GL
E
WIT
H
RO
VE
VE
RI
"
W
Pedestrian crashes
resulting in injury
ROA
O ODCO
TE
AD
AVENUE
E UR
D EL
VAN
CA S
M AIN
I
DR
"
W
"
W
E
NU
KA AV E
IS
E R PAT
E QU
IK
Marlborough
IR
O
AD
School
AD
O
R
S
ER
H
C
AR
CH
UE
EN
AV
E
AV
RI
LE
E
ER
RO
ST
OR
H
UG
"
W
AV
IE
W
S TR E E T
D O W NING
"
W
EL
TW
AR
"
W
Small section of
bus stop / footpath
BAL
CE
ROAD
ST R E
RO
13
RL B
MA
Windy Ridge
School
ED
G
U
LRY R
O AD
H
AC
W
PO
VE
AH
CO
RI
ESSA D
NT
AN
ST
M
TA
SE
W
AI
PA
Glenfield
Primary
AV
EN
CHIVA
RO
Glenfield
Intermediate
Glenfield
College
CRESCENT
IP
AT
I
AM
KA
A
AN
DI
"
W
PE
D RI
AD
E
ID
N
MA
RO
A
UK
HILLS
VE
"
W
AD
Introduction
continued
D
R
RD
DOWNING
CO
RD
AN
BIRKENHEAD AVE
E RD
RD
E
AV
BR
RD
EW
VI
N
A
CE
O
RAL
EIGH
RD
RAYMOND TCE
RD
Kauri Glen
Reserve
ONEWA RD
FAIR
HI
NE
M
ST
AVE
IEW
EAV
VALLEY R D
HUKA R
Northcote
College
GLADSTONE RD
GLEN RD
Y BYPA SS
UR
HB
HIG
ZION RD
KAURI
ROSEBERRY
ST
Y CRES
VERBENA RD
E
AV
TC E
PL
AIN
RD
TO
AL
LYDIA AVE
W
VIE
AORAN G I
BAL
M
A
EB
Willow Park
School
TUI GLE N
P
M
CO
Birkenhead
Primary
RD
COLON IAL
DR
E
POR R
IT T AV
ST
MAHARA AVE
ST
A VIE
W
I
LV
SY
N
TO
MOORE ST
UK
PUP
CIT
14
L CRES
K
BAN
AV E
BARLO
400
Meters
W P600
L
WARATAH ST
E
Cyclist crashes resulting
in injury
AV
Cycle Connector
MOKOIA RD (ACN)
E
AV
!
Steep uphill approach with
narrow lane widths.
CHELSE
DR
RD
HI
GH
D
EN
Birkenhead War
Memorial Park
EN
ATT
TB
UN
O
M
RO G
RD
S
AY
AW
E
AN
ST
AV
EN
ND
LY
AVE
RD
PL
L
WE
MCD O
INGLIS ST
ION P
OR
GRE
TE
L
RR
VE
200
RD
D
EL
FI
BY
HOB
VANDELEUR AVE
RD
RD
N
NATIO
CORO
CH AVE
M O NAR
SP E E
Eskdale
Reserve
I LL
KH
PAR
Y
WN
E LA
TR
RD
AIN
DOM
AL
E
RS
Shared Path
E
CH
OODCOT DR
E
N
LE
G
L
HIWIHAU P
N PL
NTO
BRU
ON ST
LET
C AST
PA
RS AVE
UE
PARK AVE
W
ITH
E
W
AI
EQ
CH
LM
VE
DR
LE
AN
ST
E
ER
AH
S RD
ERT
ROB
ES
KD
E
AV
Marlborough
Dual lanes southbound on Glenfield
Rd AR
McFetridge
School
with narrow lane width and no shoulder.
Park
RD
Windy Ridge
School
RLB
H
UG
O
OR
E
AV
MA
RD
ST
L
EL
TAM
SE
AV
IE
W
RD
R
ESS A D
NT
CO
RD
CE
U
L
M
A R EL P
C
FAX AVE
H
AC
PE
Glenfield
Intermediate
TW
AR
CH
DIN PL
GE
SE
A
AN
DI
CHIVA
LRY
Glenfield
Primary
W
AV
ER
LE
Kaipatiki
Reserve
CA
ME
LO
TP
AV
E
Glenfield
College
KA
IPA
TIK
I
DR
FOR
D
HE
PL
EN
GL
L
MAYFIE D RD
AT
H
RD
RD
KA
D
N
LI
NU
MA
A
ROS
1.3.3 Cycling
Introduction
SUNNYFIEL
AV
E
EY
RL
W
AV
E
BE
D OWN IN
"
EY
E
AV
H
UG
RI
CH
U
EQ
RD
H
HIG
GL
EL
R
RAYMOND TCE
"
Kauri Glen
Reserve
WARATA H ST
""
ZION RD
Northcote
College
ONEWA RD
D
H UKA R
ST
AVE
IEW
E AV
HI
NE
FAI R
ROSEBERRY
E
C
O
RAL
EIG
HR
D
FAX AVE
D
R
AN
RD
IE
GLADSTONE RD
M AIN
RD
VALLEY R D
BAL
TC E
PL
L RD
W
VIE
Birkenhead
Primary
CO LON I A
DR
E
IT T A V
C HE L SE
A VIE
W
BARLO
400
Meters
W P600
L
P OR R
200
CIT Y
AORANG I
MOKOIA RD
RD
RECREATION DR
MAHA RA AVE
"
AV
AN
LYDIA AVE
UK E
PUP
VE
Birkenhead War
Memorial Park
MOORE ST
TUI GLE N
ST
P
Y CR ES
PA
RK
GL
I
VERBENA RD
S
LL CRE
K ST
Bus Stop
ST
WE
BAN
"
TO
AL
"
N
E
PL
G
RO
TO
IA
Willow Park
School
EL
MC D O
"
P
M
LV
SY
AY
SW
IN
D
LR
HIL
O
C
PL
S
CE
AC
ST
D
AN
AVE
S
TON T
LL
AY
BY
"
E
AV
GRE
T
" SP E E
"
V
N A
A
H
HOB
E
VANDELEUR AV
TE
RC
Eskdale
Reserve
DA
L
M ON
B AT
NT
U
AW
ION P
OR
EN
AW N
EL
TR
"
N
LY
"
RD
AN
ST
AIN
DOM
E
AV
IP
BR
AV
I
NF
RD
Study Corridor
W
A
N RD
NAT IO
LE
N PL
L
HIW IHAU P
NTO
K
PAR
"
RD
ST
CORO
No seating or
shelter provided
VE
IM
S RD
ERT
BRU
ES
K
T LE
S
ER
LM
HE
T
T S
"
CAS
CH
RD
E
BEAT R I C
EN
UR
CO
IN
AR
ROB
RD
McFetridge
Park
School
E
FI
BL
AG
"
Windy Ridge
School
TH
VE
RD
PL
COU RT
EN
RD
E D
ST Marlborough
LD
LE
E
ER
OODC OT
OR
E
AV
S
ER
N
LI
OR
ST
Bus layover
AV
AH
LRY R
D
ED
G
AV E
G ST
RL
MA
"
"
SE
AV
IE
TL
"
15
D
R
E
C
U
MA
PL
R C EL
LL
H RD
Glenfield
Intermediate
PO
R
ES S A D
NT
AN
ST
TAM
CO
AC
PE
TW
GEDIN PL
SE
DR
EL
M AYFI D RD
E AL
OE
L
D D
R
""
"
CHIVA
Glenfield
Primary
IA
AR
KA
IPA
FOR
HE
AT
H
TH
E
CA
ME
LO
T
RD
KI
TI
"
WI
Kaipatiki
Reserve
HI
L LSIDE
RD
Glenfield
College
"
D
R
D CRES
PL
EN
GL A D
AV E
GL
N
EE
ND
AL I
KA
NU
MA
RD
ROS
Y S AVE
continued
Introduction
continued
16
Introduction
continued
1.4
17
Introduction
continued
VE
HILLS
D RI
RO
AD
EL
BE
OT
PL A
C
NT
LE
AV
EN
WIT
H
ROAD
RU
B
AD
ST R E E
RS
H
IG
H
O ODCO
TE
VE
RI
AR
McFetridge
Park
AD
V EL M
RO
E
TR
ET
NAT IO
D
N ROA
LA
GL ENFI
N
OU
EN
AT T
TB
E
AV
E
NU
UE
VE
UE
UE
E
UE
Y
RY B PA SS
BU
AD
Kauri Glen
Reserve
ZION ROAD
Northcote
College
ON EWA RO AD
HU KA RO A
D
Birkenhead
Primary
200
400
A X AV
EN UE
BIRKENHEAD AVENUE
E
AV E NU
ROSE
R O AD
E
AV
ROAD
MO KO
IA
GH
HI
ROA
KAURI G
ET
RE
TO
AL
L EN
LACE
AORA NGI P
Light Industry
Public Open Space - Conservation
ET
600 Meters
FAIRF
LE
RO
A
RO
Heavy Industry
RE
TUI GLE N
Business Park
U KE
PARK AVENUE
HI
LL
PA
RK
OR
PU P
EET
NU
ST
AY
W
Birkenhead War
Memorial Park
RR
BE
AD
R
K ST
ESCENT
CR
DE
T IL N AV
EN
S
LI
AD
RO
LL
E
OR
MO
BAN
General Business
S
CE
IN
G
E
DO W
MC
AVE
Mixed Use
AC
UE
City Centre
N
AVE
C
Town Centre
VI
YL
Willow Park
School
BY
STREET
OG
Local Centre
CH
R
E
AV
MON
A
HOB
R
N ST EET
TR
E
AN
EB
ELD RO
AD
CE
Y P
WN
ELA
TR
U
N
ROA
AY
AW
AN
E
AV
IHAU P LA C
LY
ND
EN
ST
ROA
A IN
DOM
Neighbourhood Centre
ER
HIW
K
PAR
CORO
Eskdale
Reserve
Single House
O AD
Special Purpose
ROA
Marlborough
School
UR
CO
IN
R
RT S
Study Corridor
M AIN
E
NU
AG
RO
AD
E
ROB
ST
E
AV
AD
RO
VE
AD
AVENUE
E UR
D EL
VAN
VERBENA ROAD
E
E QU
CH
UE
EN
AV
OR
H
UG
E
AV
S TR E E T
I
DR
RO
TO
CA ST LE
BAL
RO
O RTH
D O W NING
RL B
MA
RI
LE
E
ER
AV
IE
W
Windy Ridge
School
18
EW
AD
EL
TW
AR
H
AC
W
PO
VE
AH
CO
RI
ESSA D
NT
AN
ST
M
TA
SE
W
AI
PA
O
R
CE
LRY R
O AD
ED
G
U
PE
Glenfield
Primary
EF
Kaipatiki
Reserve
OR
D
DRI
VE
KI
CHIVA
RO
Glenfield
Intermediate
Glenfield
College
CRESCENT
IP
AT
I
AM
KA
A
AN
DI
U NNYFIELD
A
UK
E
ID
N
MA
D
OA
Problems
Pedestrian network
The problems identified with the pedestrian network are captured in
Figure 1.6 and include the following:
19
Problems
continued
Cycling network
The problems identified with the cycling network are captured in Figure
1.7 and include the following:
20
Problems
continued
Connections between the town centre and Westfield Mall are poor
with little interaction between the two areas. There are multiple
vehicle accesses to the Westfield Mall but few which provide for other
modes. The nature of access to the mall provides an inhospitable
environment for pedestrians and promotes car trips.
Figure 2.2 Glenfield Road between Bentley Ave and Kaipatiki Road (looking south)
21
Outside of the Glenfield Town Centre the problems associated with place
and urban amenity are closely linked to the problems in the pedestrian
network. For example, the majority of the corridor has narrow footpaths
with grass berms. This is not consistent with the typical look and feel
of an arterial road and does not allow for street furniture, lighting and
landscaping appropriate for an arterial road. Improving the pedestrian
network will support an enhanced interface with the places along
Glenfield Road.
Problems
continued
Section
Problem / issue
Section 1
a) The place function within the Glenfield Town Centre is dominated by vehicle movements through the area
b) The pedestrian environment in the town centre is poor
c) Connections between the town centre and Westfield Mall are poor for pedestrians
d) It is difficult and unsafe for pedestrians to cross Glenfield Road midblock
e) The pedestrian longitudinal continuity on the west side is poor
f) The access road adjacent the Mc Donalds is difficult to cross
g) No cycle provision northbound
h) No cycle provision at intersections
i) Pedestrian crossings are missing at the Bentley Ave intersection and in places across the Westfield access
j) Bus stops/layovers on the eastern side adversely affect amenity
k) The bus stop on the western side is short and can be difficult for two buses to access at the same time
Section 2
a) In the last five years there have been cycle and pedestrian crashes at the Downing Street and Kaipatiki Road
intersections with Glenfield Road
b) Cycle facilities are incomplete and inconsistent
c) No cycle provision at the Downing and Kaipatiki intersections with Glenfield Road
d) The side road intersection of Peach Road has poor pedestrian crossing provision
e) Footpaths are narrow and of a low standard
Section 3
a) Dual lanes southbound with no shoulder alongside the Oruamo Domain create a poor environment for cyclists with no
specific cycle facilities
b) There is no footpath on the eastern side of Glenfield Road and pedestrians travelling north-south must detour along
High Road or through Oruamo Domain
c) There are no pedestrian crossing facilities on this section
d) The side road intersections of High Road and Glenfield Road have poor pedestrian crossing provision
e) Footpaths are narrow and of a low standard
Section 4
a) The side road intersections of Capilano Place, Roberts Road and Park Road have poor pedestrian crossing provision
b) There are a number of safety issues at the Roberts Road intersection for pedestrians, cyclists and general vehicles.
c) There are no pedestrian crossing facilities on this section
d) The southbound bus stop near Roberts Road has poor visibility of approaching buses
e) Pedestrian longitudinal connectivity on the western side of the corridor is poor
f) Footpaths are narrow and of a low standard
g) There is no cycle provision on this section
22
Problems
continued
Section 5
a) There is no footpath on the western side of the corridor adjacent to Eskdale Reserve nor on the eastern side adjacent to
217-227 Glenfield Road
b) There are a number of safety issues at the Coronation Road intersection for pedestrians, cyclists and general vehicles.
c) The side road intersection of Coronation Road has poor pedestrian crossing provision
d) There is no cycle provision on this section
Section 6
Section 7
23
The ideal future state sets the long-term vision for the Glenfield
Road corridor. This has been defined with reference to Auckland
Transport and Auckland Council strategies and policies and
through input from the technical stakeholder groups. The ideal
future state is captured in a file note in Appendix B and defined
below:
Pedestrian network
A safer, easier and more convenient environment for all which follows
Universal Design principles.
Cycling network
24
25
26
The preferred option (shown in Figure 4.2 and Figure 4.4) aims to shift
the focus of this section from vehicle movement to enhancing the place
function, in line with the technical stakeholder desires to create a more
pedestrian friendly environment. To achieve this shift and improve
the pedestrian environment, the following elements are considered
necessary for this section of the corridor:
The future transport and land use outcomes for the town centre are
closely linked, with the success of one dependent on the success of the
other. A strategic vision for the town centre and an associated town
centre plan should be prepared to guide the future development of the
town centre. This should include a full investigation into the transport
issues identified above.
Increase footpath widths and provide more public space with more
street furniture and landscaping
27
A zebra crossing on the left-turn slip lanes into and out of the
Westfield Mall
28
parking on private
property
parking on private
property
4.4m
footpath
footpath
boundary
boundary
1.7m
raised traffic island
3.0m
traffic lane
3.1m
traffic lane
3.0m
traffic lane
3.1m
traffic lane
30m road reserve
0.8m
raised median
3.1m
right turn lane
3.0m
3.0m
3.0m
traffic lane
3.0m
traffic lane
2.1m
protected cycle
3.3m
bus stop/parking lane
4.5m
footpath
4.5m
footpath
boundary
boundary
29
30
7.0m
footpath & grass verge
2.1m
protected
cycle lane
5.4m
footpath & grass verge
boundary
boundary
6.7m
traffic lanes
3.0m
traffic lanes
2.5m
flush
median
2.8m
flush
median
3.0m
traffic lanes
3.2m
traffic lanes
6.5m
traffic lanes
2.1m
protected
cycle lane
1.5m
cycle lane
5.5m
footpath & grass verge
5.5m
footpath & grass verge
boundary
boundary
31
32
33
boundary
1.5m
cycle lane
3.2m
traffic lane
3.0m
footpath & berm
3.0m
footpath & berm
6.0m
traffic lane
3.0m
traffic lane
3.2m
bus lane
7.0m
traffic lane
3.5m
traffic lane
2.1m
protected cycle lane
3.5m
crawler
continued
boundary
34
35
2.5m
grass verge
4.5m
property access road
2.5m
grass verge
2.3m
footpath
2.1m
protected
cycle lane
7.0m
traffic lane with on street parking
3.2m
traffic lane
3.2m
traffic lane
3.2m
bus lane
7.0m
traffic lane with on street parking
9.0m
property access road
9.0m
property access road
boundary
boundary
4.5m
property access road
continued
36
Figure 4.12 Coronation Road / Glenfield Road bus and cycle priority
3.0m
unformed verge
4.7m
traffic lane
Eskdale
reserve
2.1m
protected
cycle lane
3.2m
traffic lane
2.1m
footpath
swale
boundary
37
3.2m
traffic lane
2.5m
flush median
3.5m
bus lane
6.0m
traffic lane with on street
parking
2.1m
protected
cycle lane
1.2m
footpath
7.6m
grass verge (varies)
boundary
boundary
Eskdale
reserve
continued
boundary
The main conflict on this section is between bus and cycle priority,
particularly in the locations constrained by the existing retaining walls
such as at the Pupuke Road intersection. The cantilever footpath solution
illustrated in Figure 4.16 reduces this conflict, allowing high priority for
pedestrians and cyclists while providing some bus priority.
38
39
2.1m
protected
cycle lane
3.0m
traffic lane
3.2m
bus lane
2.1m
protected
5.5m
traffic lane with on street parking
footpath
width varies
3.5m
footpath and grass berm
continued
5.5m
traffic lane with on street parking
1.5m
footpath
boundary
boundary
4.5m
grass berm and retaining wall
40
Figure 4.18 Glenfield Road / Pupuke Road intersection - southbound bus priority
41
Road intersection and allows cyclists to bypass the signals. The steep
grade of the access road will be challenging for some cyclists. Therefore
if sufficient land is acquired for the intersection upgrade, a northbound
facility on road with a more manageable grade could potentially be
provided. A southbound cycle facility, including a connection into
Pupuke Road, could also be provided. This should be considered during
further investigation and design of the intersection.
42
Figure 4.19 Section 7 - Eastern footpath and grass berm looking north
43
boundary
2.1m
protected
cycle lane
3.1m
footpath
existing
road level
3.0m
traffic lane
5.5m
traffic lane with on street parking
3.0m
traffic lane
3.2m
bus lane
5.5m
traffic lane with on street parking
grass berm
width &
slope vary
2.1m
protected
cycle lane
3.3m
grass verge
2.5m
footpath
2.5m
footpath
boundary
boundary
3.7m
footpath & grass berm
continued
boundary
44
continued
4.8 Summary
RD
POWRIE ST
P
Y CRES
TILDEN
AV
E
BIRKENHEAD AVE
BR
FAIR
HUKA R
PARK AVE
CO
RD
AN
ST
AVE
IEW
EAV
FAX AVE
HI
GH
HI
LL
IN
GL
IS
ST
SUNNYFIEL
DR
L
MAYFIE D RD
AV
E
Y
W
AV
ER
LE
GL
PA
RK
VERBENA RD
EAL
Y S AVE
T
S
OE
L
KA
IPA
TIK
I
DR
AT
H
HE
FOR
D
W
ITH
E
ROSEBERRY
Northcote
College
GLADSTONE RD
AIN
RD
RD
EW
VI
AN
E
C
O
RAL
EIGH
RD
RD
VALLEY R D
E
AV
Kauri Glen
Reserve
ONEWA RD
LYDIA AVE
BAL
M
S
AY
AW
E
AN
ST
AV
EN
ND
LY
RD
GLEN
Y BYPA SS
UR
HB
HIG
HI
NE
M
RD
RAYMOND TCE
KAURI
ZION RD
PL
W
"
RD
W
"
Birkenhead
Primary
RD
COLON IAL
A VIE
W DR
BARLO
400
Meters
W P600
L
TC E
AORAN G I
MOKOIA RD
CHELSE
W
VIE
W
"
MAHARA AVE
No Crossing
WARATAH ST
E
AV
Signalised Crossing
LM
VE
RD
UKE
PUP
CIT
I
LV
SY
N
TO
AY
W
SS
CE
AC
StudyCorridor
Signalised
Crossings
W
"
RECREATION DR
Walkway
200
N
GL E
Birkenhead War
Memorial Park
PL
Willow Park
School
TUI GLE N
ER
V
Improved
side road
crossing
P
M
CO
E
AV
W "
"
W
WNING S
MOORE ST
ST
AV E
EN
DO
TO
AL
K
BAN
RO G
Pedestrians on Access
Road R
MC
W
W"
"
RD
RD
PL
CRES
E LL
D OW
AV
E
McFetridge
Park
D
N
LA
EL
ST
BEN
TLE
Y
E
TT
BA
RC
GRE
TE
L
D
R
Reduced traffic
volumes & speeds
and improved
crossing facilities
through town centre
SP E E
W
"
VE"
LINZ and
Eagle Technology
W
NA
UNT
MO
NA
O
LE
C AST
ION P
OR
Future Bus
S Stops
TON T
RD
E
AV
E
RD
BEAT R IC IELD
F
ST
W
"
RD
E
AV
M
EI
ST
W
"
Y
WN
E LA
TR
O RT
L
EL
H
EN
T
UR
O
AL
E
W
"
RD
Eskdale
Reserve
New Footpath
PA
WH
"
C
AR
RS
NATION
CORO
D
EL
FI
AIN
DOM
ST Marlborough
LRDD
School
W
W "
"
K RD
PAR
Pedestrian Crossing
Points
W
AI
E
FI
BL
OODCOT DR
E
TW
AR
CH
KA ER S
U
EQ IPAT
CH
IK
I
NG
LI
W
"
E
AV
C
AGI N
"
W
W
"
E
AV
N
LE
G
RD
H
UG
O
OR
ST
E
POR R
IT T AV
RLB
MA
AVE
45
RIE
W
"
AVE
RD
CE
U
L
M
A R EL P
C
RD
ED
ST
BY
HOB
DOWNING
W
PO
BE
NT
LE
Y
RD
S RD
ERT
ROB
ES
KD
Glenfield
Intermediate
W
"
W
"
L
HIWIHAU P
RD
LE
AN
ST
H
AC
PE
A
AN
DI
CHIVAL
RY
Glenfield
Primary
PL
COURT
EN
RD
VANDELEUR AVE
W
"
CA
ME
LO
TP
Path through
Oruamo Domain
N PL
NTO
BRU
R
ESS A D
NT
CO
Windy Ridge
School
ST
Kaipatiki
Reserve
DR
Glenfield
College
E
ER
AH
D
R
DIN PL
GE
SE
TAM
D CRES
SE
AV
IE
W
PL
EN
GL
AVE
GLA D
D
N
LI
4.8.1 Pedestrians
N
EE
RD
A
ROS
N
MA
A
UK
continued
SUNNYFIEL
CA
ME
LO
T
W
AV
ER
L
E
AV
CH
H
GL
P
Y CR ES
AV
E
D
R
AN
RD
Kauri Glen
Reserve
RD
ZION RD
Northcote
College
ONEWA RD
0
ST
200
400
600 Meters
AVE
IEW
HI
NE
E AV
H UKA R D
E
C
O
RAL
EIG
HR
D
FAX AVE
BI R KENHEAD AVE
ROSEBERRY
IE
RAYMOND TCE
PARK AVE
TILDE
N
PA
RK
HI
IN
LL
GL
I
VERBENA RD
RD
GLADSTONE RD
M AIN
AV
AN
VALLEY R D
BAL
IA
GLEN
L RD
AY
TC E
Birkenhead
Primary
CO LON I A
W PL
E
R IT T A V
BARLO
P OR
C HE L SE
A VIE
W DR
RD
KAURI
ST
MOKOIA RD
LYDIA AVE
W
VIE
PL
LV
SY
AY
SW
Y
CIT
AORANG I
IP
MAHARA AVE
W
A
TO
S
CE
AC
UK E
PUP
WARATA H ST
PL
ST
MOORE
RECREATION DR
E
AV
AW
Birkenhead War
Memorial Park
P
M
VE
D
AN
O
C
TUI GLE N
E
AV
N
E
LL
TO
AL
CRES
E LL
RD
G
RO
PL
ST
EL
K
BAN
VE
EN
V
N A
Willow Park
School
MC D O
ST
TE
B AT
NT
U
RC
GRE
T
AVE
S
TON T
SP E E
ION P
OR
M ON
N
LY
WN
E LA
TR
AN
ST
RD
BY
T LE
BR
RD
AV
ST
ST
T
UR
EL
AIN
Eskdale
Reserve
HOB
E
VANDELEUR AV
DA
L
LM
IM
CO
I
NF
RD
ES
K
RD
NATI ON
CORO
LE
N PL
L
HIW IHAU P
NTO
K
PAR
DOM
CAS
CH
RD
VE
HE
AR
S
ER
E
BEAT R I C
EN
E D
McFetridge
Park
School
E
FI
BL
RD
ST Marlborough
LD
N
LI
AG I N
HIG
E
AV
S
ER
BRU
U
EQ
FAI R
S RD
ERT
RD
RI
RD
ROB
TH
AV
H
UG
Windy Ridge
School
OR
LL
ST
OODC OT
O
RLB
PL
COU RT
EN
RD
DR
AV E
G ST
MA
ST
TH
E
WI
EY
TW
D OWN IN
TL
D
R
E
C
U
MA
PL
R C EL
LRY R
D
ED
G
LE
E
ER
Glenfield
Intermediate
AR
H RD
AH
SE
AV
IE
AC
BE
PO
ES S A
NT
AN
ST
TAM
CO
DR
PE
CHIVA
Glenfield
Primary
IA
AV
E
Kaipatiki
Reserve
EY
KA
IPA
TIK
I
Glenfield
College
FOR
D D
R
GEDIN PL
SE
4.8.3 Cycling
46
EL
M AYFI D RD
E AL
OE
L
D CRES
HI
L LSIDE
RD
HE
AT
H
AV E
D
R
PL
EN
GL A D
ND
AL I
GL
N
EE
ROS
KA
NU
MA
RD
Y S AVE
continued
SUNNYFIEL
RL
H
UG
E
AV
U
EQ
RD
H
GL
Y CR ES
AV
E
D
R
BIRKENHEAD AVE
ROSEBERRY
Kauri Glen
Reserve
RD
ZION RD
Y BYPA SS
PARK AVE
TILDE
N
PA
RK
HI
IN
LL
GL
I
VERBENA RD
AN
Northcote
College
ONEWA RD
ST
200
400
600 Meters
AVE
IEW
HI
NE
E AV
H UKA R D
GLADSTONE RD
RD
RD
VALLEY R D
M AIN
GLEN
BAL
IE
RAYMOND TCE
KAURI
TC E
PL
R
BU
AY
RD
E
C
O
RAL
EIG
HR
D
LYDIA AVE
W
VIE
AORANG I
DR
L RD
W PL
GH
AV
AN
AY
SW
Y
CIT
S
CE
AC
UK E
PUP
Birkenhead
Primary
CO LON I A
BARLO
E
P OR R
IT T A V
C HE L SE
A VIE
W
HI
TO
IA
ST
MOORE
TUI GLE N
MOKOIA RD
AW
S
LL CRE
K ST
MAHARA AVE
Bus Lane
PA
LV
SY
WARATA H ST
W
AI
P
M
PL
TO
AL
RECREATION DR
ST
WE
Birkenhead War
Memorial Park
E
AV
D
AN
PL
BAN
LL
O
C
E
AV
AVE
VE
VE
47
EL
BY
N
E
EN
RD
G
RO
V
N A
Willow Park
School
MC D O
TE
RC
GRET
ST
B AT
NT
U
SP E E
ION P
OR
M ON
N
LY
D
AW N
EL
TR
AN
ST
HOB
E
VANDELEUR AV
S
TON T
RD
AV
ST
RD
Eskdale
Reserve
R
ST
T
UR
EL
RD
AIN
DOM
RD
I
NF
N PL
L
HIW IHAU P
NTO
K
PAR
DA
L
LM
IM
CO
LE
BRU
ES
K
T LE
S
ER
NATI ON
CORO
S RD
ERT
CAS
CH
VE
HE
AR
RD
E
BEAT R I C
EN
McFetridge
Park
School
E
FI
BL
E D
AG I N
HIG
ST Marlborough
LD
FAX AVE
RD
ROB
RD
E
AV
S
ER
N
LI
Windy Ridge
School
FAI R
RI
CH
PL
COU RT
EN
RD
O RT
ST
OODC OT
AV
R
LBO
LE
E
ER
DR
EY
AV E
ST
R
MA
LL
D OWN IN G
EY
H RD
TL
TW
AC
AH
SE
AV
IE
LRY R
D
ED
G
D
R
E
C
U
MA
PL
R C EL
AR
WI
TH
E
W
AV
E
BE
PO
R
ES S A D
NT
AN
ST
TAM
CO
Glenfield
Intermediate
PE
GEDIN PL
SE
CHIVA
Glenfield
Primary
AV
E
Kaipatiki
Reserve
CA
ME
LO
T
IA
ST
Glenfield
College
BR
EL
M AYFI D RD
E AL
OE
L
KA
IPA
TIK
I
D D
R
FOR
HE
AT
H
D
R
D CRES
NPL
LE
HI
L LSIDE
RD
GL A D
AV E
ND
AL I
N
EE
ROS
KA
NU
MA
RD
Y S AVE
continued
Glenfield
College
NA
DR
EL
M AYFI D RD
W
AV
ER
L
TH
E
AV E
H
UG
E
AV
Marlborough
School
RD
H
HIG
GL
EL
AV
E
W
VIE
TC E
HI
NE
ST
NA
LE
BI R KENHEAD AVE
ROSEBERRY
PARK AVE
200
400
600 Meters
AVE
IE W
RD
HUKA R D
RD
ONEWA RD
E AV
M AIN
Northcote
College
VALLEY R D
BAL
GLADSTONE RD
GLEN RD
ZION RD
Birkenhead
Primary
CO LON I A L
W PL
E
I T T AV
BARLO
POR R
CHEL S E
A V IE
W DR
RAYMOND TCE
KAURI
MOKOIA RD
Kauri Glen
Reserve
PL
Parking Removed
IE
Existing Clearway
Removed
AORANG I
MAHARA AVE
IP
RD
FA X AVE
LL
HI
PA
RK
TILDE
N
S
GL
I
IN
D
LYDIA AVE
RD
AN
C
O
RAL
EIG
HR
D
AY
Y
CIT
AV
UK E
PUP
WARATA H ST
E
AV
MOORE ST
Birkenhead War
Memorial Park
SS
CE
AC
S
LL CRE
TUI GLE N
AN
WE
K ST
IA
BAN
C O RO
VE
TO
TO
AL
RD
Existing Clearway
Removed
P
M
LV
SY
PL
MC D O
ST
O
C
PL
FAI R
AVE
S
TON T
D
AN
Willow Park
School
BY
VERBENA RD
GRE
T
LL
ST
Y CR ES
AY
RC
HOB
E
VANDELEUR AV
DA
L
V
N A
SP E E
Eskdale
Reserve
TE
E
AV
M ON
B AT
NT
U
EN
AW
ION P
OR
N
LY
AW N
EL
TR
RD
AN
ST
AIN
DOM
RECREATION DR
W
A
BR
AV
RD
N PL
RD
ST
ST
EL
K
PAR
L
HIWIHAU P
NTO
IM
T
UR
I
NF
BRU
ES
K
VE
RD
NATI ON
CORO
T LE
S
ER
McFetridge
Park
LM
HE
CO
S RD
ERT
Flush Median
Removed
CAS
CH
RD
E
BEAT R I C
EN
AR
LE
ROB
RD
VE
BL
Windy Ridge
School
TH
E
AV
OR
AG I N
ED
PL
COU RT
EN
RD
OR
LL
OODC OT
RI
RD
RY R
D
TW
WI
LE
RL
MA
48
ED
G
NT
Crawler Lane
Removed
ST
CH IVAL
Primary
G ST
ST
D OWN IN
H RD
LE
SE
AV
IE
AC
BE
PO
R
ES S A D
NT
AN
ST
CO
AR
Reduction in general
capacity and speed through
townGlenfield
centre.
D
R
E
C
U
MA
PL
R C EL
PE
E
ER
CA
ME
LO
T
Glenfield
vehicle
Intermediate
AV
E
Kaipatiki
Reserve
GEDIN PL
SE
SUNNYFIEL
IA
D
EY
KA
IPA
TIK
I
D D
R
AH
E AL
OE
L
D CRES
PL
EN
AV E
GLA D
FOR
HE
AT
H
N
EE
TAM
GL
RD
KA
NU
MA
Y S AVE
Implementation plan
5.1
Pedestrians
49
5.2
5
Cycling
The section of the corridor, from Downing Street to Eskdale Road, has
been identified as a section where low-cost, cycling facilities could be
implemented in the short term, with minimal effect on road drainage
and on-street parking. South of Eskdale Road the corridor is narrower, the
topography varies, and there is more on-street parking. Low-cost, short
term cycle facilities south of Eskdale Road will likely require the removal of
on-street parking, and potentially a reduction in general vehicle capacity
at the Glenfield Road intersections with Eskdale Road and Pupuke Road.
Provision of cycle facilities in the short term on these sections of the
corridor would have immediate benefits, as currently there are no
dedicated cycle facilities over this length. The long-term vision for the
corridor is to implement protected cycle lanes in both directions along
the corridor. In the short term an alternative form of facility could be
implemented as a step towards the long-term vision, particularly in
locations where the corridor is constrained. This could include shared
paths and implementation of no-stopping lines to reallocate existing
parking for cycle facilities.
The implementation of new cycle facilities north of Downing Street
is dependent on resolving a number of other transport and land use
factors, and is likely to be linked to the upgrade of the Glenfield Town
Centre. However as indicated in Section 4.1, short term options such
as providing advanced stop boxes at the signalised intersection and
repainting the existing cycle facilities could be undertaken. The existing
shared path between Peach Road and Kaipatiki Road could be widened
in the short term by paving the existing grass berm.
Along the rest of the corridor, at existing signalised intersections, cycle
advance stop boxes and lead in lanes could be considered in the shortterm, whether or not cycle facilities are provided along the rest of the
corridor.
Implementation plan
continued
5.3
Public transport
5.4
The upgrade of the Glenfield Town Centre discussed in Section 4.1, will
require significant planning and investigation. An overall vision and an
associated town centre plan should be developed to guide the future
development of the town centre. As discussed above, a collaborative
approach between Auckland Council, Auckland Transport, Kaiptiki Local
Board and private land owners will be needed to ensure a high quality
outcome.
The capital cost of the town centre upgrade, which meets the ideal
future state of the town centre, is likely to be significant. Initial planning,
investigation and consultation could be undertaken in the short to
medium term with the view to undertaking the upgrade in the long term
as benefits can be demonstrated and funding becomes available.
A number of low-cost improvements for the town centre were identified
in Section 4.1. These improvements could be implemented in the short
term while the investigation of the full town centre upgrade is being
undertaken. The improvements will not necessarily require significant
changes to on-street parking, vehicle accesses and general vehicle
capacity.
5.5
General vehicles
As the corridor is upgraded over time and the facilities for pedestrians,
cyclists and public transport are implemented, on-street parking will be
removed and in some locations general vehicle capacity may be reduced.
As discussed above, clearways may be an option to retain some on-street
parking during off peak before full time bus lanes are implemented. A
staged approach to on-street parking removal is likely to lessen the effect
on adjacent land use, and assist with managing expectations for parking,
particularly as intensification occurs.
There are two existing projects to upgrade the Roberts Road and
Coronation Road intersections with Glenfield Road, which are currently
in design stage. The design of the two intersections will need to allow
for the priorities identified in Sections 4.4 and 4.5 above, as well as
addressing the existing safety issues. The upgrades of the intersections
are expected to be implemented in the short term.
50
Implementation plan
continued
Short
Package
Number
Identifier
Component
Key Benefit to
Medium
15/16
16/17
17/18
18/19
Long
19/20
20/21
Investigation /
design
Construction
OUTSIDE LTP
21/22
22/23
23/24
Design
Construction
24/25
25-30
$50,000
(additional
design cost for
existing project)
Design
Construction
$50,000
(additional
design cost for
existing project)
Design
Construction
1,000,000
2,800,000
Rational/Objective
Cycle Improvements
1.1 Downing Street to Eskdale Road
Project Description
Addresses
Deficiency
Intersection upgrades
Safety
PT
900,000
Investigation /
design /
construction
Construction
300,000
Investigation /
design
Investigation /
design /
construction
Construction
Safety
Investigation
Design
Construction
PT
1,100,000
5,800,000
Investigation
Design
Construction
Implementation of a southbound bus lane between The southbound approach to the Pupuke Road intersection
the Glenfield Road / Eskdale Road and Glenfield has been identified as one of the worst sections along the
Road / Pupuke Road intersections
corridor for bus operation. An upgrade may require land
take. If sufficient land is acquired, there is potential to also
provide for southbound cyclists at the intersection with a
connection into Pupuke Road.
2,700,000
Investigation
Design
Construction
Implementation of a southbound bus lane between The level of service for buses along the corridor is likely to
the Glenfield Road / Downing Street and Glenfield reduce in the future as general traffic volumes increase.
Road / Eskdale Road intersections
Increases in demand for public transport will further justify
the need for a southbound bus lane
400,000
Investigation
Design
Construction
Investigation
51
Implementation plan
continued
Glenfield Road Corridor Management Plan
Short
Package
Number
Identifier
Component
Rational/Objective
10,400,000
100,000
Investigation /
design /
construction
Investigation /
design /
construction
Cost Est
15/16
16/17
700,000
Investigation /
design
Construction
1,900,000
500,000
17/18
18/19
Long
19/20
20/21
21/22
OUTSIDE LTP
22/23
23/24
24/25
25-30
Pedestrian improvements
5.1 Improved crossing facilities on side
roads
BCR Likelihood
Medium
Project Description
Key Benefit to
Addresses
Deficiency
Investigation
Investigation
Design
Design
Construction
Construction
Investigation
Design
Construction
Investigation
Design
Construction
Renewal of existing footpaths including widening by Existing footpaths in some locations can potentially be
paving grass berms. Improved pavement surface
renewed and widened without significant changes to
finish
infrastructure along the corridor.
600,000
Renewal of existing footpaths including widening by Existing footpaths in some locations can potentially be
paving grass berms. Improved pavement surface
renewed and widened without significant changes to
finish
infrastructure along the corridor.
900,000
Investigation /
design
Construction
1,400,000
Investigation /
design
Construction
Renewal of existing footpaths including widening by Existing footpaths in some locations can potentially be
paving grass berms. Improved pavement surface
renewed and widened without significant changes to
finish
infrastructure along the corridor.
700,000
Investigation
Design
Construction
Renewal of existing footpaths including widening by Existing footpaths in some locations can potentially be
paving grass berms. Improved pavement surface
renewed and widened without significant changes to
finish
infrastructure along the corridor.
900,000
Investigation
Design
Construction
Upgrade of streetscape of Glenfield Road outside of The current streetscape and general urban amenity of
the Glenfield Town Centre including new
Glenfield Road is poor and inconsistent with typical arterial
carriageway and footpath lighting, landscaping and roads
street furniture
2,500,000
Investigation
Design
Construction
Investigation /
design
Investigation /
design
Investigation/
design /
construction
Construction
52
Appendix A
Land use and transport file note
File Note
Date
10 August 2015
Project No
ZB01674
Subject
1.
Introduction
File Note
2.
2.1
Glenfield Road (red line in Figure 1-1) forms a key north-south arterial in the Auckland North
Shore road network. The CMP project scope includes Birkenhead Avenue and Glenfield Road
between the Birkenhead Avenue / Onewa Road intersection in the south and the Glenfield Road /
Bentley Avenue intersection in the north.
Birkenhead Avenue and Glenfield Road are both classified as a Primary Arterial Road in the Draft
Integrated Transport Plan1. Birkenhead Avenue and Glenfield Road are also both identified as a
cycle connector on the Auckland Cycle Network (ACN) and part of the Frequent Transport
Network (FTN) in the bus network.
Figure 2.1 shows the projects to the north and south of the corridor which have recently been
completed or have been planned in the future. This includes the following CMPs:
Tawa Drive, Albany Expressway and Greville Road (TAG) CMP, AECOM, July 2013
Oteha Valley Road CMP, AECOM, December 2014
Onewa Road CMP, Flow, September 2014
A CMP was completed in 2010 by GHD for Albany Highway from Schnapper Rock Road to SH17.
The upgrade of this section of Albany Highway is currently under construction and will include
road widening to allow for general traffic lanes, transit lanes, on and off road cycle facilities and
wider footpaths.
The upgrade of the southern section of Albany Highway from Upper Harbour Highway to Sunset
Road is currently at detailed design stage. It will include road widening to allow for intersection,
bus, pedestrian and cycling improvements.
Immediately north of the Glenfield Road CMP study area, an upgrade has recently been
completed on Glenfield Road between Bentley Avenue and Sunset Road. The upgrade focused
on provision of on road cycle lanes.
File Note
2.2
Crash history
The New Zealand Transport Agencys Crash Analysis System (CAS) was used to examine the
crash history of the Glenfield corridor between 2009 and 2013. The locations of the crashes
during this period are illustrated in Figure 2.2. In total over the five year period, there were 194
crashes along the corridor with 1 fatal and 4 serious injury crashes.
As shown in Table 2-1, there were 10 reported crashes involving pedestrians and 3 involving
cyclists. In 2009 a pedestrian was killed when hit by a car on Glenfield Road near the Downing
Street intersection while crossing the road heedless of traffic. All of the 10 pedestrian accidents
involved a pedestrian being hit while crossing the road.
File Note
Fatal
Severe Injury
Minor Injury
Total crashes
Pedestrian
10
Cyclist
Vehicle
46
181
Total
57
194
Approximately 70% of all crashes in the corridor occurred at an intersection (132 crashes). Half of
the pedestrian accidents occurred at intersections. The distribution of the intersection crashes is
provided in Table 2-2.
Table 2-2 : Crashes at intersections
Intersection
Fatal
Severe
Injury
Minor
Injury
Total Injury
crashes
Total
Bentley Ave
18
Kaipatiki Road
32
Peach Road
Downing Street
High Road
Roberts Road
10
Coronation Road
24
Speedy Crescent
Eskdale Road
McDowell Crescent
Moore Street
12
Coroglen Ave
Pupuke Road
The Bentley Ave, Kaipatiki Road and Coronation Road intersections have had the greatest
number of crashes in the five year period from 2009 2013.
It can be seen that the Glenfield Road intersections with Bentley Ave, Kaipatiki Road, Downing
Street and Pupuke Road have all had, on average, at least one injury crash per year in the five
year period from 2009 2013.
The Coronation Road intersection has had, on average, five crashes a year in the five year period
from 2009 2013 including one serious and 2 minor injury crashes.
File Note
File Note
2.3
Walking facilities
Footpaths of varying widths (from approximately 1.5m 3m) follow the Glenfield Road/Birkenhead
Ave corridor over the majority of its length. Exceptions include, adjacent to the Eskdale Reserve
where the footpath is discontinued, and at points along the corridor where retaining walls create
residential vehicle traffic access lanes that merge with pedestrian traffic.
The map shown in Figure 2.3 highlights the issues and constraints for pedestrians in the area.
This includes the location of the pedestrians crashes discussed above.
File Note
File Note
2.3.1
Crossing facilities
Two types of crossing facilities are provided along the length of the corridor. These include
signalised pedestrian crossings at intersections, and mid-block pedestrian refuges. Figure 2.3
highlights the location and type of crossing facilities provided throughout the corridor. While not
included in Figure 2.3, it should be noted that pram crossings are also an important element to
providing universal access and a quality pedestrian environment within the corridor.
2.4
Cycling
A cycle lane is currently provided for in the northern part of the corridor between Bentley Ave and
Downing Street on the southbound direction only. Along the rest of the corridor, no cycling
facilities are provided.
No facilities such as advanced stop boxes and hand rails are provided at intersections within the
study corridor.
2.5
Public Transport
A number of buses make use of the Glenfield Road/Birkenhead Ave corridor. Existing bus service
numbers and their frequencies are shown below in Table 2-3. The frequencies of most routes vary
throughout the day, both within peak periods and outside of these.
Table 2-3: Glenfield Road/Birkenhead Ave existing bus service characteristics
Routes
Route Description
Section of corridor
used
Peak hour
frequency
Midday
frequency
951
Wairau Rd to
University
15
953
Windy Ridge to
Midtown
20
955
Bayview to Midtown
10
30
957
Birkenhead Wharf to
Albany Stn via Glfd Rd
30
30
958
Constellation Station to
Midtown via Glfd Rd
10
30
905
30
30
913
60
60
915
Bayview to Takapuna
30
30
911
30
30
945
30
30
File Note
Routes
Route Description
Section of corridor
Peak hour
Midday
used
frequency
frequency
945x
15
952
30
560
Glenfield to Massey
University
30
60
555
Pupuke Rd to Onewa
Rd
30
60
Three of the services operate over the full length of Glenfield Road/Birkenhead Ave corridor,
being the 954, 955 and 957 services. The other services operate over smaller sections of
Glenfield Road and Birkenhead Ave, with the 560, 915 and 945 services only operating north of
Kaipatiki Road , 911, 913, 952 and 90 operating through the mid-section of the corridor (between
Pupuke Road and Kaipatiki Road), and the 555 service only operating south of Pupuke Road.
2.6
General traffic
2.6.1
Traffic volumes
Existing traffic count information for the corridor has been extracted from the Auckland Transport
traffic count database. Counts in a number of locations have been displayed on Figure 2-4 and
include the proportion of heavy vehicles where available. Traffic counts on key connecting roads
have also been extracted for information.
Traffic volumes around the Glenfield Road / Moore Street intersection are the highest of the data
obtained with around 21,000 vehicles per day. The speed limit along the corridor is 50 kph.
File Note
10
File Note
2.6.2
The Operations, Planning and Performance team in Auckland Transport have provided a
snapshot of the current network performance for public transport on the corridor for May 2014. At
this time, construction was complete on Glenfield Road north of the Glenfield Town centre.
In the AM peak congestion can be observed in the northbound direction after the Kaipatiki Road
intersection operating at LOS D. All other northbound traffic operates at LOS B in the AM peak
with no noticeable congestion. In the southbound direction, the approach to Glenfield Town
Centre through Kaipatiki Road is LOS F. Also in the southbound direction, delay through the town
centre onthe approach to Coronation Road intersection experiences some delay operating at LOS
D. The southbound approach to the Pupuke Road intersection also operates at LOS D.
In the PM peak, the southbound direction north of the Kaipatiki intersection experiences severe
congestion (LOS E/F). In the northbound direction, severe congestion can be observed north of
Downing Street. Congestion can be observed in northbound direction approaching the Coronation
Road intersection and in the southbound direction approaching Pupuke Road. Both these
sections operate at LOS D.
Figure 2-5: Network Operation: Level of Service in AM Peak (left) and PM Peak (right)
11
File Note
2.7
Freight
The Glenfield Road and Birkenhead Ave corridor is part of the NZ Transport Agency
overdimension vehicle route. From here, the overdimension route makes use of Onewa Road to
travel towards the Northern Motorway southbound, playing an important role in the movement of
over dimension freight.
12
File Note
3.
3.1
The Glenfield Road/Birkenhead Ave corridor falls within the Kaip tiki Local Board area. The
Kaip tiki Board is bounded by the Waitemata Harbour and the Northern Motorway to the East.
Auckland Council prepares a demographic report card for each local board within the region. The
report card provides a snap shot of the social demographics of the area. The Kaip tiki area is
described as follows:
In 2013, there were 28,428 households in Kaip tiki 6 per cent of the regional count.
The median household income was $78,600 slightly higher than the regional median
at $76,500.
3.2
Glenfield Town Centre is located between Bentley Avenue and Downing Street. It consists of
retail and small businesses, as well as containing a large Westfield Shopping Mall.
3.3
Birkenhead Domain and Birkenhead War Memorial Recreational Reserve are both large
recreational areas situated towards the southern end of the corridor.
Birkenhead Domain has a cemetery on the corner of Glenfield Road and Eskdale Roads that is
considered a Historical Heritage Extent of Place under the Proposed Auckland Unitary Plan.
Birkenhead War Memorial Recreational Reserve contains the Birkenhead Pool and Leisure
centre, as well as multiple sports fields. Both contain large areas of native bush with many popular
walking, running and cycle tracks.
Oruamu Domain is a steeply sloping park bordered by Glenfield Road and High Road. As was
noted in the Oruamu Domain Management Plan from 1995, the Oruamo Domain provides little
opportunity for interactionConstruction of a path would make the site more accessible to users.
3.4
Birkenhead Town Centre is located at the southern end of Birkenhead Avenue. It consists of
eateries and retail, as well as a NZRPG mall which includes Countdown Supermarket and The
Warehouse, amongst other shops; Birkenhead Kindergarten, Birkenhead Primary School, bowling
club, community library, churches. Hinemoa Street extends from Birkenhead Avenue and
provides access to the Birkenhead Ferry terminal at its southern end. Birkenhead Town Centre is
a key bus hub and is classified as an Intermediate interchange in the Regional Public Transport
Plan.
3.5
Schools
There are a number of schools located either side of the Glenfield Road corridor. The locations of
these are shown in Figure 3.1.
13
File Note
3.6
There are several social and community facilities on and in close proximity to the study area.
These include:
Glenfield Library
Glenfield Community Centre
Rec centre and skate rink
Police
Churches
Sports fields
Passive recreation/parks
Cemeteries
3.7
Utilities
We have reviewed the Auckland Council GIS platform to identify major services which have the
potential to affect the corridor. One major utility has been identified:
14
File Note
Water: A water main is running along the northern portion of the corridor along Glenfield Road,
north of Moore Street (700 CLS). Retail services run alongside large sections of the corridor.
3.8
Protected Heritage
The majority of the buildings fronting onto Birkenhead Avenue at the southern end of the corridor
are historic and are subject to pre 1944 building demolition control rules. There are also protected
trees along this section of the corridor.
3.9
Hydrology
The Glenfield Road corridor I situated on a ridgeline and borders on a number of water
catchments. One of the aspirations of this storm water network plan is improved environmental
outcomes, which includes the implementation of Low Impact Design (LID) storm water
management, to detail peak flows and reduce contaminant runoff into local water bodies.
In response to aspirations, Auckland Council storm water is investigating the implementation of
rain gardens adjacent to the Eskdale reserve and alongside the Oruamo Domain.
15
File Note
Glenfield
Road CMP
corridor
Stormwater
The two main goals for stormwater are to treat the carriageway runoff to ARC TP10 standards
and improve/provide attenuation to limit adverse effects downstream.
There are two Stormwater projects within the Glenfield Rd (Highbury Mall to Glenfield Mall)
Corridor Management Plan area. These have been outlined in Table 3-1.
16
File Note
Proposed
Auckland
Transport
Options
Priority
Reference
Document
1.
Birkenhead
Ave
N/A
141 Birkenhead
Ave Pipe Option
2.
394
Glenfield
Rd
N/A
17
File Note
18
File Note
4.
Future transport
4.1
Aucklands ITP sets out the 30 year investment programme to meet the transport priorities
outlined in the Auckland Plan across modes covering the responsibilities of all transport agencies.
In order to derive the greatest benefit from transport investment and to meet the transport targets
and outcomes for Auckland, a four-stage intervention process has been developed to enable the
ITP to prioritise the phasing of Aucklands 30 year transport programme. Figure 4.1 provides a
visual representation of the four stage intervention process.
Figure 4.1 : Intregrated Transport Programme Four Stage Intervention Process
The RLTP is a plan how transport providers intend to respond to growth and other challenges
facing Auckland over the next ten years. It includes a ten year prioritised delivery programme of
transport services and activities for Auckland, and is the combined transport programmes of the
New Zealand Transport Agency (NZTA), AT and KiwiRail.
Filename: Transport and Land Use Context v4.docx
Document no.:
19
File Note
20
File Note
4.3
4.3.1
The Kaipatiki Connections Network Plan (Figure 4-2) was developed by the Local Board in 2012
looking at expanding and enhancing the walking and cycling network for Kaipatiki. The plan has
not received funding; however, the local board has a limited amount of funding available for
transportation related projects and could choose to fund some of these improvements.
The plan proposes to implement a cycleway along the length of the Glenfield Road/Birkenhead
Avenue corridor, connecting with the already completed section to the north of Glenfield Road.
Important cross connections are identified in the between the following locations:
Eskdale Road and Speedy Crescent
Roberts Road and High Road
Downing Street and Peach Road
21
File Note
Existing and proposed walking track connections have been identified in the Kaipatiki
Connections document. Existing walking tracks (Figure 4-3) can be observed in a number of
locations along the corridor including:
High Road through the Oruamo Domain
Between the Greenvalley Rise cul-de-sac and Glenfield Road
Extensive network within the Eskdale Reserve with limited connections to the Glenfield Road
frontage
Walkway connecting Glenfield Road to City View Terrace
Network of trails within the Birkenhead Domain
Currently no Walking school bus routes use or cross the corridor.
Filename: Transport and Land Use Context v4.docx
Document no.:
22
File Note
4.3.2
The Proposed Auckland Cycle Network identifies Glenfield Road and Birkenhead Avenue as a
Cycle Connector (see Figure 4-4). Portions of the corridor are identified as proposed while
others are considered an existing Cycle Connector facility. The sections which are classified as
existing correspond to sections of the corridor which provide a shared bus/cycle lane.
23
File Note
4.3.3
The Skypath and Seapath proposals are planned to create a walking and cycling route across the
Auckland Harbour Bridge and adjacent to the Northern Motorway to Sulphur Beach Road/Shoal
Bay. While not having a direct effect on the corridor, the proposals will enable greater access for
cyclists and pedestrians from the City Centre to the North Shore.
4.4
Public transport
The Glenfield Road/Birkenhead Ave corridor currently provides for a large number of bus
services. The implementation of the Frequent Network is likely to rationalise these services
reducing the volume of buses on the corridor but continuing to provide for an increase demand on
the corridor. Initially fewer buses are likely to be required on the corridor during peak hours. The
FN relies on a level of interchange between services. Interchange around key points on the
corridor will increase in importance following changes to the network.
24
File Note
4.4.1
The Auckland Regional Public Transport Plan 2013 (RPTP) provides for a new network structure
for public transport in the Auckland region. The new network will provide a permanent network of
connected frequent services that supports Aucklands future growth. This will include maximising
access to rapid and frequent services from the urban area, encouraging mutually supportive land
use and public transport development policies and integrating public transport services with
parking policies.
The Auckland Frequent Service Network 2016 proposed by the 2013 RPTP is shown in Figure
4.5. The Frequent Network (services operating at least every 15 minutes, 7am-7pm, seven days a
week) will run along Glenfield Road and Birkenhead Ave with small route hubs operating at
Highbury Town Centre and Glenfield Town Centre.
A staged implementation of the new network structure is proposed, with three main stages
implemented over a three-year period, as follows:
Stage 1 (2015/16): South Auckland
Stage 2 (2017): North Auckland
Stage 3 (2016/17): Central, East and West Auckland
Figure 4.6 shows the proposed network on the North Shore which is currently being publicly
consulted upon. The new network proposes a number of services which run the length of the
corridor, connecting Glenfield Town Centre with Birkenhead Town Centre. Other proposed
services will join or leave Glenfield Road at the Kaipatiki Road, Roberts Road and Pupuke Road
intersections. The services which are proposed to operate on Glenfield Road are summarised in
Table 4-1.
Table 4-1: Proposed bus services
Routes
Route Description
Section of corridor
used
Peak frequency
(peak direction)
Midday headway
(each direction)
N8a
Constellation to
University via Glfd &
Onewa Rd
10
30
N8b
Bayview circuit to
University via Glfd &
Onewa Rd
10
30
N25
Birkenhead circuit to
Glfd, Taka, Ncote,
Highbury
Glenfield Town
Centre
15
30
N21b
Birkenhead wharf to
Smales Farm via
Highbury & Ncote
Pupuke Rd to Onewa
Rd
30
60
N49
Windy Ridge to
Constellation
Glenfield Town
Centre to Roberts Rd
30
60
N81
15
25
File Note
26
File Note
27
File Note
4.4.2
Flow Transportation Specialists have prepared a CMP for the Onewa Road corridor on behalf of
Auckland Transport. The corridor goes from Verrans Corner to SH1 and provides a main EastWest link on the North Shore. The Onewa Road CMP study area intersects Birkenhead Ave at the
southern end of the corridor. The major intersection of Onewa Road and Birkenhead Ave involves
large volumes of turning traffic.
The CMP identified the need for improved public transport links along the corridor. As part of this,
Transit (T3) lanes were proposed in the westbound direction to complement the eastbound T3
lanes that already exist. Work on implementation will begin in February 2015. A focus on
pedestrian and cycle facilities, especially in areas of high activity was also proposed with on-road
buffered cycle lanes along the corridor and improvements to pedestrian amenity at the
intersection of Onewa Road and Birkenhead Ave.
4.4.3
Albany Highway provides a regional arterial link through North Harbour and connects with the
Glenfield Road corridor at its southern end. The 2010 Albany Highway CMP by GHD looked at the
corridor and what could be done to improve transport facilities.
Doing nothing to the corridor was not considered to be an option with parts of the northern section
of the corridor already running at capacity, and the southern section to reach capacity by 2021
with predicted growth. To improve capacity implementing four lanes along the corridor length was
proposed, including transit (T3) lanes to increase public transport provision. High pedestrian
volumes with multiple schools and a university along the corridor have led to improved footpath
and crossing facilities being proposed, as well as segregated cycle path along its length.
4.4.4
In 2009, Flow transportation specialists undertook a piece of work on bus priority in North Shore
City on behalf of the North Shore City Council. The work set out with the following vision:
to future proof the whole area of investigation to ensure that the appropriate
passenger transport priority measures and facilities are in place. By providing this, we
should be able to increase the number of PT users throughout the lower west side of the
North Shore.
The work used the ARCs APT model to access future conditions for bus services on a number of
key north shore corridors including Glenfield Road and the surrounding network.
Highbury Bypass, Birkenhead Avenue and Onewa Road intersection
Observations indicate that buses turning form Birkenhead Avenue into Onewa Road are caught in
southbound queues in the PM peak. This could be alleviated somewhat by extending the left turn
southbound lane. Bus priority could be provided on the northbound approach by marking the
kerbside through lane as a bus priority area combined with a clearway on Birkenhead Avenue. It
is understood that this is being investigated further in other studies.
Birkenhead Avenue (Onewa Road to Pupuke Road)
Based on the assessment, the following priority measures are recommended:
28
File Note
29
File Note
Based on the assessment, priority measures for Glenfield Road between Roberts Road and
Coronation Road are recommended to include:
A southbound priority lane for the AM and PM peak periods, by 2021-2031
4.5
General traffic
4.5.1
Traffic modelling forecasts have been extracted from the Auckland Regional Transport model for
the Glenfield Road corridor. The location of screen lines is outlined in Figure 4-7.
30
File Note
Year
% change 33 years
Area
2013
2026
2036
2046
Demographic
s
Population
Households
2774
9
8607
Employment
5774
3388
9
1197
4
6150
3626
3
1275
2
6383
3840
0
1359
1
6770
2200
2830
3097
2972
35%
103
137
146
147
43%
1056
6
658
1206
6
1131
1307
7
1249
1423
5
1445
35%
PT
120%
(AM 2 hour
Peak)
N/A
N/A
N/A
N/A
Traffic
(AM 2 hour
Peak)
Study
Area
38%
Auckland
Ave.
61%
58%
79%
17%
59%
89%
31
File Note
4.5.2
In March 2014, Auckland Transport (AT) commissioned the Joint Transport Operations Centre
(JTOC) to undertake optimisation of 9 traffic signals along a section of the Glenfield Road
from Sunset Road to Downing Street. The optimisation report included an assessment of 3
intersections within the Glenfield Road CMP study area including:
Glenfield Road/Bentley Avenue
Gelnfield Road/Kaipatiki Road
Glenfield Road/Downing Street
A number of recommendations were made for each of the intersections relating to signage, road
marking and road surface. At the Glenfield Road/Bentley Avenue intersection, the main
recommendations include:
Right turn into Bentley Ave is filleting while ped 1 is still running.
The zebra crossing on the slip lane exiting Glenfield Road sits too close to the limit line.
The zebra crossing next to the shops does not have warning beacons.
There is no give way sign for the shops exit.
Install a no turn sign on the northern approach
At the Glenfield Road/Kaipatiki Road intersection, the main recommendations include:
There are no tactile pavers provided for any of the pedestrian crossing
Buses travelling north along Glenfield Road stop on the departure lane and cause the through
traffic to stop.
There is no cycle box in front of the right turn bay from Glenfield Road into Kaipatiki Road
The cycle lane on the departure lane of Glenfield Road (southbound) has not been painted
green
Investigate cycle lane options on Glenfield road northbound approach.
The NSAAT lines on Kaipatiki road need to be extended back to make good use of the
existing traffic lanes.
Consider installing a guard rail on this stretch of road to dissuade pedestrians from crossing
the road unsafely.
The Bus Stop on the departure lane of the northbound approach of Glenfield Road is too
close to the intersection. Re designs the position of the bus stop to allow safe lane
change/merge.
32
File Note
4.5.3
The roundabout of Glenfield Road and Coronation Road has been identified as a safety issue.
Legacy North Shore City Council has previously engaged MWH Consultants in year 2009 to
undertake a scheme assessment design to improve the operation and safety of this roundabout.
Three options were developed including; 1. Signalisation of roundabout 2. Roundabout
improvement with land take 3. Roundabout improvement without land take.The recommended
option is the third option (Figure 4-9) which is effective and easier to implement.
The option looks to increase vehicle deflection, improve legibility between right turning and
through traffic on the Glenfield Northbound approach, and improve provision for pedestrian and
cyclists.
Figure 4-9: Glenfield Road/ Coronation Roundabout preferred option
4.5.4
PT2 was commissioned by Auckland Transport to undertake an investigation into the feasibility of
improving safety at the Glenfield / Roberts Rd intersection, specifically the right turn from Roberts
Road onto Glenfield Road. The investigation into crash history at the intersection indicates a
predominant crash trend relating to crossing / turning crashes involving vehicles entering or
exiting Roberts Road.
The recommended option involves realignment of the kerb returns on the north-west and southwest corners of the Glenfield / Roberts Road intersection. The key aspects of the preferred option
include (shown in Figure 4-10): Narrowing of the northbound lane and repositioning of the limit
lines. A second scheme has since been developed which is shown in Figure 4.11.
33
File Note
34
File Note
4.5.5
The priority controlled intersection between Archers Road and Coronation Road was selected for
review as part of the AT Traffic Operations Proactive Workstream. The review highlighted the
following issues:
Long queues observed on Archers Road,
The busy traffic and high speed traffic on Coronation Road make it very challenging for
drivers exiting from Archers Road.
A steep slope on Archers Road means some vehicles struggle to cross at good pace to avoid
conflict.
Driver impatient due to long delays on Archers Road
Poor indication from vehicles turning left into Archers Road.
Intersection alignment and sight distance for vehicles on Archers Road.
Intersection concepts have been developed to address issues identified. A roundabout is the
preferred solution and is currently in the investigation and design phase.
4.5.6
A 2011 report was completed by Auckland Transport on the options for the upgrade for the
Glenfield Town Centre. As part of the assessment, various options for Glenfield Road as it passes
through the town centre are outlined, including initial design drawings. Problems around poor
pedestrian and cycle facilities, parking, safety, bus priority and general traffic flow were identified,
with opportunities for improvement identified.
As part of the project, a number of objectives were developed for the project to address:
Ref
Objectives
3.1
3.2
3.3
Kaipatiki
3.4
3.5
3.6
approach to Bentley
35
File Note
3.7
3.8
Bus priority
3.9
Parking
A total of 9 options where developed as part of the study. Options were compared against the
problems and objectives outlined above and ranked. The report recommends Option 6 (Figure
4.12) to be taken forward to consultation.
In summary Options 6 includes:
Retention of southbound cycle lane
Provision of new northbound cycle lane
Closure of service lane
Signalised mid-block pedestrian crossing
Improved signal coordination and timings through town centre
More efficient lane arrangement on Bentley Avenue approach to Glenfield Road
New car park at 450 Glenfield Road, with signal controlled entry / exit
Removal of give-way left turn into Glenfield Mall
Landscaping
Larger pedestrian spaces
Retention of parking outside White Cross
As part of the investigation, traffic modelling was undertaken for the surrounding area with closure
of Easton Park Parade was tested as a potential option. The modelling indicated closure of
Easton Park Parade would have a significant effect on the Glenfield/Kaipatiki Road intersection
with additional demand which could not be accommodated.
36
File Note
37
File Note
5.
5.1
Auckland Plan
The Auckland Plan vision is for Auckland to become the worlds most liveable city, a city that is
known for its cohesive resilient communities; productive high value economy; quality urban, rural
and natural environments; and excellent transport system. The vision is proposed to be achieved
by the six transformational shifts that Auckland must deliver, including move to outstanding
public transport within one network. The Plans strategic direction for transport is to create
better connections and accessibility within Auckland, across New Zealand and to the world.
Auckland Transports challenge is to meet travel demands, Auckland Plan outcomes and
targets associated with historical and forecast growth in population, employment, freight and to
ensure that transport networks are integrated with planned growth outlined in the Auckland Plan.
The following diagram shows the context of the Glenfield Road/Birkenhead Ave arterial corridor in
relation to the Auckland Plans network of urban centres and business areas. The action required
within the CMP process is to identify changes necessary to accommodate planned growth and
land use changes resulting from the Auckland Plan and the Unitary Plan.
The Glenfield Road/Birkenhead Ave corridor directly connects Highbury (23) with Glenfield (22).
Both are identified as Town Centres.
The Auckland Plan aims to manage population growth and to integrate the provision and
development of transport with identified growth areas. Provision of transport infrastructure and
Jacobs New Zealand Limited
Jacobs is a trademark of Jacobs Engineering Group Inc.
Filename: Transport and Land Use Context v4.docx
Document no.:
38
File Note
services is a key enabler and shaper of the future growth of Auckland set out in the
Plan. Commercial and residential developments need to be designed with all transport
modes in mind. In particular, high density, mixed-use development must be associated with
quality public transport services and infrastructure, commercial travel needs and measures
that encourage walking and cycling, while still providing for trips that are made by private vehicles.
5.2
The land zoning in the PAUP plan are represented in Table 5-1.
Table 5-1 : PAUP zones
Area
Main Zones
Main overlays
Glenfield
39
File Note
40
File Note
5.3
The corridor is situated within the Kaipatiki Local Board. The Local Board Plan outlines the
strategic outcomes and priorities for the area and the activities the board wishes to undertake.
The local board plan forms part of the Auckland Council Long Term Plan.
An outline of relevant strategic priorities and projects has been outlined below:
Proud, positive communities that embrace diversity People with a sense of belonging, who are
connected to one another and are proud to live in Kaip tiki.
Green open spaces and environments A focus on protecting and enhancing our parks and
reserves. Enabling our people to enjoy the outdoors and stay active, while conserving and
growing our natural heritage.
Connected through a range of transport links, both within and beyond our area Allowing people
to move around Kaip tiki and beyond through walking and cycling connections, enhanced public
transport and an efficient road system.
Vibrant town and village centres and a thriving local economy Working to grow and develop the
town centres so they thrive, while protecting their unique personalities and heritage character
through quality design. Strengthening the economic importance of Kaip tiki to Auckland's
economy.
Community facilities, assets and services that are high quality, well managed and meet our
communities' needs Allowing our people to continue to enjoy our existing network of community
facilities and services which are easy to access and managed to a high standard.
5.4
41
File Note
The Capacity for Growth Study monitors and reports on residential, business and rural land
availability in Auckland. Residential and business zoned parcels and rural zoned titles have been
assessed for their capacity to accommodate additional development under the provisions of the
PAUP. The Capacity for Growth Study is a quantitative assessment of capacity at a point in time,
based on the provisions of the PAUP. It measures whether each site has the potential for more
development under a selected set of rules.
Figure 5-3 provides a snap shot of the Auckland region from a land use capacity perspective.
From a regional level, the western north shore (Beach haven, Birkdale, Glenfield area) has a large
potential for residential infill and development under the PAUP rules.
Figure 5-4 provides a snapshot of development capacity within the Kaipatiki Local Board. The
yellow line outlines the CMP corridor. A significant portion of residential land in the vicinity of the
corridor has potential to increase in density. In addition, the Glenfield Town centre has been
identified as having capacity for further business land development. Looking at a wider area, the
Beach Haven and Birkdale areas have a significant potential for development. Increases in
development in this area will have a direct effect on the Glenfield Road corridor as the majority of
trips from these areas use portions of the corridor or cross over Glenfield Road.
42
File Note
43
File Note
44
Appendix B
Problem definition file note
File Note
Date
10 August 2015
Project No
ZB01667
Subject
1.
Summary
The purpose of this paper is to set out the existing problems within the Glenfield Road corridor.
Each stakeholder group has provided a description of the ideal future state for the corridor in the
longer term. Together, the existing problems and ideal future state for each mode will form the
basis on which future corridor options and implementation plan are developed.
2.
Walking
2.1
Existing problems
Stakeholders have raised the following concerns regarding walking within the Glenfield Road
corridor:
Glenfield Town Centre has a poor pedestrian and traffic dominated environment. There
are a number of slip lanes throughout the town centre which create a vehicle dominant
environment and compromise pedestrian safety and accessibility.
Access to bus stops could be improved. There is potential for accidents in some places
where there is no crossing provision connecting bus stops, such as the midblock between
Bentley Ave and Kaipaitiki Road in the Glenfield town centre. With changes to bus
network it could be beneficial to move some stops.
There is poor pedestrian connectivity across and along the corridor. Glenfield Road cuts
the corridor in two halves, creating corridor severance for the adjacent communities.
Particular focus should be placed on improving the connections between greenways in
the area.
Currently footpaths along the corridor are sporadic. Some sections of footpath are in poor
condition or non-existent. Eskdale Reserve, for instance, has no footpath along its
frontage with Glenfield Road.
Steady traffic flow makes informal crossing difficult. There are also many dangerous
points to cross due to existing topography creating poor sight distance.
The Pupuke Road corner has poor east-west pedestrian connection and is constrained
by the retaining wall and cemetery confining the corridor.
It appears that there was some recent work along the eastern side of Birkenhead
Avenue.
File Note
Entrance to the mall at the Glenfield Town Centre is inhospitable for pedestrians and car
dominated.
Footpath width and quality vary along the corridor. Some sections have narrow footpaths
with minimal separation to adjacent traffic lanes and poor surfacing.
Pedestrian and streetscape amenity along the corridor is lacking. There is a lack of street
trees and furniture and no place for people to linger.
The above problems raised by stakeholders can be summarised into three broad categories:
Cross connectivity and connection
Pedestrian longitudinal continuity
Pedestrian environment around Glenfield Town Centre
2.2
Issue investigation
The following section investigates the issues listed above associated with walking within the
corridor. To support this investigation, pedestrian surveys were undertaken along the Glenfield
Road corridor on Tuesday 10 March 2015.
Pedestrian and cyclists were counted at each of the four intersections along the Glenfield Road
corridor in the AM (07:00 09:00), Inter (12:00 14:00) and PM (14:30 19:00) peak periods.
Data was also collected on the direction travelled and a number of attributes of the pedestrians
and cyclists. Table 2.1 presents a summary of the data collected at the four intersections.
Of the intersections surveyed, pedestrian activity was highest at the Birkenhead Ave / Onewa
Road intersection and lowest at Glenfield Road / Roberts Road intersection. Across all four
intersections, 70% of pedestrians surveyed were adults and 25% were unaccompanied children.
At the Onewa Road intersection 45% of pedestrians were children.
Table 2.1 : Glenfield Road Pedestrian Data (10 March 2015)
Pedestrian
Classification
Bentley
Ave
Kaipatiki
Rd
Roberts Rd
Onewa Rd
Total
Adult
960
780
310
920
2,970
Accompanied
Child
80
60
10
110
270
Unaccompanied
Child
130
230
60
610
1,030
Elderly
40
20
10
20
90
Walking School
Bus
<5
<5
1,220
1,090
400
1,660
4,360
Total
File Note
2.2.1
Along the length of the corridor there are six signalised crossings and three pedestrian refuge
crossings. The locations of these crossing provisions relative to the bus stops and pedestrian
accidents resulting in injury are shown in Figure 2-1.
As highlighted in the Transport and Land Use Context file note, there have been 10 pedestrian
accidents including 1 fatal and 9 minor injury crashes. Half of these occurred at intersections and
all have involved a pedestrian crossing the road.
Four of the five pedestrian crashes between Kaipatiki Road and Onewa Road have occurred near
bus stops where there are no pedestrian crossing provisions. This suggests that improved
pedestrian crossing facilities are needed at these locations.
Other accidents involving pedestrians crossing Glenfield Road and Birkenhead Ave include
vehicles running red lights at signalised intersections and pedestrians crossing heedless of traffic.
Roberts Road intersection
The pedestrian survey data shows that at the Roberts Road intersection during the AM peak,
most pedestrians travel east along Roberts Road on the southern side, turn right onto Glenfield
Road and travel south before crossing Glenfield Road. This is likely to be associated with demand
for the southbound bus services and the bus stop on the eastern side of Glenfield Road. There
has also been a minor injury crash involving a pedestrian crossing at this location and a vehicle
travelling southbound.
In the PM peak, the survey shows that most pedestrians travel south along Glenfield Road on the
western side before turning right onto Roberts Road to travel west along Roberts Road on the
northern side. This is likely to be associated with pedestrians alighting from northbound bus
services at the stop on the western side of Glenfield Road, north of Roberts Road. This shows
that there are some tidal pedestrian flows on the corridor associated with the commuter peaks.
Onewa Road intersection
The pedestrian surveys show that in the AM peak at the Birkenhead Ave / Onewa Road
intersection most pedestrians travel eastbound from the northern side of Highbury Bypass. Of the
intersections surveyed, this intersection had the greatest proportion of child pedestrians. The
eastbound AM peak movement is therefore likely to be a result of Northcote College and St
Marys School being located a few hundred metres east along Onewa Road.
This intersection has left-turn slip lanes on all four approaches. This means that pedestrians must
cross two slip lanes when crossing at the intersection.
During the PM peak most pedestrians travel southbound towards the Birkenhead Town Centre.
The most common movement was pedestrians on the southern side of Onewa Road turning left
onto Birkenhead Ave.
File Note
File Note
Auckland Transport traffic counts show that Glenfield Road has a 5 day ADT of approximately
21,000 vpd and a peak hour volume of 1,600 vph (September, 2014). Roads with traffic volumes
of this order are typically difficult for pedestrians to cross without crossing provision.
There are two sections of Glenfield Road 1,200 m and 850 m long which do not have any
crossing facilities. As shown in Figure 2-1, these sections are between Downing Street and
Coronation Road and between Eskdale Road and Waratah Street.
1
The Pedestrian Planning and Design Guide illustrates that pedestrians will experience a mean
delay greater than 50 seconds and level of service F when crossing a road similar to Glenfield
Road (two-lane, two-way urban road) with no crossing provision, interrupted traffic flow and an
average peak hourly volume greater than 1,600 vph.
The signals at Pupuke Road do not provide a crossing across Glenfield Road as shown in Figure
2-2. The Bentley Ave, Downing Street and Eskdale Road signalised intersections only provide a
crossing across Glenfield Road on one intersection arm.
The geometry of the road, topography and retaining walls near the Roberts Road and Pupuke
Road intersections on Glenfield Road prevent pedestrians from being able to cross Glenfield
Road. It should be noted that the pedestrian issues discussed above are examples of deficiencies
in the corridor but should not be interpreted as an exhaustive list.
File Note
Figure 2-2 : Lack of crossing provision at Glenfield Road / Pupuke Road intersection
2.2.2
As well as poor pedestrian connectivity across Glenfield Road, there is also poor continuity for
pedestrians wishing to walk north-south along the corridor. Between the Glenfield town centre and
Onewa Road there is a 1,200 metre section of the corridor which lacks a continuous dedicated
footpath on one side of the road and a section of approximately 200 metres that lack continuous
footpaths on both sides. The sections along Glenfield Road that do not have footpaths are shown
in Figure 2-3.
Pedestrian crossing facilities at a number of side roads along the corridor are also substandard.
Some of the side roads are difficult to cross as a result of wide flared intersections. The locations
of these are shown in Figure 2-1. The width and quality of the footpaths along the corridor is also
varied.
File Note
File Note
2.2.3
The issues associated with the pedestrian environment in Glenfield Town Centre are discussed in
section 5.
2.3
The ideal future state of the network has been articulated through analysis of strategic
documentation applicable to the Glenfield Road corridor, comments and discussion between
technical stakeholder members.
The Auckland Plan sets a target that across all of Auckland by 2040, 45% of trips in the morning
peak are targeted to be non-car-based (walking, cycling or public transport) compared to 23% at
present. In order to achieve this, the ideal future state for the Glenfield Road corridor must include
the following:
2.4
Well connected pedestrian network which encourages walking for short trips
Pedestrian facilities which encourage use of public transport through safer and more
frequent crossings and enhanced walking environments
A safe pedestrian environment for children, elderly and the mobility impaired which
follows universal design principles and allows accessibility for all
Enhance pedestrian environment in and around the Glenfield Town Centre which
prioritises walking over other modes
Summary
When considering the pedestrian mode, it is important to consider both existing problems in the
network as well as an aspiration for the mode in the longer term. A summary of the problems and
ideal future state for the pedestrian mode is provided below.
1)
Problems in the
pedestrian network
1)
2)
3)
4)
File Note
3.
Cycling
A problem definition exercise was undertaken as part of the first technical stakeholder workshop.
Stakeholders have raised the following concerns regarding cycling within the Glenfield Road
corridor:
Currently existing provision for cyclists along Glenfield Road and adjoining roads does
not align with the proposed Auckland Cycle Network (ACN)
Lack of continuity in the corridor itself with cycle lanes being provided to the north of the
study area and shared path (proposed/under construction) on Onewa Road.
Not many school children are cycling to school as schools actively discourage cycle use.
Section between Roberts Road to Archers Road is particularly badly served due to lack
of safe crossing points.
The route optimisation projects should look for opportunities for cycling.
Side road connections must be thought about as well as the corridor itself.
The intersection Roberts Road/Glenfield Road currently has a property access way which
cuts the corner. This provides an opportunity to get cyclists a separation from the
carriageway.
The above problems raised by stakeholders can be summarised into two broad categories:
1)
A combination of lack of cycle facilities, continuity along the route, and no alternative routes
are contributing to suppressed cyclist demand, particularly less confident cyclists and school
children
2)
Lack of side road connections and crossing points means Glenfield Road creates a sense of
severance in the cycle network
3.1
Issue investigation
The following section investigates the issues listed above associated with cycling within the
corridor. In conjunction with the pedestrian surveys described above, cycle surveys were also
th
completed on Tuesday 10 March 2015 along the Glenfield Road corridor.
The same four intersections were surveyed and similar count data was collected. In an attempt to
remove the effects of seasonality, the survey provider converted the peak counts to AADT using
Auckland Transports AADT formula.
Cycling activity was not nearly as high as the pedestrian activity observed as the cycling numbers
ranged from 50 cyclists per day at the Glenfield Road / Bentley Ave intersection to 60 cyclists per
day at the Birkenhead Ave / Onewa Ave intersection. Age data was not collected for cyclists.
At the Bentley Ave intersection most cyclists were travelling north away from the town centre,
throughout the day. At the Kaipatiki intersection most cyclists were travelling northbound in the
AM peak and southbound in the PM peak. At the Roberts Road intersection most cyclists were
Filename: ZB01667 Problem Definition v4.docx
Document no.:
File Note
travelling northbound in the AM peak and southbound in the PM peak. At the Onewa Road
intersection cyclist numbers were relatively even in all directions across all peaks.
It is quite probable that many of the cyclists observed at the four different locations were the same
people since the surveys were completed at the same time along the length of the Glenfield Road
corridor.
3.1.1
A series of on road cycle lanes have been implemented to the north of the study area. The cycle
lanes extend between the Hogans Road intersection in the north, to the Downing Street
intersection in the South. Beyond this point cycle lanes are terminated and cyclists are forced to
merge with existing traffic. There is a short on and off-road section of cycleway in the northbound
direction on Glenfield Road between Peach Road and Kaipatiki Road.
Aside from the facilities noted above, there are currently no other cycle provisions along the
remainder of the corridor. There are also no cycle provisions on any of the east-west cycle routes
identified as cycle metros or connectors in the ACN. Figure 3.1 provides an overview of the ACN
in the study area and identifies the location of current cycle infrastructure as well. Crash locations
are also identified.
Through site observations and feedback from cycle representatives, a number of locations have
been identified as pinch points for existing cyclists using the corridor. These generally coincide
with narrowing of lanes around intersections on the corridor where cyclists movements conflict
with general vehicles movements. The locations of the pinch points are shown in Figure 3.2.
10
File Note
11
File Note
12
File Note
3.1.2
The Glenfield Road corridor is currently positioned on a ridge line. Topography is generally
sloping away from the corridor as seen in Figure 3.4. The road layout in the study area is based
around Glenfield Road as the key north-south arterial with a number of east-west connections
scattered along the corridor.
Strava data has been used to assess existing cycle route choice along the corridor (Figure 3-3).
The Strava data is inherently biased towards more confident cyclists but provides a useful
snapshot of desire lines and routes. We have compared the Strava heat map to an assessment of
grade (Figure 3.4) on the surrounding road network. In general, preferred cycle routes avoid
sections of road with significant grade whenever possible. It is worth noting that grades along
Glenfield Road are primarily less than 5%, which is favourable to cycling. However, there are a
few instances of grades between 5-10% which creates a challenge for many potential cyclists.
The distance from Bentley Ave, along Glenfield Road to the City Centre via Onewa Road and the
Auckland Harbour Bridge is approximately 12 km. Once a connection is provided across the
harbour (either via the Skypath project or other) it will be possible to make this trip via bicycle.
According to the 2013 Census, between 10-15% of trips from the study area are destined for the
City Centre and currently all of these trips are being made either via private vehicle or public
transport. The average length of active mode trips recorded by the Census was 6.7 km in 2013 so
there is likely a limit to the number of people in the study area who would be willing to cycle to the
City Centre as their primary commute option. The corridor is likely however to provide for local
cycle trips within Glenfield and Birkenhead and may be used by ferry passengers boarding at the
Birkenhead Ferry Terminal.
13
File Note
14
File Note
15
File Note
3.2
The ideal future state of the network has been articulated through analysis of strategic
documentation applicable to the Glenfield Road corridor, comments and discussion between
technical stakeholder members. The following ideal future states have been identified for the
corridor:
3.3
Capitalise on opportunities for cycling in the short and medium term. Implement low cost
quick win projects and incorporate cycle facilities into other projects on the corridor.
Provide cycling facilities for the entire length of the Glenfield Road corridor. A standard of
cycling facility within the Glenfield Road corridor that allows more vulnerable cyclists to
be able to use cycling as a safe and viable means of transport. Well connected and
integrated corridor cycle provisions that support the greater cycle network.
Summary
When considering the cycling mode, it is important to consider both existing problems in the
network as well as an aspiration for the mode in the longer term. A summary of the problems and
ideal future state for the cycling mode is provided below.
1)
2)
1)
2)
16
File Note
4.
Public Transport
4.1
Existing problems
A problem definition exercise was undertaken as part of the first technical stakeholder workshop.
Stakeholders have raised the following concerns regarding public transport within the Glenfield
Road corridor:
Travel time and delay on the corridor is the major problem. There is a desire to tie in with
the eastbound transit lane provided on Onewa Road.
Currently public bus services lay up around the Glenfield town centre. When the new
network is implemented in 2017, this will not be an issue for public bus services.
However, it could be a continuing issue for school buses.
Pedestrian access and crossing is an issue at selected spots on the corridor. For
example, the pedestrian crossing across Glenfield Road between the bus stops in the
town centre has been identified by stakeholders for improvement.
Route optimisation report (2014) has been completed for this route outlining deficiencies
however nothing has been implemented.
Stage fare boundaries are currently meaning first stop within fare boundary is
overcrowded.
Stop locations need to be rationalised. This is intended to take place after implementation
of the new network.
Variability is an important issue for the corridor. Time variability and reliability can be
costly to AT.
The above problems raised by stakeholders can be summarised into two broad categories:
1)
Travel time and reliability on the corridor is an issue. Delay and reliability needs to be
targeted in specific locations where congestion occurs.
2)
Bus stop locations, facilities and crossing points could be improved to access and experience
for users.
3)
Specific problem at the Birkenhead Avenue / Onewa Road intersection where buses are held
up by general vehicle queues from the transit lane and are delayed in reaching the transit
lane.
Bus fare boundaries are not considered a problem as integrated ticketing will resolve this problem
with the introduction of the new network in 2017. Equally, bus layovers will be reconfigured with
the implementation of the new network.
17
File Note
4.2
Issue investigation
4.2.1
The transport systems team in Auckland Transport has provided a snapshot of the current
network travel time reliability for public transport on the corridor for May 2014. This is illustrated in
Figure 4-1 which shows the Level of Service (LOS) for all buses travelling along the corridor
based on GPS travel time data. At this time, construction was complete on Glenfield Road north
of the Glenfield Town centre.
In the AM peak, congestion can be observed in the northbound direction on the section north of
the Kaipatiki Road intersection which operates at LOS D. All other northbound traffic operates at
LOS B in the AM peak with no noticeable congestion. In the southbound direction, Glenfield Road
operates with LOS F on the approach to the town centre and the approach to Kaipatiki Road. Also
in the southbound direction, there is some delay on the approach to the Coronation Road
intersection which operates at LOS D. The southbound approach to the Pupuke Road intersection
also operates at LOS D.
In the PM peak, north of the Kaipatiki Road intersection experiences severe congestion (LOS E/F)
in both directions. In the northbound direction, severe congestion can be observed north of
Downing Street as well. Congestion can be observed in the northbound direction approaching the
Coronation Road intersection and in the southbound direction approaching Pupuke Road. Both of
these sections operate at LOS D.
There is currently bus priority treatment on Glenfield Road southbound at the Coronation Road
roundabout.
18
File Note
Figure 4-1: Network Operation: Level of Service in AM Peak (left) and PM Peak (right)
Auckland Transports HOP data has been analysed to determine bus travel times and travel time
variability along the corridor throughout the day. The weekday journey times during March and
April 2015, for all bus services travelling along the corridor between Camelot Place in the north
and Onewa Road in the south are presented in Figure 4-2 and Figure 4-3 for northbound and
southbound directions respectively.
The median travel time in both northbound and southbound directions is approximately 10.5
minutes. In the northbound direction the travel times ranged from 6 to 25 minutes, corresponding
to an average travel speed of 10 kph to 39 kph. In the southbound direction the travel times
ranged from 5 to 30 minutes, corresponding to an average travel speed of 8 kph to 43 kph.
In the northbound direction, an increase in travel time can be observed in the PM peak period,
with a greater number of trips over 15 minutes and some over 20 minutes. In the southbound
direction, an increase in travel time can be observed in the AM peak period, with a greater
number of trips over 15 minutes. Outside of the peak times, the variance in travel time is not as
great.
19
File Note
20
File Note
The LOS plots in Figure 4-1 show that the southbound approach to the Pupuke Road intersection
operates with LOS D in both the AM and PM peaks. Additional HOP data for the southbound
direction through the Pupuke Road intersection has been analysed.
Figure 4.4 shows the weekday journey times during March and April 2015 for all bus services
travelling from the stop near Moore Street, 200 m north of the intersection, to the stop just south
of the intersection. The median travel time between these stops was 34 seconds. During the AM
and PM peaks, a greater number of these trips took over one minute with some taking over two
minutes.
Some variation in travel time through the Pupuke Road intersection is to be expected due to the
signal phasing, and the variable dwell times at each stop (passengers boarding and alighting).
However Figure 4.4 shows there is much greater variability during the AM and PM peaks which
corresponds to delay caused by increases in general vehicle traffic.
Figure 4.4 : Bus travel times - Pupuke Road intersection
The existing bus timetables for the services which operate on Glenfield Road have been
examined to ascertain how many buses travel on Glenfield Road during the peak. Some existing
services travel along the length of Glenfield Road while others travel only on parts of Glenfield
Road. The scheduled numbers of buses per hour on each section of the corridor during the AM
peak are presented in Table 4.1 (bus numbers are lower during the PM peak).
The Glenfield Town Centre currently carries the highest number of buses with 25 buses per hour
in the peak direction. In general, more scheduled services travel on the northern end of the
corridor than the southern end.
21
File Note
Section
Section Description
Non-peak
direction
(buses/hr)
Peak direction
(buses/hr)
Both directions
(bus/hr)
25
14
39
Kaipatiki Rd to Downing St
22
10
32
Downing St to High Rd
22
30
High Rd to Coronation Rd
22
30
Eskdale Reserve
17
23
17
23
Pupuke Rd to Onewa Rd
16
24
As discussed in the Transport and Land Use Context file note, AT is proposing to implement a
new bus network on the North Shore as part of the Regional Public Transport Plan. The new
network will be much more simplified with less services and a greater focus on interchange
between services.
The new network proposes a number of services which run the length of the corridor, connecting
Glenfield Town Centre with Birkenhead Town Centre. Other proposed services will join or leave
Glenfield Road at the Kaipatiki Road, Roberts Road and Pupuke Road intersections.
The proposed numbers of buses per hour under the new network on each section of the corridor
during the AM peak are presented in Table 4.2. It should be noted that the proposed network is
currently being consulted upon therefore routes and frequencies are subject to change.
The number of buses is generally consistent along the route with approximately one bus every
three to four minutes. Compared to the existing scheduled numbers of buses, the proposed
network generally has fewer buses on the northern end of the corridor but a similar number on the
southern end.
22
File Note
Section
Section Description
Non-peak
direction
(buses/hr)
Peak direction
(buses/hr)
Both directions
(bus/hr)
12
10
22
Kaipatiki Rd to Downing St
18
10
28
Downing St to High Rd
18
10
28
High Rd to Coronation Rd
18
10
28
Eskdale Reserve
16
24
16
24
Pupuke Rd to Onewa Rd
18
10
28
The existing bus reliability issues discussed above are likely to be similar when the new network
is implemented in 2017. However, at a later date in the future, the frequency of services in the
corridor will likely increase in response to the demand for public transport. This, coupled with
increases in general vehicles in the corridor, will create greater travel time reliability issues for
buses.
4.2.2
The ability for passengers to access bus stops has a strong influence on their willingness to use
the public transport system. A five minute (approximately 400 m) walk to and from a bus stop is
generally considered the maximum distance most passengers are willing walk to use public
transport. Ideally bus stops should not be spaced at intervals greater than 400 m along a bus
route, on the downstream side of intersections and close to major trip generators.
Passengers ability to access bus stops easily is strongly dependent on the provision of safe
crossing points. Lack of safe crossings can lead to pedestrians either not being able to cross in
time for their bus, or taking greater risks to cross which can result in accidents.
As discussed above, the existing bus stop locations in relation to crossing points and recorded
accidents are shown in Figure 2-1. The bus stops are generally spaced at 400 m intervals along
the corridor however some stops do not have crossing facilities nearby.
The provision of high quality waiting areas with seating and shelter improves passengers
experience and also encourages public transport use. The bus stop on the western side of
Glenfield Road between Moore Street and Pupuke Road is an example of a stop which does not
have any seating or shelter.
4.2.3
Auckland Transports Metro team has recently looked at the Birkenhead Avenue/Onewa Road
intersection to identify any options to improve the performance from a public transport
perspective. Difficulties arise when vehicles are queued in the outside general vehicle lane on
Filename: ZB01667 Problem Definition v4.docx
Document no.:
23
File Note
Onewa Road in the AM peak period. Buses turning onto Onewa road from either Birkenhead
Avenue north or Birkenhead Avenue south require both lanes to be free in order to track through
the intersection. Figure 4-5 outlines the movements which currently experience delay.
Figure 4-5: Birkenhead Avenue / Onewa Road intersection issues
Additional HOP data has been analysed to give an indication of the delay currently experienced
by bus services turning left from Birkenhead Ave into Onewa Road. Figure 4.6 shows the
weekday journey times during March and April 2015 for all bus services travelling from the stop
near Waratah Street to the stop 100 m east of the Onewa Road intersection.
The median travel time between the stops during March and April was 46 seconds. During the AM
peak period a greater number of these trips took over two minutes with some taking well over
three minutes. Out of the 41 weekdays (excluding public holidays) during March and April, 12
days had at least one bus service which took over three minutes to travel between the stops.
Some variation in travel time through the Onewa Road intersection is to be expected due to the
signal phasing, and the variable dwell times at each stop (passengers boarding and alighting).
However Figure 4.6 shows there is much greater variability during the AM and PM peaks which
corresponds to delay caused by increases in general vehicle traffic. This is particularly the case
when congestion on Onewa Road prevents buses turning left from Birkenhead Ave.
24
File Note
The issues and constraints for buses in the corridor are summarised in Figure 4.7.
25
File Note
26
File Note
4.3
The Auckland Plan identifies a range of targets relating to Transport for Auckland. Three of the
targets relate to enhancing public transport as a mode and include:
Double public transport from 70 million trips in 2012 to 140 million trips by 2022
Increase the proportion of trips made by public transport into the city centre during the
morning peak from 47%of all vehicular trips in 2011 to 70% by 2040
Increase the proportion of people living within walking distance of frequent public
transport stops from 14% to 32% by 2040.
The Auckland Plan and Auckland Regional Transport Plan set out strong strategic objectives of
improving travel time reliability and reducing delay on parts of the frequent network. They also
emphasize the need to increase accessibility to public transport services. The desired future
outcomes for the corridor align with this high level strategic direction as follows:
4.4
The Glenfield Road corridor provides reliable and competitive travel time for buses
compared with general traffic
Improved access to bus services through enhancement of the bus stop environment and
connectivity of surrounding pedestrian facilities
Summary
When considering the Public Transport mode, it is important to consider both existing problems in
the network as well as an aspiration for the mode in the longer term. A summary of the problems
and ideal future state for public transport are provided below.
1)
Problems in the Public
Transport network
27
File Note
5.
Place
5.1
Existing problems
A problem definition exercise was undertaken as part of the first technical stakeholder workshop.
Stakeholders have raised the following concerns regarding place (predominantly relating to
Glenfield Town Centre) within the Glenfield Road corridor.
Glenfield Town Centre has a poor pedestrian and traffic dominated environment. There
are a number of slip lanes throughout the town centre which create a vehicle dominant
environment and compromise pedestrian safety and comfort.
The existing look and feel of Glenfield Town Centre could be improved
Whilst the raised median in the town centre enables pedestrians to cross mid-block, it
may actually contribute to higher vehicle speeds through the town centre.
Council have bought land in the Glenfield Town Centre to offset parking that would be
lost as a result of previous proposals being implemented. This is located on the western
side of the road opposite Bentley Avenue.
A parking study has been undertaken in the Birkenhead Town Centre which looked at
parking on Birkenhead Avenue.
A piece of work has been done in the Glenfield Town Centre looking at ways to improve
the place function of the area. This work included recommending traffic calming and
transition zones.
School buses currently use Glenfield Town Centre as a bus hub. This is considered to
detract from the place function of the centre with multiple buses parked.
On Glenfield Road between Bentley Ave and Kaipatiki Road, there are issues with
crossing between the shops. There is potential for creating a slow speed environment.
Will Thresher had done some work looking at controlling vehicle speed and increasing
pedestrian permeability through Glenfield.
Potential for Bentley Avenue area to have low speed function with transition zones either
side.
Council has purchased land for widening the Kaipatiki Road intersection due to a
previous investigation. The right turning traffic queue on Kaipatiki Road blocks the
through traffic.
Historical work by John Stenberg and Sarah Lindsey investigated open space/plaza on
corner of Bentley Ave.
28
File Note
The above problems raised by stakeholders refer mainly to the Glenfield Town Centre and can be
summarised into two broad categories:
1)
The place function within the Glenfield Town Centre is dominated by vehicle movements
through the area; parking and bus stabling create an inhospitable environment for
pedestrians.
2)
Connections between the town centre and Westfield Mall are poor with little interaction
between the two areas.
It should be noted that local businesses in Glenfield Town Centre have expressed a strong desire
to retain existing car parking numbers as they believe the parking is critical to their livelihood.
Local board members have reminded the project team of this local business preference.
Immediately south of the CMP corridor is the Birkenhead Town Centre. While the scope of the
CMP does not include the Birkenhead Town Centre, parking impacts and pedestrian demand
from the town centre have an effect on Birkenhead Ave north of the Onewa Road intersection.
5.2
Issue investigation
5.2.1
Within every town centre, an inherent conflict exists between the movement and access functions.
In the Glenfield Town Centre, the existing situation is dominated by the movement function of the
road. In order to enhance the place and access function of Glenfield Town Centre, the balance
between place and movement must be restored to put much more emphasis on place. This would
suggest that the problems identified above relating to movement through the centre are not as
important and will be addressed as a lower priority to the public realm improvements.
Feedback from Auckland Transport Metro suggests bus priority through a town centre is not
considered necessary in most cases. Retention of some short term parking supply is not in itself a
problem but will be regarded as a key consideration when evaluating potential options for the
town centre.
Figure 5.1 to Figure 5.4 provide photos from Glenfield Road to illustrate the pedestrian
environment in the corridor. The photo of the Glenfield Road / Kaipatiki Road intersection
illustrates the lack of pedestrian priority across the slip lane into Westfield.
As shown in Figure 5.3, part of the footpath on the western side of Glenfield Road between
Kaipatiki Road and Bentley Ave is setback from the road reserve and is in private property. The
frontage over this section is dominated by parking which leads to poor pedestrian continuity along
this section.
The access road connecting Glenfield Road with the parking behind the McDonalds, shown in
Figure 5.4 creates an additional crossing for pedestrians. The access road is currently difficult for
pedestrians to cross, in particular the mobility disabled due to the grade and width of crossing and
misalignment of the pram crossings.
29
File Note
30
File Note
Figure 5.2 : Glenfield Road between Bentley Ave and Kaipatiki Road
31
File Note
32
File Note
33
File Note
The pedestrian surveys show that across all three peak periods at the Glenfield Road / Bentley
Ave intersection, most pedestrians travel southbound towards the town centre. A similar trend is
seen at the Glenfield Road / Kaipatiki Road intersection, with most pedestrians travelling
northbound towards the town centre. This confirms that Glenfield Town Centre is a significant
pedestrian attraction.
The surveys show that in the AM peak, the most common movements at the Kaipatiki Road and
Bentley Ave intersections are eastbound and westbound respectively towards the town centre. In
the PM peak the reverse is true at the Bentley Ave intersection, whereas at the Kaipatiki Road
intersection the most common movement was from the Westfield car park turning right onto
Glenfield Road. This shows Kaipatiki Road and Bentley Ave are important pedestrian connections
to the town centre and that there is also demand for a connection with the mall.
The pedestrian counts showed that in Glenfield Town Centre 1,200 pedestrians crossed Glenfield
Road at either the Kaipatiki Road or Bentley Ave signalised crossings (both eastbound and
westbound directions and across all three periods). In comparison, the total number of
pedestrians informally crossing midblock between Kaipatiki Road and Bentley Ave was 600 (one
third of pedestrians crossing in the town centre). This suggests that some form of pedestrian
crossing provision midblock could be justified.
In March 2014, Auckland Transport (AT) commissioned the Joint Transport Operations Centre
(JTOC) to undertake optimisation of 9 traffic signals along a section of the Glenfield Road from
Sunset Road to Downing Street. The optimisation report included an assessment of 3
intersections within the Glenfield Road CMP study area including:
The Westfield Mall occupies most of the land within the Glenfield Town Centre. The mall is
accessed by a number of entries and exits. One of the main access points to the mall forms part
of the Glenfield Road / Kaipatiki Road intersection and caters predominantly for vehicles. Further
access points are included on Bentley Avenue (service access) and from Downing Street. The
main access points are very car oriented, not providing for other modes.
Two alley ways are provided between Glenfield Road and the Westfield site. In the existing
situation, little way-finding is provided, the alley ways are narrow and do not comply with modern
CPTED principals and require customers to walk across a car park before entering the mall.
34
File Note
Overall the Westfield Mall faces away from Glenfield Road which creates a sense of separation
from the town centre area between Kaipatiki Road and Bentley Avenue. The nature of access to
the mall provides an inhospitable environment for pedestrians and promotes car trips.
5.3
The Glenfield Town Centre, like many other town centres throughout Auckland, needs to balance
the place function and the movement function of the Glenfield Road corridor. The ideal future
state of the corridor will have the following characteristics:
5.4
Greater focus on the access function and reduced level of service for through traffic
function
When entering the Town centre, vehicles naturally slow in response to the differing
environment they are faced with.
The Glenfield Town Centre provides a permeable urban environment with good
connection between various land parcels and active street frontage.
Summary
When considering the place function of Glenfield Town Centre, it is important to consider both
existing problems in the network as well as an aspiration for the mode in the longer term. A
summary of the problems and ideal future state for the town centre are provided below.
35
File Note
36
File Note
1)
2)
Greater focus on the access function and reduced level of service for
through traffic function
When entering the Town centre, vehicles naturally slow in response
to the differing environment they are faced with.
Pedestrian movements are prioritised above other modes.
The Glenfield Town Centre provides a permeable urban
environment with good connection between various land parcels
and active street frontage.
37
File Note
6.
6.1
Existing problems
A problem definition exercise was undertaken as part of the first technical stakeholder workshop.
Stakeholders have raised the following concerns regarding general vehicle and freight traffic on
the Glenfield Road corridor.
Glenfield Road at High Road is dual lane with no shoulder. Dual lanes are provided due
to 15% gradient but increase vehicle speed.
The AT car park within the Glenfield centre has issues with vehicle circulation and
impacts on the neighbouring property
Dip in the vehicle entrance to the Glenfield Town Centre is uncomfortable for vehicles
entering and exiting.
The bus network LOS maps discussed in section 4 also provide an indication of vehicle
delay in the corridor during the AM and PM peak commute.
Delay in a town centre is inevitable and considered a necessary compromise given the
place function of the Glenfield Town Centre.
Glenfield Road adjacent to High Road provides two lanes in the southbound direction.
The lack of shoulder and high speed of traffic creates a pinch point in the cycling network.
This problem has been discussed in Section 3.
Circulation issues within the Auckland Transport parking area and neighbouring property
are design issues which will be dealt with when developing the design of the car park
facility.
6.2
Issue investigation
6.2.1
A number of sites have been identified as having a safety issue on the corridor. These have been
identified in Figure 6-1.
Auckland Transports Road Safety and Road corridor operations have developed options to
address deficiencies at the following intersections:
Filename: ZB01667 Problem Definition v4.docx
Document no.:
38
File Note
The JTOC pre optimisation report identified some minor upgrades which will increase safety at the
following intersections:
The remaining intersections with more than ten crashes include Moore Street/Glenfield Road,
Pupuke Road/Glenfield Road, and Birkenhead Avenue/Onewa Road.
39
File Note
40
File Note
6.3
As a primary arterial road, Glenfield Roads overarching function relates to maintaining the
movement of people through the corridor. Opportunities exist to further optimise the people
movement function of Glenfield Road outside of the town centre. As noted in section 5, the
movement function of Glenfield Road is not a priority in the town centre. In fact, the movement
function should be significantly detuned to create a more conducive environment for walking in the
town centre.
The Auckland Draft Parking Discussion document sets out the strategy for parking on arterial
roads such as the Glenfield Road corridor. The parking strategy identifies a desire to reprioritise
road space for movement of people rather than provide for on street parking. This high level
strategy is considered appropriate for the majority of the Glenfield Road corridor in the longer term
and is reflected in the ideal future state being that:
6.4
Parking is removed from Glenfield road and space is reallocated for movement functions.
Road space currently allocated to parking within the Glenfield Centre is rationalised and
suitable alternatives are provided.
Glenfield Road is network optimised to achieve the best people movement function
When considering the general vehicle mode, it is important to consider both existing problems in
the network as well as an aspiration for the mode in the longer term. A summary of the problems
and ideal future state for general vehicles and freight are provided below.
1)
41
Appendix C
Options, priorities and points of tension
Date
10 August 2015
Project No
IZ036400
Subject
Glenfield Road Corridor Management Plan Options, priorities and points of tension
A number of options for the Glenfield Road corridor have been developed to address the identified problems
and provide for the ideal future state defined by the technical stakeholders as outlined in Milestone 4. These
options are discussed together with the identified priorities and conflicts between them along the corridor.
1. Problems
The following corridor problems were identified by the various technical stakeholder groups as part of the
problem definition exercise:
Pedestrian network
Cross connectivity and connection
Pedestrian longitudinal continuity
Pedestrian environment around Glenfield Town Centre
Cycling network
A combination of lack of cycle facilities, continuity along the route, and no alternative routes are
contributing to suppressed cyclist demand, particularly less confident cyclists and school children
Lack of side road connections and crossing points means Glenfield Road creates a sense of severance in
the cycle network
Public Transport network
Travel time and reliability on the corridor is an issue. Delay and reliability needs to be targeted in specific
locations where congestion occurs.
Bus stop locations, facilities and crossing points could be improved to access and experience for users.
Specific problem at the Birkenhead Avenue / Onewa Road intersection where buses are held up by general
vehicle queues from the transit lane and are delayed in reaching the transit lane.
Glenfield Town Centre
The place function within the Glenfield Town Centre is dominated by vehicle movements through the area;
parking and bus stabling create an inhospitable environment for pedestrians.
Connections between the town centre and Westfield Mall are poor with little interaction between the two
areas.
General vehicle network
Safety issues on the Glenfield Road corridor
Document number
Document number
3. Corridor sections
During the Milestone 2 technical stakeholder workshop, the Glenfield Road Corridor was divided into seven
distinct sections. The sections were divided based on the adjacent land uses and form of the road. Sections
have been outlined in Figure 3.1.
The options developed for each section are discussed below. Each option has been given rankings of High,
Medium or Low by mode to give an indication of the priority that the option provides to pedestrians, cyclists,
buses and general vehicles. (The priority rankings have been shown above each of the cross sections.) The
conflict that exists between the modes has been discussed for each section.
The options for each section have then been evaluated against the problems and ideal future state discussed
above. This has informed the identification of a preferred option for each section.
The options represent the long term vision for the corridor. An implementation plan will be presented in the
complete Corridor Management Plan which shows how this vision will be achieved over time.
Figure 3.1 : Corridor sections
Document number
Document number
Figure 4.1 : Potential future pedestrian crossings and bus stop locations
Document number
Document number
Document number
The issues on this section of the corridor have been summarised in Figure 5.3. As discussed above, the main
issues are the poor pedestrian environment with poor pedestrian connectivity to the Westfield Shopping Mall.
Document number
Document number
5.1
Options
Currently the layout of the corridor through the town centre has a strong focus on maximising efficient
movement of vehicles which has created a poor pedestrian environment. The options discussed below aim to
shift the focus of this section, in varying degrees, from vehicle movement to enhancing the place function, in line
with the technical stakeholder desires to create a more pedestrian friendly environment.
To achieve this shift and improve the pedestrian environment, the following elements are considered necessary
for this section of the corridor:
Reduce traffic volumes
Reduce traffic speed
Provide crossings across Glenfield Road and adjacent driveways
Increase footpath widths and provide more places to linger with more street furniture and landscaping
5.1.1
It needs to be recognised that Glenfield Road will still be classified as a regional arterial in the future and
therefore will still need to facilitate significant vehicle movements. The section of Glenfield Road between
Bentley Avenue and Kaipatiki Road caters for a combination of north-south and east-west regional traffic
movements.
The north-south movement is likely to originate from north of Glenfield (Bayview, Unsworth Heights and Albany)
and be destined for south of Glenfield (Northcote, Birkenhead and the City Centre). The east-west movement is
most likely to originate from Beach Haven and Birkdale and be destined for Wairau Valley, Milford and
Takapuna and vice versa.
As shown in Figure 5.4, the Glenfield Road corridor is the most direct north-south route in the area. The
alternative north- south routes via Birkdale, Northcote and SH1 are indirect and unlikely to provide for the northsouth movement. The Glenfield Road / Wairau Road intersection has also been recently upgraded to increase
the capacity for the north-south movement via Glenfield Road rather than Wairau Road and SH1. Therefore the
Glenfield Road corridor through the town centre will need to allow for this movement.
The recent upgrade of Glenfield Road, north of Bentley Ave provides two traffic lanes and a cycle lane in each
direction separated by a raised median. This design facilitates greater vehicle movement and currently differs to
the remainder of the corridor to the south which generally has one lane in each direction.
Document number
10
As shown in Figure 5.5, there are a number of east-west routes. Many of the routes which do not pass through
the town centre have been traffic-calmed in an attempt to discourage through traffic. Features such as raised
tables at side road intersections, restricted turning movements at intersections, heavy vehicle restrictions and a
Document number
11
more local road design have been implemented on Easton Park Parade, Peach Road, Sunnyfield Crescent and
Hogans Road. As a consequence, the natural route for east-west traffic is towards the Kaipatiki Road / Glenfield
Road intersection.
Figure 5.5 : Alternative East-West routes
Document number
12
One of the main east-west routes involves vehicles turning left from Kaipatiki Road into Glenfield Road and then
right into Bentley Ave.
SCATS data1 for the Bentley Avenue and Kaipatiki Road intersections with Glenfield Road has been assessed
to give an indication of the demand for the north-south and east-west movements through the town centre. The
data shows that the major movements at the Bentley Ave and Kaipatiki Road intersections are in a north-south
direction (approximately 75% and 50% of the total intersection movements respectively).
The data also shows that at the Kaipatiki Road intersection, approximately 25% of movements at the
intersection during the AM, IP and PM peaks are for movement B shown in Figure 5.6. At the Bentley Avenue
intersection approximately 15% of the total intersection movements are for movement A shown in Figure 5.6.
The movement data provided in Table 5.1 and Table 5.2 shows that, in the AM peak, 410 vehicles turn left from
Kaipatiki into Glenfield however only 100 vehicles turn right into Bentley. This suggests that in the AM peak
most people coming from Beach Haven and Birkdale via Kaipatiki Road are travelling north towards Albany
through the town centre. In the PM peak 230 vehicles turn left from Bentley into Glenfield and 360 vehicles turn
right into Kaipatiki. This suggests that the proportion of vehicles making the east-west movement is greater in
the PM peak.
Taken from the Glenfield Road Pre-Optimisation Report, JTOC, 18 June 2014
Document number
13
Document number
14
Table 5.1 : Turning flows between Kaipatiki Road and Glenfield Road
Peak
Left turn
Right turn
Kaipatiki to
Glenfield
Glenfield to
Kaipatiki
Total
intersection
movements
Sum
Proportion of
total movements
AM
410
180
590
2,200
27%
IP
170
170
340
1,500
22%
PM
220
360
580
2,500
23%
Table 5.2 : Turning flows between Bentley Ave and Glenfield Road
Peak
Right turn
Left turn
Glenfield to
Bentley
Bentley to
Glenfield
Total
intersection
movements
Sum
Proportion of
total movements
AM
100
80
180
2100
8%
IP
100
150
250
1500
16%
PM
100
230
330
2500
13%
One option to reduce traffic volumes between Kaipatiki Road and Bentley Ave is to encourage the east-west
movement via Downing Street rather than Bentley Ave. This could be done through removing the left turn slip
lane and providing two right turn lanes on the Kaipaitiki Road intersection arm as shown in Figure 5.12.
Removal of the left turn slip from Bentley Ave into Glenfield Road would also assist.
Currently the Downing Street / Bentley Ave intersection gives priority to Bentley Ave. An alternative treatment,
such as a roundabout, could be implemented to further encourage the use of Downing Street over Bentley Ave.
Downing Street currently carries in the order of 4,500 vpd (2012) between Glenfield Road and Bentley Ave. The
five day ADT on Bentley Ave between Chartwell Ave and Downing Street is 10,500 vpd (2009). The volume of
traffic on Bentley Ave between Glenfield Road and Downing Street is therefore likely to be in the order of 6,000
vpd.
Westfield Shopping Mall
The Westfield Shopping Mall has a significant amount of parking (in the order of 1,500 parking spaces) and is
likely to be a significant generator of private vehicle trips. The current vehicle accesses into the Westfield
Shopping Mall are shown in Figure 5.7. Some of these are used by businesses for delivery of goods and others
are used by patrons of the shopping mall to access the multi-storey parking building.
Pedestrian connectivity to the Westfield Shopping Mall is poor. In particular the frontage adjacent to the
Kaipatiki Road intersection is very vehicle dominated. The SCATS data indicates that during the AM and PM
peaks 90 and 230 vehicles respectively enter the Mall at this intersection, many turning left in.
Reducing the volume of vehicles accessing the mall at this intersection will allow for an improved pedestrian
environment. This would focus vehicle access to the mall on either Bentley Ave or Downing Street. This may in
turn affect the internal vehicle circulation of the mall car park and as such any changes to accesses into the
Westfield site would need to be discussed with the land owners.
Measures to reduce traffic volumes at the Kaipatiki Road access could include removing the slip lanes into and
out of the mall at this intersection and retaining the left turn slip from Glenfield Road into Bentley Ave. The two
right turn lanes on Kaipatiki discussed above would also assist.
Given that the Westfield site occupies a significant portion of the town centre, a collaborative approach with the
land owners will be essential to ensure a quality outcome for the town centre which improves pedestrian
Document number
15
connection to the mall while maintaining necessary vehicle access. Although private vehicle travel is likely to
remain the choice of mode for the majority of the shopping mall patrons, improvements in bus services and
walking and cycle facilities in the Glenfield area have the potential to benefit the mall if integrated well with the
adjacent land use and reduce general vehicle traffic volumes. For example bus stopping facilities and shelter
could be integrated within the Westfield site.
Figure 5.7 : Westfield Shopping Mall vehicle accesses
5.1.2
Reducing traffic speeds will assist with improving the environment in the town centre for pedestrians and
cyclists. Potential features which could be implemented through the town centre include:
Gateway treatments to signal to drivers that they are entering a different environment and should adjust
their speed accordingly
Landscaping on both sides of the road and in the central median to improve amenity and create side
friction and visual narrowing
Less and or narrower traffic lanes with wider footpaths
Alternative paving surfaces to reinforce the different environment
Rumble strips to provide some discomfort to drivers and remind them to slow down
Horizontal deflection with appropriate design to accommodate buses and emergency response vehicles
Document number
16
Provide crossings
The distance between the two signalised crossings points at Bentley Avenue and Kaipatiki Road is in the order
of 140 m. This potentially results in a 140 m detour for pedestrians wishing to cross Glenfield Road. The issue is
further exacerbated by the fact that it is difficult for pedestrians to walk longitudinally to reach the signalised
crossings. In particular, the slip lane into the Westfield Mall, the access road adjacent Mc Donalds and the
setback footpath on the western side impede pedestrians.
The pedestrian surveys recently undertaken at the Bentley Avenue and Kaipatiki Road intersections have
highlighted that one third of pedestrians crossing in the town centre crossed informally between the
intersections. Currently the raised median between the intersections provides a form of pedestrian refuge.
However it is difficult for pedestrians, particular elderly or disabled, to reach the median due to the number of
traffic lanes to cross and the lack of dropped kerbs and landings on either side.
The options shown in Figure 5.8 to Figure 5.14 all provide a midblock pedestrian crossing. This may or may not
need to be signalised depending on the crossing distance and whether the traffic flow is interrupted or
uninterrupted on this section. In the shared space options, a flush kerb would be provided and pedestrians
would be free to cross anywhere between Bentley Ave and Kaipatiki Road.
Removal of slip lanes and narrowing of vehicle accesses will also enhance pedestrian level of service by
improving pedestrians ability to walk along the corridor.
5.1.4
Typically wide footpaths are provided in areas such as town centres where the adjacent land use is likely to
generate high pedestrian volumes. Narrow footpaths with high pedestrian volumes lead to congestion on the
footpath and a reduced ability to move which provides a poor level of service for pedestrians. Wider footpaths
also provide more places to linger with more space for street furniture and landscaping to create a more
pleasant environment.
Through the Glenfield Town Centre footpath widths should be continuous and maximised where possible to
allow easy movement of pedestrians. In particular, the footpath on the western side of the town centre is narrow
in parts and set back from the road in others.
At the bus stops sufficient width should be provided to allow for a bus shelter and for passengers to wait clear of
pedestrians walking along the footpath. Shifting the bus stops north and south of the town centre, as shown in
Figure 5.10, would free up footpath space where the demand is greatest. However bus passengers may need to
walk further to access the stops and the northbound and southbound stops would not be paired.
A number of options have been developed for Section 1 to represent the above concepts. These include:
Bus facilities (Figure 5.8 and Figure 5.9)
Cycle facilities (Figure 5.10 and Figure 5.11)
Traffic calming (Figure 5.12)
Shared space 1 (Figure 5.13)
Shared space 2 (Figure 5.14)
Document number
17
Document number
18
Document number
19
Document number
20
Document number
21
Document number
22
Document number
23
Document number
24
5.2
In the present situation, conflict exists between the place function of Glenfield Town Centre and the movement
function of Glenfield Road which passes through the town centre. In particular, the movement of general
vehicles in all options has been given a lower priority than the existing situation with either shortening of the
right turn bays or removal of traffic lanes. The options presented above provide for a range of priority for the
movement and place functions.
At one end of the scale, the shared space options primarily provide for the place function with the greatest level
of service for pedestrians however this is at the expense of efficient movement of people along this section. The
significant reduction in capacity expected under these options is likely to create congestion upstream and
downstream of the town centre and divert traffic onto one of the alternative routes in Figure 5.4 and Figure 5.5.
Glenfield Road is an over dimensioned vehicle route which may compromise design elements of the shared
space options.
Feedback from Auckland Transport Metro suggests bus priority through a town centre is not considered
necessary in most cases and it is recognised that some delay through the town centre is inevitable. However
some conflict does exist between providing bus and cyclist priority as it may be necessary to move the bus
stops out of the town centre to provide a high quality, continuous cycle facility through the town centre. The bus
priority option, Figure 5.9, gives greater priority to buses but still allows for cyclists in a wide bus lane.
On-street parking has been given a low priority in the town centre and has been removed in all options where
possible to give priority to the other modes.
5.3
Preferred option
The priority for this section of the corridor has been identified as providing greater priority for pedestrians. In all
options pedestrians are given greater priority than the existing situation with improved pedestrian crossings
midblock and at intersections. The degree of priority provided is at the expense of moving vehicles and people
along the corridor.
Given that Glenfield Road will remain a Regional Arterial in the future, and that there are few alternative routes
for vehicles travelling north-south and east-west through the area, the preferred option is a combination of the
cycle facilities option and the traffic calming option. This retains some vehicle capacity however reduces traffic
volumes and speeds and improves the ability for pedestrians to cross.
As discussed above, reducing traffic volumes between Bentley Ave and Kaipatiki Road by encouraging
alternative routes may have flow-on effects outside of the CMP area. A further investigation to understand the
potential for reducing traffic volumes and the associated consequences will need to be undertaken. Consultation
with the Westfield site land owners to understand future development plans and opportunities to improve
pedestrian access should form part of this investigation.
Document number
25
6.1
Options
Document number
26
Document number
27
Document number
28
Document number
29
6.1.1
To improve pedestrian crossing ability at this intersection, a pedestrian crossing could be added to the northern
intersection arm and the left turn slip lanes could be removed. As discussed above, the reduction in vehicle
capacity over section 1 may increase the volume of traffic at this intersection, in particular the left turn from
Glenfield Road into Downing Street. Therefore it may be desirable to retain the left turn slip lane for this
movement.
6.1.2
The revised pedestrian crossings and bus stop locations for this section are shown in Figure 4.1. The existing
northbound bus stop currently located at the Downing Street intersection is in close proximity to the stop in the
town centre, particularly if the stop in the town centre is moved further south as shown in Figure 5.10. It
therefore may be appropriate to remove this stop in order to allow greater width for pedestrians and cyclists.
6.2
The priority for place on this section is not as great as the previous section primarily due to the lack of active
retail and business frontages. However this section is one of the main entrances to the town centre and will
need to provide a gateway to the town centre. The potential for the frontage on the eastern side to change in the
future needs to be discussed with the Westfield site land owners as this may increase the priority for place over
this section.
Consequently the need to reduce traffic volumes and speeds, provide more pedestrian crossings and increase
footpath widths is not as great. The main conflict on this section is between general vehicle capacity at the two
signalised intersections and providing bus priority. Cycle priority can be accommodated in all three options.
A slower approach to the town centre by general vehicles and buses is desirable and a more efficient exit from
the town centre for buses is also desirable. The southbound bus option would therefore seem to be the most
appropriate option. However if Downing Street is to be encouraged as an alternative east-west route (refer
section 5.1) then it may be necessary to provide two general vehicle southbound lanes.
6.3
Preferred option
The priority for this section of the corridor has been identified as cycle priority. The cycle facilities option is
preferred for the following reasons:
Cycle facilities separated from traffic are provided in both directions to cater for less confident cyclists
General traffic capacity is retained to offset the loss in section 1
Document number
30
Document number
31
Figure 7.2 : Section 3 road reserve - Proposed Auckland Unitary Plan GIS viewer
7.1
Options
A number of options have been developed for section 3 to deliver upon the ideal future state for the corridor.
The following options have been identified:
Figure 7.3 : Cycle facilities
Figure 7.4 : Northbound bus lane
Figure 7.5 : Southbound bus lane
Figure 7.6 : Footpaths on both sides of the corridor
Figure 7.7 : Footpaths both sides with road widening
Document number
32
Document number
33
Document number
34
Document number
35
Document number
36
Document number
37
7.1.1
This section of Glenfield Road does not have any midblock pedestrian crossings. The revised pedestrian
crossings and bus stop locations for this section are shown in Figure 4.1. This includes additional midblock
crossing points in the vicinity of the bus stops at the top of the hill near the High Road intersection. Pedestrian
improvements to the diagonal, flared intersections at High Street and Glenfield Road are also recommended to
encourage walking along the corridor.
7.2
Of the options developed, conflict primarily exists between bus priority and providing a footpath along the
eastern side of the corridor adjacent to the Oruamo Reserve. The pedestrian demand however on the eastern
side is low due to no immediately adjacent land use and steep slope in Oruamo Reserve. Medium to high level
of cycling provision can be provided with all of the options.
The option shown in Figure 7.7 would require removal of several mature trees and open space within Oruamo
Reserve. Depending on the width of widening, a significant retaining structure is also likely to be required. The
additional benefit that this option provides for pedestrians and cyclists was not considered great enough to
justify the effect on Oruamo Reserve and the additional associated costs. An alternative could be to provide a
second path through the park, between Glenfield Road and High Road.
7.3
Preferred option
The priority for this section of the corridor has been identified as cycling and public transport. The Southbound
bus lane option is the preferred option for the following reasons:
Provides high level of safety and amenity for cycling
Provides medium level of service for public transport
Pedestrian provision is fairly low as no footpath is provided on the east side of corridor adjacent to Oruamo
Reserve but alternative pedestrian routes exist on both sides of corridor
Document number
38
8.1
Options
A number of options have been developed for Section 4. The following options have been investigated:
Figure 8.2 : Southbound bus lane
Figure 8.3 : Cycle lanes and footpaths
Figure 8.4 : Cyclists on access road
Figure 8.5 : Southobund bus lane with western footpath
Document number
39
Document number
40
Document number
41
Document number
42
Document number
43
8.1.1
The Roberts Road / Glenfield Road intersection provides the main traffic connection (to the south and east) for
the Windy Ridge residential catchment contained by Kaipatiki Road in the north and Eskdale Reserve in the
south. The alternative connection for this catchment is at the Peach Road / Glenfield Road intersection (as
shown in Figure 5.5). The proposed future bus network includes a peak period and local bus service which turns
into the Roberts Road intersection.
The intersection is positioned on a corner and a steep section of the corridor with a substantial retaining wall
opposite Roberts Road. Above the retaining wall an access road provides for a small number of houses. The
access road begins opposite Capilano Place, north of Roberts Road, and exits in the vicinity of the southbound
bus stop south of Roberts Road.
An intersection upgrade scheme is being proposed at the Roberts Road intersection to improve safety, reduce
delay for vehicles turning out of Roberts Road and improve pedestrian and cycle crossing ability. The scheme
currently being proposed is shown in Figure 8.6. A previously proposed upgrade is shown in Figure 8.7.
The proposed upgrade of the intersection will need to allow for the preferred option for this section of the
corridor. The priorities through the intersection for each of the above options are illustrated in Figure 8.8 to
Figure 8.10.
Document number
44
Document number
45
Document number
46
Document number
47
Document number
48
Document number
49
8.1.2
The revised pedestrian crossings and bus stop locations for this section are shown in Figure 4.1. The current
northbound and southbound bus stops on this section are located north and south of Roberts Road
respectively. The southbound bus stop is currently set back from the road edge and has poor visibility to
southbound buses.
The recent pedestrian surveys indicated demand for the bus stops was predominantly coming from Roberts
Road. A pedestrian crash also occurred in the vicinity of the southbound bus stop. Improved pedestrian
crossings of Roberts Road and Glenfield Road would therefore be beneficial to provide access to the bus stops.
As illustrated in the above figures, the southbound bus stop could be moved forward to the road edge to
improve visibility, remove the need for buses to pull into and out of a recessed bay and allow cyclists to travel
behind the bus shelter.
The property boundary on the north-west corner of the intersection is set back in the order of 8 18 m from the
existing carriageway edge. Currently a northbound bus stop and a number of vehicle accesses are located in
this area. The northbound bus stop could be moved south of the intersection to allow more space for any
upgrade of the intersection subject to further investigation and design of the upgrade.
8.2
Of the options developed, conflict primarily exists between providing bus priority and footpaths adjacent to the
road reserve as there is not enough space in the corridor to do both. A high level of cycle provision can be
provided with all of the options.
8.3
Preferred option
The priority for this section of the corridor has been identified as cycling and public transport. The Southbound
Bus Lane is the preferred option for the following reasons:
Provides high level of safety and amenity for cycling
Provides medium level of service for public transport
Similar to Section 3, the preferred option does not provide footpaths adjacent to the corridor in both
directions as the adjacent access roads are considered to provide adequately for pedestrians
Document number
50
9.1
Options
Document number
51
Document number
52
Document number
53
Document number
54
Document number
55
Document number
56
9.1.1
As discussed in the problem definition, an intersection upgrade scheme is being proposed at the Coronation
Road intersection to improve safety. The proposed scheme is shown in Figure 9.7.
Figure 9.7 : Coronation Road / Glenfield Road current intersection upgrade scheme
Document number
57
9.1.2
The revised pedestrian crossings and bus stop locations for this section are shown in Figure 4.1. Currently this
section has two informal pedestrian crossings which align relatively well with two pairs of bus stops.
The southbound bus stop south of the Coronation Road intersection could be moved further south to allow more
space for the Coronation Road / Glenfield Road intersection upgrade, increase the bus stop capacity and
position the stop so that it does not conflict with driveways. Although moving the stop further south would move
it away from the catchment on Coronation Road it would be closer to the petrol station and provide access for
the proposed Community Environmental Centre in Eskdale Reserve.
A pedestrian crossing point could be provided to align with the walkway through to Greta Place as this is likely
to be a desire line to Eskdale Reserve, particularly in the future if the proposed community centre is built.
The northbound bus stop adjacent to the cemetery is approximately 250 m south of the bus stop at Speedy
Crescent and 90m north of the Eskdale Road intersection. There currently is no footpath north of the bus stop
and the Eskdale Road intersection is the closest crossing point. The stop could be moved closer to Park Hill
Road and McDowell Crescent where the demand is likely to be greater and so that it is paired with the
southbound stop.
9.2
Of the options developed, conflict primarily exists between providing bus priority and dedicated cycle facilities in
both directions. Improved pedestrian facilities can be provided with all but one of the options considered.
In order to provide space for cycle facilities and a southbound bus lane, the existing flush median and on-street
parallel parking is removed. The existing flush median provides space for vehicles turning into Speedy Crescent
and the properties on the eastern side of the corridor.
This section of the corridor has fewer side road and property accesses than the majority of the corridor yet it is
one of the few sections with a flush median. Therefore reallocating the flush median space to other modes is
considered appropriate and consistent with the remainder of the corridor. Removal of the flush median removes
space for informal crossing points, however an alternative form of pedestrian crossing facility could be
considered.
9.3
Preferred option
The priority for this section of the corridor has been identified as walking and cycling. The Protected Cycle
Lanes option is the preferred option for the following reasons:
Provides high level of safety and amenity for cyclists
Provides high level of safety and amenity for pedestrians
Provides medium level of service for public transport
Document number
58
10.
This section connects the two signalised intersections at Eskdale Road and Pupuke Road. Some of the
residential properties on the western side are situated below the road level and at the Pupuke Road intersection
some properties are above the road level. The retaining walls on the western side of the road are a significant
constraint for future options along this section.
A typical cross section is provided in Figure 10.1. Narrow footpaths and on-street parallel parking are provided
on both sides of the street with a traffic lane in either direction.
In the present situation, conflict exists between vehicular movement along Glenfield Road and walking and
cycling along and across the corridor, similar to previous sections. Vehicle movement is currently prioritised and
relatively low priority is given to pedestrians and cyclists throughout this section of the corridor. There are no
dedicated cycle facilities through this section of the corridor and the west side of the corridor does not have a
footpath for a short distance on each side of the Pupuke Road intersection. Bus priority does not currently exist
and it has been identified as important for the corridor.
Figure 10.1 : Section 6 - existing cross section
10.1
Options
Document number
59
Document number
60
Document number
61
Document number
62
Document number
63
Document number
64
10.1.1
Eskdale Road is one of the main east-west routes connecting Beach Haven and Birkdale with SH1 and the city,
Northcote and Takapuna (refer Figure 5.5). The alternative east-west route is via Waipa Street and Highbury
Bypass (part of the Onewa Road CMP). The Birkenhead / Glenfield cemetery is on the north-western corner of
the intersection and fronts approximately 400 m of Eskdale Road as it approaches Glenfield Road.
Currently the Eskdale Road intersection is signalised with two northbound and southbound lanes on Glenfield
Road and left turn slip lanes from into and out of Eskdale Road. The slip lanes do not have pedestrian priority,
there is no signalised crossing on the southern approach and the crossing on the northern arm is skewed to
avoid a driveway. Pedestrian priority could be provided on the slip lanes or they could be removed and a new
crossing could be provided on the southern approach.
The options for priority through the intersections are shown in Figure 10.7 to Figure 10.9.
Document number
65
Document number
66
Document number
67
10.1.2
Pupuke Road provides a connection between Northcote Town Centre and Glenfield Road (refer Figure 5.5).
The Pupuke Road / Glenfield Road intersection caters for some east-west regional movements from Beach
Haven and Birkdale to Northcote, Takapuna and SH1.
A retaining wall runs along the western side of the Pupuke Road intersection. On top of the retaining wall an
access road provides access to a small number of properties and Pompallier Cemetery. Currently the
intersection is constrained on the west side by the retaining wall and on the east side by property boundaries.
The options for priority through the Pupuke Road / Genfield Road intersection are illustrated in Figure 10.10 to
Figure 10.12. The southbound approach currently has a long left turn slip lane which makes it challenging for
cyclists to travel southbound through the intersection. In a northbound, uphill direction, the retaining wall also
creates an intimidating environment for cyclists.
Document number
68
One potential option for cycle provision through the intersection is to divert northbound cyclists onto the access
road on the western side of the intersection. Although the access road is quite steep, traffic volumes and
speeds are low and northbound cyclists would not need to stop at the intersection, reducing their delay. Pupuke
Road is recognised as a Cycle Connector in the Auckland Cycle Network which suggests a connection between
Glenfield Road and Pupuke Road is desirable.
The only pedestrian crossing at this intersection is on the Pupuke Road approach. The provision of pedestrian
crossings across Glenfield Road is difficult due to the retaining wall. However a pedestrian crossing point could
be provided south of the intersection to connect the two bus stops in the vicinity of the existing walkway from
City View Terrace.
This intersection has been recognised as an issue for existing bus operation in the southbound direction in the
AM and PM peaks. The currently proposed future bus network has one service which joins the Glenfield Road
corridor at Pupuke Road. In order to provide bus priority through this intersection may require some land
purchase on the eastern side of the road as indicated in Figure 10.11.
The south-east corner of the intersection is zoned for terrace housing and apartment buildings in the Proposed
Auckland Unitary Plan. This has the potential to increase the volume of pedestrian, cycle and general vehicle
traffic in the vicinity of the intersection and may warrant wider footpaths at the intersection. This further supports
the case for land take but further investigation is required to justify the need for land take.
Document number
69
Document number
70
Figure 10.11 : Glenfield Road / Pupuke Road intersection - southbound bus priority
Document number
71
Document number
72
10.1.3
The revised pedestrian crossings and bus stop locations for this section are shown in Figure 4.1. This section
currently has two southbound bus stops and one northbound. As discussed above, the northbound stop
currently north of Eskdale Road could be brought south to align with the southbound stop and cater for a greater
passenger catchment.
There has been a pedestrian crash in the vicinity of the other pair of stops on this section. A crossing point in
this location would improve access to the bus stops and pedestrian safety.
10.2
The main conflict on this section is between bus and cycle priority, particularly in the locations constrained by
the existing retaining walls such as at the Pupuke Road intersection. The southbound approach to the Pupuke
Road intersection has been identified as one of the worst sections along the corridor for bus operation. To
provide bus priority through the Pupuke Road / Glenfield Road intersection will likely require land take. If
sufficient land is acquired then there is the potential to also provide some southbound priority for cyclists.
10.3
Preferred option
The priority for this section of the corridor has been identified as southbound bus operation. The Bus Facilities
Southbound option is preferred for the following reasons:
Cycle facilities separated from traffic are provided in both directions to cater for less confident cyclists.
Footpath widths are increased on both sides by removing the existing grass berm, and providing a
cantilever footpath where the width of corridor is constrained by the large retaining wall. Further
investigation and design should consider a number of options to allow for the facilities in Figure 10.6. An
alternative to providing a cantilever footpath would be to purchase property on the eastern side.
Bus operation in the southbound direction has been recognised as an existing issue, particularly in the AM
peak. This will likely get worse in the future as traffic volumes and congestion on the corridor increase. A
southbound bus lane is provided to improve bus travel time reliability on the approach to the Pupuke Road
intersection.
The priority for pedestrians is considered low over this section however in the preferred option, the existing
footpath widths are retained and improved crossing facilities could be provided. Priority for general vehicles over
this section is considered low. One general traffic lane in each direction is retained however on-street parking is
removed.
Document number
73
11.
The Birkenhead Avenue section is largely characterised by residential properties on both sides of the road with
many private driveways having access from Glenfield Road. Birkenhead Domain and playing fields are located
on the west side of the corridor. At the southern end of the section, the corridor intersects with Onewa Road and
Birkenhead Town Centre is located to the south of the intersection. The land adjacent to the corridor between
Pupuke Road and Onewa Road is zoned for terrace housing and apartment buildings in the Proposed Auckland
Unitary Plan.
At some locations along this section of the corridor, the residential properties on the eastern side are situated
below the road level. This is shown in Figure 11.2 and illustrated in the existing cross section in Figure 11.1.
Widening the existing carriageway to the east will steepen vehicle accesses on this side, and may lead to
flooding issues for some of the properties on the eastern side. Figure 11.2 shows that currently, stormwater is
captured via a drain between the footpath and grass berm which flows into a stormwater pit built into the grass
berm. The options presented below which widen the carriageway will likely require the road to be regarded from
boundary to boundary, with adjustments or upgrades to the existing stormwater system.
Figure 11.1 : Section 7 - existing cross section
Document number
74
Document number
75
11.1
Options
Document number
76
Document number
77
Document number
78
Document number
79
Document number
80
11.1.1
As highlighted in the problem definition, there are a number of bus operational issues at the Onewa Road /
Birkenhead Avenue intersection at the southern end of the corridor. The major issue is the inability of buses to
turn left and right into Onewa Road from Birkenhead Ave and Hinemoa Street respectively when eastbound
general vehicles are queued back to the intersection.
Onewa Road currently has a T3 transit lane eastbound. The Onewa Road CMP proposes to implement T3
transit lanes in both directions through the intersection in the future.
One concept to resolve the bus operational issues at this intersection is presented in Figure 11.7. The purpose
of the concept is to provide bus turning lanes which are shifted further west than the existing turning lanes. This
allows more space for buses to turn into Onewa Road when an eastbound queue is present. A consequence of
this realignment is that a through lane is removed from the Hinemoa approach.
It may also be necessary to remove some of the on-street parking on the Hinemoa Street approach to enable
enough queuing space so buses are not blocked from entering the dedicated right turn bus lane. Similarly the
dedicated bus lane on Birkenhead Ave could be made longer, by removing the existing grass berm, to ensure
buses can access it.
The intersection currently has left turn slip lanes on all four approaches. The recent pedestrian surveys
undertaken at the intersection suggest there is high demand for pedestrians crossing the northern intersection
arm. To facilitate this movement, the left turn slip lane into Birkenhead Avenue could be removed. The left turn
slip lanes from Hinemoa Street and from Onewa Road could also be removed to improve pedestrian crossing
level of service.
The parcel of land on the north-west corner of the intersection is classified as Public Open Space Informal
Recreation in the Proposed Auckland Unitary Plan. Enhancement of this area as a public open space in the
future may increase pedestrian activity at the corner of the intersection. This would further support removal of
the left turn slip lane into Birkenhead Ave to provide more space for pedestrians.
As part of the Onewa Road CMP, Flow Transportation Specialists undertook SIDRA modelling of the
intersection to test the effect of removing all of the left turn slip lanes. It was recommended that the need for all
of the slip lanes be reviewed and that some (or all) be removed.
The modelling showed that the existing intersection is at capacity in the AM and PM peaks.
The dominant movements in the AM peak (accounting for approximately 50% of all movements) are:
Through eastbound on Highbury Bypass to Onewa Road
Left from Highbury Bypass into Bikenhead Ave
Through from Birkenhead Ave to Hinemoa Street
The dominant movements in the PM peak (accounting for approximately 50% of all movements) are:
Through westbound on Onewa Road to Highbury Bypass
Right from Birkenhead Ave into Highbury Bypass
Through from Hinemoa Street into Birkenhead Ave
The dominant movements at the intersection are in the opposite directions in the AM and PM peaks. This gives
an indication of the commuting patterns in the area. The east-west through movements likely correspond to
people commuting to the city via SH1, the movement between Higbury Bypass and Birkenhead Ave likely
corresponds to people commuting to Albany and Glenfield Town Centre and the north-south through movement
may be demand for the Birkenhead Town Centre and Birkenhead ferry.
Document number
81
Document number
82
11.1.2
There have been a number of pedestrian crashes on this section of the corridor which has few pedestrian
crossing points. The revised pedestrian crossings and bus stop locations for this section are shown in Figure
4.1.
The two bus stops near Waratah Street could be moved closer to Zion Road with an additional crossing
between them. The southbound bus stop near the Pupuke Road intersection could be moved further south and
paired up with the northbound stop adjacent to Birkenhead War Memorial Park. A pedestrian crossing point to
improve access to these stops could be provided in the vicinity of the walkway connecting to City View Terrace.
11.3
Preferred option
The priority for this section of the corridor has been identified as bus provision. The Southbound bus lane with
cycle facilities is the preferred option for the following reasons:
Cycle facilities separated from traffic are provided on both sides of the road to cater for less confident
cyclists.
A southbound bus lane is provided to improve bus travel time reliability on the approach to the Onewa
Road intersection which has been identified as one of the worst sections along the corridor for bus
operation
Document number
83
12.
Summary
A summary of the priorities for each option is provided in Table 12.1. It can be seen that throughout the corridor
general vehicles have generally been given a low priority. The exceptions to this are where an option provides
more than one lane in each direction (e.g. section 1 and 2) and / or provides on-street parking (Section 3, 4, 5
and 6).
The table below demonstrates that many of the options considered give either high or medium priority to
cyclists. It also demonstrates that there generally is conflict between providing priority for pedestrians and
providing priority for buses (when one is high, the other is low).
Table 12.1 : Priority summary
The greatest points of tension of tension along the corridor are in the two northern sections where conflict exists
between the place and movement functions and in the southern two sections where bus priority conflicts with
cycle provision. Overall, when the preferred options for each of the sections are combined, a long term strategic
direction for the Glenfield Road corridor is created. The strategic direction balances the conflicting priorities and
responds to the ideal future state defined by the technical stakeholders.
In the Glenfield Town Centre increased emphasis has been placed on slowing and reducing traffic to create a
place that prioritises people over the movement of traffic. Public transport has been prioritised in the
southbound direction in most sections of the corridor to provide improved reliability for bus movements. No bus
Document number
84
priority is provided in sections 1, 2 and 5. Cycling improvements have been proposed throughout the corridor
with dedicated facilities on most sections to attract the interested but concerned sector of the population to
start cycling. Pedestrian improvements have been proposed throughout the corridor to improve safety, comfort
and amenity of pedestrians travelling along and across Glenfield Road.
Document number
85