Snagging List: ISSUE: 02 DATE: 01.11.2012 REV.: 01 FORM NO.: SPML-CAD-F-018

This document provides a snagging list for Villa Z1-TH-20 of the Meerass 300 Villa Project in Al Ain Road, Umm Al Daman, Dubai. It was inspected on January 3, 2016 and contains 22 items needing correction, including issues like paint on manual pull stations, gaps around panels and detectors, misaligned switches and outlets, and missing or improper covers. The subcontractor Shapoorji Pallonji Mideast is responsible for addressing the items in the list.

Uploaded by

sujan1980
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
1K views

Snagging List: ISSUE: 02 DATE: 01.11.2012 REV.: 01 FORM NO.: SPML-CAD-F-018

This document provides a snagging list for Villa Z1-TH-20 of the Meerass 300 Villa Project in Al Ain Road, Umm Al Daman, Dubai. It was inspected on January 3, 2016 and contains 22 items needing correction, including issues like paint on manual pull stations, gaps around panels and detectors, misaligned switches and outlets, and missing or improper covers. The subcontractor Shapoorji Pallonji Mideast is responsible for addressing the items in the list.

Uploaded by

sujan1980
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

Description:

Snagging List
ISSUE: 02

DATE: 01.11.2012

REV.: 01

FORM NO.: SPML-CAD-F-018

PROJECT :--MEERAS 300 VILLA PROJECT @AL AIN ROAD, UMMALDAMAN,DUBAI

Snag Item Listing


Sub Contractor : Shapoorji pallonji Mideast (L.L.C)
Work Designation: Villa Z1-TH-20
Zone

ZONE-01

Level

GROUND FLOOR

Inspection Date

3-JAN-2016

Villa No

Z1-TH-20

Room

ALL

Inspected By

JAMSHEED

No.

Description

Paint found on the external surface of the manual pull station .

Sealant not provided around the DB,12 U cabinet and fire alarm control panel hence small Gap
found on the edge of the panels.

Courtyard light switch not aligned in entrance area.

Sealant not provided around the manual pull station in the entrance area.

Dummy circular covers not provided for the light points.

Identification labels not provided for the power socket and lighting.

Catv and power socket are not align in dining room.

AC unit not flush with the wall in dining room.

Installed Water heater dummy cover was not approved by the consultant .

10

Light switch inside the bedroom 4 was not aligned.

Re-inspected

With / Without RE:


Page :
Closed Out

Closed Out
Consultant

Date

11

Sealant not provided on the bottom of the AC unit in bedroom-04

12

Small gaps found near the edge of all smoke detector.so sealant to be provided around the
detector

13

Ac unit not flush with the wall. sealant to be provided around the units in bedroom-03.

14

Catv & power socket not aligned in bedroom-03.

15

3 gang and water heater dummy cover not in straight line.

16

Sealant not provided around the junction box inside bedroom toilet-02

17

Single power socket not in aligned inside the master bedroom.

18

Angle valve cover not fixed inside the kitchen.

19

Washing machine outlet not in align and protected.

20

Cooker outlet not covered and protected.

21

power socket and Telephone outlet dummy cover are not in aligned.

22

Sealant not provided around the power socket inside the driver room