Annual Budget 2016 Paper D
Annual Budget 2016 Paper D
Annual Budget 2016 Paper D
Committee
FULL COUNCIL
Date
20 JANUARY 2016
Title
Report of
EXECUTIVE SUMMARY
1.
2.
This paper identifies potential choices for the council to consider drawn from
those remaining areas where the council has no legal duty to provide a
service in order to achieve these challenging savings in response to the
Governments tight financial settlement. This settlement brings into question
the future viability of the council. It presumes an increase in Council Tax of
3.99 per cent which is assumed by Government in the settlement.
INTRODUCTION
3.
This report follows the budget review that went to the Full Council on
2nd September and 14 October 2015. It updates the councils financial position
in the context of the Comprehensive Spending Review and Autumn Statement
announced on 25 November 2015 and the Provisional Local Government
Finance Settlement announced on 17 December 2015.
4.
The budget review identified a number of further savings and Full Council
agreed further savings in 2015/16 be implemented. These amounted to
2.402 million of one off savings and 1.482 million of recurring savings a
total of 3.884 million against the projected net overspend in 2015/16 of
4 million. For 2016/17 the projected revenue budget gap was 15.794 million
of which potential savings options of 13.449 million had been identified and
were being developed leaving a remaining gap of 2.345m. The savings
identified, however, contained some options that would be very challenging to
deliver and required significant refinement.
D-1
5.
This report sets out the updated position after taking into account the
Comprehensive Spending Review, the Local Government Finance Settlement,
and the latest budget monitoring position. The overall projected position for
2015/16 is that the revenue budget will not be exceeded. For 2016/17 the
overall revenue budget gap including the impact of use of reserves in 2015/16
and budget gap carried forward (6.769 million) is now projected at 17.386
million.
6.
7.
8.
In the context of the sheer scale of grant reductions and budget pressures the
council will face over the next four financial years 2016/17 to 2019/20 the
report sets out the proposed way forward in ensuring that the council can
BACKGROUND
9.
The very serious financial challenge facing the council has been well
documented, with the impact of significant government grant cuts leading to
ongoing revenue savings of some 50 million having to be made from 2011/12
to 2015/16. The Budget Review report to the 2nd September 2015 Full Council
set out the then projected budget position for 2015/16 and 2016/17 and a
D-2
number of further savings options were agreed. The figures projected were by
no means the worst case scenario with the risk that grant reductions would be
higher than projected and the likelihood that further significant grant losses
would be suffered through the Comprehensive Spending Review (2016/17 to
2019/20).
10.
It was clear that for the foreseeable future the council faced a significant
budget gap each and every year as the reduction in government grants plus
increased costs will always substantially outweigh its ability to raise income
through council tax and local income.
11.
This means that the current level of services and activities are unaffordable
and significant reductions will need to be made to deliver lawfully balanced
budgets.
STRATEGIC CONTEXT
12.
The councils existing corporate plan was agreed by Full Council at its
meeting on 1 April 2015. This will need to be further updated as result of the
decisions taken through the budget process.
13.
To achieve the vision and deliver the priorities and outcomes within the
resources that will be available the council needs to operate radically different
than it does now. By moving to an enabling council, commissioning for
delivery of outcomes rather than directly providing services and working
through strategic partnerships means a different approach.
14.
This approach entails having a much smaller directly employed workforce with
the officer structure and corporate support directly linked to the delivery and
achievement, mainly through external arrangements, of the agreed council
priorities and outcomes.
The Chancellor of the Exchequer announced the autumn statement and the
Comprehensive Spending Review on 25 November 2015. This set out the
overall framework for public spending over the remaining life of the parliament
2016/17 2019/20.
16.
In dealing with the national deficit public services spending limits and changes
to resource levels were set out with a view to achieving a national surplus in
2019/20.
17.
A number of service areas were given relative protection such as the NHS,
Education and the Police and major investment announced in housing but for
local government it set out very significant reductions in grants over the next
four financial years.
18.
D-3
Business Rates:
18.1. Confirmation that by 2019/20 100 per cent of business rates will be retained
by local government as opposed to the current 50 per cent .Consultation on
the changes to the local government finance system to pave the way for the
change will be undertaken next year.
18.2. The Government will still set the business rate and local authorities will only
be free to reduce business rates and not increase them except under an
elected mayor model and then only in limited circumstances.
18.3. There will still be an equalised baseline at the start to protect councils like the
Isle of Wight who currently receive a top up grant. It is also likely that the 100
per cent of business rates will not be based on individual authorities but on
some form of regional grouping.
18.4. By 2019/20 the yield from 100 % of business rates is estimated to be
13 billion nationally more than the reduced spending level for local
government. To make up for this the government intends to transfer additional
responsibilities and costs to local authoritys equivalent to 13 billion. This
could include public health and housing benefits for pensioners.
18.5. The government have also extended again the doubling of the small business
relief for another year
Devolution
18.6. The government are still promoting the use of devolution deals as the
approach to redistributing powers and responsibilities away from Whitehall for
local determination and management. It sees this as being a major vehicle for
encouraging economic growth in areas with devolved powers and that this
economic growth will provide sufficient additional income to sustain the
provision of services by local government.
18.7. The government also now has powers to impose devolution arrangements
where local authorities are unable to reach collective agreements about how
they would work together. It has also made it easier for the creation of new
authorities and for new geographies of local authorities to work together in the
delivery of devolved duties.
18.8. Devolution would seem to be key to the central proposition that local
government services are funded by the retention of 100% of business rates.
Government grants and spending controls
18.9. The main general fund revenue grant the council receives is the Revenue
Support Grant (26.103 million in 2015/16). It is intended that this grant will be
phased out by 2019/20 and with other grants be replaced by having 100 per
cent of business rates. Before this, however, there is a significant decrease in
grants in each of the next four financial years:
20.
The Provisional Settlement set out individual council grant figures for the four
financial years 2016/17 to 2019/20. The government are offering every council
D-5
that desires one and which can demonstrate efficiency savings a four year
settlement to give certainty of over resource levels.
21.
22.
The table below sets out the position for 2016/17 the Isle of Wight.
Actual
2015/16
million
2016/17
Provisional
Settlement
17 Dec 2015
million
Change
million
17.294
12.449
29.743
26.103*
1.088
56.934
17.440
12.550
29.990
18.082
1.088
49.160
+ 0.247
-8.021
-7.774
3.056
3.920
+0.864
1.423
1.291
-0.132
61.413
54.371
- 7.042
*Revenue support grant includes council tax support grant. The council tax
figure is net of this grant as the support given no longer counts as council tax
Income.
23.
The table shows a significant reduction in the main grants received by the
council. In addition there is a public health grant that is ring-fenced which will
also be the subject of real term cuts over the next five years. There are also a
few other grants that are still to be announced.
24.
It can be seen that the settlement funding assessment (before New Homes
Bonus, Education Services Grant etc.) has been cut by 7.774million in
2016/17 compared to the current financial year.
25.
The council receives additional funding for adult social care via a transfer from
Health. In 2014/15 this increased to 3.513 million. For 2015/16 there were
new arrangements for a Clinical Commissioning Group (CCG) and local
authority pooled Better Care Fund (BCF). This fund is to enable integration of
health and care services. The Clinical Commissioning Group and local
authorities must agree locally through Health and Wellbeing Boards how the
funding will be spent across health and care services. For 2015/16 the Council
received 6.674 million.
D-6
26.
For 2016/17 the council is still in discussion with the CCG over the allocation
but there is a risk that this will be reduced by 2.1 million .If this is the case it
will add to the overall budget gap.
27.
28.
29.
The additional 1.5 billion national funding for adult social care is very
weighted to the later years with nil in 2016/17, 105 million in 2017/17,
825 million in 2018/19 and the full 1.5 billion in 2019/20. The councils
indicative allocation is a mere 100,000 in 2017/18, 2.2 million in 2018/19
and 4.2 million in 2019/20. To offset this however 700 million of this
nationally is being funded by transferring grant from the New Homes Bonus
and therefore the council will have reduced funding from that source of
1.5 million in 2018/19 and 1.6 million in 2019/20.
30.
Budget pressures
31.
32.
33.
The latest revenue budget monitoring position indicates that the overall
revenue budget will not be exceeded.
(b)
Capital Programme
34.
The council received a 17.5 million capital receipt as part of the disposal of
the employment land at Pan to Asda. Full Council on 2 September 2015, as
part of the consideration of the Budget Review, agreed that the capital receipt
be used proactively to reduce revenue costs and/or generate revenue income.
36.
A member group chaired by Cllr Lumley met to consider ideas and options for
the use of the capital receipt. They made recommendations to the Budget and
Policy Liaison Group and these were endorsed by that group. The
recommendations are set out in Appendix C.
37.
The council agreed, as part of the budget for 2014/15 and 2015/16 to increase
council tax at the maximum level that did not trigger a referendum i.e. by
1.99 per cent each year. In calculating the budget gaps it has been assumed
that there will be further annual increases of 1.99 per cent each year. It is also
assumed that, because of the councils very difficult financial challenge and
the scale of savings required anyway that an additional 2% increase will be
levied in respect of adult social care costs.
39.
To put it into context a 1.99 per cent increase on the councils element of
council tax would cost an extra 26.70 per annum on a Band D property
equivalent to some 50 pence per week. The 2% on adult social care would
cost an extra 26.83 on a Band D equivalent. Together a 3.99% increase
would cost some 53.53 just over a 1 per week. For those on low incomes,
who get local council tax support, about a half are pensioners and if their
income level supports it they can get up to 100 per cent support. In addition
under the local council tax support scheme those classified as working age on
low incomes can also get support towards their council tax bills. A separate
report on the agenda sets out the proposed local council tax support scheme
for 2016/17.
The majority of the councils reserves and balances are set aside for a specific
purpose and are not useable as part of the budget strategy e.g. Highways PFI
D-8
The useable general fund balances and insurance risk reserve totalled
15.409 million at 31 March 2015. This included the extra 241,000 from the
savings on the outturn for 2014/15. As part of the 2014/15 -2016/17 budget
strategy agreed at Full Council in February 2015 the use of a total
4.367 million in 2015/16 was agreed.
42.
After use of the repairs and renewals fund the estimated total used in 2015/16
is 5.706 million leaving a net total of 9.703 million at 31 March 2016
43.
44.
46.
This shows a total budget gap over the four financial years of 31.455 million
of which 23.504 million (75 per cent) falls in the next two financial years.
BUDGET STRATEGY
47.
48.
The overall strategy that the Council has been pursuing to deal with this
position is to achieve a medium-term financial approach that seeks to match,
over time, the net cost of the activities that the Council undertakes with the
resources it has at its disposal.
D-9
49.
To ensure that the limited resources the council has are directed to fulfilling its
statutory duties and achieving its priorities a refreshed vision and priorities
were developed and a corporate plan was agreed by Full Council on 1 April
2015. In order to deliver lawfully balanced budgets the strategy has been to:
Work in partnership to deliver outcomes for the island that the council
can no longer afford to do by itself and to enable the opportunities of
the social capital of the Island to be fully utilised
The council has faced a significant financial challenge over the last few years
as a result of the government austerity measures. Local government has been
subjected to an programme of grant cuts and from the Comprehensive
Spending Review and Local Government Finance Settlement will face even
greater challenges over the next four financial years 2016/17 to 2019/20. In
agreeing a budget for 2016/17 the council also needs to have due regard to
the total projected budget gap for 2017/18, and the likely resources position in
2018/19 and 2019/20.
51.
fenced to local authority services. The council must therefore ensure it is able
to create robust financial and service delivery plans for it to prevail through the
immediate challenges it faces.
52.
To prevail the council must first be assured that it allocates the limited
resources it will have available to meet its legal duties and obligations and that
it is providing these services in the most cost effective manner. This does not
mean that it has to provide the services directly itself but that it is receiving
value for money from all of its suppliers which stands comparison with
councils in similar circumstances across the country. Part of reaching this
affordable position will be to consider many of those services which although
related to its legal duties (much work that it is preventative could be
considered in this regard) do not actually have to be provided although likely
to save the council money over the longer term.
53.
Only when the council is certain it can discharge its legal duties and
responsibilities can it then look to provide other services the community may
want/need but which the council does not have to provide. Its challenge will
be in considering which services it has the power to provide that could help
secure additional income and economic growth over the medium term which
could help to fund its legal obligations.
54.
Having consolidated its activities to a baseline position the council can then
focus its attention on further improving the delivery and impact of these
services ultimately seeking to make them best in class for the money
available. These improvement activities themselves should aim to ensure the
services are sustainable in the longer terms and release resources that could
be added back to reintroducing activities that seek to prevent and reduce
service demand over the longer term.
55.
56.
The proposed Hampshire and Isle of Wight devolution deal with government
continues to offer an opportunity for the council to rebuild from its baseline
position far sooner than if it continues to operate independently. The current
proposition pools any economic growth across the whole area for its
redistribution based on a number of criteria including need and reward. If the
deal is agreed it is unlikely to begin before April 2017 and there would be a lag
in the start of any economic benefits, so the council would still need to secure
its baseline position and operating model at the start of the devolution deal.
One challenge which the council would need to take account of in developing
D - 11
The expeditious use of the councils capital receipts from the sale of the
employment land to Asda will be central in securing the councils baseline
position from which it can develop. The proposals in Appendix C are
consistent with the councils aim to reduce revenue costs or increase income
and if the full businesses cases for these proposals do not meet this test then
alternative schemes should only be considered where this is the case.
Council may also wish to consider to what extent it is prepared to use capital
receipts earned after 31 March 2016 to support the revenue costs of projects
to transform the organisation and agree local criteria in this approach.
58.
The council has made representation to government about the use of capital
receipts to fund the revenue costs of transformation projects and asked that it
be allowed to use up to 5 million of the Asda receipt for this purpose;
3 million being earmarked for regeneration (economic growth) projects and
2 million for corporate transformation.
59.
In the published provisional local council tax settlement the government has
assumed that the council will increase its council tax by 1.99 per cent and
introduce an increase of 2 per cent to fund increasing adult social care costs
in each and every year of the four year settlement. Officers have therefore
had to assume that Full Council will agree to these changes for at least
2016/17 as to not do so would increase the significant funding gap still further.
60.
The council is able to consider increasing the council tax rate beyond the
currently assumed 1.99 percent (for the council overall) but this would require
a referendum which would have to take place only after the budget has been
set. Any referendum would come at a significant cost to organise (estimated
100,000) and if not supported the council would also have to reissue the
council tax bills. All at a time when the councils overall resource availability is
extremely limited. A 10.3% increase in the Council Tax (134.15 a year for a
Band D property) would be necessary to generate revenues of 7 million and
replace the reduction in government grant funding.
61.
62.
63.
64.
65.
Amount ()
17,386,000
Planned Savings
Agreed savings in MTFP for 16/17
(D1)
-7,886,500
-2,100,000
66.
-9,986,500
7,399,500
-7,168,568
CONSULTATION
67.
The council has been in dialogue about its challenging budget position with
governments Department of Communities and Local Government (DCLG)
since summer 2015. Further meetings and discussions were held following
the publication of the Comprehensive Spending Review and Provisional Local
Government Finance Settlement. Part of the focus of these discussions has
been to understand how the government might agree the council has reached
the tipping point where it no longer has sufficient resources to meet its legal
duties. These discussions remain ongoing.
D - 13
68.
A meeting with Marcus Jones MP; Minister for Local Government, was held on
6 January. Facilitated by the Islands MP the councils delegation included the
Leader, Leader of the main Opposition Group. Chief Executive and Head of
Finance and 151 Officer. The brief sent in advance of the meeting is attached
at Appendix E for information. The Minister acknowledged the challenges
facing the Island and the council but was unable to commit to any additional
funding for it in the finance settlement given the constraints on the national
budget. He encouraged a further written response in the use of capital
receipts earned before March 31 for transformation revenue projects.
69.
70.
71.
The outcomes from these will be taken into account and a summary included
in the final budget report to the Executive and Full Council in February 2016.
72.
There is continuing consultation with staff and unions on the overall budget.
Regular meetings have been held of the Joint Consultative Meeting which
comprises elected members and union representatives. Depending on the
savings options developed and agreed for implementation there will need to
be appropriate formal consultation with stakeholders, staff and unions. Those
savings that relate to staffing may result in redundancies and the formal
statutory HR1 notification.
This report is entirely about the overall financial and budgetary position of the
Council and updates the financial and budget issues that the Council is
facing that were reported as part of the Budget Review to Full Council in
September and October 2015.
74.
The council faces a significant level of reduction in the resources that it will
have available to fund services. The level of grant reductions from
government is significant each and every year for the foreseeable future. The
current level of service delivery and the activities it undertakes is not
affordable and therefore budget options must be developed to deal with this
position.
75.
The budget gap relates to the revenue position of the council .For capital
spend those costs not able to be met from government grants or capital
receipts have to be met from borrowing. The borrowing costs have to then be
provided in the revenue budget. Details of the draft capital programme for
2015/16 to 2016/17 are set out in Appendix B.
D - 14
LEGAL IMPLICATIONS
76.
The Council will need to set a lawful and balanced budget and Council Tax
level for 2016/17 at the Full Council meeting on 24 February 2016. In
developing any proposals for budget changes the necessary equality impact
assessments and consultation processes will need to be followed.
77.
The council has many duties which it must undertake by law. There is
currently no guidance or precedent for what might happen if the council
considered it had insufficient resources for it to undertake the legal duties
required of it. It may be necessary for the council to seek external guidance
in this regard as it develops the budget over the period of the local
government settlement.
78.
The council is unlikely to be able to accept any agreement for a four year
settlement from government if it is uncertain that it will be able to meet its
legal duties as result of the funding it will receive in any agreement.
79.
The ability to implement savings that deliver a full year effect in 2016/17 is
dependent on undertaking the necessary statutory processes and
consultation within a timescale that enables savings proposals to be
implemented with some effect from 1 April 2016. It is therefore necessary
now to identify any areas that are likely to be the subject of savings
proposals so that they can be properly worked up to allow for as much of an
effect as possible in 2016/17.
80.
If the totality for the scope of the proposed reduction in number of required
posts and therefore potential redundancy exceeds more than 100 employees
within a 90 day period the council is required to issue a formal notice under
section 188 of the Trade Union and Labour Relations (Consolidation) Act
1992 (as amended) and related regulations, reported through the HR1. This
provides staff with the opportunity to be consulted upon proposals for staffing
reductions and to explore ways in which redundancy situations might be
avoided.
PROPERTY IMPLICATIONS
81.
There are no specific property implications of this report but the ability to
support the capital programme is dependent in part on the ability to dispose of
surplus assets and generate capital receipts. The delivery of the strategic
asset management strategy is also essential in driving the councils on-going
revenue costs down.
The council has to comply with Section 149 of the Equality Act 2010. This
provides that decision makers must have due regard to the elimination of
discrimination, victimisation and harassment, advancing equalities, and
fostering good relations between different groups (race, disability, gender, age,
sexual orientation, gender reassignment, religion/belief and marriage/civil
partnership). Equality impact assessments will be completed in respect of
relevant proposals as part of the decision making process to enable members
D - 15
to take into account and if necessary mitigate the impacts as part of the
decision making process. An Equality Impact Assessment on the overall
Medium-Term Financial Strategy will be set out in the final budget
considerations in February 2016.
OPTIONS
83.
Agree the overall approach and strategy as set out in this report as the
basis for finalising the budget strategy for 2016/17 to 2017/18.
2.
3.
Agree the use of the Asda capital receipt as set out in Appendix C.
4.
To identify and agree any specific further areas that should be worked
up for consideration in the budget decisions in February 2016.
5.
6.
To not agree the overall approach and strategy as set out in this report
suggest an alternative version for development and consideration by
members in due course.
EVALUATION
84.
For 2016/17 and beyond the council faces a significant financial challenge and it is
essential that budget options for dealing with these are developed in a timescale that
enables effective implementation. These need to include options that cover both
financial years rather than just 2016/17 as well as looking to the medium longer term
position facing local government and the council.
85.
86.
RISK MANAGEMENT
87.
Currently interest rates are low and no new long-term external borrowing has
taken place since January 2005. This has led to significant one-off savings on
capital financing costs. The councils reserves and surplus cash flow is used
D - 16
instead of long-term borrowing. If this was invested short term the interest
earned would be very low some 0.5 per cent whereas the long-term
borrowing rates would be around 4 per cent. Ultimately when longer-term
borrowing and/or interest rates rise then additional revenue costs of
2 million+ per annum may need to be met.
88.
The key risks of the 2016/17 to 2017/18 budget strategy relate to budget
pressures being even higher than anticipated, government grant reductions
being significantly higher than expected, savings and efficiencies not being
achieved, proposed income levels not being achieved and inflation being
higher than expected. These risks are contained in the strategic risk register.
89.
90.
91.
The latest budget monitor indicates that the overall budget should not
overspend in 2015/16 although this is a continuing risk. Any overspend will
impact on the general fund balances and make the position in 2016/17 even
worse. Management action is being taken to try and ensure that there is no
overall overspend at the end of the financial year.
92.
For 2016/17 and future years it is essential that the council identifies the
necessary measures to deliver a lawful, balanced and sustainable budget.
Proposals need to be developed so that the necessary decision-making
processes can be followed.
RECOMMENDATIONS
93.
That Full Council considers the updated financial position facing the Council
over the next two financial years and:1.
Agrees the overall approach and strategy as set out in this report as the
basis for finalising the budget strategy for 2016/17 to 2017/18.
2.
3.
Agrees the use of the Asda capital receipt as set out in Appendix C.
D - 17
APPENDICES ATTACHED.
Appendix A Overall projected budget position 2016/17 to 2019/20
Appendix B 2016/17 -2017/18 draft Capital Programme
Appendix C Recommendations on use of Asda capital receipt
Appendix D Possible Budget Choices
Appendix E Brief to Marcus Jones MP; Minister for Local Government
DAVID BURBAGE
Head of Finance and s151 Officer
D - 18