Construction Engineering Ce 332-Lecture Notes 2014
Construction Engineering Ce 332-Lecture Notes 2014
TABLE OF CONTENTS
TABLE OF CONTENTS .... 1
FOREWORD .... 2
CHAPTERS
1 CONSTRUCTION PROJECT MANAGEMENT AND COMPANY ORGANIZATION
. 3
2 THE CONSTRUCTION INDUSTRY .. 15
3 PROJECT DELIVERY SYSTEMS AND CONTRACTUAL ARRANGEMENTS ... 27
4 CONSTRUCTION COST ESTIMATING ... 39
5 CONSTRUCTION PROJECT PLANNING .... 56
6 MANAGING QUALITY .. 90
7 MANAGING HEALTH AND SAFETY .... 102
8 CONSTRUCTION MACHINERY AND EQUIPMENT ... 108
FOREWORD
These Lecture Notes have been prepared for the use of METU Civil Engineering students
taking CE 332 Construction Engineering and Management Course. It brings together the
collected chapters on contemporary construction management topics. Some parts of these
Lecture Notes have been compiled from the various books and articles about the
construction management discipline in order to provide civil engineering students with a
complete coverage of the construction management topic.
CHAPTER 1
CONSTRUCTION PROJECT MANAGEMENT AND
COMPANY ORGANISATION
Each project is unique. Although exactly the same project is to be carried out, as
the location, external factors (climate etc.), parties involved, time and budget
constraints etc. are different, projects have their unique features which make them
unique undertakings.
impacts of the plant on the community? What is the environmental impact? What is
technical and economic feasibility? In order to find out answers to the above
addressed questions, normally, this phase is carried out by the client and/or its
consultants.
2. Engineering and design: It involves 2 main phases as; preliminary engineering
and design and detailed engineering and design. Preliminary engineering and
design involves architectural concepts, evaluation of technological process
alternatives, size and capacity decisions, comparative economic studies. These
steps usually coincide with feasibility studies.
Example: In a high-rise building, preliminary engineering and design determines the
number and spacing of stories, general layout of the service and occupied floor
spaces, general functional allocations (parking space etc.), and overall design
approach. Overall design approach involves decisions such as the choice between
steel frame and a reinforced concrete structure. Further refinements cover whether the
structure will be precast or cast-in-place concrete.
In infrastructure projects, engineers often need substantial input from geologists,
hydrologists, ecologists etc. In designing a dam, preliminary design requires analysis
of the watersheds hydrologic characteristics to determine the necessary reservoir
storage characteristics, geologic nature of the foundation and abutments. During
preliminary engineering and design, the precise location of the dam on its site,
geology, size, shape and availability of materials are determined and the choice
among structural types such as concrete, earth-fill, earth-rock etc. is made. Further
decisions are necessary (concrete structure may be gravity, arch etc.) and serve as
departure points for detailed engineering and design.
Once the preliminary engineering and design is complete, there is an extensive review
process before detailed work is allowed to proceed.
Detailed engineering and design: Detailed engineering and design involves the
process of successively breaking down, analyzing, and designing the structure and its
elements so that it complies with recognized standards of safety and performance
while presenting the design in the form of a set of explicit drawings and specifications
that will tell the constructors exactly how to build the structure in the field.
3. Procurement/project delivery: It involves two major types of activities:
contracting and subcontracting for services of general and specialty contractors,
obtaining materials and equipment required to construct the project. Traditional
form of procuring construction services is to solicit competitive bids for a single
general contractor after the design phase is over and general contractor handles all
subcontracting, plus the procurement of materials and equipment. However, there
are other procurement routes today (design-build, professional construction
management etc.).
Owner authorises
project
Operation
DESIGNER/
ENGINEER
GENERAL CONTRACTOR
SUBCONTRACTORS
Figure 1.2: Parties involved in a Construction Project according to
Traditional Project Delivery System
Responsibilities of these 3 principal parties may further be described as follows:
Owner/client: Owner/client organization is responsible for setting the operational
criteria for the completed project such as usage of a building, amount of gas to be
transported in a pipeline etc. Any special equipment, material or company
standards that are to apply to the project must be defined. They also need to
identify their involvement in the project, the review process, required reports,
levels of approval etc. Owner should set parameters on total cost, payment of
costs, major milestones and project completion date.
Designer/engineer/consultant: Design company is responsible for producing
design alternatives, drawings and specifications that meet the needs of the owner.
In addition, there may be other duties that may be delegated to the designer by the
owner such as on-site inspection, review of shop drawings, etc. Designer should
produce a project design that meets all technical codes, standards, environmental
and safety regulations. Design budget and schedule should be prepared.
Contractor: Contracting company is responsible for the performance of all work
in accordance with the contract documents that have been prepared by the
designer including furnishing of all labor, material, equipment, know-how
necessary to finish the project. Contractor should prepare an accurate estimate of
the project, develop a realistic construction schedule and establish an effective
project control system for cost, schedule and quality.
The contractual relationships and types of contract will be discussed in more detail during
the project delivery systems part of this course.
PROJECT MANAGEMENT
Management may be divided into two different types:
Functional management: it involves the coordination of repeated work of a similar nature
by the same people.
Project management: it involves coordination of one time work by a team of people who
often have never previously worked together.
Although the basic principles of management apply to both of these types of
management, there are distinct differences between the two.
Project management requires a multi-discipline focus to coordinate the overall needs of a
project. Project manager should delegate authority and responsibility to others and still
retain the focus on the linking process between disciplines. According to the definition of
Association of Project Managers, project management is the planning, organization,
monitoring and controlling of all aspects of a project and motivation of all involved to
achieve project objectives safely and within a defined time, cost and performance.
A project consists of 3 components (Oberlender, 1993);
1. Scope: The work to be accomplished - quantity and quality of work
2. Budget: Costs
3. Schedule: Logical sequencing and timing of the work to be done
When a project is first assigned to a project manager, it is important that all three of these
components must be clearly defined. Not only individually defined but each must be
linked together since one affects the other significantly.
In order to put together the scope, budget and schedule within a project, project
management team has to carry out some basic functions. 5 basic functions of project
management and tasks of a project manager (PM) may be summarized as follows;
1. Planning: It is the formulation of a course of action to guide a project to
completion. The establishment of milestones and consideration of possible
constraints are major parts of planning. There must be an explicit operational plan
to guide the entire project throughout its life.
PMs role in planning:
Develop a plan
Establish objectives and performance requirements early so everyone involved
knows what is required
Establish clear milestones so everyone knows what is to be accomplished
and when it is to be completed
Build contingencies into the plan to provide a reserve in the schedule for
unforeseen future problems
Communicate the project plan
10
11
INPUTS:
Human resources
Materials
Money
Equipment
Information
ORGANIZATION
The transformation
process
OUTPUTS:
Constructed
facility
Construction
services
Feedback
ENVIRONMENT
Figure 1.3: Construction Organization as an Open System (adapted from Pilcher, 1992)
Figure 1.4 illustrates the different levels of management in a construction company,
although they may merge and overlap. In small firms, the same manager may perform all
three roles (general manager, organizational manager and site manager) but in larger
firms, the three levels are likely to be separate. The site manager is the top manager of the
smaller task force system. This job involves welding together an effective team as well
as dealing with outside influences such as the local labor market, competitors, local
authorities, suppliers, etc. Some site managers have considerable autonomy in running
their sites whereas others have a narrower role and are expected to leave some of the
tasks to more senior managers (contract manager or director) and concentrate their efforts
on the day-to-day running of the site.
12
EXTERNAL SYSTEMS
Competitors, clients, designers, government etc.
Pressures and constraints
GENERAL MANAGERS
CONTRACTS MANAGERS AND OTHER
ORGANIZATIONAL MANAGERS
Input
Information
Money
People
Materials
etc.
SITE MANAGERS
Efficient production of goods and
services
Balancing long-term and short-term tasks
and requirements
Output
Buildings
Economic
value
added
etc.
13
1.3 REFERENCES
1. A Guide to the Project Management Body of Knowledge (PMBOK Guide), Third
Edition, Project Management Institute, USA.
2. Barrie, D.S, and Paulson, B.C. (1990). Professional Construction Management,
McGraw-Hill, USA.
3. Harris, F., and McCaffer, R. (2001). Modern Construction Management, 5th Edition,
Blackwell Science, UK.
4. Kelly, J., Morledge,R., and Wilkinson, S. (2002). Best Value In Construction,
Blackwell Science, RICS Foundation, UK.
5. Oberlender, G.D. (1993). Project Management for Engineering and Construction,
McGraw-Hill, USA.
6. Pilcher, R. (1992). Principles of Construction Management, 3rd Edition, Mc-Graw
Hill International Series, UK.
7. Smith, N. J. (1996). Engineering Project Management, Blackwell Science, UK.
8. Winch, G. M. (2002). Managing Construction Projects, Blackwell Publishing, UK.
14
CHAPTER 2
THE CONSTRUCTION INDUSTRY
The role of construction in national economy and development has been widely studied.
Gross domestic product GDP (gayri safi yurt ii hasla - GSYH) is the total annual value
of all goods and services produced by a country less income from investments abroad.
Various development patterns for construction related to GDP have been suggested. The
Gross National Product (GNP) is a similar figure, but unlike GDP it includes earnings of
domestic companies abroad. The inverse U shape pattern by Ranko Bon (1992)
suggests that the share of construction in national output increases in the early stages of
development but ultimately will decrease in absolute and relative terms in more advanced
industrial countries (Bon 1992, Figure 2.1). An important aspect is that while the
proportion for new construction decreases with later stages of development, the share of
improvement and maintenance in total construction increases (Bon, 1992).
New
Ma
Economic Development
dev
elop
a
ce
nan
e
t
in
nd
men
t
nt
me
ish
b
r
u
ref
Economic Development
15
16
17
trillion dollars. This situation continued between 2001 and 2002 where the market
dropped to 3 trillion dollars. In 2003, the sector showed increased activity and a better
performance was anticipated in the years ahead. In 2007, world construction output
reached 4,7 trillion dollars with 5% percent growth. However, global economic crisis in
2008 dropped output of the sector significantly. The construction sector showed signs of
recovery in 2010 and output reached 4,6 trillion dollars in 2011 but it was below the
levels achieved in 2007. It is predicted that volume of output in the construction sector
will grow to 15 trillion dollars worldwide by 2025. (DPT 9. Kalknma Plan, 2006; WTO,
2007; AECOM, 2012; Global Construction, 2013).
Drawing the boundaries of the construction industry is therefore not easy. Construction
can be seen not as a separate industry, but as agents and activities which can be
unpackaged and packaged in different ways. The enterprises engaged in construction
activity are extremely diverse. They range from self-employed individuals providing a
service to private house owners in the local community to multinational firms operating
on a global scale (ILO, 2003).
GLOBALIZATION
Traditionally, construction used to be a domestic industry, but this is now far from the
case. The construction market is now international. The general trend towards
globalization of markets caused by elimination of trade barriers, adoption of international
standards, opening of private and public national markets to foreign competition increase
the feasibility of exporting construction services to foreign markets. Contractors may be
motivated to operate internationally by saturation or instability of home construction
demand. Merger and acquisition activity has increased dramatically over the past decade,
leading to rapid, international consolidation within the industry. The largest players of the
construction industry are operating world-wide, and many Turkish contractors are
operating internationally. With new information technologies the distance and spatial
boundaries have been blurred to the point where any organization can theoretically
participate in a design and construction project in any location. However, the vast
majority of enterprises involved in on-site construction are small and local. Despite the
existence of an international construction industry, more than 95% of construction
activity is still undertaken by firms from within the country, the region or the
neighborhood (ILO, 2003). A global main contractor will subcontract large portions of
the works when performing international work. In specialized civil engineering and
facilities projects, the main contractor will typically subcontract low-skill civil works.
18
with a project-based operation; it has however characteristics unique for the construction
industry (Harris and McCaffer, 2001; Riley and Clare-Brown, 2001; ILO, 2003):
Clients of the construction industry in the public sector such as central government
departments, local authorities and public corporations rely almost exclusively on
competitive tendering to justify the awarding of contracts. Clients from private industry
tend to follow the same practices and also largely employ competitive tendering
procedures. Thus, most construction contracts are awarded after several contractors have
submitted a tender and most civil engineering and building contractors derive the major
portion of their workload in this way (Harris and McCaffer, 2001).
The construction market is very volatile to the national economic situation. It is also a
competitive market, i.e. a market with sellers and buyers that are small and numerous
enough to take the market price as given when they decide how much to buy and sell.
The construction market has characteristics of a competitive market, e.g. many buyers
and sellers, and this creates a supply and demand situation. In times of recession,
competition for available construction work intensifies, and contractors will tend to lower
the mark-up (profit margin) of their bids to increase chances of winning. If the contractor
is really desperate to win they could submit a bid at something less than cost (Harris and
McCaffer, 2001). When a contractor obtains such a contract based on a very low cost
estimate, they issue claims to attempt to achieve a positive mark-up. This was an often
seen situation in the UK, and other places in Europe, in the early 1990s. Jobs would end
without the contractor being fully paid, but with large claim files for conclusion after
completion of the works.
As terms of human resources, construction has the following characteristics (Riley and
Clare-Brown, 2001; Harris and McCaffer, 2001; ILO, 2003):
19
Public sector is a much more important client than in most other sectors
Contracts are based on relationships where the project participants constantly
oppose each other instead of co-operating and sharing joint objectives.
Tendency to competition on price alone
Cash flow dominates behavior (cash is king)
Reliance on credit and retention
During the 1980s there was an enormous growth in the use of subcontractors by the main
contractors. The reason for this development was to enable the contractor take on
additional workload without the need for increasing internally the level of employment
and capacity required to execute the extra workload, thus ensuring greater flexibility. The
trend towards the use of subcontractors has continued through the 1999s (Harris and
McCaffer, 2001).
20
Table 2.1: GDP Growth Rate and Construction Sector Growth Rate (TCA, 2012)
Years
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012 9 months
Construction Sector
Growth Rate (%)
-3.1
4.9
-17.4
13.9
7.8
14.1
9.3
18.5
5.7
-8.1
-16.1
18.3
11.3
1.0
Public construction investments amount to over 30%. The major clients of construction in
Turkey are:
21
awarded to date. They are not only involved in construction but are also active in the field
of industry and engineering.
The projects completed by the member companies cover a range of works related to all
kinds of civil engineering and industrial activities, such as dams, hydropower and thermal
power plants, industrial buildings, large scale oil and natural gas pipelines, petrochemical
refineries and complexes, motorways, tunnels and bridges, seaports and airports, largescale housing projects, high-rise and prestige buildings, hotels and tourist resorts.
Table 2.2: Total Project Value and Average Distribution of Works Conducted by TCA
Member Firms (TCA, 2012)
Fields of Activity
TCA prepares and submits reports to the relevant public authorities reflecting its
members' opinions and observations on matters related to the construction industry. The
association also provides technical counsel in the determination of short and long term
general policies concerning the construction sector. The TCA is member to the European
Union of Developers and House Builders (UEPC) since 1992 and became full member to
the European Construction Industry Federation (FIEC) on 25 May 2000 (Turkish
Contractors Association, 2012).
TURKISH CONTRACTING IN THE INTERNATIONAL MARKET
Turkish contractors started working internationally during the early 1970s, a period
when Turkey faced serious economic and political difficulties. The embargo imposed
after the Cyprus crisis in 1974 particularly hurt the economy. The depressed home market
coincided with the recession in the world caused by the surge in oil prices. The first
country where Turkish contractors offered their services was Libya. Turkish contractors
started their Libyan projects by importing the necessary technology from European
countries. Later on, the growing Turkish contracting activities extended to other
international markets, beginning with the Middle-East countries such as Iraq, Jordan,
22
Saudi Arabia, Kuwait, the United Arab Emirates (UAE), Yemen and Iran. Today, they
are working in approximately 100 countries with a business capacity of 242 billion USA
Dollars. Turkish contractors have established very good relations with clients, gained
first-hand knowledge of the region and its business environment and successfully
completed a wide variety of projects employing Turkish labor and using Turkish goods
and materials (Turkish Contractors Association, 2012).
Three decades of international work are described in the following paragraphs (Turkish
Contractors Association, 2012):
In the first decade (1972-1979) most of the works were undertaken in North
Africa, primarily in Libya (72.53%), followed by Saudi Arabia (15.45%), Iraq
(7.25%), Kuwait (4.71%), Greece (0.06%), and Iran (0.01%). The most important
activity field in this period was housing (32.1%) followed by seaports (18.1%),
industrial plant (15.6%), road/bridge/tunnel construction (11.7%), and urban
infrastructure (8.2%), amounting to a total revenue for the period of US$ 1.5
billion.
In the second decade (1980-1989) the largest share of the total work performed
was still in Libya (55.2%), although the importance of this country declined in
relative terms. Saudi Arabia (23.4%) and Iraq (11.5%), which were the second
and third countries respectively in the first decade, maintained their position while
operation in other countries commenced. A new development in this period was
the emergence of the former USSR as a market (3.8%). In this decade the share of
housing (36.7%) and urban infrastructure (17.2%) increased, followed by
road/bridge/tunnel construction (7%) and irrigation (5.4%). The total value of
projects undertaken in this period was US$ 11.5 billion.
In the third decade (1990-1999) the trend changed. The share of the Russian
Federation rose to 34.5% while the share of Libya fell drastically to 13.7%,
followed by Kazakhstan (7.8%) and Turkmenistan (6.7%). Seen as a whole, the
share of the former USSR countries amounted to 58.3%. A development in this
period was the great diversification of the countries where work was carried out,
with the emergence of markets such as Kazakhstan (7.8%), Turkmenistan (6.7%),
Pakistan (6.6%), Uzbekistan (3.9%), Azerbaijan (2.6%), Bulgaria (2.6%), USA
(2.5%), and Croatia (2.2%). A drastic fall in the share of Saudi Arabia (3.1%) and
the clearance of Iraq from the scene are very significant. Under the classification
"others" there are 33 countries accounting for 6.2 % of the work volume. The
share of housing decreased (24.9%), followed by road/bridge/tunnel construction
(12.7%), industrial facilities (9%) and commercial centers (8.1%). The total value
of the projects in this period amounts to US$ 18.2 billion. The Russian Federation
accounts for US$ 6.3 billion and US$ 10.6 billion together with the former USSR
countries.
In 2001, Turkish contracting firms continued the negotiations for projects totaling to an
amount of approximately US$ 1 billion. As a result of these business development
23
activities, several projects have been undertaken in Ireland, India and Morocco. Being a
new and potential market, Ireland has an important place in business development
activities of the member firms. In Ireland, projects totaling to US$ 100 million varying
from power plants to highways and housing are being carried on. Also, a US$ 55 million
highway rehabilitation project in India and a US$ 85 million highway construction
project in Morocco are few examples of the achievements of Turkish contracting firms in
2001. Romania, the Russian Federation and Iran are also among countries where the
member firms have progressed to contract signing stage for various projects.
During the 2000-2012 period, the annual volume of business undertaken abroad increased
from 2.6 billion dollars in 2002 to 25.0 billion dollars in 2007. In the following years,
under the effects of the global crisis, this figure decreased to 20 billion dollars in 2011.
However, in 2012 Turkish international contracting services reached its peak level by
26.6 dollars.
Table 2.3: Turkish International Contracting Services in 2012 (TCA, 2012)
Number of Project Project Value (USD) Share (%)
Turkmenistan
Iraq
Russian Fed.
S. Arabia
Iran
Ethiopia
UAE
Qatar
Morocco
Other
80
114
40
27
4
1
5
15
5
150
441
4,885,604,764
4,384,036,891
3,640,667,064
2,245,458,430
1,855,495,000
1,699,900,000
1,288,870,744
892,285,480
860,986,410
4,857,068,147
26,610,372,930
18.4%
16.5%
13.7%
8.4%
7.0%
6.4%
4.8%
3.4%
3.2%
18.3%
100.0%
24
COMPETITIVENESS
CONSULTANCY
OF
TURKISH
DESIGN
ENGINEERING
AND
Turkish design engineering and consultancy is also operating internationally but has a
relatively weak competitive position compared to the contractors. The lag may be
explained by the fact that related Turkish government agencies assumed the engineering
role themselves for a long period of time. An example is the State Hydraulic Works
(Devlet Su leri DS) which did their own engineering rather than acquiring
engineering services from private firms.
The lag of Turkish engineering has also been attributed to the fact that Turkish firms first
started internationalize as subcontractors to foreign firms during the 1970s, which
delayed the development of design engineering and consultancy firms. It has been argued
that the relative lagging competitive position of Turkish design engineering and
consultancy firms is not favorable for long-term competitiveness of Turkish construction
as a whole. Weaknesses in engineering services could result in uncompetitive bids in
design and build contracts, and furthermore during the design phase of a project it may
lessen the opportunity to promote the use of materials and/or contractors from Turkey
(z, 2001).
25
2.4 REFERENCES
1. AECOM, retrieved from
http://www.aecom.com/deployedfiles/Internet/About/CAM/WorldConstructionReport
_2012.pdf
2. Birgnl, T., and zdoan, I. (2000). Competitiveness of Turkish Contractors in
International Markets, Proceedings of ARCOM 16th Annual Conference, September
6-8 2000, Volume 1.
3. Bon, R. (1992). The future of international construction: Secular patterns of growth
and decline, Proceedings of Habitat International, Volume 16.
4. DE, retrieved from http://www.die.gov.tr/TURKISH/SONIST/BINA/161003tr.htm
5. DPT 9. Kalknma Plan 2007-2013 (2006). naat, Mhendislik-Mimarlk, Teknik
Mavirlik ve Mteahhitlik Hizmetleri K Taslak Raporu.
6. Global Construction Perspectives, retrieved from
http://www.globalconstruction2025.com/
7. Harris and McCaffer, (2001). Modern Construction Management, 5th Edition,
Blackwell Science.
8. International Labor Organization, retrieved from
http://www.ilo.org/public/english/dialogue/sector/sectors/constr.htm
9. KLM Press, retrieved from http://www.intlconstruction.com
10. Porter, M. A. (1985). Competitive Advantage, The Free Press, New York, NY.
11. Riley, M. J., and Clare-Brown, D. Comparison of Cultures in Construction and
Manufacturing Industries, Journal of Management in Engineering, July 2001.
12. Turkish Contractors Association, retrieved from http://www.tca-uic.org.tr
13. International Labor Organization, retrieved from
http://natlex.ilo.ch/public/english/dialogue/sector/techment/tmcit01/tmcitr.pdf
14. Turkish Contractors Association, retrieved from
http://www.tmb.org.tr/genel_dokumanlar/ulkeler-firmalar_activities.xls
15. WTO, retrieved from
http://www.wto.org/english/tratop_e/serv_e/construction_e/construction_e.htm
26
CHAPTER 3
PROJECT DELIVERY SYSTEMS AND CONTRACTUAL ARRANGEMENTS
3.1 INTRODUCTION
In this chapter, project delivery systems (sometimes called as procurement methods or
contracting methods) commonly used in the construction business will be introduced as
well as contract types (sometimes known as payment types). Before a more detailed
discussion of these topics, following definitions are given to clarify the terminology of
project delivery systems, contract types and bidding types.
Project Delivery System (PDS): A PDS is a way (a method) of organizing all phases of
a construction project by establishing relations (contractual or non-contractual) between
parties involved in the project. PDS is chosen by the client (or known as the owner) and it
determines the responsibilities of different parties involved in the construction process.
Client (project owner) may carry out the construction process himself/herself; hire a
single contractor or a number of specialty contractors to carry out the construction work.
He may assign design to a separate design company or to the contractor. He may organize
the construction process himself or hire a professional construction management firm to
organize everything. Thus, a number of methods, which are known as PDSs, are used in
the construction industry depending on the needs of the client, project characteristics etc.
A PDS is also called as a procurement method or contracting method.
Contract Type: Construction contracts may be classified into two major categories on
the basis of payment terms: fixed-price contracts and cost-plus contracts. A contractor
may be paid in fixed prices (which is also divided into two categories such as lump-sum
and unit-price contracts) determined before the construction starts or actual costs realized
during the construction plus a fee. Thus, contract type determines how a contractor is
paid. There are no strict rules about which contract types may be used in different PDS.
For example, in design-build, contract type is usually lump-sum. However, this cannot be
generalized as it depends on project characteristics. For example, if necessary, a
combination of lump-sum and unit-price payments may be preferred in design-build
depending on type of job, predictability of quantities etc.
Bidding Type: It is a way of awarding contracts to different parties by the client. It is
also known as contract award mechanism. There are two methods: competitive
bidding or negotiation. In competitive bidding, a number of interested contractors submit
bids and client chooses the best option based on predetermined criteria; usually the
lowest cost bidder is awarded the contract. In negotiated bidding, client invites a party (or
sometimes a number of parties) and evaluations are made based on criteria like
experience, managerial capabilities, technical know-how etc. Contract award is based on
evaluation of skills rather than price competition. There are no general rules about which
type of bidding shall be used in different PDSs as it depends on factors such as client
preferences, project type etc. This is also valid for contract types, however, there are
certain common practices which are widely observed in the construction industry. For
example, in negotiated bidding, cost-plus types of contracts are mostly used.
27
To sum up, there are three decisions that should be made by the client before
commencement of the project:
Which PDS shall be used?
Which contract type shall be used?
What kind of bidding shall be used?
In the forthcoming chapters, factors that affect the answers of these questions are
discussed in detail.
3.2 PROJECT DELIVERY SYSTEMS
Due to the macro-factors (sustainability issues, technological advances, cost-time
limitations, focus on quality etc.) affecting the construction industry, the relationships
between the parties involved in a construction project resulted in different ways of project
delivery. Each PDS has its advantages and disadvantages. Choosing the right PDS
according to the needs of the customer is a crucial task in the early stage of any
construction project. The decision that will most affect the relationships and risk
allocation on a construction project is the choice of PDS. There is no perfect PDS for
every construction project. The best method should be chosen after careful evaluation of
the needs of the customer, time and budget constraints, completeness of design, project
complexity, the owners qualifications and experience. Types of PDS are discussed in the
forthcoming sections.
3.2.1 Traditional Construction Contracting (Design-Bid-Build or DBB)
In the traditional method of construction contracting, which is also known as Design-BidBuild (DBB), owner has separate contracts with designer and contractor. He contracts
with a designer for the design, and separately contracts with a general contractor for the
construction of the project (Figure 3.1). This is the most common method of construction.
Legal obligations
Informal, inf. exchange
Owner
General
Contractor
Engineer
Designer
Workers
Subcontractors
Workers
Figure 3.1: Traditional Contracting Method (DBB)
28
Contractor
Engineering firm
In DBB, owner has a dominant role due to separate contractual relationships with both
the design entity and the contractor. In this arrangement, the owner warrants to the
contractor that the plans and specifications are buildable. If problems arise during the
course of construction - or even after substantial completion - the owner becomes the
intermediary between the contractor and design firm. The traditional system has several
disadvantages. The primary disadvantage is the potential for conflict. The traditional
system often hinders communication among the parties which can result in misinterpreted
plans and specifications causing delay, cost overruns and legal problems. DBB creates
greater potential for time and cost overrun since the design and construction processes are
performed independently.
3.2.2 Separate Contracts Method
In this type of system, owner lets contracts to a number of specialty contractors. In other
words, owner acts as a general contractor which hires a number of subcontractors to carry
out the work (Figure 3.2). The owner should have the necessary organizational skills,
knowledge and experience in construction works so that this PDS can be successful.
Owner
Engineer
Designer
Contractor1
Contractor2
Contractor3
Workers
Figure 3.2: Separate Contracts Method
29
Subcontractors
Owner
Engineer
Designer
Workers
Owner
Designer-Contractor
or
Designer
Engineer
Workers
Subcontractors
30
DB is very popular in recent years, especially for industrial type projects. It gives design
firms and contractors the opportunity to work as a team, and to deliver a quality project
on time and within budget. Design and construction are overlapped resulting in time
savings from the project completion time. For example, once foundation design is
completed, the construction may start. Fewer changes will arise during construction since
the design evolves with construction. When compared with DBB, DB has significantly
less design changes and construction cost overrun. Quality associated with DB is usually
claimed to be better than quality performance in DBB. Also, an advantage for the owner
is that the owner is in communication with one company for the responsibility of the
whole project. In this type of system, the owner is less involved with the project.
Supporters of this method claim that the owner enjoys lowest cost in shortest time. Thus,
DB can minimize many of the problems which often lead to claims in the DBB process.
One of the many advantages of DB is that the general contractor is involved early in
coordinating cost issues and structural issues with the architect. The architect and
contractor are more motivated to communicate well and work together since they are part
of the same team or venture. This decreases the risk of delay and poor constructability.
However, for DB system to be successful, owner should clearly define the scope of the
project prior to construction during design brief. The most important task for an owner is
to prepare clear performance, technical and quality criteria for the project. These criteria
will include objectives for durability, design life, operational criteria, standards of finish
and aesthetics, community and environmental standards. The next input from the owner
is conditions of contract that appropriately allocate risks and create contractual
arrangements that can accommodate a likely range of events and circumstances. In this
way, uncertainty and the potential for dispute can be minimized.
Some of the problems associated with DB are;
Lack of clarity in respect of the specifications in the design brief may lead to
disputes as it may be unclear whether the contractor has in fact constructed the
product described in the contract or not. The finished product may not turn out to
be what was expected.
It can be difficult for the owner to comparatively assess tender proposals
submitted by prospective contractors as proposals may differ significantly.
The total cost of project is usually not known until the construction phase.
There is a potential for contractors to affect savings and increase profit within the
lump sum contract by under-designing some aspects of the project. This may
happen as a result of the design brief which defines performance or quality
requirements inadequately.
From a practical viewpoint, the owner has significantly less control than it would
by other delivery methods.
31
Owner
CM
Engineer
Designer
General
Contractor
32
institutions, operator firms etc.) is established to finance, construct and operate the
facility for a concession period awarded by the government. Ownership of the facility is
transferred to the government at the end of the concession period, which will be of such
length as to allow the builders and financiers to recover their outlays with a return. In
some cases, government guarantees a certain amount of demand to generate agreed
minimum revenue for the organization to recover the investment costs. Although it is an
innovative PDS specifically developed to finance infrastructure projects needed in
developing countries, its success is not guaranteed. It may be sometimes difficult for the
government to find a company that may be financially strong enough to cover the project
budget. The project must be feasible so that it may attract potential investors. Thus,
government should give some guarantees to increase feasibility of projects such as
demand guarantee etc. The legal background of the BOT system has to be very strong so
that responsibilities of parties and risk allocation schemes can be clearly defined. Another
complication about this system is that the government has limited control over a facility
during the operation period by the company, which can be a very strategic project for the
country. Finally, due to the high number of parties involved, significant uncertainties
about future revenues and cost, and legal complications, BOT projects are risky
undertakings. BOOT (Build Own Operate Transfer) and BOO (Build Own Operate) are
variations of the BOT system which are developed to increase applicability of BOT
formula.
3.3 CONTRACT TYPES
There are two general classifications of contracts used in the construction industry based
on the way in which a contractor is paid for: fixed price contracts and cost-plus contracts.
In fixed price contracts, contractors agree to construct the facility on a fixed price basis
where either the overall price (lump sum contract) or unit prices (unit price contract) are
fixed.
In lump-sum (gtr usul) pricing, a contractors fee for services is established as a
total contract amount. A price is agreed upon by the client (owner) and the contractor for
the whole project. The risks due to market fluctuations belong to the contractor. So, it is a
nice system for the client (owner) who knows exactly how much the job will cost (unless
there is an unforeseen event) and will get his job completed in the minimum time.
However in this system, a complete control must be kept on the job since the contractor
may use poor material and unqualified labor. The owner may be in an adversary position
with the contractor especially if the scope of work is not clearly defined. For the
contractor, the advantage of lump sum pricing is that it gives him a set target to shoot for.
The disadvantage lies in the fact that a lump sum contract allows no flexibility for
adjustments thus, a risk premium is required to financially cover the cost of unforeseen
job conditions. Poor cost estimating may result in disastrous situations for the contractor.
The unit pricing method (birim fiyat) establishes payments based on the amount of
production or quantity of works completed at a fixed price. It is a steady and guaranteed
system for the contractor who is covered against any fluctuations in the market. In
Turkey, in unit price contracts, costs can be calculated by multiplying quantities with unit
33
prices which are published every year by the Ministry of Environment and Urban
Planning. Sometimes, rather than the unit prices published by Ministry of Environment
and Urban Planning, unit prices offered by the contractor are used. In case of offered
unit-prices, the contractor should accurately estimate the unit price of production and
complete the job successfully to ensure profitability.
A combination of lump-sum and unit-price contracts is also possible. In mega projects
where quantities associated with some part of work are determined, whereas some
quantities cannot be clarified due to uncertainties (about geological conditions, poor
scope definition etc.), a combination of lump-sum and unit-price can be used. Although a
lump-sum price is determined, for the unclear part of work, contractor may be paid in
unit-prices.
In cost-plus-fee (maliyet art kar) pricing (often called simply cost-plus), payments
for services are based on the contractors actual expenses plus a predetermined fee, which
is usually a percentage of the expenses. Here the contractor has the advantage that if he
carefully records all his costs, he is almost certain of a profit. On the other hand, the
enormous amount of paperwork involved can be very time-consuming, and if any
expenses are not recorded, the costs of those expenses as well as the profits may be lost.
The success of a cost-plus contract relies heavily on the good faith of the contractor.
Client should control that the contractor claims the real costs and does not exaggerate
the costs with the aim of earning more money. Cost-plus-fee contracts are mostly used in
negotiated bidding. Most widely used forms of cost-plus contracts are cost-plus fixedfee and the cost-plus-percentage fee contracts. A cost-plus contract provides a formula
for determining the fair price of the work as it is done and often sets a guaranteed
maximum price (GMP) for the project. As a result, both the contractor and the project
owner are protected. In this type of contract, only major changes in the scope of work or
the original intent of the contract results in adjustment of the GMP. Finally, although
quality of the work is claimed to be higher in cost-plus contracts, it is also known that
cost-plus may not be the most economical solution for the client.
34
satisfactory working conditions, fair treatment and timely payment. The project owner
expects quality work at a reasonable cost, timely completion and fair treatment. Both sets
of expectations are based on the desire for profit. Seen from this perspective, the contract
becomes the ground on which each party tries to establish conditions in which it can
maximize its profit. For his part, the contractor wants a contract that allows him
maximum opportunities for doing a quality job at the lowest reasonable cost and for the
highest reasonable fee. The project owner, on the other hand, wants the contract to ensure
that he gets quality work but for the lowest reasonable fixed price or fee, and here is
where the potential for conflict arises. The contract recognizes that the conflict exists but
also expresses each sides willingness to compromise for mutual benefit and to trust the
others fairness. It defines the business relationship and provides guidelines for dealing
with the unforeseen events that plague every project and threaten one or both parties
profits.
Gaining an advantage begins with thoroughly understanding what the contract says and
then organizing and implementing the construction efforts accordingly (ASCE, 1988).
Despite its legal terminology, a construction contract essentially states six simple things:
Unfortunately, it is the nature of the construction process for these simple things to
become enormously complicated. Thus, contract documents must be precisely worded
and thoroughly detailed.
The term contract documents includes the contract for construction between the owner
and constructor, together with other documents referenced by and made a part of the
owner/constructor agreement. These documents, taken together, define the
responsibilities of each party during the construction phase. Contract documents
generally include:
35
The basic definitions of various terms discussed in a contract are listed below:
Construction plans are drawings that show the location, dimensions, and details of
the work to be performed. Taken together with the specifications, they should provide a
complete description of the facility to be constructed. Types of contract drawings include
site drawings and detailed working drawings. Contract drawings are usually organized
and numbered according to specialty, such as structural, electrical, and mechanical.
Construction technical specifications provide the detailed requirements for the materials,
equipment, and workmanship to be incorporated into the project. Contract
drawings and specifications complement each other and must be used together.
Shop drawings are drawings, charts, and other data prepared by a contractor or supplier
which describe the detailed characteristics of equipment or show how specific
structural elements or items of equipment are to be fabricated and installed. Thus
they complement but do not replace the contract drawings.
Subcontracts are contracts between a prime contractor and secondary contractors or
suppliers. Subcontracts are widely used in building construction for the installation of
electrical, plumbing, and heating and ventilating systems.
A claim is a request by the contractor for a time extension or for additional payment
based on the occurrence of an event beyond the contractor's control that has not
been covered by the contract. Most claims fit into one of the following categories; injury
or damage claims, delay or disruption claims, change in conditions claims, change in
scope claims, time extension claims, termination claims and payment delay claims.
Disputes are disagreements between the contractor and owner over some aspect
of contract performance.
In general, one will have a good basic understanding of the project contract if the
following questions (MCAA, 1984) can be readily answered:
1. Who are the parties in the contract?
2. Who gives orders, in what circumstances?
3. Who pays who and how is the payment method?
36
37
5. Genesis (2003). Selecting the Right Project Delivery System, retrieved from
www.Genesisplanners.Com
6. Gould, F. (1997). Managing the Construction Process. Prentice Hall. Upper
Saddle River, NJ.
7. Hanna, A.S. (2001). CEE 498 Class Notes, Integrated Project Estimating and
Scheduling. University of Wisconsin, Madison.
8. Harris, F. and McCaffer, R. (2001). Modern Construction Management, 5th
Edition, Blackwell Science, UK.
9. HK Highways Department Project Delivery System (2003), Volume 1, Selection
of Project Delivery Options.
10. Humphreys, K. and Wellman, P. (1987). Basic Cost Engineering. Second Edition.
Marcel Dekker Inc. New York, NY.
11. Ibbs C.W., Young H. K., Tzeyu N., and Odabasi, A. M. (2003). Project Delivery
Systems And Project Change: Quantitative Analysis, ASCE Journal Of
Construction Engineering And Management, Vol. 129, No. 4, July/August 2003,
pp. 382-387.
12. MCAA Project Managers Manual (1984). Mechanical Contractors Association of
America, Inc. Bethesda, MD.
13. Mcwhorter, V.S., and Hanson, M. E. (2000). Twenty-First Century Project
Delivery Systems. Proceedings of North American Tunneling 2000 Conference.
14. Mincks, W., and Johnston, H. (1998). Construction Jobsite Management. Delmar
Publishers.
15. Newcombe, R. (1999). Procurement as a Learning Process. Journal of
Construction Procurement, 5(2), 211-220.
16. Nunnally S.W. (1993). Construction Methods and Management. Third Edition.
Regents /Prentice Hall, Englewood Cliffs, NJ 07632.
17. Parsons Brinkerhoff Network, March (2000). Alternative Project Delivery
Systems.
18. Robertson P.A., and Associates, P.A. (1997). Newsletter. Project Delivery
System: Methods and Risks.
19. Russell, J.R. (2001). CEE 498 Notes. Construction Project Management.
University of Wisconsin, Madison.
20. Tennant, T.R. (1998). Advanced Project Delivery Systems: Design-Build And
Design Delegation Insurance Issues, Presented At The American Bar Association
Forum On The Construction Industry And Section Of Public Contract Law By
Terry R. Tennant On October 16-17, 1998 At The Fairmont Hotel, Chicago, IL.
38
CHAPTER 4
CONSTRUCTION COST ESTIMATING
4.1 INTRODUCTION
Cost estimating is an attempt to forecast the actual cost of a project. Cost estimates play
an important role for determination of the bid amount as well as development of the
project budget. Inaccurate cost estimates may lead to lost opportunities, lower than
expected returns, and unsuccessful projects. Estimating in general requires detailed study
of the bidding documents including construction drawings and specifications, a quantity
takeoff, and determination of costs. There are numerous estimating methods that could
be used depending on the project type, delivery method, and details of the drawings
available. This chapter presents only general aspects of construction estimating rather
than a very detailed discussion of estimating methods.
TYPES OF ESTIMATES
There are several classifications about the cost estimates depending on their accuracy
level, or methods being used to determine the estimated cost. In general cost estimates
could be classified into two groups; preliminary cost estimates and detailed cost
estimates. Preliminary cost estimates also sometimes named as conceptual cost estimates
are usually prepared before drawings and specifications are available and detailed cost
estimates are prepared after construction drawings and specifications are available.
According to cost estimate definitions of Construction Cost Institute (CII SD-6)
preliminary cost estimates are expected to have an accuracy range of 10% to 50%
depending on the level of information and estimating method being used. Detailed cost
estimates on the other hand, are expected to have an accuracy of 1 to 10% depending
on the type of project.
4.2 PRELIMINARY ESTIMATES
Preliminary cost estimates are usually performed at the early stages of the projects with
very limited information since drawing and specifications are not available. One of the
main reasons for having preliminary estimates is to decide about feasibility of a project.
If a project is determined as feasible based on the preliminary estimate than detailed
design, bidding, and construction stages could be initiated, therefore early estimates play
a crucial role on committing resources for further development of a project. Preliminary
estimates could also be used for evaluation of different project alternatives and also for
development of an initial project budget.
Preliminary cost estimates are not expected to be very accurate since detailed drawings
are not available and there are several uncertainties present about project cost at the early
39
stages of a project. However, a quick and reasonably accurate estimate is needed based
on the information available, especially when a feasibility decision is to be made.
Numerous techniques could be used for preliminary cost estimating. In general data of
past projects are used to develop preliminary cost estimates. A very simple method to
determine a preliminary cost estimate is to use average unit cost of similar projects such
as 250 $/ m2 for building construction, or 100 million $/km. for metro construction. Cost
estimates determined by average unit cost method are not expected to be accurate since
these estimates are very general, and are based on very limited project information.
Modeling techniques such as regression analysis method could be used to improve
accuracy of preliminary cost estimates.
4.3 DETAILED ESTIMATES
Detailed estimating requires determination of the quantities and all of the costs to
complete the project. The costs to complete the project can be grouped into four
categories; material, labor, equipment and machinery, and overhead costs. A profit is
added to the total cost estimate for determination of the bidding price. Material costs
include cost of all the bulk materials such as concrete, steel, lumber, cables, as well as
cost of the mechanical and electrical items such as elevators, boilers and transformers.
Labor costs are the cost of the workers that will participate in the project such as;
carpenters, electricians, welders and helpers. Equipment and machinery costs include
expenses for the construction equipment and machinery such as cranes, trucks and
excavators. Overhead costs are the expenses that cannot be related to a specific
construction activity but rather general project expenses such as; office expenses,
mobilization and camp expenses, bond and insurance expenses.
QUANTITY TAKEOFF
The first step of detailed estimation is investigation of the bidding documents for
preparation of quantity takeoff. A quantity takeoff is a detailed calculation of quantities
for each work item that is going to be performed to complete the project. Quantity
takeoff is an important step of estimating and bidding and a complete set of bid
documents including drawings, specifications and conditions of contract are needed for
preparation of quantity takeoff accurately. Although the bid documents for a unit-price
project usually provide contractors with estimated quantities of each bid item, these are
approximate quantities and contractors should perform their own quantity takeoff not
only to check bid quantities but also to provide more detailed quantities for accurate
pricing of the project.
Quantity takeoff process is mainly calculation of volumes, areas and counting of
elements, but it requires an organized approach to every drawing and construction item to
ensure that not a single work item is missed. To accomplish this effectively the project
must be divided into smaller work packages and each work package must be utilized with
the correct units. During quantity takeoff a common unit of measure should be used for
40
each item included. For example; for excavation and backfill m3, for formwork m2, for
concrete m3, for structural steel tons are used as a unit of measure.
At the end of this chapter quantity take-off for basic building activities are illustrated with
two examples. It is important for the quantity surveyor to visualize the drawings properly
and adjust calculated quantities for waste. As an example, when ordering concrete some
concrete may be spilled when transported from the mixer by a bucket and this waste
amount should be considered during takeoff.
MATERIAL COSTS
Once the approximate quantities of material that will be used for the project are
determined the contractor would request quotations (prices) from material suppliers and
manufacturers for all materials required. Although sometimes prices of manufacturers
may be available as a list, it is more desirable to obtain written quotations that include
specifications of the material, transportation details, time required for delivery, materials
included in the price, taxes, guarantees and terms of payment. When material costs
quoted by different manufacturers are being compared they must be brought to common
basis; for example, delivered to site including all expenses.
LABOR COSTS
Labor costs are generally classified into two groups; direct labor costs, and indirect labor
costs. Direct labor contributes physical completion of a construction task for completion
of a permanent facility. Examples for direct labor are; carpenter, electrician, concrete
finisher, welder. Indirect labor supports the completion of the project but cannot be
identified as directly working for a specific task. Examples for indirect labor are; project
manager, planning engineer, and timekeeper.
In order to estimate direct labor costs accurately the estimator must make a detailed
quantity takeoff, analyze job conditions and project schedule carefully, and also maintain
a comprehensive library of actual worker hours and labor costs from past projects. One
of the methods that is being used commonly for estimating direct labor costs is to use
average worker hours per unit quantity. For example using historical records it could be
estimated that to produce 1m2 of formwork 0.75 carpenter and 0.75 laborer hours is
needed. Once the average work hours per unit is determined for a task this could be
multiplied by the total quantities calculated to determine total worker hours, and the total
worker hours are multiplied by the hourly wages of the workers including taxes and
social security expenses to calculate labor cost. If major deviations from average job
conditions are expected average worker hours should be adjusted to reflect these
deviations.
Indirect labor costs could be estimated after staffing requirements for the project is
determined. Once the decision about the size of the indirect project staff is made using
project schedule the periods that the staff will be needed for the project could be
41
determined. These durations are multiplied by the gross salaries to determine the indirect
labor costs.
EQUIPMENT AND MACHINERY COSTS
Determination of the equipment and machinery that will be used for the project and
durations that the equipment and machinery will be used are needed for estimation of
equipment and machinery costs. In order to estimate equipment and machinery expenses
accurately, early management decision must be made concerning the machinery sizes and
types and also whether existing machinery will be used or additional machinery will be
rented or purchased. Estimation of equipment and machinery expenses will be discussed
in Chapter 8.
OVERHEAD COSTS
Overhead costs are expenses that cannot be related to any specific item of work. If the
costs can be related to an item of work they should be included under the material, labor,
or equipment costs. The overhead costs are usually estimated as a percentage of total
project cost. In calculation of unit prices of Ministry of Environment and Urban Planning
the overhead expenses and profit is taken as % 25 of the cost.
The overhead costs are generally divided into two groups; general overhead costs and
project overhead costs. General overhead expenses cannot be related to a specific project
but often referred as general or administrative costs. Examples for general overhead
expenses are head office expenses, salaries of personnel at the head office, and company
legal expenses. Project overhead costs are expenses that are related to a specific project
but that cannot be related to a specific item of work. Some examples for project
overhead cost are salaries of indirect site personnel, mobilization costs, site office
expenses, project travel expenses, cost of bonds, project insurance expenses. Since most
of the project overhead costs depend on the project duration a project schedule is
necessary for calculation of project overhead expenses.
4.4 BIDDING STRATEGY
One of the critical decisions for bidding is determining the amount of profit that will be
added to the detailed cost estimate. If profit amount is too high, than the company may
not be awarded the contract but on the other hand, if profit amount is too low there may
be a risk of a loss at the end of the project instead of a profit. The profit amount depends
on several parameters including market conditions, the workload of the contractor, the
number of companies bidding for the project and contractors business strategy. A risk
premium called contingency may also be included in the bid amount. The contingency is
generally used to cover the uncertainties and risks involved for the bid project.
42
4.5 EXAMPLES
Example-1: Section views, normal floor column and ceiling plans of a building project
are given in Figures 4.1 to 4.5. Determine the quantities of following items:
1) Formwork for slab D302, beam K302 (between S2 and S3), and column S2
(between +3.70 to +6.50).
2) Support for ceiling formwork for Bedroom 1 and Bedroom 2 (including K301,
K313, K312, K308, K314, K305 and, K315 but, excluding roof extensions)
3) Reinforcement for column S2 between +3.70 to +6.50, excluding reinforcement
extensions from previous floor (For 8 rebars unit weight is 0.395 kg/m and for
16 rebars unit weight is 1.578 kg/m)
4) Concrete (C20) for slab D302, beam K302, and column S2 (between +3.70 to
+6.50).
5) Exterior walls between +3.70 to +6.50 (masonry block-Gazbeton)
6) Interior walls for the normal floor. (Lintel length is 1.3 m.)
7) Interior plastering for the bedrooms and bathrooms (1.2 cm thickness).
8) Scaffolding for interior plastering of ceiling for the gallery opening.
9) Exterior plastering of wall in A1-D1 direction (between +3.70 to +6.38, excluding
roof extensions)
10) Scaffolding for exterior plastering for the wall in A1-D1 direction between 0.80
to +6.38 (Assume that the site in A1-D1 direction has been graded to -0.80 level)
11) Interior painting for the bedrooms
12) Flooring for the bedrooms (hardwood parquet 3 cm. thickness, thickness of the
door frame is 3 cm, cornice 10 cm)
13) Baseboard for the flooring in the bedrooms (10 cm.)
14) Polishing of parquet and baseboard for the bedrooms
15) Window frames for the bedrooms and bathrooms (pine with no cornices)
16) Heat insulation of roof (glass wool, including roof extensions)
43
GALERY OPENING
BEDROOM 1
B
44
BEDROOM 3
BEDROOM 2
Bathroom2
Bathroom 1
45
Figure 4.2: Section A-A
46
Figure 4.3: Section B-B
47
Figure 4.4: Normal Floor Column Plan
48
Figure 4.5: Normal Floor Ceiling Plan
NO TYPE OF JOB
Location
Formwork for Slab
1a D302
D302
Formwork for Beam
1b K302
K302 (outer face)
Width(m) Length(m)
2.40
1c
Void
2.40
Height(m)
0.25
Qty.
2.40
0.60
1.44
m2
2.40
0.48
1.152
m2
0.60
m2
2.40
(2*0.25)
2.20
1.10
m2
S2 (outer face)
0.60
2.80
1.68
m2
S2 (inner face)
0.60
2.68
1.608
m2
K315
0.25
0.48
-0.12
m2
S2 (sides)
Bedrooms 1 & 2
Reinforcement of
Column S2
0.12
4.268 m2
A1-A2-D1-D2
S2
8 Stirrup
16 Vertical Bars
8 Ties
8.30
3.85
number
34
8
68
length
1.75
3.10
0.42
85.639 m3
2.68
mass(kg/m)
0.395
1.578
0.395
23.503
39.134
11.281
Total (8)
Total (16)
Width(m) Length(m)
4b
4c
5
m2
3.192 m2
Total
Formwork for
Column S2
Total
Support for Ceiling
Formwork for
4a
5.76
Kg
Kg
Kg
34.784 Kg
39.134 Kg
Height(m)
D302
2.40
2.40
0.12
0.691 m3
K302
0.25
2.40
0.60
0.36 m3
S2
D1-D2
Window
Window
Column S10
D2-D3
Window
D3-D5
Column S11
Column S12
Window
Window
A1-A5
Column S1
Column S2
Column S3
Column S4
A1-D1
Column S1
Column S7
Column S9
Window
Window
A5-C5
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.25
0.60
3.50
0.85
0.85
0.50
2.40
0.50
(1.50+4.45)
0.50
0.60
0.50
0.45
11.60
0.25
0.60
0.60
0.25
8.30
0.60
0.60
0.60
1.60
1.60
3.90
2.80
2.20
1.30
1.30
2.20
2.20
0.60
2.20
2.20
2.20
0.60
1.60
2.20
2.20
2.20
2.20
2.20
2.20
2.20
2.20
2.20
2.20
2.20
1.80
0.42 m3
m3
m3
m3
1.0975 m3
m3
1.245 m3
m3
m3
m3
m3
2.4125 m3
m3
m3
m3
m3
5.445 m3
m3
m3
m3
m3
m3
1.815 m3
m3
49
0.2763
0.2763
0.275
0.075
0.275
0.33
0.075
0.18
0.1375
0.33
0.33
0.1375
0.33
0.33
0.33
0.88
0.88
1.925
-0.27625
-0.27625
-0.275
1.32
-0.075
3.2725
-0.275
-0.33
-0.075
-0.18
6.38
-0.1375
-0.33
-0.33
-0.1375
4.565
-0.33
-0.33
-0.33
-0.88
-0.88
1.755
NO
5
TYPE OF JOB
Exterior Walls
Continued
Cum.
Location
Width(m) Length(m)
Height(m)
Void
Qty.
Qty.
Window
0.25
2.50
1.8
1.125
-1.125
Column S4
0.25
0.35
1.8 0.1575
-0.1575
0.4725
C5-D5
0.25 (4.150.25*)
2.2
2.145
*The portion of 0.25m is already included in D3-D5 Section.
C5 Extension
0.25
0.45
2.2
0.2475
Window
0.25
0.45
1.6
0.18
-0.18
Window
0.25
0.85
1.6
0.34
-0.34
Window
0.25
0.85
1.6
0.34
-0.34
Window
7a
7b
Total
Internal Wall
(Normal Floor)
0.25
0.85
1.6
A2-C2
Column S5
Door
Lintel
C2-D2
Door
Lintel
C3-D3
Door
Lintel
C1-C2
C3-C5
2--3 (BR 1)
Door
Lintel
3--4 (BR 2 a)
Door
Lintel
3.90
0.70
0.90
1.30
3.80
0.90
1.30
3.80
0.90
1.30
3.60
(5.100.35)
2.40
0.90
1.30
1.50
0.90
1.30
2.20
2.20
2.10
0.10
2.20
2.10
0.10
2.20
2.10
0.10
2.20
2.20
2.68
2.10
0.25
2.68
2.10
0.25
C--D (BR 2 b)
(3.801.25)
2.68
Total
Interior Plastering of
Bedroom 1
A1-A2
C1-C2
A1-C1
Window
A2-C2
S5 Extension
Door
Interior Plastering of
Ceiling
A1-A2-C1-C2
Column S5
Total
Interior Plastering of
Bedroom 2
C1-C2
D1-D2
Window
C1-D1
Window
C2-D2
Door
Interior Plastering of
Ceiling
C1-C2-D1-D2
Total
0.34
1.54
1.89
0.13
1.89
0.13
1.89
0.13
1.89
0.325
1.89
0.325
Unit
m3
m3
m3
m3
m3
m3
m3
-0.34
1.1925 m3
8.58
-1.54
-1.89
-0.13
8.36
-1.89
-0.13
8.36
-1.89
-0.13
7.92
10.45
6.432
-1.89
-0.325
4.02
-1.89
-0.325
13.68 m3
m2
m2
m2
5.02 m2
m2
m2
6.34 m2
m2
m2
6.34 m2
7.92 m2
10.45
m2
m2
4.217 m2
m2
m2
1.805 m2
6.834
6.834 m2
48.926 m2
3.50
3.50
3.90
1.60
3.90
(2*0.15)
0.90
3.90
0.15
2.68
2.68
2.68
2.20
2.68
2.20
2.10
3.50
0.70
3.50
3.50
(2*0.85)
3.80
1.60
3.80
0.90
3.80
3.50
50
2.68
2.68
1.30
2.68
2.20
2.68
2.10
1.89
9.38
9.38
10.452
-3.52
10.452
0.66
-1.89
m2
m2
m2
m2
m2
m2
m2
0.105
13.65
-0.105
m2
m2
48.459 m2
9.38
9.38
-2.21
10.184
-3.52
10.184
-1.89
m2
m2
13.30
m2
44.808 m2
3.52
2.21
3.52
1.89
m2
m2
NO TYPE OF JOB
Location
Interior Plastering
7c of Bathroom 1
C2-C3
Door
D2-D3
Window
C2-D2
C3-D3
Interior Plastering of
Ceiling
C2-C3-D2-D3
Total
Interior Plastering of
7d Bedroom 3
C3-C5
S8 Extension
Window
D3-D5
Width(m) Length(m)
2.40
0.90
2.40
0.50
2.45
2.45
2.45
Door
C5-D5
Window
Interior Plastering of
Ceiling
C3-C5-D3-D5
7e
Column S8
Total
Interior Plastering of
Bathroom 2
C3-C4
Door
D3-D4
Window
C3-D3
C4-D4
Interior Plastering of
Ceiling
Total
Scaffolding for
Gallery Opening
A3-A5-C3-C5
Column S6
K316 & K317
10
Total
Exterior Plastering
of the Wall A1-D1
for Normal Floor
Total
Scaffolding for
Exterior Plastering
for the Wall A1-D1
(-0.8 to +6.38)
2.68
2.10
2.68
0.60
2.68
2.68
Void
4.10
1.60
0.15
2.68
2.20
1.60
2.68
2.68
1.60
2.10
2.68
2.68
2.10
2.68
1.60
3.80
1.25
0.60
Cum.
Qty.
Qty.
Unit
6.432
-1.89
6.432
-0.30
6.566
6.566
m2
m2
m2
m2
m2
m2
5.88
m2
29.686 m2
m2
4.08
15.276
0.66
-0.72
10.988
4.288
-0.72
-1.89
3.35
6.834
-1.89
10.184
-4.08
m2
0.09
15.58
2.00
-0.09
1.89
0.30
2.40
5.70
(2*0.15)
0.45
4.10
1.60
0.45
0.90
1.25
(3.80 1.25)
0.90
3.80
(3*0.85)
Window
Door
C3-D3
Height(m)
0.72
0.72
1.89
1.89
m2
m2
m2
m2
m2
m2
m2
m2
m2
m2
59.77 m2
1.50
0.90
1.50
0.50
2.45
2.45
1.50
2.68
2.10
2.68
0.60
2.68
2.68
1.89
0.30
2.45
3.90
5.00 (5.48-1.50*)
*1.50m is reserved for worker on scaffolding.
0.15
0.70 (5.48-1.50*)
0.418
0.15 (3.90-0.70)
0.48 0.2304
A1-D1
Window
Window
8.30
1.60
1.60
2.68
2.20
2.20
A1-D1
8.30
7.18
51
3.52
3.52
4.02
-1.89
4.02
-0.30
6.566
6.566
m2
m2
m2
m2
m2
m2
3.675
m2
22.657 m2
77.61
m3
-0.418
-0.230
m3
m3
76.962 m3
m2
m2
m2
15.204 m2
22.244
-3.52
-3.52
59.594 m2
NO TYPE OF JOB
Painting of
11a Bedroom 1
Painting of
11b Bedroom 2
Painting of
11a Bedroom 3
Flooring for
12 Bedroom 1
Flooring for
Bedroom 2
Flooring for
Bedroom 3
Location
Same as
Plastering
Same as
Plastering
Same as
Plastering
13
Baseboard for
Bedroom 2
Baseboard for
Bedroom 3
14
15
Height(m)
Void
Cum.
Qty.
Qty.
48.603 m2
44.808 m2
55.558 m2
3.90
3.50
13.65
m2
Door
Column S5
0.10
0.15
0.84
0.70
0.084
-0.109
m2
13.625 m2
C1-C2-D1-D2
3.80
3.50
13.30
m2
Door
0.10
0.84
0.084
13.384 m2
C3-C5-D3-D5
4.10
1.60
0.10
0.15
3.80
1.25
0.84
0.60
15.58
2.00
0.084
-0.09
m2
m2
m2
17.574 m2
44.583 m2
14.80
-1.04
0.30
m
m
14.06 m
1.04
14.60
-1.04
m
13.56 m
1.04
1.04
19.00
-1.04
-1.04
m
m
16.92 m
44.54 m
m2
m2
49.037 m2
A1-A2-C1-C2
Door
Column S5
0.09
14.80
1.04
2*0.15
C1-C2-D1-D2
Door
14.60
C3-C5-D3-D5
Door
Door
19.00
Total
Polishing
Parquet
Baseboard
0.109
0.10
44.54
44.583
4.454
A1-C1
1.60
2.20
3.52
3.52 m2
Bedroom 2
A1-C1
D1-D2
1.60
2*0.85
2.20
1.30
3.52
2.21
m2
5.73 m2
Bathroom 1
D2-D3
0.50
0.60
0.30
0.30 m2
Bathroom 2
D3-D4
0.50
0.60
0.30
0.30 m2
Bedroom 3
D5
C5-D5
0.45
3*0.85
1.60
1.60
0.72
4.08
m2
4.80 m2
Window Frames
Bedroom 1
14.65 m2
Total
16
Unit
A1-A2-C1-C2
Door
Column S8
Total
Baseboard for
Bedroom 1
Width(m) Length(m)
Heat Insulation
A1-A5-C1-C5
12.60
3.40
42.84
m2
C1-C5-D1-D5
13.30
5.15
68.495
m2
111.335 m2
Total
52
Example-2: For the quantities calculated in Example-1 determine the cost of the
following items using 2006 unit prices of Ministry of Environment and Urban Planning
(including overhead expenses and profit).
a) Formwork for column S2 (between +3.70 to +6.50).
b) Reinforcement for column S2 between +3.70 to +6.50, excluding reinforcement
extensions from previous floor.
c) Concrete (C20) for column S2 (between +3.70 to +6.50).
Example-3: Typical plan and sections views of a building footing and foundation wall
are given in Figure 4.6.
a) Determine the volume of excavation for the site which has been graded to
elevation +17.9 m.
b) Determine the amount of formwork required to pour footings, walls and slab.
c) Determine the total labor and material cost of formwork. To complete 1m2 of
formwork 0.75 carpenter and 0.75 laborer hours is needed. Hourly wage for the
carpenter is 4 TL/hour and hourly wage for the laborer is 3 TL/hour. Material
cost of 1 m2 of formwork is 8 TL.
53
Figure 4.6: Plan and section views for the footing and walls
a) Excavation calculations:
The excavation is in a form of shape called prismoid. The volume of prismoid is
calculated by the formula:
Volume = h/6 x (ABASE + 4 x AMID + ATOP)
h = 17.9 16.4 =1.5 m.
ABASE = (25.6 + 2 x 0.9) x (10.6 + 2 x 0.9) = 339.76 m2
AMID = (25.6 + 2 x 0.9 + 2 x 0.75) x (10.6 + 2 x 0.9 + 2 x 0.75) = 401.71 m2
ATOP = (25.6 + 2 x 0.9 + 2 x 1.5) x (10.6 + 2 x 0.9 + 2 x 1.5) = 468.16 m2
Volume of excavation = 1.5/6 x (339.76 + 4 x 401.71 + 468.16) = 603.69 m3
54
4.6 REFERENCES
1. Akal, . (2002). 2002 Yl naat Birim Fiyat Analizleri, afak
Matbaaclk, Ankara
2. Dagostino, F.R., and Feigenbaum, L. (2003). Estimating in Building
Construction, Prentice Hall, Upper Saddle River, New Jersey.
3. Oswald, P.F. (2001). Construction Cost Analysis and Estimating,
Prentice Hall, Upper Saddle River, New Jersey.
55
CHAPTER 5
PLANNING
Everyone, whether good or bad, short-term or long-term, important or unimportant,
consciously or unconsciously, makes plans. Construction managers do make plans also
like everyone else.
Then, the definition of planning is:
Planning is a decision making process performed in advance of action which
endeavors to design a desired future and effective ways of bringing it about
(Ackoff, 1970).
Trying to anticipate what will happen and devising ways of achieving the set of
objectives and targets (Fryer, 1992).
Both definitions emphasize that in planning there are goals (objectives) that are desired
(or instructed or specified) to be realized in future, and that planning is a process during
which efforts and decisions are made to achieve the goals at the desired time in the
desired way.
The main objectives of a construction project are:
56
Before going into the discussion of construction project planning, a few points will be
highlighted about planning in general.
2.
3.
Who should perform each activity and with what means? (resources)
4.
57
components (work items). Execution should be understood to mean that early decisions
the plans become either direct assignment, or at least guide-lines for site management to
make operational decisions later on. The essential elements of how, when and who are
thus prepared for the execution of the construction project.
The second planning function is to coordinate and communicate with the many parties
involved into the realization of a construction project, i.e. owner, designer, licensing
authorities, subcontractors and suppliers, and numerous specialists and functionaries on
site and in home office. The construction technology being inherently interdependent
provides few or no buffers, and requires many diverse parties to work in close liaison
with each other in terms of time and / or space. Maintaining coordinated production
becomes thus a key function of construction management.
The third function of the planning is to facilitate project control which encompasses
control and forecasting. If planning establishes targets and the course to reach them,
control is the process that ensures the course of action is maintained and desired targets
are reached. Control involves measuring and evaluating performance and the taking of
corrective action when performance diverges from plans. To be effective, a control
system must be modeled closely after planning system.
information gathering
preparation of plans
information diffusion
58
Planning the
planning
Gathering
information
process
Preparation
of
the
Diffusion of
information
plans
Evaluation of
the planning
process
Project Cycle
Action
Continuous,
Intermittent)
updating frequency,
59
Information gathering
The next phase, information gathering, may require considerable resources. The source
material required for planning a typical construction project includes:
Contract documents
Construction technology
Goals and constrains dictated by top management, the client, and various external
authorities regarding quality control, finance and law.
After construction has started, information regarding progress on site is also collected for
control and forecasting purposes, with emphasis on resources consumed and goals
achieved.
Preparation of plans
In the third stage, working out the plans, decisions are made based on the evaluation of
the collected information using techniques adapted to resource planning and scheduling
(e.g. site layout, temporary facilities, flow diagrams and process charts, Gantt, Line of
Balance (LOB), Critical Path Method (CPM) and Program Evaluation and Review
60
Technique (PERT)) and their respective cost implications (e.g. cash flow, break-even and
risk analysis).
1. Decide the level of detail for the project schedule
2. Decide the preliminary work breakdown structure (Activities=What?)
3. Decide
construction
methods
and
resources
(Methods=How?
and
resources=Who?)
4. Decide project completion constraints
5. Divide project into milestones (Timing=When?)
6. Prepare milestone schedule (Master Time Plan)
7. Develop the detailed work breakdown
8. Collect scheduling information from subcontractors
9. Decide activities sequence and duration (CPM, When?)
10. Perform scheduling calculations (obtain construction schedules)
Information diffusion
The preparation of the plans is followed by information dissemination according to users
needs. Information overload can be as harmful as a shortage. The planner must take a
realistic, and to a certain degree psychological assessment, of what information is
required by whom and in what format. After each planning iteration during the projects
cycle, needs must be reassessed to adjust to the constant changes in the staffing of key
recipients of information and particularly in consequent changes in the plans. If a drastic
change in the execution of the project is called for, or if the response time must be very
short, the medium and format of the information distribution must be adapted
accordingly. Under these circumstances, the planner not only makes the decisions
concerning information distribution but often has to take an active role in its assimilation.
The evaluation of factors made during this phase includes:
61
Content (e.g. guidelines and goals, results and status, variances and reasons,
analysis and calculations, assumptions and explanations, and remedy suggestions)
Medium (e.g. visual paper screen, auditory take, telephone, direct meeting)
62
A bar chart is generally organized so that all activities are listed in a column at the left
side of the diagram. A horizontal time scale extends to the right of the list, with a line
corresponding to each activity in the list. A bar representing the progress of each activity
is drawn between its corresponding scheduled start and finish times along its horizontal
line. A simple bar chart is shown in Figure 5.2.
Bar charts are the easiest to understand and the most widely used form of planning tools.
Even when the network analysis is used, the initial work schedule is presented usually in
bar chart form.
63
The CPM was developed in 1956 by the DuPont Company, with Remington Rand as
consultants, as a deterministic approach to scheduling. The CPM method is commonly
used in the engineering and construction industry. In order for a project to be scheduled
by CPM the followings have to be known:
Work breakdown structure of the project, so that each activity of the project is
determined,
For project management the CPM is the most commonly used network analysis
technique. The concept is simple, the computations only require basic arithmetic, and a
large number of computer programs are available to automate the work required of CPM
scheduling. There are two basic methods of constructing CPM diagrams: the arrow
diagram (activity on arrow) and the precedence diagram (activity on node). Although
both methods achieve the same results, most project managers prefer the precedence
diagram because it does not require the use of dummy activities.
64
65
Figure 5.2: A Simple Bar Chart
Activity
Activity
A
duration
event
Arrow Diagram
Flow
line
Activity
B
Precedence Diagram
Event
Network
H
C
F
H
G
E
Arrow Diagram
Duration (D)
Precedence Diagram
Early Start
(ES)
Early Finish
(EF)
Late Finish
(LF)
Late Start
(LS)
66
Total Float
(TF)
TF=LETj-EETi-D
where the subscript i represents the preceding event and the
subscript j represents the following event.
: The amount of time an activity may be delayed without
Free Float
(FF)
activity.
FF=EETj-EETi-D
Independent
Float (IF)
IF=EETj-LETi-D
where the subscript i represents the preceding event and the
subscript j represents the following event.
EETi
LETi
EETj
TOTAL FLOAT
ACTIVITY DURATION
ACTIVITY DURATION
FREE FLOAT
IND.
FLOAT
ACTIVITY DURATION
Critical Path
LETj
TF=LETj-EETi-D
FF=EETj-EETi-D
IF=EETj-LETi-D
Dummy
Activity
67
dummy are completed. The dummy does not require any time
and resource.
i
dummy
WRONG!!
Installation of
door frames
identity
dummy
Installation of
window frames
Painting of walls
RIGHT!!
Installation of
door frames
Installation of
window frames
Painting of walls
Installation of
door frames
Installation of
window frames
WRONG!!
Glazing of windows
RIGHT!!
Installation of
door frames
Painting of walls
68
NETWORK CONSTRUCTION
Network diagramming techniques:
Activity on Arrow (AoA)
Activity on Node (AoN)
Summary of Denotations:
A-o-A
denotation
Activity
Event
Dummy
Flow line
A-o-N
denotation
none
none
none
A-o-A
C depends on
A&B;
A&B starts at the
same time
B depends on A
A
A
C
B
C depends on A;
D depends on
A&B
C depends on
A&B;
D depends on
A&B
D depends on A;
E depends on
A,B&C;
F depends on C
C
A
B depends on A;
C depends on A;
B and C starts at
the same time;
D depends on
B&C
A-o-N
A
B
69
CPM CALCULATIONS
The major aims of calculation of activity times are to find the critical path, total
project time and floats of activities. As a result of forward pass and backward passes,
the activities are classified as critical and non-critical; free and total floats of the
activities are determined.
Forward Pass: In forward pass calculations, early start and early finish of each
activity are calculated. The largest early finish of all preceding activities defines the
early start of all following activities. The calculations start from the first event to the
last.
Backward Pass: In backward pass calculations, late start and late finish of each
activity are calculated. The smallest late start of all following activities defines the
late finish of all preceding activities. These calculations cannot be performed without
ending the forward pass calculations. This pass starts from the last event to the first.
Example 5.1:
In the following table you are given a set of activities, their durations and
relationships between them.
Activity
A
B
C
D
E
F
G
Duration
(days)
4
7
5
4
8
8
16
Dependence
A
A
B
B,C,E
-
70
Solution:
a) A-o-A diagram
A
4
B
7
D
4
C
5
F
8
E
8
G
16
b) A-o-N diagram
A
Start
Finish
E
G
A
4
B
7
D
4
C
5
F
8
11
8,9,11
E
8
G
16
71
19
15,16,19
BP:15
11
11
A
4
BP:3
3
0
B
7
D
4
C
5
F
8
11
BP:6
4
E
8
11
19
19
FP:15
16
19
11
FP:8
9
11
G
16
11
A
4
11
B
7
D
4
C
5
F
8
11
11
E
8
G
16
TF
EF
Act. name
LS
dur
LF
72
19
19
Forward Pass:
4
11
11
15
11
19
19
19
Finish
Start
0
0
E
8
16
G
16
Backward Pass:
4
11
11
B
4
Start
0
11
15
11
C
4
0
0
E
3
11
16
G
3
16
15
19
73
19
19
19
F
11
11
19
Finish
19
19
19
11
11
B
4
11
15
19
11
19
C
4
15
19
11
11
Finish
19
19
Start
0
19
19
0
0
E
3
11
16
G
3
Activity
A
B
C
D
E
F
G
Duration
4
7
5
4
8
8
16
EST
0
4
4
11
0
11
0
16
19
EFT
4
11
9
15
8
19
16
LST
0
4
6
15
3
11
3
LFT
4
11
11
19
11
19
19
TF
0*
0*
2
4
3
0*
3
Example 5.2:
Carry out CPM calculations for the given A-o-A network below to find project
duration (days) and the critical path(s).
A
3
E
3
B
1
F
5
G
6
C
4
H
5
74
K
3
Solution:
3
A
3
0
5
4
10
B
1
14
F
5
14
10
G
9
6
C
H
5
4
4
11
Activity Duration
EST
EFT
LST
LFT
TF
Critical
(days)
A
0*
Yes
No
0*
Yes
0*
Yes
No
10
No
10
10
0*
Yes
11
No
14
14
0*
Yes
10
14
10
14
0*
Yes
12
11
14
No
75
Example 5.3:
A contractor is responsible to complete the excavation and basic construction works
(except the finish works) of a 2 story building. There is one excavator and 1 team for
each activity (R/C works, formwork, plastering, wall construction, floor covering etc.)
Following are the activities and estimated durations of these activities:
Abbreviation
EXC
FORMF
MECH
R/CF
INSU
FORM1
R/C1
FORM2
R/C2
WALL1
WALL2
PLAS1
PLAS2
FRAM1
FRAM2
FLOOR1
FLOOR2
CLEAN
Activity Description
Excavation
Formwork for foundation
Installation of mechanical & electrical conduits and
pipes
R/C works (reinforcement and concrete casting) for
the foundation
Water insulation of foundation
Formwork for 1st floor
R/C works for 1st floor
Formwork for 2nd floor
R/C works for 2nd floor
Wall construction in 1st floor
Wall construction in 2nd floor
Plastering in 1st floor
Plastering in 2nd floor
Installation of window/door frames in the 1st floor
Installation of window/door frames in the 2nd floor
Floor covering in the 1st floor
Floor covering in the 2nd floor
Cleaning, mobilizing
Duration
(days)
5
6
8
5
2
8
6
8
6
10
10
8
8
2
2
10
10
1
Required:
1. Draw the A-o-A and A-o-N diagrams
2. Perform the CPM calculations on both of the network diagrams; find the total
project time and critical path.
76
Activity
EXC
FORMF
MECH
R/CF
INSU
FORM1
R/C1
FORM2
R/C2
WALL1
WALL2
PLAS1
PLAS2
FRAM1
FRAM2
FLOOR1
FLOOR2
CLEAN
Duration
(days)
5
6
8
5
2
8
6
8
6
10
10
8
8
2
2
10
10
1
EST
LST
EFT
LFT
TF
Critical
0
5
5
13
18
18
26
32
40
32
46
42
56
50
64
50
64
74
0
7
5
13
24
18
26
32
40
36
46
46
56
70
72
54
64
74
5
11
13
18
20
26
32
40
46
42
56
50
64
52
66
60
74
75
5
13
13
18
26
26
32
40
46
46
56
54
64
72
74
64
74
75
0*
2
0*
0*
6
0*
0*
0*
0*
4
0*
4
0*
20
8
4
0*
0*
Yes
No
Yes
Yes
No
Yes
Yes
Yes
Yes
No
Yes
No
Yes
No
No
No
Yes
Yes
77
3
MEC
7
1
EXC
FORMF
R/CF
INSU
6
4
81
FORM1
7
4
R/C1
8
4
FORM2
WALL1
10
9
4
R/C2
11
10
PLAS1
WALL2
13
10
12
PLAS2
14
16
FRAM2
FRAM1
2
17
FLOOR1
10
15
FLOOR2
10
CLEAN 18
13
3
MEC
EXC
5
0
20
18
8
FORMF
R/CF
INSU
6
4
FP:42
46
13
82
FP:11
13
FP:52
64
32
FORM1
7
4
R/C1
40
8
4
FORM2
56
46
R/C2
9
4
11
WALL2
64
64
PLAS2
13
10
16
14
FRAM2
26
FP:20
26
WALL1
10
10
50
9
PLAS1
12
8
74
FRAM1
FP:66 17 CLEAN 18
1
74
75
42
FLOOR1
15
10
FLOOR2
10
64
FP:50
64
13
13
BP:24
18
18
18
3
MEC
8
1
EXC
FORMF
5
5
83
BP:7
5
R/CF
6
13
20
INSU
26
6
4
BP:36
32
32
32
13
FORM1
7
4
8
26
R/C1
8
4
40
FORM2
40
46
R/C2
9
4
11
56
46
WALL2
10
BP:72
64
64
64
56
13
PLAS2
14
64
16
72
FRAM2
26
WALL1
10
10
42
50
9
PLAS1
12
8
BP:70
54 54
74
FRAM1
2
17
46
BP:46
46
74
CLEAN 18
75
FLOOR1
15
10
64
FLOOR2
10
64
75
Duration
(days)
5
6
8
5
2
8
6
8
6
10
10
8
8
2
2
10
10
1
EST
LST
EFT
LFT
TF
Critical
0
5
5
13
18
18
26
32
40
32
46
42
56
50
64
50
64
74
0
7
5
13
24
18
26
32
40
36
46
46
56
70
72
54
64
74
5
11
13
18
20
26
32
40
46
42
56
50
64
52
66
60
74
75
5
13
13
18
26
26
32
40
46
46
56
54
64
72
74
64
74
75
0*
2
0*
0*
6
0*
0*
0*
0*
4
0*
4
0*
20
8
4
0*
0*
Yes
No
Yes
Yes
No
Yes
Yes
Yes
Yes
No
Yes
No
Yes
No
No
No
Yes
Yes
84
MECH
INSU
EXC
R/C1
R/CF
FORM2
R/C2
WALL2
PLAS2
FRAM2
CLEAN
FORMF
FORM1
85
WALL1
PLAS1
FRAM1
FLOOR1
FLOOR2
TF
EF
Act. name
LS
dur
LF
FP: 42
46
1
8
1
3
FP: 11
13
1
3
FP: 20
26
INSU
MECH
3
2
2
0
2
6
1
8
4
0
4
0
4
6
FP: 50
56
4
6
5
6
5
6
PLAS2
FRAM2
1
0
3
2
86
1
1
FORMF
6
FORM1
8
FP: 66
74
7
4
7
5
CLEAN
FP: 60
64
6
6
WALL2
6
4
5
2
6
6
4
R/C2
R/C1
1
8
6
4
FORM2
R/CF
EXC
FP: 52
64
7
4
FLOOR2
3
2
4
2
4
2
5
0
5
0
5
2
WALL1
PLAS1
FRAM1
1
0
1
0
5
0
6
0
FLOOR1
1
0
1
8
1
3
8
2
4
1
3
1
3
87
1
3
BP: 7
5
2
6
1
8
3
2
2
6
1
1
FORMF
1
3
1
3
1
8
BP: 24
18
4
0
4
6
4
0
5
6
5
6
WALL2
R/C2
4
0
4
6
4
6
4
6
1
0
6
4
6
4
PLAS2
5
6
5
6
3
2
6
6
FRAM2
6
4
BP: 72
64
7
2
7
4
7
4
1
8
2
6
FORM1
1
8
2
6
2
6
7
4
3
2
BP: 36
32
6
4
7
4
FLOOR2
3
2
4
2
4
2
WALL1
3
6
1
0
5
0
5
0
BP: 46
46
4
6
6
4
FRAM1
PLAS1
4
6
5
2
5
4
BP: 70
56
54
7
0
7
2
5
0
6
0
FLOOR1
5
4
1
0
6
4
7
5
CLEAN
R/C1
R/CF
EXC
0
4
0
FORM2
INSU
MECH
5
3
2
2
0
1
0
7
4
7
5
1
8
88
2
4
1
3
1
3
2
6
1
8
1
3
5
5
1
8
1
3
1
3
4
0
3
2
2
6
4
6
4
6
4
0
5
6
WALL2
R/C2
4
0
5
6
4
6
4
6
1
0
6
4
6
4
PLAS2
5
6
5
6
3
2
6
6
FRAM2
6
4
7
2
7
4
7
4
1
8
2
6
FORM1
1
8
2
6
2
6
7
5
CLEAN
R/C1
1
1
FORMF
4
0
FORM2
R/CF
EXC
0
3
2
2
0
INSU
MECH
5
7
4
3
2
6
4
7
4
FLOOR2
3
2
4
2
4
2
WALL1
3
6
1
0
5
0
5
0
4
6
6
4
FRAM1
PLAS1
4
6
5
2
2
0
5
4
7
0
7
2
5
0
6
0
FLOOR1
CP: EXC-MECH-R/CF-FORM1-R/C1-FORM2-R/C2-WALL2-PLAS2-FLOOR2-CLEAN
5
4
1
0
6
4
1
0
7
4
7
5
5.3 REFERENCES
1. Harris, F., and McCaffer, R. (2001). Modern Construction Management, 5th Edition,
Blackwell Science, UK.
2. Fryer, B.G. (1997). The Practice of Construction Management, 2nd Edition, Blackwell
Science, UK.
3. Oberlender, G.D. (1993). Project Management for Engineering and Construction,
McGraw-Hill, USA.
4. Pilcher, R. (1992). Principles of Construction Management, 3rd Edition, Mc-Graw
Hill International Series, UK.
5. Ackoff, R.L. (1970). A Concept to Corporate Planning, Wiley-Interscience, USA.
89
CHAPTER 6
MANAGING QUALITY
QUALITY OF PROCESSES
Quality management is now a major function within major construction companies.
Unless a construction company can guarantee its clients a quality product, it can now no
longer compete effectively in the modern construction market (Harris and McCaffer,
2001). Crucial to the delivery of such quality products is the quality of processes that
produce the product. The reason is simple: technical specifications may not in themselves
guarantee that a customers requirements will be consistently met, if there are deficiencies
in specifications or in the organizational system to design or produce the product or
service. Quality of the product is the ultimate goal, but quality of the management
processes is a significant contributor to the consistent quality of the companys products.
Quality assurance (QA) has the objective to provide the client with the quality of work
required without the need for clients checking during the process. A customer for a car
does not insist on checking the assembly of the car, for example. This objective is
achieved by documenting what processes are performed and how they are accomplished,
by self-checking that each process is completed correctly and finally by creating records
of the processes. The policy of recording the processes undertaken, together with the
checking and recording of procedures, provides the customer with the assurance that the
company is aiming to achieve an acceptable standard of quality. Although 'satisfying the
client' is the most important objective, the essence of QA is primarily to address 'getting it
right first time' in order to avoid unnecessary costs to the contractor.
90
Management of quality normally involves three steps (Harris and McCaffer, 2001):
91
There are also advantages of implementing the ISO 9000 to a construction company,
which are:
1. Optimizes resources usage in the organization.
2. Improves awareness of company's objectives and policies.
3. Improves communication between various departments in the same organization.
4. Improves tractability of quality problems.
5. Cuts down material wastage.
6. Formalized systems ensure consistent quality services.
7. Provides useful documented reference.
8. Improves work quality with fewer rejects and less repeated work.
9. Rectifies errors at early stage.
10. Improves relationship with the owner, subcontractors, engineer architect and
material suppliers.
11. Improves corporate quality image.
12. Introduces continuous improvement through a review of the quality system.
13. Improves records and makes retrieval of information easy in case of litigation.
14. Helps project to be completed within the time frame stipulated in the contract.
(Chew and Chai, 1996)
A possible disadvantage of ISO 9000 is that registration may become the goal in itself.
To be certified as operating to the ISO 9000 standard is now virtually seen as essential in
todays construction industry, many companies has set up QA systems merely to register.
Many clients will not do business with companies not certified to ISO 9000. ISO 9000
currently includes three main quality standards, as seen in Figure 6.1:
92
ISO 9000:2000
Fundamentals and vocabulary
ISO 9004:2000
ISO 9001:2000
Requirements
Figure 6.1: Structure of the ISO 9000 Standard (adapted from Nee, 1996)
ISO 9001 presents requirements, while ISO 9000 and ISO 9004 present guidelines. ISO
9004 is recommended as a guide for organizations whose top management wishes to
move beyond the requirements of ISO 9001, in pursuit of continual improvement of
performance. However, it is not intended for certification or for contractual purposes.
All of these are process standards, not product standards.
93
Hand-over / completion
Mark up drawing to as-built state
Prepare handover packages and submit
Figure 6.2: Contractors Quality Actions (adapted from Harris and McCaffer, 2001)
Some often used documents in construction site quality management are mentioned in the
following text.
METHOD STATEMENTS
Method statements are frequently seen documents in construction QA. Method statements
are the equivalent of a standard operating procedure (SOP), however SOPs are often
used for works having a repetitive character. SOPs may apply to many functions in a
construction firm, for example workflow in the site or head office. However, few site jobs
in construction are completely identical and contractors are therefore required, as part of
their QA submittals, to prepare site-specific method statement for major tasks, such as
excavation, concreting, cladding, painting etc. The method statement serves to explain
that proper procedures and best practice will be followed. In many cases a method
statement is required for a very specific sub-task, such as concreting in extreme weather
conditions, early striking of formwork or also where extraordinary construction methods
are used.
94
The execution steps are normally explained in plain language. As an example for an
excavation job:
The method statement must emphasize those details that are critical for quality. For
example, a method statement for concreting works must stress the issues of joints - e.g.
exposure of aggregate in joint prior to adjacent casting - temperature control, curing
conditions, formwork level and plane, and so on.
INSPECTION AND TEST PLANS
Inspection and test plans (ITPs) are lists with check-points of a specific work tasks. It
may or may not also function as record of work performed, in some cases the ITP will
just refer to the relevant quality document or record. In-process activities that cannot be
verified after the fact by inspection must have stringent in-process controls by qualified
personnel to assure conformance to specifications. Construction has numerous such
examples and many features of a construction project are hidden by subsequent
construction, and these are often the most vital. Examples are the concrete reinforcement
or sealing of concrete walls prior to backfill. In such cases check items may be hold
points; i.e. points where production cannot continue before the item is checked off on the
inspection sheet, a typical example is reinforcement before concrete is poured. A variety
of the hold point is the witness point, meaning that the work item cannot continue unless
the controlling engineer is witnessing the work.
Table 6.1: Example Excerpt of Inspection and Test Plan for a Deep Excavation
Item
Excavation
plan
Plant
requirements
Dewatering
Inspection
Earthwork
supervisor,
Site
personal
Earthwork
supervisor
Site
engineer
Inspection
methods and
reference
papers
When
Who
Criteria of
acceptance
Documentation
(QD)
Construction
sequence
drawings
All
excavations
Site
engineers
In
accordance
to drawing
RIW
All
excavations
All
excavations
Site
engineers
Site
engineers
Plant dept.
FOR/MS/1303
95
Site diary
60 m3/h
Site diary
NON-CONFORMANCE REPORTS
A non-conformance report (NCR) is an important instrument to register works that have
been performed not in accordance with specifications. The finding of improperly done
site work causes a NCR to be raised and signed by both contractor and Engineer. The
procedure for an NCR can be simplified as follows:
1. A non-conformance is observed on site NCR is raised and registered
2. NCR is reviewed, typically by Engineer in collaboration with designer and
contractor, etc.
3. Engineer decides the disposition (action to be taken), these are typically one of the
following: Demolish/Rework, Repair or Accept-as-is.
4. Contractor carry out the disposition
5. Works are checked to be in conformance with Engineers disposition
6. Contractor takes appropriate steps to avoid recurrence
ISO 9000 requires documented procedures for handling of non-conforming product, and
the NCR is the typical instrument in construction. The objectives for such control are to
prevent the customer receiving nonconforming product and to optimize costs of further
processing. NCR forms often require several signatures, and the NCR work flow can be
very bureaucratic, having a negative bearing on progress. It is therefore important to have
a simple NCR system. The accept-as-is solution to an NCR can be chosen when the nonconformance is a deviance from the specification, but extremely costly to rectify and not
a major breach of design intent. The disposition must therefore be made by someone with
authority, and the owners representative must have the final signature.
Client and designer may misunderstand the details of the brief with regard to the
building's purpose, performance or appearance.
The designer may perceive quality in a different way to the client. The designer
may, through misunderstanding or ignorance, misinterpret the objectives
regarding quality specified by the client.
The construction may be insufficiently financed to build to the quality levels
desired by the client. Failure to balance cost with quality at the brief and design
96
stages can lead to a reduction in the level of quality achieved during construction
through re-specification of some items to an inferior standard.
The time schedule may be strained, putting at risk the desired quality level
through hasty work.
The designer may design the building that cannot be built to the required levels of
quality due to buildability issues not being addressed.
The contractor may fail to understand what the desired standards of quality are. If
the design stage is completed before appointing the contractor, as in the case of
'traditional' procurement, there is no opportunity for the designer to effectively
communicate desired quality levels to the contractor first hand. The designer has
to rely on the clarity of drawings and specifications and upon the contractor's
correct interpretation of these when construction proceeds. The builder does not
always know the 'real' standards before commencing work on site.
The contractor may not be able to build to the desired quality standards due to a
mismatch between the design and construction systems. The contractor may not
be sufficiently competent to undertake the task or may misunderstand the
requirements through inadequate communication of the design concept.
Construction quality assurance has in certain instances been confined to
permanent works, i.e. excluding the contractors temporary works. In many
types of construction, this is a very are artificial division. QA must include all
aspects vital to the permanent works, and temporary works must not escape QA.
Design requirements may not be communicated simply and effectively to the
operative at the workplace.
Life cycle, operation and maintenance cost of the project are not properly
addressed. This can result from an inadequate brief making the building too
expensive to operate and maintain.
97
Cost of conformance:
(a) Prevention
Quality planning
Process control
Design and development of quality information equipment
Quality training and work force development
Product design verification
Systems development
Other prevention costs
(b) Appraisal
Test and inspection of purchased materials
Laboratory acceptance testing
Laboratory and other measurement services
Inspection, testing, checking labor, setup for test and inspection
Test and inspection and material and minor quality equipment
Quality audits
Outside endorsements
Maintenance and calibration of quality information test and inspection equipment
Product engineering review and shipping release
Field testing
Cost of Non-conformance
(a) Internal failures
Scrap
Rework
Material procurement costs
Factory contact engineering
(b) External failures
Complaints in warranty
Complaints out of warranty
Product service
Product liability
Product recall
These are not the only ways of organizing costs. In construction some of these do not
apply, and certain costs are often seen in construction or project work in general:
98
It should be kept in mind that the more effort spent on prevention means that the less
failure costs will arise. In quality environment this principle is summarized by the general
rule of thumb: Ounce of prevention is worth a pound of cure On the other hand
spending too much money on the prevention and appraisal costs decreases the failure but
increases the total cost of quality. Figure 6.3 indicates conceptually the trade-off between
failure cost and prevention/appraisal costs. The figure indicates the optimal level of
quality efforts, at which the total quality costs are minimized.
COST
Total cost of
quality
Minimum
Prevention +
appraisal cost
Failure cost
100%
Defects
QUALITY LEVEL
0%
Defects
Figure 6.3: Cost versus Quality Level classic view adapted from Brown and Kane,
1984
An important non-conformance cost is revenue loss (lost sales) due to poor quality this
is a hidden cost because it is not easily measured. Costs associated with poor quality are
identified and measured for three reasons:
To quantify the size of the quality problem to help justify an improvement effort
To guide the development of that effort
To track progress of improvements
Quality cost data should not be used for reporting purposes; publication of costs alone
has shown to solve no problems. Quality-related costs should be used to support a quality
improvement program and to sell the quality efforts to higher management by using the
language of money.
99
improved. The management representative shall oversee the quality system and report on
its performance to management for review and improvement. There must not be any
conflict of interest if the representative has other duties than quality, and typically the
Quality Manager will report directly to the General Manager.
This management representative can be entitled the Quality Manager, Quality Assurance
Manager, QA/QC Manager or similar. In a construction firm, however, there is usually a
project official with quality-related duties assigned to the quality of each project. This
official will usually be entitled QA Manager or similar.
A quality manager may have the following duties:
6.6 REFERENCES
1. Harris, F., and McCaffer, R. (2001). Modern Construction Management, 5th Edition,
Blackwell Science, UK.
2. EN ISO 9001:2000, Quality management systemsRequirements, International
Standards Organization.
3. Nee, P. (1996). ISO 9000 in Construction, John Wiley & Sons, Inc.
4. Griffith, A. (1990). Quality Assurance in Building, Macmillan.
5. Bennett, F.L. (1996). The Management of Engineering, Wiley & Sons, Inc.
6. Juran, J.M. (1999). Jurans Quality Handbook Fifth Edition, McGraw-Hill.
7. Brown, F.B., and Kane, R.W. (1984). Quality cost and profit performance, in:
Campanella, J. Editor, Quality costs: Ideas and application, Milwaukee, WI: ASQC
Press.
8. Bubshait, A.A. and Al-Atiq T.H. (1999). ISO 9000 Quality Standards in
Construction, Journal of Management in Engineering, Vol. 15, No. 6,
November/December 1999, pp. 41-46.
9. Chini, A.R. and Valdez, H.E. (2003). ISO 9000 Implementation in Turkish Industry,
Journal of Management in Engineering, Vol. 19, No. 2, April 2003, pp. 69-77.
10.Phenol, L.U. (1994). ISO 9000: Implementation Problems in the Construction
Industry, Quality World, American Society of Quality Control, May, pp. 2-4.
100
11.Chew, Y.S., and Chai, L.N. (1996). ISO 9002 in Malaysian Construction Industry.
McGraw Hill Book Co.
12. http://www.iso.org/iso/en/ISO 9000-14000/ISO 9000/ISO 9000index.html
13. http://www.baldrige.nist.gov/
14. http://www.efqm.org/model_awards/eqa/intro.htm
15. http://www.juse.or.jp/e/deming/index.html
16. http://www.kalder.org.tr
17. http://www.bath.ac.uk/management/agile/summary/summary.html
101
CHAPTER 7
MANAGING HEALTH and SAFETY
102
A company should base its safety program not on one source of safety information
but on a variety of sources, such as:
Current laws
Where possible, one individual in the company should be appointed Safety Engineer
and charged with responsibility for staying informed on new safety developments and
laws, reviewing company policies and recommending changes, and enforcing company
safety policies on the jobsite.
This review should be followed by a meeting with the owner's and/or general contractor's
safety representative to discuss (MCAA, 1984):
103
Necessary safety procedures that are lacking or unclear in the existing policies
Provide and maintain safety-related equipment such as: first aid kits, hard
hats, gloves, goggles, helmets, respirators, and other personal protection
equipment
Regularly inspect tools and construction equipment, including extension
cords, and tag worn or damaged items for return to the company shop for
repair or replacement
Regularly inspect personnel and material handling equipment and facilities,
particularly hoists and rigging, scaffolding and man lifts, storage areas and
traffic paths
Enforce and verify lock-out/tag-out procedures
Regularly check the condition of special items such as fire extinguishers and
acetylene and oxygen cylinders, valves, hoses and other accessories
Ensure that mechanics know how to use the tools needed for the job,
instructing new mechanics in the proper use of bask tools and all mechanics in
the proper use of specialized tools
Monitor the use of all tools, construction equipment, and jobsite facilities
Enforce safety procedures for special conditions such as working inside tanks,
enclosures and other confined spaces
Monitor compliance of company personnel and subcontractors with all
company and project-specific safety policies
Correct or have corrected all safety violations and hazardous conditions that
are the responsibility of the contractor
Report to the project manager or other project authority all unsafe practices
by other trades and hazardous conditions that are the responsibility of the
general contractor or the owner to correct
Educate field personnel in safety matters, making sure that every employee
receives a copy of and clearly understands all company, owner/general
contractor, and the safety regulations
104
Utilize guides or signalmen when the operator's visibility is limited or when there
is danger to nearby workers. Backup alarms or guides must be used when
equipment operates in reverse.
Exercise extreme caution and comply with safety regulations when operating near
high-voltage lines. In case of contact with a high-voltage line, the operator should
attempt to move the equipment enough to break contact.
Use care when operating equipment on side slopes to prevent overturning.
When operating cranes, be extremely careful not to exceed safe load limits for the
operating radius and boom position. Electronic load indicators are available.
Do not allow workers to ride on equipment unless proper seating is provided.
Park equipment with the brake set, blade or bowl grounded, and ignition key
removed at the end of work.
When hauling heavy or oversized loads on highways, make sure that loads are
properly secured and covered if necessary. Slow-moving and over-sized vehicles
must use required markings and signals to warn other traffic.
Take positive action to ensure that equipment under repair cannot be accidentally
operated.
Utilize blocking or other positive support when employees must work under
heavy loads supported by cables, jacks, or hydraulic systems.
105
Ensure that any guards or safety devices removed during equipment repair are
promptly replaced.
Shut down engines and do not allow smoking during refueling.
7.6.3 Excavations
The sides of excavations must be properly shored or sloped to the angle of repose
to prevent cave-ins in accordance with safety regulations.
Avoid the operation of equipment near the top edge of an excavation because this
increases the chance of slope failure. The storage of materials near the top edge of
an excavation, vibration, and the presence of water also increase the chance of
slope failure. When these conditions cannot be avoided, additional measures must
be taken to increase slope stability. If workers are required to enter the excavation,
no spoil or other material may be stored within the close edge of the excavation.
Ensure that workers are not allowed under loads being handled by excavators or
cranes.
Watch out for buried lines and containers when excavating. Possible hazards
include toxic and flammable gases, electricity, and collapse of side slopes due to
sudden release of liquids. If a gas line is ruptured and catches fire, get personnel
and flammable material away from the fire and have the gas turned off as quickly
as possible. Do not attempt to extinguish the fire because an accumulation of
unburned gas poses a great threat for environment.
106
Unless workers can safely step onto vessels, a ramp or safe walkway must be
provided. Access ways must be adequately illuminated, free of obstructions, and
located clear of suspended loads.
Working areas should have nonslip surfaces, be maintained clear of obstructions,
and be equipped with adequate handrails.
Workers on unguarded decks or surfaces over water must wear approved
lifejackets or buoyant vests. Life rings and a rescue boat must also be available.
Workers high above a water surface must be protected by safety belts, safety nets,
or similar protective equipment.
7.7 REFERENCES
1. AGC Guidelines for a Basic Safety Program (1989). The Associated General
Contractors of America, Inc., Washington, D.C.
2. Akal, nal (1998). Yap Yasalar ve artnameleri Dkm. Yap lerinde i
Sal ve Gvenlii Tz. 6. Bask, Ankara.
3. Feld, J. (1968). Construction Failure. New York: Wiley.
4. Manual of Accident Prevention in Construction (1992). The Associated General
Contractors of America, Inc., Washington, D.C.
5. MCAA Project Managers Manual (1984). Mechanical Contractors Association of
America, Inc. Bethesda, MD.
6. Nunnally, S.W. (1993). Construction Methods and Management. Third Edition.
Regents /Prentice Hall, Englewood Cliffs, NJ 07632.
107
CHAPTER 8
8.1 INTRODUCTION
Construction can also be defined as making a facility, on land, for the use of people using
the materials of nature, raw or processed, by the help of manpower and equipment. In the
definition, the word equipment has been used in general to mean also machines and
plants. A few examples of construction machines, equipment and plants are given below.
Machines
Equipment
Plants
Excavators
Formwork
Concrete Plant
Loaders
Scaffolding
Crushing Plant
Dozers
Surveying Instruments
Asphalt Plant
It should be noted that plant is also meant to be the collection of several machines,
equipment and plants. In this chapter, the words machines, equipment and plants will be
used to mean the same thing.
Why should machines be used? What are the points to consider to be economical when
machines are used in construction?
Should standard or special machines be used? What about maintenance of machines?
108
Economical considerations
To be economical, machines and equipment must be fully utilized and not left standing
idle since they will have to be paid for if hired or they will cost if owned even if when
they are non-productive. Full utilization of plant is usually considered to be in the region
of 85% of on-site time, thus making an allowance for routine, daily and planned
maintenance. Maintenance of machines needs to be carried out to avoid, as far as
practicable, machine breakdowns which could disrupt the construction program. Many
pieces of plant work in conjunction with other items of plant such as excavators and
haulage trucks, therefore a correct balance of such plant items must be obtained to
achieve an economical result. In Table 8.1, purchase costs (initial brand new purchase
price) of some of construction equipment are given.
Type
WA320-1
WA420-1
WA500-1
WA600-1
Type
PC200-5
PC300-5
PC400-5
PC650-3
Type
GD611A-1
GD621A-1
GD661A-1
LOADERS
HP
Bucket (m3)
150
2.5
204
3.7
291
4.0
415
5.4
EXCAVATORS
HP
Bucket (m3)
123
0.80
207
1.32
276
1.3-2.2
404
3.8-4.5
MOTOR GRADERS
HP
Blade Size
155
3710x645x19mm
155
3710x645x19mm
180
3710x645x19mm
109
A ($)
140,000
165,000
210,000
258,000
A ($)
152,000
187,000
360,000
800,000
A ($)
259,000
283,000
307,000
Maintenance considerations
On large contracts where quite a number of plant items are to be used, it may be
advantageous to employ a skilled mechanic to be on site to carry out all the necessary
daily, preventive and planned maintenance tasks together with any running repairs which
could be carried out on site. If there are many different types of machines and equipment,
it might be necessary to set up a workshop.
e.g.
110
Whether the equipment is owned or hired, the hourly cost of the equipment should be
known for the purpose of:
pricing,
cost control.
In general, the hourly cost of a machine is broken into two main components as fixed cost
and operating costs. Fixed cost consists of those costs that occur whether the machine is
used or not, on the other hand operating costs occur when the machine is used.
Breakdown of the main components may change from company to company or from
country to country. In this Chapter, the practice of Turkish Ministry of Environment and
Urban Planning will be explained. In Table 8.2, the cost components given by Peurifoy
and Schexnayder (2002) are also indicated to compare with the Ministrys cost
breakdown.
111
Table 8.2: Hourly Cost Components by Turkish Ministry of Environment and Urban
Planning and by Peurifoy
Hourly Cost Components
Turkish Ministry of Environment
and Urban Planning
Peurifoy
A. Fixed Costs
A. Ownership Costs
1. Purchase expense without tires
1. Depreciation
2. Salvage
less tiresvalue
cost)
5. Property taxes
6. Insurance
7. Storage and miscellaneous
B. Operating Costs
B. Operating Costs
- Fuel
- Fuel
- Manpower
- Repairs
- Tires
- Replacement of high-wear items
C. Manpower Costs
112
1) Depreciation Cost:
This is the cost contribution of initial price (cost) of machine due to the loss in value of
the machine due to time.
Turkish practice is to use Straight Line Depreciation with no salvage value, therefore:
Hourly Depreciation Cost = A/(Nn)
where,
A = Initial purchase price of the equipment,
N = Depreciation life of the equipment
n = Working hours per year
For some equipment, N and n values used by the Ministry given in Table 8.3.
2) Spare Parts
Spare parts cost is assumed to be 53% of depreciation cost:
Hourly Spare Parts Cost = 0.53 A/(Nn)
4) Investment Cost
Investment cost is considered because money spent to purchase the equipment could be
made use of in other ways to earn money, for example could be deposited in a bank.
113
Either capital recovery or average value per year consideration can be employed.
Ministrys practice is to use average value of equipment for interest amount calculations.
Average value per year can be calculated directly from the following expression:
Average Value per year= A (N+1) / (2N)
or can be numerically evaluated as shown in Table 8.4 for an equipment purchased for
75,000 TL with a depreciation life of 5 years and no salvage value, (Depreciation per year
=75,000/5 = 15,000 TL)
114
The average value for cost purpose is estimated to be: 0.0171 kg/HP per hour.
3) Workmanship Cost
i)
Hourly paid labor is paid for the hours they actually worked
Cost = Number of Hours Actually Worked x Hourly Rate
ii)
Monthly paid personnel (operators, foremen, etc.) are paid for 240 hours but
actual hours worked in a month is usually 167 hours (2000 hours per year/12
months), the remaining hours are weekends, holidays and paid vacations.
115
Example 8.1
In this example, rate calculation of a 1 cu.yd. excavator is given according to the
procedure of the Ministry Environment And Urban Planning. Calculations are shown in
Table 8.5 in the same way as it is shown in the Price Analysis Book of the Ministry
(Bayndrlk ve skan Bakanl, 2006). Prices are for the year 2006. For comparison, cost
rates are also given in US dollars.
116
Table 8.5: Hourly Rate Calculation of The Excavator: Pos. No. 05.501
EXAMPLE 8.1
Pos.no.03.501/1 EXCAVATOR (3/4-1&5/8) cu.yd. diesel engine 125HP
2006
year =
169,713.00
A=
0.08
i=
N=
n=
HP =
2.20
1$ =
Annual
Annual
Hourly
Depreciation
A/N
21,214.125
10.607
Spare Parts
0.53 * A/N
11,243.486
5.622
Maintenance
Investment Cost
Freight, Unloading
0.13 * A/N
2,757.836
1.380
i*(N+1)*A/2N
7,637.085
3.819
0.02 * A
3,394.26
1.697
Fixed Cost
46,246.792
(1.7+0.06N)/(Nn)
0.0855 kg / HP hrly
0.0171 kg / HP hrly
01 404
Motorin
Engine Oil, Grease,
Lub. Oil
Operator
01 408
Helper
04 109
04 109
23.125
1.3625*10-4
*A
Unit
Amt.
Unit Price
Total
Kg
10.6875
2.02
21.589
Kg
2.1375
2.02
4.318
Hour
1.4400*
4.08 hrly
5.875
Hour
0.3333**
2.64 hrly
*A
Operating Cost
03 - 005/1
Fixed Cost
23.123
0.880
32.662
1.3625*10-4 * A
23.123
TL/hr
Total Cost
55.785
13.946
Hourly Rate
69.731
TL/hr
31.696
$/hr
557.85
TL/day
13,946.25
TL/month
Note
Daily Cost = Hourly Rate* 8 hrs/day
Daily Cost
Monthly
Cost
117
Example 8.2
In this example, hourly rate calculation of a wheel loader is shown for year 2002 in Table
8.6 where the tires cost is included in the initial purchase price A.
Table 8.6: Hourly Rate Calculation of The Wheel Loader: Pos. No. 03.521
EXAMPLE 8.2
Pos.no.03.521 LOADER WITH TIRES 1.5 cu.yd. diesel engine 80HP
2002
yr=
26,190.00
A=
0.08
i=
5.00 (Table 8.3)
N=
2,000.00 (Table 8.3)
n=
80.00
HP =
2.20
1$ =
Annual
Annual
A/N
5,238.00
Depreciation
0.53 * A/N
2,776.14
Spare Parts
0.13 * A/N
680.94
Maintenance
i*(N+1)*A/2N
1,257.12
Investment Cost
0.02 * A
523.80
Freight, Unloading
10,476.00
Fixed Cost
*A
0.0002
by fixed cost factor (1.7+0.06N)/(Nn)
04 109
Motorin
04 109
01 404
01 - 408
03 - 005/1
0.0855 kg / HP
hrly
0.0171 kg / HP
hrly
*A
Hourly
2.619
1.388
0.341
0.629
0.262
5.238
5.238
Amt.
Unit Price
Total
Kg
6.8400
0.92
6.293
Kg
1.3680
0.92
1.259
Hour
Hour
1.4400*
0.3333**
1.89 hrly
1.23 hrly
Total Cost
Profit (25% of cost)
Hourly Rate
2.722
0.410
10.684
5.238
15.922
3.981
19.903
9.047
$/hr
159.224
TL/day
3,980.60
TL/month
0.0002 * A
Note
Daily Cost = Hourly Rate* 8 hrs/day
Daily Cost
Monthly
Cost
118
TL/hr
TL/hr
Example 8.3
Tires are considered separately
Same loader as in example 8.2, but tires are taken separately to see how much it effects
the hourly cost.
A = 26,190 TL
At= cost of tires = ~2,600 TL
Nt = life of tires = 2 years
nt = 2,000 hours per year
Maintenance and repair of tires = 0.15 (At / Nt),
where (At / Nt) is depreciation of tires
Transportation of tires = 0.05 (At / Nt)
0.08 TL/hr;
0.03 TL/hr
0.86 TL/hr
119
8.3.1 INTRODUCTION
Excavation is an important work item in construction works. For example, there is
excavation in road, airport, dam, building constructions, etc. Some of the excavated
material is sometimes left near-by the excavation area for back-fill such as in foundation
or trench excavation. But most of the time, all of the excavated material is to be
transported (hauled) to another place such as fill area or dump area.
Draglines
Clamshells
Scrapers (are used for large area excavations such as highways and airports)
Dozers
Graders
Hauling equipment
wheel borrows and hoist drawn carriages
trucks and other heavy hauling equipment
scrapers
conveyer belts
cabled transport
rail wagons
compressed air
Depending upon the type of excavation and other factors, one of the above machines or
combination of them can be used for excavation and hauling.
In general, following factors affect the excavation and hauling:
1. Types of machines used,
2. Skill of the operators of the machines,
120
3. Method of excavating,
4. Job conditions,
The terrain of the natural ground, uniformly leveled; the height of cut always
close to optimum,
The cut is narrow; no room for truck to come on the side of the machine,
the angle of swing is too large
5. Management conditions
Maintenance of equipment
Haul-road condition
Hydraulic excavators are classified by the digging motion of the hydraulically controlled
boom and stick to which the bucket is attached (see Figure 8.1). A downward arc unit is
classified as a hoe. It develops excavation breakout force by pulling the bucket toward
the machine and curling the bucket inward. An upward motion unit is known as a front
shovel. A shovel develops breakout force by crowding material away from the machine.
121
The downward swing of a hoe dictates usage for excavating below the running gear. The
boom of a shovel swings upward to load; therefore, the machine requires a material face
above the running gear to work against.
Obtain the heaped bucket load volume from the manufacturers data sheet.
This would be a loose volume value.
Step 2.
Apply a bucket fill factor based on the type of machine and the class of
material being excavated.
Step 3.
Step 4.
Bulk pit excavation: large area, large volume, excavating equipment stands inside the
area, excavates the faces (e.g. foundation excavation of a large building) front
shovel, loaders and hauling equipment
Limited area, vertical excavation (e.g. trench excavation, small channel) excavators
or backhoes
122
Backhoe
Selecting an Excavator
Two main factors, which should be taken into account when selecting an excavator, are
the cost per cubic meter of excavated material and the job conditions under which the
excavator will operate. The main factor, of course, is the cost but sometimes a more
powerful excavator is needed for the hard job conditions even if it becomes costly.
123
Power shovels are more specialized compared to backhoes. Shovels are mostly utilized in
large excavation.
In this lecture notes, the output of backhoes will be discussed since these equipment are
more known in Turkey.
BACKHOE PRODUCTION
The components of a hydraulic excavator are illustrated in Figure 8.2. In this machine,
the boom and dipper arms are raised and lowered by hydraulic cylinders. In addition, the
dipper is pivoted at the end of the dipper arm so that a wrist-like action is provided.
124
available to increase the cutting width of dippers. Other suitable backhoe applications
include excavating basements, cleaning roadside ditches, and grading embankments.
The size of an excavator is indicated by the size of the bucket, expressed either in cu.yd
or in m3. Depending on the manufacturer, the bucket size is either given for struck
capacity or heaped capacity or both, though usually it is the heaped capacity used in
output estimation calculations.
Standard Bucket Size: range from 3 8 cu.yd (0.285 m3) to 2
be as large as up to 5 to 6 m3.
Struck Capacity: The volume actually enclosed by the bucket with no allowance for the
bucket teeth is the struck capacity.
Heaped Capacity (qh): The maximum volume of the material which can be held in the
bucket without spillage (allowance for the bucket teeth is also considered). Depending
upon rating standard, the heaped volume is given either for a repose angle of 1:1 or 2:1.
Fill Factors (kd): Rated heaped capacities represent a net section bucket volume;
therefore they must be corrected to an average value by the characteristics of the material
being handled. These corrections suggested by the manufacturers are known as fill
factors or dipper factors which will be designated by kd as the dipper factor of the
shovel (See Table 8.7).
It should be mentioned that the material in the bucket after being excavated is in loose
form. That is to say the volume of the material before excavation is not same as the
volume after it is excavated due to swelling of the material. One must be careful in
excavation calculations with the form of the material. The volume of material before
excavation is referred as in-place or bank-measure (bm), on the other hand the volume
after excavation is referred as loose. For example, a typical clay of 100 m 3 (bm) in-place
volume will measure 135 m3 loose volume after excavation due to swelling (See Table
8.8).
125
Vloose = 135 m3
How many and what capacity trucks are needed to haul the excavated material to
dump to a distance of 7 km?
Operator skill
It should be restated that job conditions such as conditions of haul roads and loading area,
variability in depth of cut, possibility for the trucks to spot on both sides, etc. and
management conditions such as good maintenance of equipment, providing sufficient
126
3600 3600
( kd )
ct
cs
ct is obtained by correcting cS, standard cycle time, for angle of swing and maximum
depth of cut where cS is picked up from manufacturers tables or from past data where
cycle time of backhoe/shovel is observed for an optimum angle of swing and depth of
cut.
The output is corrected by a, so called, swing-depth factor which is given in Table 8.10
for depth of cut % of maximum and angle of swing.
Type of Material & Machine Size Cs & Maximum Digging Depth (Table 8.9)
Calculate Depth Ratio (%) = Actual Average Depth of Cut / Maximum Depth of Cut
* 100
Depth Ratio (%) & Angle of Swing Swing-Depth Factor (kd) (Table 8.10)
Hence, knowing angle of swing and depth ratio, from Table 8.10 correction factor kd can
be picked up.
ke = correction due to job and management conditions efficiency; it will be found from
estimated working time in an hour for the specific job and management conditions.
Ql = qh kd
3600
3600
c
kd ke = qh k d
k e where ct = s
cs
ct
kd
127
Example 8.4
A cu. yd backhoe will be used to excavate 3,980 m3 of earth (average) in bm. Average
depth of cut is about 3.5 meter and angle of swing is about 120. For job and management
conditions, 45 minutes working time is estimated per hour. Determine how many hours it
will take to finish this job if backhoe works 8 hours per day.
Solution:
Bucket capacity:
qh = * 0.76 = 0.57 m3
Dipper factor:
cu. yd
Depth ratio:
Swing-depth correction
3600
kd ke
cs
128
ke = 45/60 = 0.75
Ql 0.57 * 0.975
3600
* 0.94 * 0.75 78.4 m 3 hrloose
18
Qb = 78.4 / 1.25 where 1.25 is the swelling factor, ks, for earth (Table 8.8)
Qb = 62.72 m3/hr (bm)
Daily output = 62.72 * 8 = 501.76 m3 (bm)
Hence,
No of work-days needed to finish the job= 3,980/501.76= 7.93 work-days 8 work days
t dumping
Excavation Area
t hauling = d / vh
t return = d / vr
t loading = nct * ct
t spotting
d
,
vh
d
vr
129
60
k et (loose)
t ct
3600
k e (loose)
ct
Ql qh k d 3600 t ct k e
=
Vt k t
Qt
ct
60 k et
nct
hence, Ntr equation simplifies to N tr
Vt k t
qh k d
1 3600 t ct k e
nct
ct
60 k et
Truck Loading Time (tl) = Number of cycles needed to load the Truck * Cycle Time
of Backhoe
nct ct
(in minutes)
60
In estimating the truck loading time, it is reasonably assumed that while the shovel is
loading the truck, which is about 3 to 6 minutes, the shovel works with 100% efficiency.
In other words, it is not expected that for example, the operator will stop for a break to
have a cup of coffee or the rain will start all of a sudden in the middle of loading or the
machine will break suddenly. Therefore, only angle of swing and depth of cut are to be
considered in estimating the cycle time.
Then, nct
t l 60
ct
1
and
then Ntr is:
ct
nct t l 60
130
N tr
ct
3600 t ct k e
t l 60
ct
60 k et
N tr
t ct k e
, if truck cycle time is expressed in components then,
t l k et
N tr
tl t h t d t r t s ke
tl
k et
Ntr 1
th td tr t s
if ke = ket
tl
That is to say, if job and management efficiency of the backhoe is same as those of the
trucks which usually is.
Example 8.5
An excavation of 16,500 m3 (bm) is to be made for the foundation excavation of a
building in 3 weeks assuming 6 workdays per week and 10 hours working time per day. It
is expected that during excavation 1.5 workdays will be lost due to bad weather
conditions.
The excavation will be done in dry clay (hard) with an average depth of cut of 3 meter.
Angle of swing is about 75. Estimated working time in an hour is about 51 minutes.
a) Determine the size of the backhoe if only one backhoe will be used?
b) If distance to dump area is 7.5 km, determine the number of trucks for: Truck
capacity=12 m3 (loose), vh=30 km/hr, vr=60 km/hr, ts=2 min., td=3.5 min. Truck
efficiency and dipper factor are same as those of the shovels.
c) Calculate the equipment cost and unit cost of excavation if hourly costs are 40 TL for
the selected shovel and 15 TL for the trucks.
Solution:
a) Determine the size of the excavator:
Required Hourly Output (bm)
16,500
100 m3 hr (bm)
(3 6 1.5) 10
131
0.75 0.95
0.85
2
(Table 8.7)
3600
1.105 0.85 95 m 3 hr (loose)
23
3
cu. yd. shovel
4
qh = 1.75*0.76 = 1.33 m3
kd
0.75 0.95
0.85 (Table 8.7)
2
3600
1.17 0.85 145 m 3 hr (loose)
28
Select 1
3
cu. yd. shovel
4
N tr 1
3
cu. yd. shovel:
4
th td tr ts
can be used in this case since ke=ket.
tl
th = 7.5 / 30 * 60 = 15 minutes
td = 3.5 minutes (given)
tr = 7.5 / 60 *60 = 7.5 minutes
ts = 2 minutes (given)
tl = nct * ct (truck loading time=no. of cycles needed to load * cycle time of shovel)
nct
Vt k t
12 0.85
and
ct = cs / kd = 28 / 1.17 = 23.93 seconds
tl = (9.023 * 23.93)/60 = 3.60 minutes
N tr 1
15 3.5 7.5 2
8.78 Take 9 trucks
3.60
3600
k e (loose)
ct
Ql (1.33 0.85)
Qt = Vt k t
3600
1.17 0.85 145 m 3 hr (loose)
28
60
k et (loose)
t ct
133
Qt = 12 0.85
60
0.85 16.46 m3/hr (loose)
31.6
c) Cost calculations:
The equipment must work 16 work-days and must stay idle 1.5 work-days. Therefore, the
idle staying cost of equipment is needed. Since manpower is paid during this idle time,
fuel and oil costs should not be considered. For this kind of equipment, it can be seen
from the equipment data that fuel and oil cost is about 35% to 45% of the total cost. So
the cost of equipment when idle can be taken as about 60% of the total cost.
Hence, total cost of equipment:
When worked for 16 work-days = 16*10 (1*40 + 9*15)
When idle for 1.5 work-days
= 28,000 TL
8.4 REFERENCES
1. Bayndrlk ve skan Bakanl (2006). naat Birim Fiyat Analizleri.
2. Nunnally, S.W. (2003). Construction Methods and Management, 6th edition,
Pearson Prentice Hall, USA.
3. Peurifoy, R.L., and Schexnayder, C.J. (2002). Construction Planning, Equipment
and Method, 6th edition, McGraw-Hill, USA.
134
Name of Equipment
Excavator or Power Shovel (Ekskavatr)
Excavator or Back-hoe
Forklift (Kaldrc g sistemi) (2.0,3.5 ton)
5 Ton Crane
Tractor Scraper (Traktr + Skreyper)
Tractor Bulldozer (Traktr + Buldozer)
Tractor Ripper (Traktr + Ripper)
Motor Grader (Motor Greyder)
Wheel Tractor Scraper (Lastik tekerlekli traktr
+ Skreyper)
Vibrating Roller (Titreimli Silindir)
Smooth Wheel Roller and Pneumatic-tired
Roller (Demir ve lastik tekerlekli silindir)
Sheep's-foot Roller (Kei aya)
Wheel or Crawler Loader or Tractor-shovel
(Lastik tekerlekli ve paletli ykleyici)
Pump, Concrete Mixer, Motor Compactor
(Motopomp, betonyer, motorlu kompaktr)
Compressor, Vibrator (Kompresr, Vibratr)
Water Sprinkling Truck (Kamyon Arazz)
Truck with water tank (Su tankl kamyon)
Pneumatic Hammer (Kompresrl ahmerdan)
Steam Hammer (Buharl ahmerdan)
Crusher (konkasr)
Sieving Machines (Eleme makinalar)
Drilling Equipment for Bored Piles (Fore kazk
iin delgi makinas)
Generator (Jeneratr)
Barger (Duba)
Tug-boat (Rmorkr)
Dockyard Crane (Maula)
Darbeli tip su sondaj makinesi
Rotari tip su sondaj makinesi
Agricultural Tractor (Ziraat Traktr)
Lawnmover (im bime makinesi)
Briquette Production Machine (biriket imal
makinas)
Aluminum Production Plant (alminyum
imalat atlyesi)
PVC door and window systems Production
Plant (Plastik dorama imalat atlyesi)
Mechanical Concrete Plant (otomatik beton
santrali)
135
Hours
(N1)
2,000
2,000
2,000
2,000
2,000
2,000
2,000
2,000
8
8
8
6
6
6
6
6
16,000
16,000
16,000
12,000
12,000
12,000
12,000
12,000
2,000
12,000
2,000
12,000
2,000
12,000
2,000
12,000
2,000
10,000
1,000
6,000
1,250
250
2,000
2,000
2,000
2,000
2,000
6
6
6
6
9
6
6
7,500
1,500
12,000
12,000
18,000
12,000
12,000
2,000
18,000
2,000
2,000
2,000
2,000
4,000
5,000
8
9
9
9
6
6
16,000
18,000
18,000
18,000
24,000
30,000
1,000
4,500
1,000
6,000
1,000
7,500
1,000
7,500
2,000
12,000
Loose
weight
Swelling
factor
Clay, dry
kg/m3
1,600
kg/m3
1,185
(ks)
1.35
Clay, wet
1,780
1,305
1.35
Earth, dry
1,660
1,325
1.25
Earth, wet
1,895
1,528
1.25
1,895
1,575
1.20
Gravel, dry
1,660
1,475
1.12
Gravel, wet
2,020
1,765
1.14
Limestone
2,610
1,630
1.60
2,490
1,565
1.60
Sand, dry
1,542
1,340
1.15
Sand, wet
1,600
1,400
1.15
Shale
2,075
1,470
1.40
Material
136
Soft
15
18
24
Average
18
23
30
Hard
23
28
36
Maximum Digging
Depth (In Meter)
4-6
5.5-7.5
7.5-9
Soft
: Sand, gravel, loam
Average: Common earth, soft clay
Hard : Tough clay, rock
Note: Cycle time picked up from Table 8.9 is modified by dividing it with the swingdepth factor obtained in Table 8.10
60
75
90
120
180
30
1.33
1.26
1.21
1.15
1.08
0.95
50
1.28
1.21
1.16
1.10
1.03
0.91
70
1.16
1.10
1.05
1.00
0.94
0.83
90
1.04
1.00
0.95
0.90
0.85
0.75
137