Manual Gencon
Manual Gencon
IOB1 This is an auxiliary 16 input and 8 output relay board that is mounted on a DIN rail
inside the control cubicle. It takes care of engine management (eg fuel-solenoid), handles
external alarms (eg low oil pressure), etc. Standard models nominal battery Vdc: 12 and
24.
IOB2 The IOB2 has all the facilities of the IOB1 but also has 4 multi-range programmable
analogue inputs for reading such things as oil pressure, water temperature, charger rate
etc. All readings can be displayed on the LCD display of the Gencon and also read remotely
via the communicator.
AVRx This is a small interface circuit between the main unit and the generator's
(alternator) automatic voltage regulator (AVR). It is required for voltage matching during
synchronization and for reactive power (kVAr) control when in parallel.
Outlook
There are many situations that can be handled best by operating two or more generator
sets in parallel on a common bus. Typical reasons are -Reliability: In a standby system, when there is a mains failure, all generators in the
system are started. The probability of having a generator start and achieve nominal voltage
and frequency is increased according to the number of sets available.
Flexibility: Maintenance operations can be performed without having to shut down the
whole system.
Economy:
When the loads are expected to expand substantially, the initial investment is
minimized by installing one smaller generator set, and then adding more sets in parallel as
the loads increase. The number of generator sets running can change according to the
load. In contrast, having one large genset run under light load conditions accelerates
engine wear.
There are reasons to let a single generator set also have switch gear for paralleling with
the mains -Reliability: A standby generator set with a paralleling switch gear, when the mains supply
is restored, can transfer the load back to the mains smoothly without the consumers having
to undergo a (second) power cut.
Flexibility: Exercising standby generator sets under load does not interrupt the
consumers supply.
Economy:
Exporting to the mains lines can reduce the peak kilowatt demand of a
facility at high tariff hours. Also, when an engine heat recovery system is installed
(Combined Heat & Power), the generator set can export power through the mains lines to a
local community and reach high overall efficiency.
With all these good reasons to use paralleling, for a given project kW requirements, the
decision whether to opt for paralleling depends to a large extent on the following costs'
ratio:
Control Equipment + Design/Installation/Commissioning Man-Hours
kW Generating Set
The GENCON II is designed to bring this ratio as low as possible with present day
electronics.
Each numerator factor is carefully optimised:
Equipment: The generator set controller takes complete care of measurement, engine
management, protection and paralleling. Virtually nothing but an electric governor and an
AVR is additionally required.
Design: Numerous delays, set points and options (parameters) adapt the controller's
software to suit any application. Software programming skills are not necessary.
Installation: Compact design and unprecedented integration of functions, which are
"interconnected" by software, makes wiring extremely simple (see the installation
diagram).
Commissioning: With a built in measurement system, one can find wiring mistakes easily,
eg incorrect phasing of a CT. As fault messages are logged in memory in plain language,
marked with the time of their arrival, one does not confuse a "cause" with a "result". The
large stock of parameters is edited using the controller's own LCD and keypad. Each
parameter value is displayed with a short explanation -- no need to consult the manual
each step.
The result: Paralleling is no longer the realm of heavy kW genset
projects.
Frostechnic Rev 9.00 June 2004
Front panel
LED's
The green LED should always blink. Fast blinking rate indicates existence of one or more of
the following conditions:
1.
Normal engine oil pressure (ie In#5 OIL PRESS SHUT = OFF),
2.
Engine speed greater than 60 RPM,
3.
Gen frequency greater than 15 Hz.
Blinking red LED indicates detection of a shutdown fault.
Blinking yellow LED indicates detection of a warning fault.
Press RESET to clear fleeting faults.
To stop the genset press the red STOP push-button. Shutdown fault is declared.
To silence the audible alarm press the yellow RESET push-button once.
To clear fleeting faults, if the audible alarm was silenced, press the RESET pushbutton again.
Pending faults cannot be cleared. If you press RESET, the faults will be re declared.
Press any push-button to return from a measurement display function back to the
menu mode.
#1
Model variations affect one low cost PCB (A50-3). Re-calibration must follow its
replacement.
#2 Contact factory for special requirements.
Short-cuts:
1.
Enter any menu. The option that is selected by default is the one that was selected
before leaving the menu by Esc . Example: You are using a function from the MEASURE
menu and need to call a function from COMMAND. Go up to the root (by Esc s) and down
to COMMAND... To return to the MEASURE function, go up to the root, select MEASURE and
make a series of blind ENTER s.
2.
When a fault is detected, if no push-button is pressed for 20 seconds or if ESC is
pressed, REPORT is automatically called. Quit REPORT and you are back at the previous
location.
Key
Description
Messages log
Synchroscope
The numeric keypad also acts as a fast navigator of the Most popular menus (see table)
The normal screen to leave the Gencon showing is Overview as this informs the user of the
gencons actions as they happen.
In this manual, references to functions are preceded with the path leading to them,
beginning from the top most menu level, the root. For example,
MEASURE\GENERATOR\POWER+PF shows how to call the function that displays the genset
power output and the power factors (cos). Ie starting from the root call MEASURE, call
GENERATOR and finally call POWER+PF.
OVERVIEW
OVERVIEW is a useful display function. It explains what the controller is doing at any
moment. Hence, in addition to reaching OVERVIEW through the menu, you can call
OVERVIEW by:
1.
Pressing the 0 push-button at any menu level,
2.
Pressing the ESC push-button at the highest (root) menu level. The following are a
few OVERVIEW "snapshots" taken during the operation of a Euro standby generator-set
installation with soft load transfer. See configuration #5 in applications.
Snapshot 1
Snapshot 2
Snapshot 3
Snapshot 4
Snapshot 5
Snapshot 6
Line 1 shows the controller operating mode and the clock. The clock appears only if
the operator initialised the clock by the COMMAND\SET-CLOCK.
Line 2 shows the genset current activity and the remaining time to its end. Asterisk
(*) indicates that the genset is running in sync with the auxiliary phase V4, ie the mains
phase A.
REPORT
REPORT examines the log of messages. Each message includes the time it entered the log.
If the clock was not running, "time ???" will appear.
Most messages report some fault such as the
HIGH WATER TEMP SHUT
Logged -- Sat 17:06
example on the left.
Clear message by
Earlier Later Esc
COMMAND
OFF mode
When in OFF mode, the monitoring system is active except for the relays R#3
AUDIBLE ALARM and K#4 AIR DAMPER. If Mains Standby ATS = 1, the mains contactor,
irrespective of the mains (V4) status is closed (ie K#8 MAINS CONTACTOR relay is
off). It is possible to define the OFF mode as a warning fault.
OFFAUTO
This function changes the operating mode to AUTO. User password may be required.
OFFMAN
This function changes the operating mode to MAN. The genset immediately starts
unless a shutdown fault exists.
Manual mode
When in MAN mode, the genset runs unless a shutdown fault exists. It is possible to
define the MAN mode as a warning fault.
MANOFF
This function changes the operating mode to OFF. The genset stops after cooling
down if necessary.
LOAD-GEN
This function instructs the genset to take the load. User password may be required.
OFF-LOAD
This function instructs the genset running in MAN mode to remove the load.
Automatic mode
When in AUTO mode, unless a shutdown fault exists, the genset
Starts immediately on active In#1 RUN WITH LOAD signal.
Starts immediately on active In#2 TEST W/O LOAD signal. Stops after a time delay
following In#2 deactivation.
3.
Starts after delay following a mains failure (ie abnormal V4 voltage). Stops after
delay following the mains return. All this is provided that SET-UP\OPTIONS Mains
Standby ATS = 1.
4.
SLEEP is a special AUTO mode where genset start is disabled. It is selected by
active In#3 SLEEP signal.
AUTOOFF
This function changes the operating mode to OFF. User password may be required.
1.
2.
EXPORT
This function examines and changes the amount of active (kW) and reactive (kVAr) power
that is exported to the mains in configurations #4, #5 and #6.
The user may be required to enter a password to change the
/ kVA
genset p.f. = cos = kW
export quotas. In configurations #4 and #6, export to the mains
is continuous. In configuration #5, export to the mains is
kVA
kVAr
maintained until ramp up brings the genset power output to
the defined export quotas, the mains contactor opens, and the
load is completely transferred to the genset. See Applications
kW
for further details. The export quotas must be within the
genset kW and kVA ratings, which are defined in SET-UP\BASICS. The user should be
familiar with the power right triangle relationship and with the generator derating
characteristics at low power factors (below 0.8 p.f.).
In configuration #4 it is possible to control dynamically the kW export quota through In#16.
See Applications for further details.
SEQUENCE
IDs 2 1 3
This function examines and changes the order in which
This Gen-Set ID No=1
controllers start and stop their gensets in response to an
Exchange Command 2,3
increase or decrease in their common load. If any genset
Initial Sequence 0,0
in the sequence cannot run, the next one is called. This
function is applicable to controllers in configuration #3 (random access paralleling) that
have the option Parall Auto Start set. In this example three controllers are connected to
the RS-485 network. The genset whose Controller ID No is 2 runs all the time. As the load
increases genset 1 and later genset 3 join the bus. When the load decreases genset 3 is
disconnected from the bus first.
The exchange command propagates to all the network controllers. It is called up by the
ENTER key (cancelled by ESC ) followed by pressing 0. Entering the 2,3 exchange
example results in the 3 1 2 sequence.
MEASURE
ENGINE
Battery Volts: 13.8
MPU: 1513rpm 50.39Hz
kW Hours: 00,001,234
HoursRun: 000,150:10
GENERATOR
OVERVIEW
Gen Volts Amps
Hz
A
221 115 50.07
B
222 117
kW
C
220 125 69.9
POWER+PF
Total-Power
kVA: 78.9
kW:
69.9
kVAr: 36.4
COS(PF)
A: 0.91
B: 0.88
C: 0.87
Generator
Total apparent power, Phase-A power factor
Total true power, Phase-B power factor
Total reactive power, Phase-C power factor
MAINS or BUS
This function displays V4 phase measurements.
The caption is MAINS or BUS according to SETMains A
UP\OPTIONS Mains Standby ATS
Frequency Hz: 50.14
Voltage Vrms:
223
Distortion %THD: 0.1
SYNCscope
Synchroscope display example:
Gen A v Mains A
Freq Slip Hz: -0.07
Phase Shift :
11
Voltage Match:
-2
IN 1..16
This function shows which IOB1 input channels are active. Use the left and right push
buttons to move the LCD cursor to any input channel column to find its name. The input
channel type, "normally open" or "normally closed", is defined by SET-UP\IN 1..16.
SYSTEM
This display function provides general system
information.
Function:
Master
Network IDs 12-----ANALOG OUT (V): 1.50
PWM OUT (%):
50.0
SET-UP
This menu defines the systems parameters: set points, delays, etc. The parameters are
non-volatile (unaffected by battery disconnection). You need to know the installation
engineer password to enter the menu. See Set-up menu options for further details.
HELP
SET-UP MENU
You can set-up the system parameters from the front panel keypad or from the remote PC
console (running the program REMOTE.EXE). The parameters are organized in several lists
according to their type: Time-delays, set-points, yes/no options, N/O or N/C definitions of
the IOB1 inputs, basic definitions and factory calibration data. Each parameter is
presented with a brief text prompt. The parameters are stored on a non-volatile memory.
They are not affected by battery voltage disconnection.
Select a list and enter :
Use the left and the right arrow push buttons to get to the parameter that you
want to edit.
Press ENTER to begin the parameter value editing. A cursor starts blinking at the
value field. If you come across the "Remove Write Protect" response, refer to the next
paragraph ("Attention!").
Press the left and the right arrow push buttons to move the LCD cursor across
the value digits.
Press ESC to quit parameter editing (this leaves the parameter value unchanged).
Press ENTER to replace the parameter value with a new one. Choose different
parameter value if you come across the Value Outside Range! message.
Important! Begin the first SET-UP session with a careful review of the SET-UP\ BASICS
parameters.
Attention!
There are two methods the installation engineer can protect the system parameters:
LEVEL 1:
SET-UP entry password is 1993. After typing the password you can leave and
enter the SET-UP menu for 15 minutes without being asked for the password again.
LEVEL 2:
Parameters can be made "read-only" by SET-UP\OPTIONS Write Protect. This
protection is implemented in hardware -- IT IS RECOMMENDED TO USE THIS OPTION! To
inhibit write protect temporarily (ie effective until the battery voltage is removed) press
the push-button 0 while switching on GENCON II battery volts.
Parameters
Basics:
Adjust the following parameters first as the set-points depend on them!
Controller ID No
Each controller that is connected to the RS485 network should have a unique ID
number, a number between 1 to 8 (use smaller ID numbers first). The ID numbers of
all the controllers that are connected to the network can be examined by the
MEASURE > SYSTEM menu function (note though that "exclude rules" can hide other
controllers from view).
Number of Poles
The number of rotor poles, a value between 2 to 20 is expected. 4 is the common
number of poles where then RPM = 30 * Hz. See the magnetic pick-up formulas page
64. The {Number of Poles } can be an odd number for cases where the engine drives
the generator through a frequency converter.
Pick-up Teeth
The number of pulses generated by the magnetic pick-up per one revolution of the
engine. See the magnetic pick-up formulas page 64. Enter 0 if the engine has no
magnetic pick-up.
CT Ratio
The current transformers ratio. The standard GENCON model is suitable for CTs with
5A secondary current, a current level that typically corresponds to 100% gen-set
load. GENCON's maximal reading is 5.9A for overcurrent implementation. The largest
{CT Ratio} value is 1023, admitting 5000/5A current transformers.
PT Ratio
Potential transformers ratio. Enter 0 or 1 if the voltage channels, V1 to V4, are
directly connected. 127 is the highest acceptable ratio but since the displayed
voltage cannot exceed 16383 a lower limit may exist. For example, a 120V model
whose full-scale {Vx Volt Max} value is 143.5V imposes a limit of 114 on the {PT
Ratio}.
Xap: Rated kVA
The generator-set maximal continuous kVA (apparent) load.
Xre: Rated kW
The generator-set maximal continuous kW (real) load. Usually Xre=0.8*Xap.
Double-up WYE Gen
This option makes it easier to reconnect a rental generator-set for low and for high
WYE (star) operation. In both cases the V1/V2/V3 channels measure the voltage of a
single (internal) alternator coil. This coil has another one in parallel when operating
in low WYE or another one in series when operating in high WYE. The generator
current is externally measured, just as usual. The use of this option is preferred to
assigning a {PT Ratio} of 2 for the high WYE case as here all the other parameters
are automatically adjusted -- the {Gen OvCurrent} is halved and all the kW/kVAr
related parameters keep their value, e.g., the {Gen Revrse kW} set-point, etc.
Ideal Voltage
The desired bus voltage. Changes to this set-point automatically pass to the
overvoltage and undervoltage set-points.
Frostechnic Rev 9.00 June 2004 12
Ideal Freq Hz
The desired bus frequency, usually 50 or 60 Hz. It is the nominal frequency that the
software for hydraulic/mechanical govnernors establishes. Changes to this set-point
automatically pass to the overfrequency and underfrequency set-points.
Options:
WRITE PROTECT...!
1 locks the parameters to prevent change of values by end users. To unlock the
parameters switch on the DC supply of the controller while pressing and holding the
0 key.
The following 4 options -- Generic, Parallel, ATS and Cogen -- select the fundamental
operating mode of GENCON software, the configurations:
Config
Application
#0
#1
#2
#3
#4
#5
#6
Generic Configure
In configuration #0 GENCON cooperates with an external PLC: Through In#15 and
In#16 the PLC tells GENCON what parallelling function to activate: sync, load-sharing
or export... Through K#7 and K#8 GENCON reports back to the PLC its status: ready
for load, in-sync,... Detailed documentation is available in another section.
The following three options select software configurations #1 to #6 as shown above.
In these configurations GENCON controls the generator contactor/breaker via the
normally open contact of relay K#7 and, if applicable, it controls the mains
contactor/breaker via the normally closed contact of relay K#8:
Frostechnic Rev 9.00 June 2004 13
Parallelin System
Is the parallelling system active or not. This option is ignored when selecting the
generic configuration.
Mains Standby ATS
Does relay K#8 control the mains contactor/breaker or not. This option introduces a
European style AMF (automatic mains failure) standby logic: channel V4 serves as a
single phase mains failure detector, etc.
Cogeneration Mode
This parameter tells GENCON if it used for continuous parallelling with the mains or
not.
Generator Syn|Asy
Enter 1 for induction generators. This option is mainly used with config#4. Note:
1. V1, V2 and V3 connect to the mains, i.e., before the generator breaker. V4 is
not used.
2. The synchronizer matches the engine speed as read by the magnetic pick-up
with the frequency of the mains as read by V1. Only the {SY stability V/Hz}
setpoint is effective. The synchronizer does not work in test run (active In#2)
and its ANALOG-OUT is then fixed at {Gov Volt Bias}. When running the set by
In#1 and the engine speed stays within 0.4Hz from the mains frequency for
{Sync Dwell Time} the generator breaker (K#7) energises, the synchronizer
loop then stops and the load-sharing closed-loop control takes over.
3. Since in induction generators there is no control over the reactive power
(kVAr), disable the GEN EXCITATION LOSS shutdown by selecting a high {Gen
Rvrs kVAr} value and disable the AVR CONTROL FAILURE warning by selecting
zero {LSgain%P/Xap} and {LSstbl%P/Xap} values.
Disable AUTOOFF
1 tells to controller to lock the software operating mode in "auto" mode.
NOT IN AUTO Warn
1 tells the controller to declare a warning fault when the operating mode is taken
out of "Auto" by an AUTOOFF command or an active In#3 SLEEP line.
Energize Run|Stop
This option defines the fuel solenoid type as either (0) energize to run or (1)
energize to stop.
Cool After NoLoad
1 tells the controller to enter the {Coolin Down} delay before stopping the engine
even if the genset ran without load earlier, i.e., with the relay K#7 de-energized.
Bat OverVolts S|W:
HIGH BATTERY VOLTAGE alarm is declared when the DC voltage at terminal C11 is
{Bat OvVoltage} or higher for 1 second. This typically happens when the battery is
disconnected while the engine is running. The DC voltage rises due to the engine
charging alternator. It is recommended to shut down the genset immediately, i.e.
choose option 0, as this high DC voltage can damage the electric governor, etc.
Gen UnderVolt S|W :
0 = gen undervoltage fault is shutdown.
1 = gen undervoltage fault is warning.
Gen UnderFreq S|W :
0 = gen phase A under frequency fault is shutdown.
1 = gen phase A under frequency fault is warning.
LowWaterLevel S|W
In#10 LOW WATER LEVEL fault is: 0 = shutdown, 1 = warning
Ext. Overload S|W
0 would cause the generator breaker to open (by de-energizing K#7) immediately
when In#14 becomes active. A shutdown fault is then declared and the engine stops
after a cooling off period. If the option is 1 active In#14 would just cause a fault
message to be logged.
R#2 Alarm|Usable
With the "0" option relay #2 serves as a visual alarm relay, energized when the
genset has a shutdown or a warning fault.
When this option is "1", an energized relay #2 state indicates that the genset can be
used. I.e., if the genset has a shutdown fault, if the operating mode of GENCON is
Off or Sleep (see In#3) and, of-course, if GENCON has no DC supply, relay #2 will
NOT be energized. This status is important for supervisory systems (PLCs) having to
know if a certain genset is available for work or if another one has to be chosen.
K#6 Engine|Gen On
With the 0 (default) option, K#6 energises when the engine speed is higher than 60
RPM. With 1, K#6 energises only when the generator voltage is normal.
K#8 Delay|Neutral
This option concerns the load-sharing config#3:
"0" tells GENCON to use the relay K#8 as a delayed K#7 follower, with a {K#7
On K#8 On} time delay. I.e., K#8 energizes a programmable number of seconds
after the generator breaker closes. However, K#8 de-energizes immediately when
K#7, the generator breaker, de-energizes. Typically all the K#8 N/O contacts of the
load-sharing gensets are strung together in series to create a common bus breaker
command.
"1" tells GENCON to use the relay K#8 for neutral breaker switching when paralleling
generators with star windings. Only one generator, whose GENCON is the bus
master, will have its neutral connected to the bus to prevent circulating harmonic
currents through the neurtals.
The neutrals of generators of dissimilar construction and differing output and
power factor ratings should ... never be interconnected (LLJ MAHON, DIESEL
GENERATOR HANDBOOK, page 227)
kW Drop=LoadSurge
This option tells GENCON when paralleling with the mains to consider a sudden load
decrease, where the measured load falls by {Mains kW Surge} or more, also as a
PARALLEL LOAD SURGE, i.e., loss of mains during paralleling. We recommend to set
this option.
Smooth MainsGen
This option concerns config#5, i.e., standby with soft transfer. It tells GENCON not
to log PARALLEL MAINS FAIL messages.
When one activates In#1 for testing the genset, the mains breaker opens when the
genset power reaches the EXPORT QUOTA level. In some cases it is desired to open
the mains breaker exactly when the genset power reaches the plant demand. This is
done by installing a reverse power relay on the plant mains input and the EXPORT
QUOTA is set at its highest. The reverse power relay then disconnects AC from V4
exactly when the genset power reaches the plant demand. GENCON's immediate
response in config#5 is to log a PARALLEL MAINS FAIL message and open the mains
breaker. Since in our case (*) disconnection of the V4 is normal, it is desired to
suppress the PARALLEL MAINS FAIL message.
(*) Loss of mains during paralleling is detected by the built-in PARALLEL LOAD SURGE
mechanism. If a secondary (external) means for loss of mains detection is required it
should, when it activates, disconnect the AC input from channel V4. GENCON then
immediately isolates the plant from the mains through the appropriate breaker and
it logs a PARALLEL MAINS FAIL message.
Frostechnic Rev 9.00 June 2004 17
Setpoints:
User Password
This is a four digit password that is needed for changing the operating mode
(AUTO/OFF), the export quota levels and for erasing alarms from the report log (*).
If you don't require this password mechanism enter a 0000 value.
(*) To protect erasure of alarms from the report log you also have to enable the
{WRITE PROTECT...!} option.
Cranking Attempts
The number of starter motor cranking attempts (through the relay K#3) before
ENGINE OVERCRANK or ENGINE SLOW CRANK shutdown is declared. This limit does
not apply if the {In#3 Sleep|Bypass} option is 1 and In#3 is active (when powering
fire pumps).
Overspeed RPM
This threshold applies to the speed read from the magnetic pickup. Make sure that
a correct number of teeth is defined in SET-UP\BASICS.
CrankStop RPM
Engine "firing" speed. This threshold applies to the speed read from the magnetic
pickup. Make sure that a correct number of teeth is defined in SET-UP\BASICS.
Bat OvVoltage
Battery over voltage threshold. Note, the battery equalize/recharge voltage, per
cell is for lead-antimony 2.35, for lead-calcium 2.40 and for nickel-cadmium=1.65.
Fault is declared after a 1 sec delay.
Bat UnVoltage
Battery under voltage threshold. The battery cell final voltage is dependent on the
discharge rate. For a lead-acid type at high discharge rate it may even be 1.0V.
Typical value is 1.75V. Battery undervoltage is ignored during engine cranking. Fault
is declared after a 1 sec delay.
Gen OvVoltage
Over voltage threshold. Applies to each gen phase to neutral voltage
Gen UnVoltage
Under voltage threshold. Applies to each gen phase to neutral voltage.
Gen OvFrequen
Generator phase A (V1) over frequency threshold.
Gen UnFrequen
Generator phase A (V1) under frequency threshold.
Gen OvCurrent
The overcurrent protection applies to each phase. This value (denoted Is) should be
the maximal allowable current. The time delay (denoted t) before shutdown follows
the "very inverse" curve, t = T*Is/(I-Is), where T denotes the {G 2x OvCurr} timedelay value and I denotes the measured phase current.
Gen Revrse kW
The smallest total negative kW load that would cause, if it exists for {G Revrse kW}
time, a GEN REVERSE POWER shutdown.
Gen Rvrs kVAr
The smallest total negative kVAr load that would cause, if it exists for {G Rvrs kVAr}
time, a GEN EXCITATION LOSS shutdown.
Mains Offset
This set-point is subtracted from the Phase Shift that is measured by the
Gen A v Mains A Synchroscope. It is useful for LV generators that need to
synchronize across a breaker on the HV side of a step-up power transformer (power
transformers typically introduce a 30 phase shift due to their delta to star wiring).
The set-point is not applied in the generic and in the load-sharing AMF
configurations when the generator is synchronizing as a slave without load
assunming that it is then synchronizing to the LV generator bus. Here is a typical 1line diagram of such installation:
LSgain V/Xre
This is the active (kW) load-sharing loop gain "trimmer".
LSstbl V/Xre
This is the active (kW) load-sharing stability "trimmer".
LSgain%P/Xap
This is the reactive (kVAr) load-sharing gain "trimmer".
LSstbl%P/Xap
This is the reactive (kVAr) load-sharing stability "trimmer".
Ramp +kW/Sec
This is the kW loading rate of a paralleling generator-set.
Ramp -kW/Sec
This is the kW unloading rate of a paralleling generator-set.
Ramp+kVAr/Sec
This is the kVAr loading rate of a paralleling generator-set.
Ramp-kVAr/Sec
This is the kVAr unloading rate of a paralleling generator-set.
kW Quota++
When paralleling with the mains this is the individual active (kW) increment that the
dynamic export quota controls can introduce. Note that the actual generator-set
output power only gradually changes at the {Ramp +kW/Sec} rate and the effective
(cumulative) quota level is its target. Also note that after parallel connection the
effective quota levels always start from zero. The effective quotas can be displayed,
for debugging purposes, through the COMMAND / EXPORT menu function. The
EXPORT command itself sets a limit on the quota level.
kW Quota-When paralleling with the mains this is the individual active (kW) decrement that
the dynamic export quota controls can introduce...
In#00 kW Quota++
Determines which free input channel from the available 06, 08, 09, 12, 15 and 16
increases the kW export quota level in configurations #0, #4 and #6. To increase the
kVA exoprt level select the same channel in {In#00 kVAr Quota++}.
In#00 kW Quota-Determines which free input channel from the available 06, 08, 09, 12, 15 and 16
decreases the kW export quota level in configurations #0, #4 and #6. To decrease
the kVA exoprt level select the same channel in {In#00 kVAr Quota--}.
kVAr Quota++
kVAr Quota-In#00 kVAr Quota++
In#00 kVAr Quota-%kW/XreR#1 On
%kW/XreR#1 Off
+%kW/Xre Start
This set-point applies to the {System Auto Start} option of configuration #3 which
applies to equal-size generator-sets. It is the percentage of spare capacity under
which the next generator-set on the priority list is started.
+%kW/Xre Stop
Likewise... this set-point determines when one generator-set with the least priority
can be stopped.
Delays:
Set Overspeed
The time delay from detecting engine overspeed to the declaration of fault.
Gen OverVolts
The time delay from detecting over-voltage in any gen phase (V1,V2,V3) to the
declaration of fault.
Gen UnderVolts
The time delay from detecting under-voltage in any gen phase (V1,V2,V3) to the
declaration of fault.
Gen OverFreq
The time delay from detecting over-frequency in gen phase A (V1) to the declaration
of fault
Gen UnderFreq
The time delay from detecting under-frequency in gen phase A (V1) to the
declaration of fault
G 2x OvCurr
The time delay before declaring an over-current fault in each channel I1, I2 or I3 is inversely
proportional to the phase current I:
Time-Delay =
Is is the current level that is defined in SET-UP\SET-POINTS.
Is
I Is
Coolin Down
The genset run on time, without load, to cool off the engine
Stoppin Max
The limit on the time from blocking fuel supply (through IOB1 K#2 FUEL SOLENOID
relay) to reaching genset standstill conditions The genset run time, without load, to
cool off the engine.
AlarmOn Max
This parameter sets a time limit on the audible alarm (Relay#3) activity. There is no
time limit if the value zero.
LubPump On
K#5 lubrication Pump cycle: on time
LubPump Off
K#5 lubrication Pump cycle: off time
LoadBreakMake
This delay applies to the closed configurations, #1-#6, where GENCON controls the
breakers. It forces the load to stay cut off this minimal length of time from any
power source (mains or generator) once disconnected. By delaying the reconnection
of motor loads overloading of the power source to which the load is transferred or
reconnected is prevented. When using an air breaker with a motor charged spring
enter a long enough time delay to make sure that the spring gets fully charged
before the breaker close command is allowed to go through.
Contactor Delay
In the closed configurations, #1-#6, when the option {Check Contactors} is 1,
GENCON compares the open/closed status of the generator breaker, as it reads
through In#15, with the state of its command relay, K#7 N/O. The breaker status
must follow the state of the command relay within this time delay or the
CONTACTOR(s) FAILURE shutdown is declared. Similarly, if the software
configuration also includes control over the the mains breaker, the state of the N/C
contact of relay K#8 is compared with the mains breaker status as read through
in#16. It should be noted that when the option {Motor Contactors} is 1, conflicts
between K#7/K#8 state and In#15/In#16 status are tolerated in the absence of a
power source.
In the generic configuration #0, where the breakers are controlled by an external
PLC, this delay sets the maximal time that is allowed for GENCON to be in modes 2-4
though its K#7 is de-energized, indicating that it cannot take load. A GENERIC
CONFIG ERROR shutdown is otherwise declared. In most cases this indicates having a
bug in the controlling PLC program.
K#7 On K#8 On
This time delay is associated with the {K#8 Delay|Neutral} = 0 option and applies to
configurations #1 and #3. It marks the time delay between closure of the generator
breaker through relay K#7 to the moment when relay K#8 energizes too. K#8 deenergizes immediately when the relay K#7 de-energizes, i.e., when the generator
breaker opens. Thus, K#8 can be used in logic circuits which ensure that the loadsharing gen-sets run without load a few seconds before closing their common bus
breaker.
kW Quota++
kW Quota-kVArQuota++
kVArQuota
R#1 OffOn
When R#1: Trip|kW Load option is 1, this is the time delay before RELAY#1 is
energized.
See Basic load control in Applications.
R#1 On->Off
When R#1: Trip|kW Load option is 1, this is the time delay before RELAY#1 is deenergized.
See Basic load control in Applications.
Parll Start
When the Parall Auto Start option is active, in parallel genset systems, as the
system load increases this is the time delay before starting the next genset in the
COMMAND\SEQUENCE. See Applications.
Parll Stop
When the Parall Auto Start option is active, in parallel genset systems, as the
system load decreases this is the time delay before removing and stopping one
genset. See Applications.
LS Settling
When the Parall Auto Start option is active, in parallel genset systems, this is the
minimal time between consecutive gensets start/stop in response to load changes.
The load-sharing feedback loops should re-distribute the load evenly within this
time. See Applications.
Sndr1 loOHM
Sndr2 loOHM
Sndr3 loOHM
Sndr4 loOHM
Sndr1 hiOHM
Sndr2 hiOHM
Sndr3 hiOHM
Sndr4 hiOHM
FACTORY
Access to this menu is protected by the password 311794. It is possible to change this
password through the program NED. This menu allows access to two sensitive lists:
1. SET-COUNT
Adjusts the following activity counters: kW Hours, HoursRun, Engine Cranks and
GenSet Runs.
2. CALIBRATE
Vx Volt Max
This is the full scale AC volts reading of channels V1 to V4. This value is selected
according to GENCON model. To calibrate the voltage channels (if this is really
required!) adjust the first four trimmers on GENCON side (V1 trimmer is topmost). It
is recommended to restore the weak glue (or use a common nail polish) that
prevents trimmers position changes due to vibrations.
Ix Amps Max
This is the full scale AC amps reading of channels I1 to I3. It is 5.9 Amps for the
standard models. To calibrate the current channels adjust the lower three trimmers
on GENCON side. Restore the weak trimmers glue...
B+ Volt Max
Full scale reading of the battery DC volts. This value is used for calibration. Its
nominal value is 40V.
D/A VoltMax
Full scale DC volts of ANALOG OUT. This value is used for calibration. Its nominal
value is 7.5V.
Adj Sec/Week
This parameter calibrates the clock and the frequency metres. A positive value
accelerates the clock, a negative value slows it down. The required value is 0 for all
the new controllers as marked on their rear panel. Unmarked old controllers require
slowing down of their clocks by 399 seconds per week, i.e. -399 (which is the default
value). As computer clocks slightly "drift" due to "aging" and different operating
temperatures you may wish to adjust the clock in the future.
Ignore PhaseOrder
Phase input V2 is expected to lag after V1. Otherwise an ILL GEN PHASE ORDER
warning is issued. When GENCON is used for single phase applications this warning
has to be disabled. We hide this option in the FACTORY list to discourage its use in
normal 3-phase projects...
RMS use Harmonics
This option tells the controller how to compute the electrical parameters, VAC's,
etc. With the 0 option the computed values are based on the fundamental frequency
only, with 1 the 3rd, 5th and 7th harmonics are included too.
Software Code
If the displayed number is not 0, the installed software has some non standard
operating rules in effect. Also in this case the HELP screen shows the software
version with a capital letter, for example, 2.8M rather than 2.8m. The software
code is a hexadecimal number. For example, when the special options 10 and 11 are
effective the software code is 0600 ( = 29 + 210). Contact Wexler if you need any one
from the following special options:
1. Don't cool off the engine when stopping it by In#3.
2. Don't add up the measured V3xI3 power components to the total kW and kVAR
values which the closed-loop load-sharing and export controls use. See the
page on measuring 3 wire systems.
3. Skip the test for 20 RPM after 2 seconds of cranking. This may be required
when using compressed air starters.
4. Work in 1 phase 3-wire applications (where there is 180 degrees phase shift).
5. Apply 10 seconds to the GOV CONTROL FAILURE alarm. In the standard
software the delay is 0.5 sec.
6. Apply the generator over/under voltage/frequency alarms to the induction
(asynchronous) generator case too. In the standard software abnormal voltage
and frequency condition just stops the induction generator.
7. 10 second AVR CONTROL FAILURE delay. In the standard software the delay is
0.5 sec.
8. De-energize the fuel solenoid K#2 during the {CrankFail Rest} time delay. This
is required for MTU's MDEC engine controller.
9. In non-paralleling applications this option turns the ANALOG-OUT and the
PWM-OUT ports into kW and kVAR load monitors, respectively. This option is
available from version 2.9I. It can also be identified on the first HELP display
line as IOB1:M or IOB2:M. The following two adjustable set-points define the
monitoring full-scale:
{Monitor V/Xre} which defines the ANALOG-OUT voltage level when the
engine runs with full load, i.e., when it carries {Xre: Rated kW}
kilowatts.
{Monitor %/Xap} which defines the PWM-OUT duty cycle when the
generator carries {Xap: Rated kVA} kilovars.
This special option is required by modern gas powered engine
governors.
10. Relay#1 under the option {R#1 Shunt|kW Load} = 0 energizes on any shutdown
fault. In the standard software, as a shunt trip driver, it energizes only if the
generator-set was running when shutdown was declared.
11. Relay#1 under the option {R#1 Shunt|kW Load} = 1 energizes when the
generator load is between the {R#1 Lowest kW} set-point to the {R#1 Highest
kW} set-point (set-points included). The {R#1 Off->On} and {R#1 On->Off}
delays apply here too. This behaviour is required for dual fuel engines where
R#1 tells when to switch on the gas supply.
12. Disables the warning COMM2 TIMEOUT ERROR. When the MODBUS master is a
non-critical SCADA system it may be difficult to comply with the requirement
to repeat the run/test commands...
13. Turns In#7 (HIGH TEMP SHUT) and In#13 (AIR DAMPER SHUT) into general
purpose warning inputs.
14. Modifications:
Energize K#6 immediately past cranking.
Shut down the genset immediately upon In#14 OVERLOAD and not after
cooling off.
Frostechnic Rev 9.00 June 2004 29
15. Turns the set-point {In#00Bypass Shutdn} into {In#00Disable Parll}. Any
spare input, #6 #8 #9 or #12, can be used to disable the paralleling system. An
active input logs a PARALLELING DISABLED warning and the system replaces
soft transfer (configs #5 and #6) with delayed transition (effectively
config#2), etc. In addition, the relay K#4 (usually the air-flap relay) is used to
indicate activity of the synchronizer. This option also applies to the generic
configuration only that instead of resetting the ANALOG/PWM controls they
freeze at the levels existing immediately before the spare channel of choice
became active.
16. Disables the RPM v FREQUENCY ERROR warning. This was required for a
generator-set whose 1500 RPM engine drove (through frequency conversion
gear) a 60Hz alternator.
17. Turns In#07 into a general purpose, non-bypass-able shutdown (ned the "HIGH
TEMP SHUT" and the "HIGH WATER TEMP SHUT" text messages). Turns In#13
into a general purpose warning (ned the "AIR DAMPER SHUT" and the "AIR
DAMPER CLOSED" text messages).
18. Include harmonics in the RMS computation.
19. Immediate COMM2(phone) command execution. By default GENCON has to be
told the same command twice for any genset start/stop or power
increase/decrease command takes effect. We need however an immediate
response when managing a group of config#4 peak-shavers where the
Communicator has also the onus of (proportional) load-sharing to manage
through GENCON's export quota mechanism.
20. Paralleling with analog gensets: The KW load is read by Sender1 of the IOB2
rather than from GENCON's own three phase inputs. With Sender1 reading the
analog paralleling line of an old/existing genset systems we can parallel them
with new GENCON based gensets. More information is available.
21. Based on the IOB2 Sender4 readings and after a one second filtering delay the
relay K#4 switches on and off according to the set-points {Sndr4K#4 On} and
{Sndr4K#4 Off}. A typical use is for fuel pump control based on the fuel
sender readings. Note that like the sender alarm set-points the greater-than
(>) and the less-than (<) signs can be changed by placing the cursor on the
sign and pressing any number key. The K#4 relay resets on any immediate
type generator-set shutdown.
22. In#07, normally the high coolant temperature shutdown, becomes a general
purpose warning channel.
In#14, under the option {Ext. Overload S|W}=0, becomes an immediate
shutdown alarm (normal "overload behavior" is to shut down the genset after
the cooling off interval).
Applications
It is obvious that a switchboard design depends on the
generator-set use: prime, standby, mains peak demand
lopping (shaving), etc. However, the difference in the
scope of the switchboard design between the continents is
less known. Here is a block diagram of a classic standby
set:
Transfer
Normal Source
Switch
Loads
G
Emergency Source
However, particularly in Europe, all these functions are normally included in the
genset switchboard. Typically the switchboard with two contactors directly implements the
load transfer (called the changeover contactors).
The Americans claim that their approach is more reliable
The Europeans claim that their approach is more economical
GENCON II does not take sides -- It supports both traditions and its large number of
parameters (delays, set points,), all adjustable from the front panel, make it easy to
adapt to any application.
Abbreviation
SET-UP\OPTIONS
Description
GENERIC
Generic Configure?
PARALLEL
Parallelin System?
ATS
COGEN
Cogeneration Mode?
NO
GENERIC?
NO
#0
NO
#1
ATS?
YES
PARALLEL?
NO
YES
#2 NO
#3
COGEN?
ATS?
YES
NO
#4
#5
YES
COGEN?
YES
#6
The generic configuration, #0, is designed for the "special projects" department. Access is
given to all the GENCON II functions, but the "glue logic", particularly control over the
contactors (breakers), is handled by an external logic device, a PLC usually.
The configurations #1..#6, however, constitute complete solutions, including control of the
contactors.
The following description of the applications assumes that the controller is in AUTO mode
and that no shutdown fault is pending.
#2 Euro standby
K#8
The controller monitors the voltage and frequency of one
phase of the mains by its V4 input (for 3 phase protection the
Mains Contactor
external relay should disconnect V4 input on a mains failure).
K#7
On a mains failure the controller energizes relay K#8 which,
LOAD
V4
through a normally closed#1 contact, opens the mains
In#1
G
contactor. After a predetermined time delay the genset is
Gen Contactor
started. When the genset is ready for load, the relay K#7 is
energized and its normally open contact closes the generator contactor. When the mains
power is restored, after a predetermined time, the load is transferred back to the mains.
To protect the load (eg synchronous motors), a time delay is introduced between the load
power cut and load power re connection. In this configuration the two contactors are
electrically interlocked (and sometimes mechanically interlocked) to prevent simultaneous
engagement.
An active In#1 input starts the genset. When the genset is ready for load the relay K#8 is
energized and the mains contactor opens, there is a time delay and then the relay K#7 is
energized and the genset takes the load.
Momentary activation of the In#2 input starts the genset for a test without load session.
LOAD
K#7
In#1
G
The genset starts immediately on an active In#1 input. The
genset is synchronized with the mains. When the voltage and
phase of V1 (generator) are sufficiently close to the voltage and phase of V4 (the mains),
the relay K#7 is energized and parallel connection begins. The genset raises the amount of
active (kW) and reactive (kVAr) power it exports to the mains at a predetermined rate,
until the export quotas are met. When the In#1 input is deactivated, power export is
reduced at a predetermined rate. When reaching zero the relay K#7 is de energized, the
generator contactor opens and the genset stops after a cooling off period:
#1
In this way the mains is connected to the load when GENCON II is without DC supply.
+ kW/Sec Ramp
- kW/Sec Ramp
+ kVAr/Sec Ramp
kW Export Quota
- kVAr/Sec Ramp
Time
Sync with Mains
Parallel Connection
In#1 ON
Time
Cooling-off
In#1 OFF
Parallel Connection
In#1 ON
Cooling-off
In#1 OFF
Momentary activation of the In#2 input starts the genset for a test without load session -the genset is synchronized with the mains but the relay K#7 is not energized.
When detecting loss of mains during paralleling, the relay K#7 is de energized and the
generator contactor opens. Loss of mains is detected within 100 ms, as follows:
1.
PARALLEL LOAD SURGE: Built-in protection mechanism: A sudden load change is
measured, larger than the Parll kW Surge set-point. Response to load decrease is optional,
see kW Drop=LoadSurge?.
2.
PARALLEL MAINS FAIL:
External protection: Low voltage is measured by V4 -- an
external relay disconnects V4 input.
The user can select export quotas within the genset ratings, ie Export-kW Rating-kW and
(Export-kW) + (Export-kVAr) (Rating-kVA). See SET-UP\BASICS Xre and Xap.
In this configuration the genset is used to parallel and export power to the mains in order
to reduce the electricity supply tariff for peak loads. The electricity companies also
surcharge consumers with low power factor (PF). The user should know that improper
choice of the export quotas can worsen the mains supply PF: Suppose a plant load is
444 kVA at 0.9 PF, ie 400 kW & 193.7 kVAr. If the genset exports 200 kW only, ie the mains
still carries the full 193.7 kVAr load, it turns that the mains is supplying power at an
uneconomic 0.72 PF. However, if the genset export quotas are 200 kW and 150 kVAr (using
a 250kVA genset at 0.8 PF) the mains is supplying power at an excellent 0.98 PF.
K#8
Mains Contactor
+ kW/Sec Ramp
- kW/Sec Ramp
- kW/Sec Ramp
kW Export Quota
Time
Time
Isochronous
Governor
Operation
Mains Failure
Sync
Cooling-off
Parallel
Connection
with
Mains
Mains Return
Isochronous
Governor
Operation
Cooling-off
Parallel
Connection
In#1 OFF
When the mains is available, an active In#1 input starts the genset immediately. Before the
genset takes the full plant load it reaches through paralleling a user selected export power
quotas.
Momentary activation of the In#2 input starts the genset for a test without load session -The genset is continuously synchronized with the mains but there is no load transfer.
In this configuration the genset stays in parallel with the mains only for the brief time it
takes to perform a smooth power transfer (called "occasional paralleling"). Most electricity
boards are more lenient in approving an installation of this sort than approving continuous
paralleling with the mains.
#6 Euro standby with soft mains return & paralleling with the mains
K#8
This configuration provides an automatic mains failure standby
operation with one power cut only as in configuration #5.
Mains Contactor
Active In#1 input starts the genset for continuous paralleling
K#7
with the mains as in configuration #4.
LOAD
V4
When detecting loss of mains during paralleling, the relay K#8
In#1
G
is energized, the mains contactor opens and the genset
Gen Contactor
remains with the load. Loss of mains is detected within 100
ms, as follows:
1.
PARALLEL LOAD SURGE: Built-in protection mechanism: A sudden load change is
measured, larger than the Parll kW Surge set-point. Response to load decrease is optional,
see kW Drop=LoadSurge?.
2.
PARALLEL MAINS FAIL:
External protection: Low voltage is measured by V4 -- an
external relay disconnects V4 input.
A.K#7
A.In#1
G1
A.V4
B.K#7
B.In#1
G2
B.V4
GENERATORs
C.K#7
GENCON (R) controllers, in a multiple generator-set
BUS
plant with equal size engines, can automatically
G3
start and stop their generator-sets according to the C.In#1
plant active (kW) load. The operator can change
C.V4
the sequence in which the generator-sets start and stop from any controller panel.
The sequencing logic is designed for plants with a slowly varying load level. Hotels,
hospitals and large residential and office blocks fall into this category. The objective of the
sequencing logic is to keep the number of parallel running generator-sets to the minimum.
In this application all the controllers are in configuration #3 and the{ Parall Auto Start}
option is 1.
2.2 Definitions
N : Denotes the number of generator-sets that currently run in parallel.
Unity : The engine { Xre: Rated kW} parameter in BASICS is defined as one unit of power.
The following , and _ variables use this unit. For example, if Xre is 800kW then a 50% _
level represents a 400kW load.
: Denotes the generator-set load. Note that (1- ) is the spare generator-set power and N
* (1- ) is the total spare power in the parallel running generator-sets, i.e., how much extra
load the running generator-sets can safely take.
: Denotes the set-point { +%kW/Xre ! Start}. is the total spare power threshold that
requires an increase in the number of parallel running generator-sets. can be larger than
100% and its value must be the same in all the controllers.
: Denotes the set-point { +%kW/Xre ! Stop}. 1 + is the total spare power threshold that
requires a de-crease in the number of parallel running generator-sets. can be larger than
100% and its value must be the same in all the controllers. Make sure that < or
otherwise one generator-set will start and
stop incessantly.
T1 : Denotes the { Parll Start } time delay for the threshold. Its value must be the same
in all the controllers.
To : Denotes the { Parll Stop } time delay for the threshold. Its value must be the same in
all the controllers.
2.3 The rules
1. One generator-set should start and take load immediately when the condition N * (1- )
0 is true.
This condition exists when:
(a)
(b)
too high.
N = 0, i.e., the plant must have at least one generator-set powering the load.
_ 1, i.e., the load on the current number of parallel running generator-sets is
2. A generator-set should start and join the parallel running generator-sets T1 time after
the condition
N * (1- ) becomes true. I.e., when the total spare power in the parallel running
generator-sets
is or lower.
3. A generator-set should stop To time after the condition N* (1 - ) 1 + becomes true.
I.e., even after stopping one generator-set the total spare power in the remaining
generator-sets, N * (1- ) - 1, is or higher.
4. When a generator-set connects to the bus or when a generator-set disconnects from the
bus, rules 1-3 are suspended for { LS Settling } seconds. These rules are suspended to avoid
false decisions while the load is re-distributed among the new number of generator-sets.
5. Black start:
Before software version 2.5n
When the generator-set controllers mode changes from Sleep to Auto by simultaneously
deactivating their In#3 command lines, all the generator-sets start and connect to the bus.
The generator-sets run in parallel for T0 time and then, according to the bus load level
(rule 3), some of the generator-sets stop.
From software version 2.5n
When all the In#16 command lines are simultaneously released all the generator-sets start
and connect to the bus. The generator-sets run in parallel for T0 time
and then, according to the bus load level (rule 3), some of the generator-sets stop.
6. When the generator set controllers mode changes from Auto to Manual by simultaneous
activation of
their In#1 terminals, all the generator-sets connect to the bus. When the controllers mode
changes back to Auto by simultaneous deactivation of their In#1 terminals, according to
the bus load level (rule 3) some of the generator-sets stop without delay.
4 A Real Application
A, B and C denote the controllers of three equal size generator-sets that serve for mains
failure standby; The sequence is 1 2 3; The Automatic Transfer Switch (ATS) logic
is external.
Let the signal x = A.In#16 = B.In#16 = C.In#16 (version 2.5n onward).
When the mains is healthy the ATS should hold x active.
Upon mains failure the ATS releases the signal x 1 .All the generator-sets start
together according to rule 5; the generator-set that has stabilized first connects to the
(dead) bus without delay and becomes the bus master 2. The other slave generatorsets connect to the bus after synchronization 3 . The generator-sets run in parallel for T0
= { Parll Stop} time and then, if the load is low enough, generator-sets 3 and 2 stop (no. 2
stops { LS Settling} time after no. 3)
1 The expected plant load is unknown. Probably it will be at its peak because of the need to recharge the UPS.
2 The
3 If
generator-set whose governor and AVR determine the bus frequency and voltage.
the master stops, the remaining set with the lowest ID number becomes the new bus master.
Hybrids
A hybrid paralleling system is made of one (but only one) controller in configuration #1,
#2, #4, #5 or #6 and a number of controllers in configuration #3. The controllers in
configuration #3 are said to be "permanent slaves" -- the different controller is said to be a
"permanent master". The use of the hybrid system is similar to the use of the master
controller. The slave gensets constitute an auxiliary power generation capacity that
augments the capacity of the master genset. The following operating rules are common to
all hybrids:
1.
2.
3.
4.
5.
When the master genset starts, all the slave gensets start#1,
When the master genset is taken off load, all the slave gensets are taken off load,
When the master genset stops, all the slave gensets stop,
The master genset is always first to be connected to the bus,
The slave gensets maintain the same load share of the master genset.
CONFIG.#1
Augmented American standby
ESSENTIAL
When A.In#1 starts genset G1, controller B
G1
A.In#1
LOAD
automatically starts up genset G2. G1 takes the
essential load first. Controller B, sensing the bus
phase through V4, synchronizes G2 with the bus
B.K#7
B.K#8
and the two gensets share the essential load. After
NON ESSENTIAL
G2
CONFIG.#3
a certain time, through B.K#8 the non essential
LOAD
load is also introduced and the two gensets share
B.V4
GEN BUS
both loads proportionally. Since controller A does
not use the auto synchronizer function,
G1 does not require an electric governor, nor an AVR with external voltage control.
A.K#8
#1
#0 Generic configuration
This configuration provides
maximal flexibility in the
design of parallel systems. The
controller operates under the
command of a PLC
(Programmable Logic
Controller) that also controls
the system contactors.
GEN
BUS OR MAINS
V1
V4
In#1
GENCON II
TEST W/O LOAD
In#2
SLEEP (BYPASS)
In#3
In#15
K#7
n
o
p
q
MODE
OFF OFF
OFF ON
EXPORT
ON
OFF
LOAD-SHARE
ON
ON
The controller's operating mode is selected by In#15 and In#16 according to the above
table. If the genset is not ready for load, ie the relay K#7 is not enerwized, mode n must
be selected by the PLC within a Contactor Delay time or the GENERIC CONFIG ERROR
shutdown is declared.
In modes n and q the synchronizer is active. By adjusting the genset speed and voltage it
tries to match the generator phase (V1) with the bus/mains phase (V4). The synchronizer
energizes the relay K#8 any time it succeeds in holding V1 within a Sync Window and
Sync Window V distance from V4 continuously for Sync Dwell Time.
In mode o the controller runs the genset in parallel with the mains. If the command In#1
RUN is active, the genset power increases at Ramp +kW/Sec and Ramp+kVAr/Sec rates until
reaching the Export Power Quotas where they are maintained as long as the command is
active. When removing the In#1 RUN command, the genset power reduces at
Ramp -kW/Sec and Ramp-kVAr/Sec rates until, when reaching zero, the relay K#7 is de
energized, indicating to the PLC that it needs to take the genset off load.
Note: Detecting PARALLEL LOAD SURGE in mode o de energizes the relay K#8 to warn the
PLC against a possible mains failure.
In mode p the controller runs the genset in parallel with other sets. If one of the other
genset controllers is in mode o or q that controller is "the master" and all the other
controllers in mode p, "the slaves", try to match their active (kW) and reactive (kVAr) load
share with that of the master (ie in proportion to each genset Xre: Rated kW and
Xap: Rated kVA). If all the controllers are in mode p, one of them is nominated as the
master and its genset determines the speed and the voltage of the bus.
Example: Given a group of standby gensets sharing a common load, ie the controllers run
in mode p under In#1 RUN commands. The PLC needs to transfer the load softly from the
generators to the mains:
1.
The PLC selects one of the paralleling controllers and switches its V4 channel to
measure the mains (before V4 is connected to the bus). The PLC places the controller in
mode q. This controller automatically becomes the bus master and drags the other gensets
into synchronism with the mains.
2.
When the selected controller relay K#8 energizes, the PLC connects the bus with the
mains and places the controller in mode o.
3.
4.
The PLC removes all the In#1 RUN commands. The gensets power export gradually
reduces. When each genset power reaches zero the controller's relay K#7 is de energized.
The PLC then opens the genset contactor and places the controller in mode n.
GENCON V3.0f
3. The {Eng Preglow|Idle}=1 option is introduced to run the engine at idle speed
for {IdleRunTime} delay after starting up the engine. Relay K#1 is energized
and through a suitable governor contact it holds the engine at the desired idle
speed. Idle speed run can be terminated by bringing the engine to normal
speed (most likely by installing a push-button in series with K#1...).
Load-sharing is enabled by the {System Auto Start} option. For example, a loadsharing config#6 is introduced by:
{Generic Configure} = 0
{Parallelin System} = 1
{Mains Standby ATS} = 1
{Cogeneration Mode} = 1
{System Auto Start} = 1
All the controllers must be programmed the same.
Under normal conditions the GENCON controller that has its K#6 relay energized is
the bus master and in control of the mains breaker, however:
If all the controllers have pending shutdown faults (or if they all are in "off mode")
they keep their K#6 relays energized.
If the DC supply of all the controllers is switched off no K#6 relay can of-course be
energized.
To detect these two special cases one can set the option {R#2 Alarm|Usable} in all
the controllers to 1 and connect the N/C contact of their R#2's in series...
When running in parallel with the mains only the master directly controls the export
kW/kVAr level, the slaves operate their load-sharing controls only to match their
output with their master's load%.
Miscellaneous
Mechanical mode switches
TEST
AUTO
Traditional rotary mode switches can be
In#2 TEST W/O LOAD
OFF
constructed using the IOB1 In#1/2/3 lines.
In#3 SLEEP
See this figure:
MAN
In#1 RUN WITH LOAD
It is an alternative to the controller's OFF
AUTO, AUTOOFF, OFFMAN and MANOFF software commands. The rotary switch
operates in AUTO mode only. It is also possible to reset the pending faults by activating
In#3 SLEEP, see the SleepClearsFaults? option.
kW Quota Dec.
set-point
In#16 is active
kW Quota Inc.
set-point
In#16 is inactive
kW QuotaDec
time-delay
kW QuotaDec
time-delay
kW QuotaInc
time-delay
Time
CAVEATS
GENCON II reliability had already been proven in many installations. Nevertheless, in a
good switchboard design there should exist additional means, even duplicate, to prevent
catastrophic consequences if there is a single component failure -- GENCON II is a single
component in this respect.
Since the probability of simultaneous failure of two, same function, protection devices
whose failure mechanism is statistically independent is the product of the failure
probability of each, the effective overall system reliability is greatly enhanced.
For a generator-set operating in parallel with the mains we recommend to add as a
minimum a short-circuit and a sync-check protection relays.
The analogue channels are not damaged. If using single lead senders it is
important to install protective TransZorbs.
(where the the {Mains Standby ATS} option is set). Note that spring driven (stored
energy) type of breakers need some time to charge before the breaker can obey the
close command. With a sufficient {LoadBreakMake} delay you can prevent this
common reason for CONTACTOR(s) FAILURE...
SHUTDOWNS BYPASS ON!
The result of active In#3 BYPASS. Most shutdown faults become warning only!
EMI (NOISE) DETECTED
Unexpected program restart due to electrical noise. As a precaution the program
"write protects" all the EEPROM based parameters even if the {WRITE PROTECT...!?}
option is not set. See our "tears saving" guide.
In rare cases this EMI (NOISE) DETECTED message can be a result corrupt EEPROM
data or a result of some software bug. The EEPROM can be erased by the eraser.exe
utility -- the next time the program starts it would initialize the EEPROM to its
factory default state. If the EMI report is a result of a software bug then in most
cases you would be able to provide an exact sequence of actions/events that can be
repeated to evoke this bug.
It is important to rid the control panel of EMI sources as they affect the reliability of
the system. Program restarts due to EMI also cause loss of accumulated kWH and
RunTimeHours count as their values in RAM could not be written into the EEPROM for
safe keeping.
RPM OVERSPEED SHUTDN
Engine speed higher than SET-UP\SET-POINT existed for SET-UP\DELAY.
SYNCHRONIZER TIMEOUT
This alarm indicates that within the allotted {SyncTimeout} time-delay the
synchronizer failed to bring the generator phase (V1) "in sync" with the reference
phase (V4). If while watching the synchronizer action on the MEASURE / SYSTEM
display you notice that the ANALOG/PWM "levers" are frozen check to see if the
mains/bus reference phase that is measured by channel V4 is perceived by GENCON
as being abnormal, that is, being outside the permitted {V4 Ov Voltage} through {V4
Un Frequen} setpoint range. Note that in some cases this alarm is just a warning. For
example, if the AMF genset that needs to return the load to the mains through
ramped parallel unloading declares a SYNCHRONIZER TIMEOUT alarm it would return
the load through delayed open transition, just as in configuration #2.
GENCON PROGRAM ERROR
Built-in test message. FLASH data error (software memory). Try loading the
controller software again under safe DC conditions. If the problem continues contact
the nearest service facility.
GENCON MEMORY ERROR
Built-in test message. EEPROM data error (parameters memory). Contact nearest
service facility.
General
IOB1 is an auxiliary input and output interface board. It adds to GENCON II 16 input and 8
output channels. The input channels implement the set of alarms and pre-alarms that is
specified in NFPA 110 level 1 (USA code), control the diesel engine and control the
generator and mains (when applicable) contactors.
IOB1 is mounted on a DIN rail inside the control cubicle. It is connected to GENCON II by a
special 120 cm symmetrical cable. Proper operation of the IOB1 is continuously monitored
and shutdown fault is declared on any malfunction. If the cable is removed all IOB1 relays
are off.
Input channels
The 16 input channel terminals are connected through "normally open" (N/O) or "normally
closed" (N/C) contacts to the battery (-) potential. The type of contact to use with each
input, N/O or N/C, is defined by SET-UP\IN 1..16. The input channels activity is displayed
by MEASURE\ IN 1..16.
In#1RUN WITH LOAD
Active In#1 starts the genset in AUTO mode unless a shutdown fault exists. When the
genset is ready it takes the load or enters paralleling.
In#2 TEST W/O LOAD
Active In#2 starts the genset in AUTO mode unless a shutdown fault exists. When
In#2 is deactivated, following the Test Delay time, the genset stops.
In#3 SLEEP or BYPASS
In#3 can be used in two ways according to the In#3 Sleep|Bypass option:
SLEEP:
Active In#3 inhibits genset startup in AUTO mode. When it is active OVERVIEW
displays "Mode=Sleep." It can be activated by a clock to disable standby operation
after working-hours.
BYPASS:
Active In#3 converts most shutdown faults to warnings (except In#4 EMERGENCY
STOP). Active In#3 is also a warning fault. It is typically used when powering fireextinguishing pumps.
In#4 EMERGENCY STOP
Active In#4 is a shutdown fault. It also activates the K#4 AIR DAMPER relay.
In#5 OIL PRESS SHUT
Active In#5 indicates low lubricating oil pressure (see In#6). In#5 passes 0.5 sec
delay to filter out transient contact statuses. When the engine is running it causes a
shutdown fault. When the engine stops, after Stoppin Max time delay, it causes an
ENGINE SHUTDOWN FAIL warning.
Output channels
There are 8 output relays, K#1 to K#8, driving 24 output terminals. The relays have
Single Pole Double Throw (SPDT) contact configuration. 3 terminals belong to each
relay: Pole, N/C Throw, N/O Throw. Follow the PC-board marking. Each contact
rating is 380 Vac / 10 Amps.
K#1 PRE-GLOW
K#1, through a N/O contact, energizes an electric heater before cranking the
engine. Use SET-UP\DELAYS to define the pre-glow time.
K#2 FUEL SOLENOID
K#2, through a N/O contact, operates the fuel solenoid. The fuel solenoid can be
defined as either "energize to run" or "energize to stop", see SET-UP\OPTIONS. The
genset should stop within a predetermined time after blocking its fuel supply (see
SET-UP\DELAYS) or otherwise a fault is declared. If it just the oil pressure not falling
fast enough (In#5 OIL PRESS SHUT), it is a warning fault only. However, if speed and
voltage are measured, shutdown fault is declared and the K#4 AIR DAMPER relay is
also activated.
K#3 CRANK
K#3, through a N/O contact, energizes the starter motor solenoid. Use SETUP\DELAYS to define the maximal cranking time and the delay between the cranking
attempts. Use SET-UP\SET-POINTS to define the number of cranking attempts and
the minimal speed to stop cranking (ie engine "firing" RPM).
K#4 AIR DAMPER
K#4 is active for 2 seconds following an engine overspeed or following failure to stop
the genset by K#2 FUEL SOLENOID. K#4 is inhibited if In#13 AIR DAMPER is already
active.
K#5 LUBRICATION PUMP
K#5, when the genset is stationary, activates an auxiliary lubrication pump
repetitively, with a predetermined on and off duration. See SET-UP\DELAYS.
K#6 SET RUNNING
If the K#6 Engine|Gen On option is:
0 K#6 is active when the engine is running: RPM 60 or Hz 15.
1 K#6 is active when the generator voltage is high: V1, V2 and V3 Gen
Undervoltage setpoint.
K#7 GEN CONTACTOR
K#7, through a N/O contact, operates the generator to load contactor. In
conjunction with K#8, complete automatic transfer switch (ATS) logic is provided. If
the genset parallel operation with the mains is enabled, the ATS contactors should
not use a mechanical or electrical interlock mechanism. It is recommended,
especially when paralleling is used, to bring to In#15 GEN CONTACTOR an auxiliary
contact from the gen contactor, to compare K#7 command with the contactor
status.Under the Generic Configure? option this relay indicates that the genset is
ready for load.
Current inputs
GENCON channels I1=[A51-A52], I2=[A61-A62] and I3=[A71-A72] measure the generator
phase currents through standard 5A current transformers (CTs). Their full-scale reading is
5.9A.
To improve the accuracy of measurement choose CTs with {CT Ratio} as small as possible.
GENCON units built before January 2001 have non-isolated current inputs. Check how the
rear panel is marked.
NON-ISOLATED
The generator CTs should be potential free. The wires leading to each CT should be
twisted:
If the CT is not kept potential free (#1) current will flow through the 100 ohm resistor and
will cause measurement errors. Large current may even burn out this resistor.
Measurement errors are usually caught by GENCON and reported as GENCON AMPS READ
ERR.
ISOLATED
Since the revised current inputs are isolated and since they have low input impedance the
following wiring method is safe:
Voltage models
GENCON model is specified in terms of the nominal phase-to-neutral Vrms level of the
generator. The full-scale reading of each voltage measuring channel in GENCON is
approximately 20% above the model nominal Vrms. The following models are currently
standard:
Nominal Vrms Full-scale Vrms
120V
143.5V
127V
150.5V
220V
260.4V
240V
286.8V
277V
330.8V
345V
420.7V
415V
497.0V
For maximal accuracy the model voltage should be as near as possible to the nominal
generator voltage. However, if the input voltage is larger than the full-scale value, the
GENCON "sees" a distorted waveform where the AC sinusoid peaks are clipped. The
following shows what a 220V model sees (in red) when connecting a 280Vrms input:
Connect:
V1 = UTS (i.e., A11 = T, A12 = S)
V2 = URS (i.e., A21 = R, A22 = S)
V3 = any phase to phase voltage
I1 = IT
I2 = IR
I3 = Not connected
This technique, known as Aaron's technique for measuring 3-wire systems using two
wattmeters, gives an accurate reading of the total active (kW) and reactive (kVAr) power
output of the generator-set also for non-symmetrical loads. The total kW's and total kVAr's
are what the load-sharing PID loops in GENCON regulate.
Since UTS leads URS by 60, we have to connect them to V1 and V2 respectively to avoid ILL
GEN PHASE ORDER error messages; See the following phasor diagram. We connect a phaseto-phase voltage also to V3 just to avoid GEN UNDERVOLTAGE error messages. V4, the
generator-set synchronization reference, should be connected to the corresponding bus UTS
phase-to-phase voltage.
If the magnetic pickup is shared with the electric governor connect it as follows:
IMPORTANT! -- 15 Feb 2001 -- The following applies to the new model "C":
If GENCON measures an RPM value that is twice the correct one, attenuate the MPU signal
by inserting a series resistor before B11.
All the reported problem cases had a strong MPU signal, 15Vac and more. With 5Vac and
lower signals there was never a problem.
Attenuation Resistor
Factor
Value
2
200k
430k
4
620k
It is suspected that in the problem cases large ground noise is being added to the pick-up
signal due to the engine governor (sharing the magnetic pickup). Hence, lowering the
ground noise through the use of lower resistance cables may work too.
This is done since in most governors the input terminal MPU- is internally connected to
BAT- and SHIELD (also in GENCON B12 is internally connected to C13 DC-).
The smallest signal that can be detected by B11 is 0.7V peak-to-peak relative to B12/C13
(ie, 0.5V rms).
The MEASURE\ENGINE menu function displays the engine speed in RPM (r) and displays the
alternator frequency in Hz (h). It derives its values from the PICK-UP frequency (f) and it
uses the definitions Number of Poles (p) and Pick-up Teeth (t) from SET-UP\BASICS. The
formulas are:
h=(f/t)*(p/2), r=(f/t)*60, r=h*(120/p).
Usually the Number of Poles is 4. Hence, the formulas become: h=(f/t)*2, r=(f/t)*60,
r=h*30.
switched coils.
The correct place for the suppressor is across the coil, not across the switch.
Do not forget to suppress the fuel-solenoid, starter-relay, breakers, electric heaters,
buzzer... Even the primary transformer of a battery charger, when switched on/off, can
cause interference if it is not properly suppressed!
Move the electric governor and its DC supply wires away from the GENCON/IOB cubicle.
I.e., use a slave relay that is adjacent to the governor to switch the governor DC supply
on/off. Do not use the IOB relay K#2 FUEL SOLENOID to switch the governor DC supply
directly! Of-course; twist the DC supply wires leading to the governor and its actuator.
Apply the same rule to other power devices that are under GENCON control. For example,
the lubrication pump place is next to the engine, so should be the place of its supply
contactor, don't place it inside the GENCON/IOB cubicle!
Move the generator AVR away from the GENCON/IOB cubicle. The recommended place for
the AVRx and its 24VAC transformer is in the AVR box.
The most sensitive circuits in GENCON are at its centre, next to terminals B11,..., B43 and
B5. Let all the high AC voltage and current carrying conductors pass as far as possible from
this part of the controller. For example, the battery charger, especially the switching
regulator type, should not be installed near this sensitive part of the controller.
Make the control cubicle an effective electrostatic shield (a Faraday cage) by connecting
the DC- terminals of GENCON/IOB to the cubicle as shown in the section on battery
supply.
The current transformers (CTs) should be potential free -- do not ground them! Connect a
twisted pair of wires to each CT -- do not use a common return wire! See also the section
on the current inputs.
Segregate the cables in the system into AC power and return, DC power and return, analog
controls and digital controls. For example, do not run the RS485 communication cable in
parallel to AC power cables; Keep a safe distance.
Being so compact, the natural place to install the GENCON controller is on the genset
itself. In this case make sure that the control cubicle where GENCON is installed is well
protected from the genset vibrations: the cubicle should be mounted through rubber shock
absorbers that also insulate it from the genset body. If you have to install GENCON
elsewhere be aware of the caveats.
Software set-up
BASICS
{Ideal Freq Hz} -- The desired bus frequency, usually 50 or 60 Hz.
SETPOINTS
{HYD Gov Hz ERR} -- The "master" controller will up/down the motor if the measured
frequency vis--vis the ideal is so and so Hz in error.
{HYD Gov Hz/Sec} -- The minimal rate of frequency change effected by the up/down
contacts. Note that the larger this value is the longer will be the up/down pulse duration.
In the demo software the simulated motor changes the frequency at 0.15 Hz/sec so we
enter 0.1 Hz/sec here by default.
{HYD Gov kW ERR} -- A load-sharing/exporting controller will up/down the motor if
the generated kW versus the required is so and so kW's in error.
Since PM100 6/7 terminals (originally provided for an external 10k Remote Voltage
Adjust) are very sensitive to noise, it is recommended to install the AVRx and this
voltage divider as near as possible to the PM100.
The above circuit was tested on a 277Vac L-N generator. In response to a 50% to 0%
PWM-OUT change (simulated by pulling out the B31 wire) the generator voltage fell
by 40Vac.
Customer comment: The above voltage divider was found to cause the generator to
have a 10Vac droop (between zero to full load), an unexpected phenomenon. It was
also noted that when the voltage "trim pot" on PM100 is fully counter clockwise
(minimal setting) the droop is at its minimum.
Set the AVRx trimmer to the minimal 3Vdc range. The AVRx transformer can be as
low as 16Vac
Caterpillar VR3
Remove the VR3 droop CT1 and 8 ohm rheostat if they are installed. Remove also
the remote level 10K ohm potentiometer.
Power the AVRx off a 24Vac transformer and adjust its trimmer to achieve a +/- 10%
response to the 100/50/0 PWM% simulation around the chosen VR3 nominal Vac
level.
1.
2.
3.
4.
Mecc-Alte's UVR6
When the genset runs with the paralleling system disabled (when PWM-OUT is 50%),
adjust the Vac level of UVR6 to the nominal level using their "tensione"
potentiometer. Simulating 0% and 100% PWM change should cause the generator Vac
to fall and rise by 10% respectively.
1.
2.
3.
4.
While running the genset under Parallelin System?0 adjust the generator voltage
level to its nominal Vac (for example, 230Vac).
While running the genset under Parallelin System?0 stop the PWM_OUT pulse train
by disconnecting the wire leading to GENCONII terminal B32. The generator voltage
should fall (to 200Vac in the example).
With the AVRx trimmer set at maximum, GENCON's 0 to 100% PWM range is expected
to produce a 11% change around the generator nominal Vac (the nominal Vac is set
under PWM of 50%).
Basler Electric
All the models that can be used with Basler's own SCP-250G PF/VAR CONTROLLER can be
used with GENCON's AVRx. In particular:
1. AEC63-7: The following interface provides 10% Vac control range. It was tested on a
380V Marathon generator.
(preliminary)
1. Adjust the AVRx trimmer to the minimal 3V range (hence, the AVRx power transformer
can be 16Vac).
2. Link terminals CT1-CT2 as no C/T is required. Remove the RVT or LINK from terminals ST and install the voltage divider.
3. Calibrate REG37 voltage under 50% PWM level.
The voltage read by B22 REF-IN is added to the internal digital to analog converter output:
In this way what the speed setting input of the remote governor "sees" is exactly the
voltage that GENCON's internal digital to analog converter has set. Fluctuations in the
engine speed due to the voltage between the control cubicle ground (where GENCON is
installed) and the governor ground are eliminated. In the following example if the ground
voltage of the EFC (COM) with respect to GENCON ground (C13) drops by 250mV, the D/A
output (B21) would immediately drop by 250mV too. Hence, the voltage applied between
RMT-SPD (8) and COM (2) remains constant.
It is recommended to connect B22 REF-IN to all engine governors whose speed setting input
is not potential free. This is particularly important to do so with governors whose Hz/Volt
response is very high, CUMMINS EFC, BARBER-COLMAN DYNA, ...
General
B21 is connected to the electric governor of the engine. The electric governor, usually,
operates in isochronous (zero droop) mode. When synchronizing and when running in
parallel, GENCON changes the voltage of B21 to adjust the engine speed and the engine
load share. Ideally, the 0 to 7.5V range of B21, when applied to a free running gen-set,
would be able to adjust the gen-set frequency to 2.5% around the nominal 50 or 60 Hz
frequency.
Some electric governors can be driven by B21 directly. Some, due to excessive Hz/Volt
response, require an interface. The voltage level of B21 under which the governor
frequency is calibrated is defined by the parameter {Gov Volt Bias}.
Here is how to connect several common governors:
In Woodward 8290 speed control (part of the 1724 EPG governor) connect B21 D/A
to terminal [11] Aux Input+. Set {Gov Volt Bias} to 1.5V. If GENCON model C is used
it is recommended to connect [12] Aux Input- to B22 REF-IN.
Woodward's (digital) ProAct:
The auxiliary input of ProAct is potential free, its effective input range is 2.5V.
GENCON can apply on terminals 12(+) versus 13(-) a 3.75V range. Set the {Gov Volt
Bias} to 3.75.
Frostechnic Rev 9.00 June 2004 77
Woodward's 2301A family of speed controllers, like ProACT, also has potentialfree biploar speed setting inputs. Hence, use terminals B21 D/A versus B22 REF-OUT
and a {Gov Volt Bias} of 3.75V to create a speed control signal. The sensitivity of
the SPM INPUT is approx. 0.5 Hz/Volt. The sensitivity of the AUX INPUT is approx.
2.5 Hz/Volt.
Woodward's (digital) GenDec:
GenDec's auxiliary speed reference input requires a 500Hz PWM (Pulse Width
Modulated) signal with 24V amplitude. Wexler's Analog to PWM module converts the
0 to 7.5V range of B21 into the required PWM signal. Order "ANALOG/PWM 500Hz".
CUMMINS QST30
Connect B21 ANALOG-OUT to their "Woodward Compatible Speed Input", terminal
16. Use a {Gov Volt Bias} of 5.0 Volts. Since this speed control input is not potential
free it is recommended to configure terminal B22 as a REF-IN to read the governor
signal ground. More information about this governor is wanted, for example, what is
its Hz/Volt response. Thanks!
-- R1 --+-- #23
|
GENCON
R2 ECM Connector 03
|
B22 REF-IN --------+-- #14
Select resistors R1 = 1000 and R2 = 560.
The EFC is used in "Run Mode", its RMT SPD input range is 0 to 8V. Adjust RUN1 to 5% below the nominal frequency, eg, 50-2.5=47.5Hz. Adjust RUN2 to +5.7% above
the nominal frequency, eg, 50+2.8=52.8Hz. Set the {Gov Volt Bias} to 3.75V.
GENCON can change the genset frequency by 2.5Hz. Set the {Gov Volt Bias} to
3.75.
The old Cummins EFC and Barber-Colman models respond to Vdc around 3.5 and
4.0 volts respectively. Since the RMT SPD input is too sensitive the following 25:1
voltage divider is required:
Set the {Gov Volt Bias} to 3.5 or 4.0 as appropriate. It is recommended to enable the
ground voltage compensation circuit.
DPG-2201 - Digital Programmable Governor
Since LS-SIGNAL, DPG-2201's analog input, has 10 Hz/Volt sensitivity the following
voltage divider is required:
Set GENCON's {Gov Volt Bias} to 3.75V. B21 0-7.5V is expected to command 2Hz
speed change around the nominal engine speed. Note that B22 should be configured
as a reference input.
GENCON was using a {Gov Volt Bias} of 3.50V and had a 2 Hz/Volt effect.
Deutz EMR: Connect B21 D/A to the EMR pin 25 of plug F. Adjust the EMR response
to 2V around a 2.50V {Gov Volt Bias} to 5% change around the nominal engine
speed.
VOLVO
MTU's MDEC
Set the {Gov Control Bias} to 5.0 Volts. Important! By default MDEC has this speed
setting input disabled. Contact MTU.
MDEC has five positive switched alarm outputs and four 0-10V analog outputs. An
interface circuit is available, marked A65, to convert these signals into IOB2
compatible digital and analog inputs. Contact WEXLER.
Since GENCON is not in direct control of the engine the following changes are
necessary:
o
o
Use the special software with option #8 to enable multiple cranking attempts.
Set the {Pick-up Teeth} count in BASICS to zero and the {Extrn Engine Ctrl} in
OPTIONS to 1.
Set the {Gov Control Bias} to 2.6 Volts for 1800 RPM / 60 Hz.
Generator-set commissioning
1. PATIENTLY make sure that the wiring fully complies with our Tears Saving Notes. If
GENCON is installed at some distance from its generator-set, be aware of the problems
that can result from having a different ground potential at the generator-set and at the
control cubicle.
If the generator-set is used for paralleling make sure that fast closing breakers were
provided, for example, contactors or spring operated breakers.
2. Make sure that the frequency and the voltage of the generator-set is stable under
various load conditions. The frequency should be stable to 0.01-0.02 Hz. Also adjust the
governor potentiometer to high gain, just below the point where the engine starts to
"hunt" -- We can't work with lazy governors! Similarly adjust the AVR.
3. Put the generator-set under resistive load and check the readings at the MEASURE menu
of each phase. Consult section on common cts faults advice how to find common CT
wiring mistakes if you see kVArs or negative kWs on any phase.
4. Confirm that we have good governor and AVR response by changing the {Gov Volt Bias}
and by simulating 0% and 100% PWM conditions.
The governor response should not exceed 3 Hz/Volt.
The AVR should not change the generator voltage by more than 10% in response to 0%
and 100% PWM conditions.
Calibrate the engine speed to the appropriate 50 or 60 Hz frequency under the {Gov Volt
Bias} value, which is appropriate for your governor model
Calibrate the generator voltage to the appropriate 120V,..., 346V L-N level under PWM of
50%.
In load-sharing systems it is important to calibrate the frequency and the voltage of all
the generator-sets to exactly the same level in order to prevent kW and kVAr transients
when generator-set master/slave roles have to change.
5. Make sure that the generator breaker cannot close. Set the {Parallel in System} option
to 1 and run the genset in test mode (via In#2) with a live mains or bus. Two closed
control loops simultaneously work:
The frequency and phase synchronizer that is controlled by the {SYgainV/180} and
{SYstbl V/Hz} parameters and the voltage matching loop that is controlled by the
{SYgain %P/V} parameter. Our aim is to find a max-gain/min-stability adjustment for
each control loop. Use the SYNC scope and the SYSTEM display to see how these
independent control loops work (and also listen to the engine noise). Note that each
time that the genset is within the acceptable phase and voltage window for {Sync Dwell
Time} an asterisk appears in the OVERVIEW display. In a stable loop ANALOG-OUT and
PWM-OUT gently fluctuates around the bias points.
If the synchronizer does not work check the four {V4 Ov Voltage}... {V4 Un Frequen}
setpoints. Probably one of them tells GENCON to regard V4 state as abnormal.
At this stage GENCON holds the genset in sync with the bus/mains (the asterisk on the
OVERVIEW display should appear often). If you have a 3-pole breaker use a voltmeter to
make sure that the voltage across EACH POLE is near zero when the "*" appears on
OVERVIEW. If you are using a 4-pole breaker use another GENCON and with its SYNC
scope (V1 vs. V4) check that there is no phase shift and voltage difference across EACH
breaker pole. DO NOT TRUST phase sequence meters.
6. Change to the appropriate parallel configuration. Use basic configs and not the more
complex variants of it (for example, plain config#3, even if the final project requires
the {Parall Auto Start} option). The {LSgain V/Xre} and the {LSstbl V/Xre} parameters
control the ANALOG-OUT "lever" (and kWs). The {LSgain%P/Xap} and {LSstbl%P/Xap}
parameters control the PWM-OUT "lever" (and kVArs). Pay close attention to the POWER
and SYSTEM display to check how each loop performs. Again we are interested in maxgain/min-stability set of parameters.
CE mark
The CE mark indicates GENCON's compliance with the Low Voltage Directive (73/23/EEC) of
the European Union (EU).
The Electromagnetic Compatibility (EMC) Directive does not apply to GENCON, as it is a
"component" (sub-assembly) and not an "apparatus".
Year 2000 (Y2K) Compliance
The GENCONII pro software, as its notion of time is limited to 7 days only, is inherently
safe vis--vis the calendar change from the 19. Years to the next millennium. See the SETCLOCK command.
Note!
The contrast of the LCD characters may change slightly with temperature (visibility is guaranteed from -20C
to +70C). For adjustment use the trimmer on the rear panel. Common menu options
Software maintenance
Text editing
You may wish to change the name of an input alarm channel,. You can do this by yourself using the
PC program NED.EXE. After editing the texts by NED.EXE, load the revised software into GENCON
PRO using the procedure described in the following load section.
Run the program by NED SET to define the program input and output file, note you must use a file
name that exists in the current directory this file must be a gencon will be over written when you end
the program. If you omit the argument SET, NED.EXE will use the file names that it used in its
previous execution. You can edit an existing software file by specifying the same input and output file
names.
The text editing process is straightforward: Type over the existing text (the PC left, right, insert and
delete keys are at your disposal). Skip text line editing by striking the down arrow key.
Backtrack by striking the up arrow key. To introduce your text changes strike the ENTER key. End
NED.EXE by striking the Esc key. Be careful not to place text where measured values are displayed!
Procedure:
1. Connect GENCON PRO to the PC RS-485 serial port. Only one controller can now be connected
to the PC!.
2. Run NED.EXE by NED SET. Change RS-485 communication port as necessary and follow on
screen instructions. If you type NED only, the program uses the set of arguments it used last.
3. Using a long and thin screw-driver prepare the dip switches for Flash
programming by: SW2 =DOWN. You don't have to open the instrument cover!
See also Dip-switches
4. Turn on GENCON PRO power supply.
5. Press ENTER to begin the software transfer. '>'s appear on the PC screen to
indicate transfer progress. PROG message appears on the GENCON PRO LCD.
Wait for successful programming completion message.
6. Turn off GENCON PRO power supply.
UP
7. Prepare GENCON PRO dip-switches back for normal operation by:
SW2=SW3=UP.
SW1
SW2
8. Turn on GENCON PRO power supply.
SW3
B6
AUX...
DOWN
B6
AUX...
DOWN
TRAN.EXE is a utility program which picks up translations made for an earlier GENCON II software
version and automatically introduces them to a newly released English software version. Run the
program for further details.
Turn on GENCON PRO power supply. The minimal power supply voltage is 15 volts.
Press ENTER.
Turn off GENCON PRO power supply.
Prepare GENCON PRO dip-switches for normal operation by: SW2=SW3=UP.
Index
#
#0 Generic configuration............................................................................................................................................................................. 39
#1 American standby................................................................................................................................................................................... 32
#2 Euro standby........................................................................................................................................................................................... 32
#3 Load dependent start/stop sequencing .................................................................................................................................................... 35
#3 Random access paralleling ..................................................................................................................................................................... 34
#4 Paralleling with the mains ...................................................................................................................................................................... 32
#5 Euro standby with soft load transfer....................................................................................................................................................... 33
#6 Euro standby with soft mains return & paralleling with the mains......................................................................................................... 34
A
Applications ................................................................................................................................................................................ 8, 27, 31, 57
Augmented American standby .................................................................................................................................................................... 38
Augmented Euro standby ...................................................................................................................................................................... 38, 39
Automatic mode............................................................................................................................................................................................. 8
AUTOOFF .............................................................................................................................................................................................. 8, 45
AVRs........................................................................................................................................................................................................... 69
AVRx .............................................................................................................................................................................. 1, 67, 69, 71, 73, 74
B
Basic load control.................................................................................................................................................................................. 27, 45
BASICS............................................................................................................................................................8, 9, 10, 11, 19, 33, 36, 65, 68
Bat OvVoltage ............................................................................................................................................................................................. 19
Bat UnVoltage............................................................................................................................................................................................. 19
Battery and DC supply ................................................................................................................................................................................ 66
C
Calibrate ...................................................................................................................................................................................................... 86
Caterpillar VR3 ........................................................................................................................................................................................... 71
CAVEATS .................................................................................................................................................................................................. 47
CE mark ...................................................................................................................................................................................................... 88
Cogeneration Mode..................................................................................................................................................................................... 31
COMMAND ........................................................................................................................................................................... 3, 4, 5, 7, 9, 27
Contactor Delay .................................................................................................................................................................................... 39, 57
Controller ID No ........................................................................................................................................................................................... 8
Controlling voltage regulators..................................................................................................................................................................... 69
CrankStop RPM .......................................................................................................................................................................................... 19
CT CONNECTION FAULTS / TESTING ................................................................................................................................................. 61
CT Ratio ...................................................................................................................................................................................................... 60
Current inputs.............................................................................................................................................................................................. 60
D
Definitions................................................................................................................................................................................................... 36
Delays ......................................................................................................................................................................................................... 46
E
EMC questions for the control panel builder............................................................................................................................................... 88
EMI (NOISE) DETECTED......................................................................................................................................................................... 88
ENGINE............................................................................................................................................................................................ 9, 56, 65
EXPORT........................................................................................................................................................................................................ 8
EXTERNAL OVERLOAD ............................................................................................................................................................................ 57
G
G 2x OvCurr................................................................................................................................................................................................ 24
G Over %THD............................................................................................................................................................................................. 24
G Revrse kW................................................................................................................................................................................................ 24
G Rvrs kVAr ................................................................................................................................................................................................ 24
GEN A, GEN B and GEN C ......................................................................................................................................................................... 9
H
Heinzmann KG 604 governor ..................................................................................................................................................................... 85
HELP........................................................................................................................................................................................................... 10
HIGH WATER TEMP SHUT....................................................................................................................................................................... 7
Hybrids........................................................................................................................................................................................................ 38
I
Ideal Freq Hz .............................................................................................................................................................................................. 68
ILL GEN PHASE ORDER ......................................................................................................................................................................... 63
IN 1..16 ....................................................................................................................................................................................................... 10
In#11 LOW FUEL WARN ........................................................................................................................................................................... 57
In#12 CHARGER FAULT.................................................................................................................................................................... 51, 57
In#13 AIR DAMPER SHUT ........................................................................................................................................................................ 57
In#15 GEN CONTACTOR..................................................................................................................................................................... 57, 58
In#16 MAINS CONTACTOR................................................................................................................................................................. 57, 59
In#1RUN WITH LOAD ............................................................................................................................................................................... 56
In#2 TEST W/O LOAD .................................................................................................................................................................... 8, 25, 56
In#3 SLEEP or BYPASS .............................................................................................................................................................................. 56
In#4 EMERGENCY STOP ................................................................................................................................................................... 51, 56
In#5 OIL PRESS SHUT.............................................................................................................................................................. 3, 51, 56, 58
In#6 OIL PRESS WARN ...................................................................................................................................................................... 51, 57
In#7 HIGH TEMP SHUT...................................................................................................................................................................... 51, 57
In#8 HIGH TEMP WARN.................................................................................................................................................................... 51, 57
In#9 LOW TEMP WARN............................................................................................................................................................................. 57
Input channels ............................................................................................................................................................................................. 56
IOB1...................................................................................................................................................................1, 4, 6, 10, 11, 26, 45, 56, 88
IOB2.......................................................................................................................................................................................................... 1, 4
ISOLATED ................................................................................................................................................................................................. 60
K
K#1 PRE-GLOW ......................................................................................................................................................................................... 58
K#2 FUEL SOLENOID .................................................................................................................................................................. 26, 58, 67
K#3 CRANK ................................................................................................................................................................................................ 58
K#4 AIR DAMPER .......................................................................................................................................................................... 7, 56, 58
K#5 LUBRICATION PUMP........................................................................................................................................................................ 58
K#6 Engine|Gen On .............................................................................................................................................................................. 46, 58
K#6 SET RUNNING .................................................................................................................................................................................... 58
K#7 GEN CONTACTOR ..................................................................................................................................................................... 57, 58
K#8 MAINS CONTACTOR............................................................................................................................................................. 7, 57, 59
kW Drop=LoadSurge ............................................................................................................................................................................ 33, 34
L
LED's ............................................................................................................................................................................................................ 3
Leroy-Somer's R448.................................................................................................................................................................................... 74
LOAD-GEN .................................................................................................................................................................................................. 7
LOW WATER LEVEL......................................................................................................................................................................... 15, 57
LowWaterLevel S|W .................................................................................................................................................................................... 15
LS Settling ....................................................................................................................................................................................... 27, 36, 37
LSgain V/Xre ............................................................................................................................................................................................... 87
LSgain%P/Xap ............................................................................................................................................................................................ 87
LSstbl V/Xre ................................................................................................................................................................................................ 87
LSstbl%P/Xap ............................................................................................................................................................................................. 87
M
Magnetic Pickup.......................................................................................................................................................................................... 64
Mains Standby ATS ............................................................................................................................................................. 7, 8, 9, 31, 57, 59
MANOFF ................................................................................................................................................................................................ 7, 45
Manual mode................................................................................................................................................................................................. 7
Marathon Electric PM100 ........................................................................................................................................................................... 70
Marelli's M25FA600A ................................................................................................................................................................................ 73
MEASURE.......................................................................................................................................................................... 3, 4, 9, 56, 65, 86
Measuring 3-wire systems........................................................................................................................................................................... 63
Mechanical mode switches.......................................................................................................................................................................... 45
Motor Contactors ........................................................................................................................................................................................ 46
MPU.................................................................................................................................................................................................. 9, 64, 65
Multiple generator-set applications ............................................................................................................................................................. 34
N
Newage Stamford........................................................................................................................................................................................ 69
NON-ISOLATED ....................................................................................................................................................................................... 60
Number of Poles.......................................................................................................................................................................................... 65
O
OFF mode ..................................................................................................................................................................................................... 7
OFFAUTO .............................................................................................................................................................................................. 7, 45
OFF-LOAD................................................................................................................................................................................................... 7
OFFMAN ................................................................................................................................................................................................ 7, 45
Outlook ......................................................................................................................................................................................................... 2
Output channels........................................................................................................................................................................................... 58
OVERVIEW ............................................................................................................................................................................................. 5, 9
P
Parall Auto Start ..................................................................................................................................................................................... 8, 87
Parallel genset automatic start/stop............................................................................................................................................................ 46
PARALLEL LOAD SURGE .......................................................................................................................................................... 33, 34, 40
PARALLEL MAINS FAIL................................................................................................................................................................... 33, 34
Parallelin System .................................................................................................................................................................................. 31, 74
Parameters............................................................................................................................................................................................. 11, 12
Parll Start.............................................................................................................................................................................................. 27, 36
Parll Stop ........................................................................................................................................................................................ 27, 36, 37
Pick-up Teeth .......................................................................................................................................................................................... 9, 65
POWER+PF .................................................................................................................................................................................................. 9
R
R#1 On->Off ............................................................................................................................................................................................... 27
R#1 Shunt|kW Load..................................................................................................................................................................................... 45
Ramp +kW/Sec ............................................................................................................................................................................................ 40
Ramp -kW/Sec ............................................................................................................................................................................................. 40
Ramp+kVAr/Sec.......................................................................................................................................................................................... 40
Ramp-kVAr/Sec ........................................................................................................................................................................................... 40
REPORT ............................................................................................................................................................................................... 3, 4, 7
S
SEQUENCE .................................................................................................................................................................................................. 8
Set Stabil Min ........................................................................................................................................................................................ 39, 46
SET-CLOCK....................................................................................................................................................................................... 5, 8, 88
SETPOINTS.......................................................................................................................................................................................... 52, 68
SET-UP ....................................................................................................................................................................................................... 10
Short-cuts ...................................................................................................................................................................................................... 4
Single generator-set applications................................................................................................................................................................. 32
Software features......................................................................................................................................................................................... 68
T
Tears saving notes ....................................................................................................................................................................................... 67
Test Delay ............................................................................................................................................................................................. 39, 56
The SET-UP menu ...................................................................................................................................................................................... 11
V
V4 Ov Frequen ............................................................................................................................................................................................ 20
V4 Ov Voltage ....................................................................................................................................................................................... 20, 86
V4 Un Frequen............................................................................................................................................................................................ 86
V4 Un Voltage ............................................................................................................................................................................................. 20
Voltage models............................................................................................................................................................................................ 62