Chapter 6 Road Construction Techniques

Download as pdf
Download as pdf
You are on page 1of 21
swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES CORPORATE DOCUMENT REPOSITORY Produced by: Forestry Department Title: Watershed management field manual ‘spafiol Francais More detail CHAPTER 6 ROAD CONSTRUCTION TECHNIQUES 6.1 Road Construction Techniques 6.1.1 Construction Staking Prior to the construction activity the design information has to be moved from the plan to the ground. This is accomplished by staking. Slope stakes are an effective way to insure compliance with the design standards and to keep soil disturbance to an absolute minimum. Various staking methods can be employed. (Dietz et al., 1 Pearce, 1960) The method discussed here is but one example. Stakes, marking various road design points, are typically obliterated during the clearing and grubbing phase. In order to relocate the stakes (centerline, slope stakes) it is helpful to establish reference points outside the clearing limits. Reference points should be set at least 3 to 5 meters behind the uphill clearing limits. On the average, reference points (or RP's) should be set at least every 70 to 100 meters. Typically, reference points are placed at points where the center line alignment can be easily re-established, such as points of curvature. Figure 102 shows the necessary stakes and stake notation needed by the equipment operator to construct a road Stakes are used by the equipment operator in locating where to begin cutting, If the selected starting point is too high, considerably more material has to be cut in order to construct the proper subgrade (Figure 103). For example, if the cut results in a 20 percent wider subgrade, approximately 50 percent more volume has to be excavated. (See Section 3.2.2.) If the cut is placed too low, an overstepped cut slope or extra side casting may result, both of which are undesirable. Starting the cut at the proper point becomes more important as the side slope increases. As a rule, slope stakes should be set when sideslopes exceed 40 to 45 percent depending on the sensitivity of the area and the operator's experience, The use of RP's (Reference Points) or slope stakes for proper excavation is shown in Figure 104, Here, the engineer stands on the preliminary centerline of the construction grade and sights for the RP. A slope reading of 30 percent and a slope distance of 5.53 m is recorded. Converting the slope distance of 5.53 m to a horizontal distance of 5.30 m and to a vertical distance of 1.59 m allows the engineer to determine how much the "present" or preliminary centerline has to be shifted to conform with the design centerline. The RP tag requires 6,50 m horizontal distance to centerline with a vertical drop of 4.80 m. From that information, it can be seen that an additional 1.56 m [4.80 - (1.59 + 1.65) = 1.56] has to be cut and the present location has to be shifted by 1.2 m (6.50 - 5.30 = 1.20). Height of instrument or eye-level is assumed to be 1.65 m, Figure 102. Road cross section showing possible construction information. hiipihwww foo ordocrenOosno099e 008805 im 11 swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES "3 10.m, approx. +237 30m 7 m———+ 285 m Down = fo subgrade 90 m—H-—3.29 m ae se | lo 2s oom [& rol 3 1a Centering stoke i Reference tg nated to bate of tree o stump outside clearing with Reference Tag Explanation ‘Staton= 15100 (1500 m fom road beginning) anne centetine fs 2.65 m below ths point Centeine is 637 m horzoral dence away Cutsipe steepness | 37 mt point where cusiope begins 240 Aa.= Compass deeton from RP to ceterine stake ies Figure 103. The effect of improperly starting the cut as marked by the slope stake. Starting the cut too high results in excess excavation and side cast. Starting the cut too low leaves an overstepped cut bank. oni Slope Stake (Cut too low Oversteepened cut slope c Designer Cross Section igure 104, Construction grade check. Engineer stands on center of construction grade and sights to RP tag Measured distance and slope allow for determination of additional cut. hhapihwww foo ordocreni00et0098erT0088e05 im ant swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES 6.1.2. Clearing and Grubbing of the Road Construction Area Preparing the road right-of-way or construction area is referred to as clearing and grubbing. During the clearing phase, trees are felled. Grubbing refers to the clearing and removal of stumps and organic debris. Trees should be felled and cleared a minimum of 1 to 3 m from the top of the cut or toe of the fil (Figure 105). The logs can be decked outside the construction area (Figure 105, B to E) or skidded away Figure 105. Clearing limits in relation to road bed widths. Significant quantities of organic materials are removed between B and E. Stumps are removed between B and D. Stumps may be left between D and €. Organic debris and removed stumps are placed in windrows at F to serve as filter strips (see Section 6.3.1). | Topo Fi aring limits or Right of Way This additional width between construction width and forest edge ensures that space is available to deposit organic debris outside the road construction width and that there is no overlap between forest edge and construction area ‘A good construction practice to follow is to remove stumps that are within the construction width (Figure 105, B to E). Trees should be felled to leave a stump 0.8 to 1.2 m high. This helps bulldozers in stump removal by providing added leverage. Organic overburden or topsoil typically has to be removed over the full construction width (Figure 105, B to D). This is especially true where organic layers are deep or considerable sidecast embankment or fills are planned Organic material will decompose and result in uneven settlement and potential sidecast failure. Organic material should be deposited at the lower edge of the road (Figure 105, E to F). This material can serve as a sediment fitter strip and catch wall (see Section 6.3.1), however care should be taken that this material is not incorporated into hiipihwww foo ordocrenOosno099e 008805 im sat swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES the base of the fill. Past road failures show that fill slope failures have been much more frequent than cut slope failures (70 percent and 30 percent, respectively). In most cases, poorly constructed fills over organic side cast debris was the reason for the failures, During the grubbing phase, or preparation phase, a pioneer road is often constructed to facilitate equipment access, logging equipment movement, and delivery of construction materials, such as culverts. This is often the case when construction activities are under way at several locations. If pioneer roads are constructed, they are often built at the top of the construction width and are usually nothing more than a bull dozer trail. When considerable side hill fill construction is planned, however, the dozer trail should be located at the toe or base of the proposed fill. The trail will serve as a bench and provide a catch for the fill to hold on (Figure 106), Figure 106. Pioneer road location at bottom of proposed fill provides a bench for holding fill material of completed road. Designed Cross Section 6.2 General Equipment Considerations The method and equipment used in road construction is an important economic and design factor in road location and subsequent design. A road to be built by an operator whose only equipment is a bulldozer requires a different design than a road to be built by a contractor equipped with hydraulic excavator, scrapers, and bulldozer. Table 38 lists common road construction equipment and their suitability for the different phases of road construction. A bulldozer can be used in all phases of road construction from excavation and drainage installation to final grading The front end loader performs well in soft material. Front end log loaders can be fitted with a bucket extending thelr usefulness under the correct conditions. 6.2.1 Bulldozer in Road Construction Probably the most common piece of equipment in forest road construction is the bulldozer equipped with straight or U-type blades. These are probably the most economical pieces of equipment when material has to be moved a short distance. The economic haul or push distance for a bulldozer with a straight blade is from 17 to 90 meters depending on grade. The road design should attempt to keep the mass balance points within these constraints. The road design should consider the following points when bulldozers are to be used for road construction 1. Roads should be full benched. Earth is side cast and then wasted rather than used to build up side cast fills. 2. Earth is moved down-grade with the aid of gravity, not up-grade. 3. Fill material borrowed rather than pushed or hauled farther than the economic limit of the bulldozer. 4, Rock outcrops should be bypassed. Unless substantial rock blasting is specified requiring drilling and blasting equipment, solid rock faces should be avoided (This, however, is primatily a road lacator's responsibility.) Table 38. Road construction equipment characteristics. (from OSU Extension Service, 1983) Dump trucks or scrapers hiipihuww foo ordoerenOo6to029e 008805 im ant Frontend | Hydraulic Loader | excavator Farm Criteria | Bulldozer tractors (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES swzr2015 | | I I I Excavation | Digs and |Minor digging) Digs, | Scrapers can} Minor digging mode (level | pushes; of soft | swings, & load and carrying; of control of | adequate |material; lifts] deposits; | themselves; | good control excavated | control | &carries; | excellent | ‘top down’ | because it materials) | (depends on | good control | control; can | subgrade handles blade type) avoid mixing | excavation; materials | used for long-distance] small material | quantities movement; excellent control Operating | 91 m; 91mon }23m (limited No limit 31m distance for | pushing |good traction} to swing | except by_| (approximately) materials | downhill | surfaces | distance) | economics; movement | preferred trucks must be loaded [Suitability for, Adequate | Good || Limitedto | Good for | Not suitable fill smaller fills | larger fills construction Clearing and Good | Adequate | Excellent | Not suitable | Handles only grubbing ‘small materials (capacity to handle logs and debris Ability to | Adequate | Digging | Excellent | Not suitable | Adequate for install limited to small tasks drainage soft features materials Operating | Moderate, | Relatively | Moderate to | Very high Low lcost per hour, depending on} low high, but machine size productivity excellent Special | Widely | Cannot dig | Good for | Limited to | Very dependent limitations or available; hard roads on | moving on site advantages | can match | material; steep __| material long]| conditions and size to job; | maybe hillsides; can| distances; | operator can do all’ | traction do all can haul skill required with | limited required | rock, rip rap, good except ete. operator spread rock for rock surfacing When using bulldozers, the practice of balancing cut and fil sections should be used only when hiipihwww foo ordocrenOosno099e 008805 im sat swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES + sideslopes do not exceed 45 to 55 percent + proper compaction equipment is available such as a “grid roller" or vibrating or tamping roller - fills have a sufficient width to allow passage of either compaction equipment or construction equipment, such as dump trucks, ‘Adequate compaction cannot be achieved with bulldozers alone. The degree of compaction exerted by a piece of equipment is directly related to its compactive energy or ground pressure. Effective ground pressure is calculated as the weight of the vehicle divided by the total ground contact area, or the area of tires or tracks in contact with the surface, Bulldozers are a low-ground pressure machine and therefore are unsuitable for this process. Ground pressure of a 149 kW (200 hp), 23 tonne bulldozer (Cat D7G, for example) is 0.7 bar (10.2 Ib / ing). By comparison, a loaded dump truck (3 axles, 10 m3 box capacity) generates a ground pressure of 5 to 6 bar (72.5 to 87.1 Ib / in2), Comparative production rates for various size bulldozers are shown in Figure 107. One should note that production curves are based on: 100 % efficiency (60 minutes/hour), Power shift machine with 0.05 minute fixed time, machine cuts for 15 m then drifts blade load to dump over a high wall, soil density of 1,370 kg/m3 (85.6 Ib/ft3) loose or 1790 kg/ m3 (111.9 Ib/ft3) bank, coefficient of traction > 0.5, and hydraulic controlled blades are used oahens Figure 107. Maximum production rates for different bulldozers equipped with straight blade in relation to haul distance. (from Caterpillar Handbook, 1984) 1one. LEGEND ‘4 09S Caterpitiar 10 D7S Caterpitiar me 1m DGS Caterpitiar © DSS Caterpitlar ee; © D4S Caterpitlar ‘CuMiie (loose) 400 ‘DOZING PRODUCTION - UNIVERSAL & STRAIGHT BLADES ESTIMATED TRACK-TYPE TRACTOR ° 20 «40 0«= 6080S s100 AVERAGE DOZING DISTANCE (me 140160 The graph provides the uncorrected, maximum production. In order to adjust to various conditions which affect production, correction factors are given in Table 39. Adjustment factors for grade (pushing uphill or downhill) are given in Figure 108. Table 39. Job condition correction factors for estimating bulldozer earth moving production rates. Values are for track-type tractor equipped straight (S) blade. (Caterpillar Handbook, 1984) TRACK TYPE | WHEEL TYPE TRACTOR | TRACTOR OPERATOR hiipihuww foo ordoeren0o6to029e 008805 im eat swernats (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES lExcellent 1.00 1.00 lAverage 0.75 0.60 [Poor 0.60 0.50 MATERIAL lLoose stockpile 1.20 1.20 Hart to cut; frozen— Iwith tilt cylinder 0.80 0.75 jwithout tilt cylinder 0.70 - lcable controlled blade 0.60 - lHard to drift; “dead” (dry, non- Jcohesive material) or very 0.80 0.80 sticky material SLOT DOZING 0.60 - 0,80 - ISIDE BY SIDE DOZING 1.15 - 1.25 1.15 -1.25 \VISIBILITY — usta snow, fog, 0.80 0.70 JOB EFFICIENCY — [50 minvhr 0.84 0.84 {40 mindhe 0.67 0.67 DIRECT DRIVE TRANSMISSION hiipihuww foo ordoeren0o6to029e 008805 im 78 swernats (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES (0.1 min. fixed time) 0.80 - IBULLDOZER™ [Angling (A) blade 0.50 - 0.75 - ICushioned (C) blade 0.50- 0.75 0.50 -0.75 IDS narrow gauge 0.90 - Light material U-blade (coal) 1.20 1.20 * Note: Angling blades and cushion blades are not considered production dozing tools. Depending on job conditions, the A-blade and C-blade will average 50-75% of straight blade production, Figure 108. Adjustment factors for bulldozer production rates in relation to grade. (Caterpillar Performance Handbook, 1984), 13 12 1 21° S Bo Qos © or os: os: 04. 30-20-10 PERCENT GRADE NOTE: (~) FAVORABLE (+) UNFAVORABLE EXAMPLE: Determine the average hourly production of a 200 hp bulldozer (D7) equipped with a straight blade and tit cylinder. The soil is a hard packed clay, the grade is 15 percent favorable, and a slot dozing technique is used. The average haul or push distance is 30 m. The soil weight is estimated at 1,200 kglm3 loose, with a load factor of 0.769 (30 % swell). An inexperienced operated is used. Job efficiency is 50 min/hour. The uncorrected maximum production is 430 m3 loose/hour (from Figure 107) bulldozer curve D7S. Applicable correction factors are Job efficiency (60 minvhr) 0.84 Poor operator. 0.60 hiipihwww foo ordocrenOosno099e 008805 im aot swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES Hard to cut soil 0.80 Slot dozing 4 9 technique Weight correction 0.87 Production = Maximum Production * Correction Factor = (430 m3 loose/hr) (0.84) (0.60) (0.80) (1.20) (0.87) = 181 m3 loose/hour Production (bank m3) = (181 m3 loose/hr) (0.769) = 139 bank m3/hr Production rates for bulldozers are also influenced by grade and side slopes. Percent change in haul distance with respect to changes in grade are shown in Table 40. As side slope increases, production rate decreases. Typical production rates for a medium sized bulldozer in the 12 to 16 tonne range (for example, Cat D6) are shown in Table 41 Table 40. Approximate economical haul limit for a 185 hp bulldozer in relation to grade. (Production rates achieved are expressed in percent of production on a 10 percent favorable grade with 30 m haul). (Pearce, 1978). Haut Grade (%) distance (mete) | 4a) 5 | 0 | 45 | +10 | +15 | +20 percent 5 54 | 72 90 | 126 | 161 | 198 | 234 23 43 30 44| 56 | 76 | 100 | 122 | 144 37 47 45 s4 | 70 | 96 | 102 60 42 | 54 | 65 | 77 5 43 | 52 | 62 90 43 | 51 bhapihwww foo orgdocreni00et0098eT0088e05 im eat swernats (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES ,= iit} | | dt Bulldozers, to summarize, are an efficient and economical piece of equipment for road construction where roads can be full benched and excavated material can be side cast and wasted. It should be noted, however, that side cast material is not compacted. Typically, this type of construction equipment should only be used when: (1) side slopes are not too steep (ideally less than 50 percent), (2) adequate filter strips are provided along the toe of the fil, together with a barrier (natural or artificial) to catch side cast material, and (3) erosion is not considered to be a significant factor either as a result of soil type, precipitation regime, or both. Under these circumstances, bulldozers can be used on slopes steeper than 50 percent. If sidesiopes exceed 60 percent, end hauling and/or use of a hydraulic excavator is highly recommended. Side cast wasting from bulldozer construction represents a continuous source for raveling, erosion, and mass failures. On steep slopes, bulldozers should only be used in combination with special construction techniques (trench excavation, see Section 6.3.1). Table 41. Average production rates for a medium sized bulldozer (12 - 16 tonnes) constructing a 6 to 7 m wide subgrade. ISidestope (%) 0-40 | 40-60] >60 IProduction rate in ee 12-18 | 8-14 | 6-9 6.2.2 Hydraulic Excavator in Road Construction The hydraulic excavator is a relatively new technology in forest road construction. This machine basically operates by digging, swinging and depositing material. Since the material is placed, as opposed to pushed and/or sidecast, excellent control is achieved in the placement of the excavated soil. This feature becomes more important as the side slope increases. Fill slope lengths can be shortened through the possibility of constructing a catch wall of boulders along the toe of the fill. This feature is particularly important when side slopes increase to over 40 percent. Mass balance along the centerline is limited to the reach of the excavator, typically about 15 to 20 meters. However, because of excellent placement control, construction of a balanced cross section can be achieved with considerably less excavation. Raveling disturbance and erosion is reduced as well because of lesser excavation and little or no downhill drifting of embankment material (Figure 109) Figure 109. Fillslope length reduction by means of catch wall at toe of fill. (See also Figure 55). Fillsiope tength eduction hiipihwww foo ordocrenOosno099e 008805 im 071 swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES Production rates for hydraulic excavators are given in Table 42. Production rates are shown for three different side slope classes. The values given are for a medium sized excavator with a 100 kW power rating (e.g., CAT 225, Liebherr 922) Table 42. Production rates for hydraulic excavators in relation to side slopes, constructing a 6 to 7 m wide subgrade. Side slope | Production rate % meter / ...hour 0-40 12-16 40-60 10-13 > 60 8-10 The excavator production rate approaches the dozer production rate as side slope increases. There are now indications that excavator production rates are higher than dozer production rates on slopes steeper than 50 percent. This difference will increase with increased rock in the excavated material. The bucket of the excavator is much more effective at ripping than the dozer blade. Excavators are also more effective at ditching and installing culverts. 6.3 Subgrade Construction 6.3.1 Subgrade Excavation with Bulldozer Proper construction equipment and techniques are critically important for minimizing erosion from roads during and after the construction, There are clear indications that approximately 80 percent of the total accumulated erosion over the life of the road ocours within the first year after construction, Of that, most of it is directly linked to the construction phase. In order to keep erosion during the construction phase to an absolute minimum, four elements must be considered, 1. Keep construction time (exposure of unprotected surfaces) as short as possible 2. Plan construction activities for the dry season. Construction acti be halted ss during heavy or extended rainfall should 3. Install drainage facilities right away. Once started, drainage installation should continue until completed 4. Construct filter strips or windrows at the toe of fill slopes to catch earth stumps and sheet erosion (see Section 635), The formation or construction of the subgrade begins after the clearing and grubbing (stump removal) phase. Three basic construction techniques are commonly used: side cast fills and/or wasting, full bench construction with end haul, and balanced road sections with excavation incorporated into layered fills (Figure 110). Side cast and wasting traditionally has been the mast common construction method. It also has been responsible for the highest erosion rates and making large areas unproductive. In this method, most if not the full road width is placed in undisturbed soil (Figure 110). Excavated material is side cast and wasted, rather than incorporated into the road prism. The advantage is uniform subgrade and soil strength. It is unlikely that the travelled road width will be involved in fill failures, An obvious disadvantage is the potential for erosion of loose, unconsolidated side cast material Side cast construction is the preferred construction method for bulldozers. The bulldozer starts the cut at the top hitpihuw foo ordoeren0o6no029e 008805 im sn swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES of the cutslope, and excavates and side casts material until the required road width is achieved (Figure 111). It is important that the cut be started exactly at the "top of cut” construction stake (point B, Figure 105) and the cutting proceed with the required cut slope ratio (see Section 6.1.4). Depending on the type of blade (S - or U - blade) the bulldozer can push or drift excess or excavated material up to 100 meters in front of the blade along the road section to deposit it in a stable place. As the side slope becomes steeper, less and less of the side cast material is incorporated into the side fil. Bull dozer equipment has very little placement control especially on steeper side slopes where "sliverills" often result (Figure 112). These fills perform marginally, at best, and "full benching’ with side cast and wasting of excavated material is preferred by many road builders. The result is a stable road surface but with a very unstable waste material fill Figure 110. Three basic road prism construction methods. SIDECAST AND WASTE Most of the road width is cut into the stable sidebill Excavation is wasted LOOSE SIDECAST- EXCESS EXCAVATION FULL BENCH ‘AND ENDHAUL Excavation is hauled to safe waste area [TTT BALANCED ‘AND LAYERED ROAD SECTION Excavation is incorporated into road prism (fil.) Figure 111. Road construction with a bulldozer. The machine starts at the top and in successive passes excavates down to the required grade. Excavated material is side cast and may form part of the roadway. hiipihwww foo ordocrenOosno099e 008805 im a) swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES HILL SIDE WITH TOP OF CUT PIONEER ROAD FINAL ROAD WIDTH Figure 112. Sliver fills created on steep side slopes where ground slope and fill slope angles differ by less than 7° and fill slope height greater than 6.0 meters are inherently unstable. hhapihwww foo ordocreni00et0098erT0088e05 im sa swerrots (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES SLIVER FILL >6m 40cm DIA) secured against tree, stump, rock SLASH ( TOPS, BRANCHES,<15 om dia.) LITERATURE CITED Caterpillar. 1984. Caterpillar Performance Handbook, No. 14. Peoria, Illinois Cook, M.J, and J.G, King,1983, Construction cost and erosion control effectiveness of filter windrows on fill slopes. USDA Forest Service, Research Note INT-335, November 1983, Dietz, P., W. Knigge and H. Loeffler, 1984, Walderschliessung. Verlag Paul Parey, Hamburg and Berlin, Germany. Haber, D. and T. Koch. 1983. Costs of erosion control construction measures used on a forest road in the Silver Creek watershed in Idaho. U.S. Forest Service, Region 1 and University of Idaho, Moscow, Idaho. Nagyayor, S.A. 1984. Construction of environmentally sound forest roads in the Pacific Northwest. In (ed Corcoran and Gill) C.O.F.E/U.F.R.O. Proceedings, University of Maine, Orono, and University of New Brunswick, Fredericton, April 1984, p.143 - 147. Oregon State University. 1983. Road construction on woodland properties. Or. St. Univ. Ext. Cir. 1135. Corvallis, hiipihwww foo ordocrenOosno099e 008805 im sa wero ‘CHAPTER 8 ROAD CONSTRUCTION TECHNIQUES Oregon. 24 p Pearce, J. K. 1960. Forest Engineering Handbook. US Dept. of Interior. Bureau of Land Management. 220 p. hhapuhwww foo orldoerepl00ston9eT 008805 fim 200 ‘warns (CHAPTER 6ROAD CONSTRUCTION TECHNIQUES bhapihwww foo ordocrepioosto09ser70098e05 im ant

You might also like