Calculating Total Power Requirements Transcript - 2
Calculating Total Power Requirements Transcript - 2
Transcript
Slide 1
Welcome to the Data Center University course on Calculating Total Power Requirements.
Slide 2: Welcome
For best viewing results, we recommend that you maximize your browser window now. The screen controls
allow you to navigate through the eLearning experience. Using your browser controls may disrupt the
normal play of the course. Click the attachments link to download supplemental information for this course.
Click the Notes tab to read a transcript of the narration.
.
Slide 3: Learning Objectives
At the completion of this course, you will be able to:
Calculate total power requirements for a data center.
Understand the components of the data centers electrical capacity calculation:
Critical and non-critical loads
Electrical Service via the utility
Generator Standby Power Systems
Recognize the benefits to right sizing your power needs.
Discuss the power evolution in the data center as well as the impact of multi-core processor
technology and new dynamic loads.
Slide 4: Introduction
An essential part of data center planning and design is to align the power requirements of the IT equipment
with the capacity of the supporting infrastructure.
Page |1
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Over the years, the architecture of data center physical infrastructure which includes cooling, power,
security, fire suppression, racks and cabling, has evolved from fixed, hard-wired, centralized components to
mobile, modular components that employ standardized technologies.
These innovations simplify the process of calculating power needs and allow for a much higher degree of
flexibility in data center design. With the adoption of scalable pay as you grow UPS architectures, its
becoming easier and less costly to install and grow these back-up systems.
Slide 5: Introduction
Despite these new technology innovations, data center designers still need an organized methodology for
calculating future electrical needs of the data center or server room.
Confronted with the challenge of determining both current and future power requirements, data center
managers often over size their power requirements by as much as 70%.
This leads to both the drastic under utilization of the infrastructure and the commitment of financial
resources to fund unrealized investments. Accurately determining power requirements is one of the most
important pieces of the overall data center project process.
This course will provide you with the working knowledge needed to determine current, and future, total
power requirements for your data center.
Lets begin by identifying availability requirements.
Slide 6: Identifying Availability Requirements
Successful design initiatives begin with a needs assessment that includes the identification of availability
requirements for the data center.
Page |2
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
This assessment essentially establishes the availability needs of the business applications being processed
by IT equipment.
Some popular availability configurations, from a power and cooling perspective, include N, N+1, and 2N.
Slide 7: Identifying Availability Requirements
Its important to remember that the redundancy architecture deployed will impact the amount of power
consumed in the data center.
No matter what the actual physical infrastructure system design configuration is, the core issue will be to
provide sufficient power to the critical load while keeping that critical load cool enough to operate without
experiencing downtime. It is important to address this carefully, because underestimating the required
capacity may result in future power disruptions. Over estimation can lead to excessive upfront installation
costs and higher ongoing maintenance expenses.
Once availability requirements have been identified, the next phase of the design process includes the
identification of load components and their power requirements.
Slide 8: Determining Load Requirements
Determining the load requirements is critical because most data centers are part of a larger building.
Data centers and network rooms draw a total load, which is the sum of the power consumed by the installed
IT and physical infrastructure equipment.
Before we explore each of the components which contribute to the total load requirements, lets establish
our data center assumptions.
Page |3
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
For purposes of this course, our breakdown assumes a 50 square foot, (4.64 square meters) data center
with an initial steady state critical load of 50kW, plus a future steady state load of 50kW. The cooling system
is assumed to be 50% direct expansion (DX) and 50% chilled water. The utility voltage is 480 volts AC.
Now lets use this information to determine the load components for the data center.
Slide 10: Critical Load Requirements
Regardless of whether the data center consists of a single rack environment or a full scale data center, the
first step in calculating total power requirements is to determine the size of the critical load that must be
served and protected.
The critical load includes all of the IT hardware components that make up the IT business architecture:
servers, routers, computers, storage devices, telecommunications equipment, etc., as well as the security
systems, fire and monitoring systems that protect them.
Page |4
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Page |5
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
For the purposes of this example, we are making the assumption that one rack of equipment will represent
the entire critical load component in our imaginary data center. In reality, a typical 5,000 square foot (465
square meter) data center could consist of 100 to 200 of these racks with various types of servers and other
installed components.
Page |6
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
In this example, Server #1, the first component in our rack, does have a nameplate that reveals a rating of
300 watts.
For simplicitys sake all of our component power readings should be converted to Kilowatts which is the
easiest measurement to calculate power requirements. 1 Kilowatt is equivalent to 1000 Watts. Therefore,
we have converted our 300 watt nameplate rating for Server #1 to .3 kilowatts.
Page |7
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Both Server #2 and Disk Array #2 are a bit more problematic because, in our example, neither has a visible
nameplate rating. Although this is unusual, it can happen. However, we can use a formula that will allow us
to calculate a kW rating for these two devices.
If the wattage is not listed on the device, it can be determined by multiplying the incoming current in amps
by the voltage of the device, which is typically 120 or 208V in North America and 220V outside of North
America, to get the VA or volt-amps.
Slide 15: Calculating Critical Loads
If you dont know the voltage information off hand, you will need to contact your electrician or facilities
manager. If you dont have power consumption of the individual component in amps, consult either the
product manual or the vendors website. Then, multiply the anticipated VA number by 0.67 to estimate the
Page |8
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
actual power, in watts, that the critical load will represent. Finally, divide the number by 1000 to establish
the Kilowatt (kW) load level of the anticipated critical load.
In our example, we have determined the voltage for Server #2 to be 120 V and the amps coming in to be at
5 amps. Therefore, 120V x 5 amps = 600 VA. To covert to watts we need to multiple the VA by .67. That
gives us a total of approximately 400 Watts. We convert this figure to .4 Kilowatts.
We follow the same procedure for determining our kilowatt rating for Disk Array #2. (310 watts / 1000 =.31
kW)
The sum of our four components is equal to 1.51 kW.
Page |9
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
P a g e | 10
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Lets assume that our server base in the data center will grow by 20% over the next 3 years to reflect an
anticipated growth in business.
(Although over the last five years, servers have consumed increasingly large amounts of power, this trend
may be reversed in the near future as multi-core processors begin to replace the traditional CMOS chip. We
will discuss more about multi-core processors later on in this course. For the purposes of this example, well
assume that the power consumption will be the same.)
Since our projected growth will be 20%, we will add 20% to our current critical load numbers to establish our
future load.
This equation illustrates the additional power requirement increase of our future load and shows how we
have taken our existing critical load of 1.51 kW and multiplied by 20% to determine how much in extra kW
we have to account for in our future critical load.
Slide 20: Calculating Future Critical Loads
In order to ensure that our electrical system is capable of supporting peak power draws (due to some
variations that might exist in the critical load) we will also add the critical load and future load kW amounts
Calculating Total Power Requirements
P a g e | 11
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
and multiply by a factor of 1.05. This will give us a total of 1.90 kW (1.51 + .3 x 1.05). This would be the
peak power draw. In order to calculate the net amount of extra capacity needed to address this peak power
draw consideration, we simply take this peak power draw number (1.90) and subtract the sum of the existing
load. In this case, 1.90 -1.81 results in an extra .09 kW of power required.
Slide 21: UPS Load Requirements
Although the UPS will support the critical loads in the event of an outage or power anomaly, the UPS
equipment itself will also consume a portion of the available power. While UPS models will vary in terms of
their efficiency and some UPS architectures are less efficient at lower load levels than others, for purposes
of this particular course, lets assume a UPS efficiency rating of 88%.
UPS battery charging or external battery banks are a significant but intermittent power consumer. Under
normal operation with a charged battery the battery charging load is negligible. However, when a battery
has been partially or completely discharged the battery charging power can be on the order of 20% of the
rated UPS load.
Now lets take this information and calculate UPS loads.
Slide 22: Calculating UPS Loads
To derive the UPS load you need to know the existing load, future load and the inefficiency factor for the
UPS & UPS battery charging.
For purposes of this example, we assume the UPS inefficiency rating to be 12%, and the UPS battery
charging factor to be 20%. Adding these 2 together will result in an inefficiency factor of 32%.
Now, take the Existing Load of 1.51 kW and add it to the Future Load of .3 kW and multiply it by the UPS &
battery inefficiency of .32. This will result in the UPS Load of .58 kW (for this example).
(Image on next page)
P a g e | 12
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Now that weve calculated the UPS load, lets move on to lighting loads.
Slide 23: Lighting Load Requirements
Lighting loads account for all the lighting in the data center portion of the building. To perform this
calculation, you will need to know:
The square footage of the data center: in this example of an imaginary one rack data center, we are
assuming the space to be 50 square feet (4.64 sq meters). A simple formula for average lighting
consumption is 2 watts per square foot or 21.5 watts per square meter. Again, for the purpose of producing
consistent numbers, we are converting watts to kilowatts. Therefore, 2 watts will be converted into .002
kilowatts, or if calculating in meters, 21.5 watts will be converted to .0215 kilowatts.
So, to calculate the lighting load:
Take the square footage and multiply by the average consumption to get the Total Lighting Load, in this
case: 50 x .002 = .1 kW or 4.64 x .0215 =.1kW for calculation in square meters
Cooling will comprise the largest draw on the data center requirements, so lets estimate that next.
P a g e | 13
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
P a g e | 14
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Lets assume that half of the installed air cooling equipment consists of chilled water system and the other
half is a direct expansion architecture. So, dividing 2.58 in half give us 1.29 kWs for each of the two air
cooling architectures.
Finally, you will need to know the Cooling Efficiency Factor for these cooling architectures. DX is multiplied
by 1 which results in a factor of 1.29 and chilled water is multiplied by .7, resulting in a factor of .90. By
adding the DX load to the chilled water load, we can derive the total cooling load of 2.19 kW.
Slide 27: Total Power Requirements Summary Calculation
Now the total power requirements for the data center has been calculated. This chart is a summary of the 6
steps we have taken to arrive at our total power requirements sample number.
(Image on next page)
P a g e | 15
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
P a g e | 16
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
These sources must be sized to the peak power consumption of the loads, plus any de-rating or oversizing
margins required by code or standard engineering practice.
Using the same percentage breakdown of the data center electrical requirements as discussed previously,
this illustration emphasizes the important distinction between peak power and steady state power by
comparing the electrical service requirements for both. (In practice, this difference between peak and steady
state requirement causes the electrical service and generator sizing to be substantially larger than might be
expected.)
Observe that the electrical service required at peak is almost 4 times the steady state critical load value.
(It also must be noted that this is only an estimate, and that the final determination of the service size is
highly dependent on accurate site specific information.)
P a g e | 17
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
P a g e | 18
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
It is important to identify that the data center can be just one of many loads on the system, so this diagram
can be interpreted as a subset of a much larger electrical system.
Air conditioning loads, for example, require high starting currents and can impose harmonic currents on a
generator that may impact its ability to supply the power needed. The UPS itself may contribute to this
problem if it does not operate at a high input power factor, and may cause generator failure.
It is sufficient to note that the UPS must be chosen carefully to achieve end-to-end reliability. A UPS system
that exhibits poor efficiency characteristics under low load conditions is to be avoided.
P a g e | 19
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Certain UPS topologies, such as the delta conversion, are better suited for generator supplied systems.
They can produce less harmonic distortion and manage various load levels more efficiently.
When selecting a UPS, the choice between a typical double conversion UPS and a Delta Conversion UPS
can influence the required generator size greatly, frequently by a factor of 3 (meaning: the generator would
have to be 1.75 to 3 times larger for a typical double conversion UPS than a Delta Conversion UPS).
When selecting a generator, base the choice on the kW rating of the generator, but be aware that
generators are designed to operate loads at a lower power factor than 1.0, typically 0.8. This means that the
current and voltage will be slightly out of phase and that the generator must withstand that difference. A
1000 kW generator, designed to operate loads having a power factor of 0.8 will be rated at 1200 kVA.
It is important not to confuse the kVA rating with the true power capacity of the generator, which is always in
kW.
Slide 32: Calculating Estimated Generator Size
Now lets determine the generator size for the data center.
To calculate the correct generator size, you will first need:
The number of kilowatts of the existing power load requiring generator back-up. This is made up of
the critical load, plus the future load, plus the peak power draw, plus the UPS and battery plus the
light load. In our example, the number equates to 2.58 kW.
Next, you need to assess the status of the UPS. For this example the UPS is assumed to be a
fully power factor corrected UPS, so the existing load of 2.58 kW will be multiplied by 1.3, to result
in 3.35 kW.
(If your UPS consists of a traditional double conversion UPS with input from harmonic filters, the existing
load of 2.58 kW will be multiplied by 3.0 which calculate to 7.74 kW.)
P a g e | 20
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
Then, you need the number of kilowatts from the cooling load requiring generator back-up. This
was figured previously, when we calculated the cooling load. In this particular case, we will be
using the number 2.19 kW and multiplying it by a factor of 1.5 to get 3.28 kW.
Finally, add the 3.35 and 3.28 to result in 6.63 kW for the estimated generator size.
Slide 33: Planning for Future Changes
Now that we have reviewed all the elements involved in data center power capacity planning, lets look
ahead. New technologies will be introduced that will impact our power and cooling load calculations in
different ways.
Slide 34: Planning for Future Changes
The basic building block of computer architecture has, for many years, been the CMOS chip. This chip,
which is commonly found in todays servers, has dominated the desktop computer and server market since
the early 1970s.
Over the last three decades, the chip manufacturers have continually improved the CMOS chip, but are now
quickly reaching the theoretical limits of the design. Any further enhancements to the
CMOS chip are difficult to justify financially, because the cost of additional engineering is high and the
increases in horsepower and throughput are negligible.
Slide 35: Planning for Future Changes
This illustration depicts the evolution of the CMOS chip and demonstrates the architectural wall that has
been encountered.
Now, chip manufacturers are introducing new multi-core processor chips. These new chips consume power
in a different manner than the traditional CMOS chip. While CMOS generally consumed power at a steady
rate, multi-core processors power consumption will go up and down depending upon the level of processing
required.
P a g e | 21
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.
P a g e | 22
2013 Schneider Electric. All rights reserved. All trademarks provided are the property of their respective owners.