The document provides an assessment of civil works needed for an animal feed processing plant to begin operations. It estimates that completing small finishing and roofing work on the main factory will cost 950,633 birr, constructing the necessary boiler room will cost 210,000 birr, and improving site works like roads and fencing will cost 650,000 birr, for a total of around 1.81 million birr to allow the plant to begin operating. Additional facilities like offices can be delayed but temporary structures would cost up to 1.2 million birr.

Uploaded by

Haftamu Tekle
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views1 page

Animal Feed Processing Project Proposal

The document provides an assessment of civil works needed for an animal feed processing plant to begin operations. It estimates that completing small finishing and roofing work on the main factory will cost 950,633 birr, constructing the necessary boiler room will cost 210,000 birr, and improving site works like roads and fencing will cost 650,000 birr, for a total of around 1.81 million birr to allow the plant to begin operating. Additional facilities like offices can be delayed but temporary structures would cost up to 1.2 million birr.

Uploaded by

Haftamu Tekle
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Animal Feed Processing Project Proposal for Operational

purpose only
After site visit, the following observations and comments are made with
regard to civil work:
1. The main factory is almost completed and only small finishing and
roofing work is important and estimated to be 950,633.25 Birr to
complete for the operation of the plant. The remaining work can not
obstruct the operation of the plant.
2. The Boiler Room in not constructed and it is important for the
operation of the plant and its civil work cost is estimated at the current
market price about 210,000 Birr for completion of the building.
3. The Site work; the entrance road, the road to the loading and
unloading of the raw material and product inside the plant is important
since the soil is clay soil and its civil work cost is estimated about
650,000 Birr. And the fence work needs to strengthen with gabion
mesh and LTZ steel post.
4. The office, cafeteria, Guard house, Spare part house and power house
shall be constructed at a later stage since it does not affect the
operation of the plant. But temporary office, cafeteria and toilet and
shower can be constructed at a minimum cost (up to 1,200,000.00
Birr) at site if there is no financial constraint.
5. The weighing room is important to be constructed if the weigh bridge
is on site, However there is no weigh bridge and it is not necessary to
construct now.
6. The power house in the design shall be placed on the boiler room
already constructed earlier by modifying and completing the building
and its civil costs 50,000 Birr.