Selection Transformer Based On Load
Selection Transformer Based On Load
Contents
[hide]
1 Introduction
3.1 Step 1 and 2: Collect the AC UPS Loads and Construct Load Profile
Introduction
This calculation deals with the sizing of an AC uninterruptible power supply (UPS) system (i.e.
rectifier, battery bank and inverter). In this calculation, it is assumed that the AC UPS is a
double conversion type with a basic system topology as shown in Figure 1.
An external maintenance bypass switch and galvanic isolation transformers are other
common additions to the basic topology, but these have been omitted from the system as
they are irrelevant for the sizing calculation.
power supplies that provide a reasonably constant voltage and frequency output, independent
of voltage input. This is particularly useful for sensitive electrical equipment on main power
supplies that are prone to voltage / frequency fluctuations or instability.
The AC UPS sizing calculation determines the ratings for the main AC UPS system
components: 1) rectifier, 2) battery banks and 3) inverter.
In some cases, the manufacturer will independently size the system and it is only necessary
to construct the AC UPS load schedule and load profile. However the calculation results will
also help determine the indicative dimensions of the equipment (e.g. size of battery banks)
for preliminary layout purposes.
Autonomy time(s)
Battery type
Calculation Methodology
The calculation procedure has four main steps:
1) Determine and collect the prospective AC UPS loads
2) Construct a load profile and determine the UPS design load (VA) and design energy
(VAh)
3) Calculate the size of the stationary battery (number of cells in series and Ah
capacity)
4) Determine the size of the inverter, rectifier/ charger and static switch
DC output voltage range of the rectifier the rectifier must be able to output the
specified DC link voltage
DC input voltage range of the inverter the DC link voltage must be within the
input voltage tolerances of the inverter. Note that the battery end of discharge
voltage should be within these tolerances.
Number of battery cells required in series this will affect the overall dimensions
and size of the battery rack. If physical space is a constraint, then less batteries in
series would be preferable.
Total DC link current (at full load) this will affect the sizing of the DC cables and
inter-cell battery links. Obviously the smaller the better.
(1)
(2)
where Nmax is the maximum number of battery cells
Nmin is the minimum number of battery cells
Vdc is the nominal battery / DC link voltage (Vdc)
Vi,max is the inverter maximum input voltage tolerance (%)
Vi,min is the inverter minimum input voltage tolerance (%)
Vf is the nominal cell float (or boost) voltage (Vdc)
Veod is the cell end of discharge voltage (Vdc)
The limits are based on the input voltage tolerance of the
inverter. As a maximum, the battery at float voltage (or
boost if applicable) needs to be within the maximum input
voltage range of the inverter. Likewise as a minimum, the
battery at its end of discharge voltage must be within the
minimum input voltage range of the inverter.
Select the number of cells in between these two limits
(more or less arbitrary, though somewhere in the middle
of the min/max values would be appropriate).
12kVA, then the next size unit (e.g. 15kVA UPS) would be
selected.
Inverter Sizing
The inverter must be rated to
continuously supply the UPS
loads. Therefore, the inverter can
be sized using the design AC load
Static Switch
Sizing
Like the inverter,
the static switch
must be rated to
continuously
supply the UPS
loads. Therefore,
the static switch
can be sized using
the design AC load
current (as above
for the inverter
sizing).
Worked
Example