Case Study (3 to 5 months test plan)

Test Deliverable

Responsibility

Completion Time

Test strategy

Project or test manager

5-10 days

Test plan

Test lead

5-10 days

Training sessions to test engineers

10-15 days

Test scenarios or title selection

Business analyst or subject or


domain experts
Test engineer

Test cases documents

Test engineer

5-10 days

Review test cases

Test lead and Test engineer

1-2 days

Receive initial build and Sanity


testing
Test automation (if possible)

Test engineer

1-2 days

Test engineer

10-15 days

Test execution (level1 and level2)

Test engineer

30-40 days

Test reporting

Test engineer and test lead

On going

Status reporting

Test lead

Weekly twice

Test closure and post marten

Test lead and Test engineer

5-7 days

UAT (User Acceptance Testing)

Customer/ model customers with


involvement of developers & testers
Test lead

5-7 days

Sign off

5-10 days

1-2 days