Project Report Cherthalai Ochira NH-47 PKG-I
Project Report Cherthalai Ochira NH-47 PKG-I
Project Report Cherthalai Ochira NH-47 PKG-I
Sl.
Description Page Nos.
No.
1. Introduction 1-1
2. Contract 1-1
1. INTRODUCTION
M/s Intercontinental Consultants and Technocrats Pvt. Ltd., New Delhi have been appointed
as Consultants to carryout the Feasibility Study and preparation of Detailed Project Report
(DPR) for 4/6-laning of Cherthalai to Thiruvananthapuram section of NH-47 in Kerala State
(Package No. NHDP Phase III/DL4/22). The work will be executed on BOT basis.
2. CONTRACT
i) Amount of Consultancy Contract : Rs. 2,21,69,400.00 (Excluding service
tax)
ii) Agreement Date : 08.09.2005
iii) Contract Period : 12 Months
iv) Length : 173 km
3. PROJECT BACKGROUND
National Highways Authority of India has decided to take up the development,
maintenance and management of various National Highway corridors / section under
NHDP Phase-III Programme of 4/6- laning of 10000 km on BOT basis where the
intensity of traffic has increased significantly and their is a requirement for
argumentation of capacity for safe and efficient movement of traffic. The Present
Project study concerned with Cherthalai- Thiruvananthapuram section of NH-47,
(length –172.8km) in Kerala state including the bypasses under construction i.e.
Alappuzha and Kollam and proposed new by pass in Attingal.
NHAI is employer and executing agency for the consultancy services and the
standards of output required from the appointed consultants are international level
both in the terms of quality and adherence of the agreed time schedule.
M/S Intercontinental Consultants & Technocrats Pvt. Ltd., A-8 Green Park, New
Delhi, India have been appointed as Consultants vide letter no NHAI/ BOT/
11012/67/20054 (Pt) ‘H’ /399 dated 18.08.2005 to carry out the Feasibility Study and
Detailed Project Report (DPR) for 4-laning of the section from Cherthalai (Km.
379.100) of NH-47 to Thiruvananthapuram (km 551.900) of NH-47 in the State of
Kerala. The scope and principal objectives of the consultancy services, shall be in
accordance with the Terms of Reference, which is part and parcel of the contract
agreement. The services were commenced with the effect from 23.09.05 and the date
of submission of Detailed Project Report for this Project was 23.09.2006.
The Quality Assurance Plan and Inception Report were submitted vide letter no.
ICT:436:WR:8503 dt. 27.09.05 and ICT:436:WR: 9268 dated 20.10.05, respectively.
Draft Feasibility Study report for Stage-II, from Km 431.000 (Purakkad) to km
551.900 (Kazakuttam Junction) of NH-47 was submitted vide letter no.
ICT:436:WR:1488 dated 13.02.2006.
Present submission Draft Preliminary Project Report (PPR) for Stage-I from Km.
379.100 to Km. 465.000 of NH-47, has been prepared in various chapters
incorporating the suggestions received from time to time from Member Technical
(BOT), CGM (BOT) and GM (BOT).
The total project road length is 168.950 km. It starts from km 379.100 ch. 379.100 of
NH-47 at the junction of Thiurvoor and ends at Kazakuttam junction at km 551.900
ch. 548.05. This stretch of road passes through populated areas such as Cherthalai,
Alappuzha, Kalavoor, Punnapra, Ambalapuzha, Haripad, Kayamkulam,
Krishnapuram, Ochira, Karunagapally, Chavara, Kollam, Umayanallore, Kottiyam,
Pariapally, Vavakavu, Puthiyakavu, Kavanadu, Attingal, Mamam, Pallipuram, and
Mangalpuram. The existing road is two lanes with paved shoulder on either side.
informed about the presentation to be given by ICT consultants to the chief minister of Kerala
and other officers of Kerala Govt. on 8.11.2005 based on the Inception Report submitted by
ICT on 20.10.05.
The CGM, BOT-I, NHAI, inspected the project site on 7th November 2005. The presentation
as per the direction of CGM, BOT-I, NHAI was given by the Team Leader for the above
project on 8.11.2005 in the CM’s conference hall at Thiruvananthapuram. The meeting held
on 08.11.05, was chaired by Honorable Chief Minster of Kerala Govt., presided by Minister
(Works) Kerala Govt., meeting was also attended by Minister (Revenue), Minister (Power),
Minister (Water Recourses and Forest), Vice Chairman (State Planning Board), CGM, BOT-I,
NHAI, Mr. Ashok Wasson; Secretaries of the various department of Kerala Govt. Inspector
General of Police and various Head of the departments of Kerala Govt.
The minutes of the above meetings has been issued by Kerala Govt. on dated 9th Nov. 2005
conforming that in this stretch of road ROW is limited to be 30m, wherein it was intimated
that (NHAI) agreed to start the work of four laning for minimum one stretch by Jan’ 06.
Further in Continuation of the Minutes of the meetings on 8.11.2005 it was communicated by
Secretary PWD Kerala Govt. that the section from Km 379.100 to Km 431.000 will be taken
up in first phase. Subsequently, during discussion on phone between CGM, BOT-I, NHAI and
Executive Director- III of ICT, it was intimated by CGM that minimum stretch of 50 Km of
the project road, i.e. Km 379.100 to Km 431.000, to be considered by ICT as BOT package,
in the first phase, for the preparation of feasibility study and detailed project report.
The Feasibility Study cum Preliminary Project Report, for Stage-I (km 379.100 to km
427.860) was submitted by the consultant, vide letter dated 29.12.05. The comments by the
Client, on the report is received on dated 05.01.06, during the discussion held on Feasibility
Study Cum Preliminary Project Report, at the office of CGM, BOT-I, NHAI. In accordance to
the said comments, Final Feasibility Study Report Cum Preliminary Project Report for Stage-
I (from Km 379.100 to 427.860) was modified, and submitted vide letter no
ICT:436:WR:1363 dated 08.02.2006. For the preparation of Feasibility Study report, for
Stage-II, from km 431.000 to km 551.900, the comments received by Consultant, on Draft
Feasibility Study report for Stage-I was considered, as applicable and found relevant for
Stage-II. The Feasibility Report Study Report for the section km 431.000 to km 551.900 was
submitted vide letter no. ICT:436:WR:1488 dated 13.02.2006.
A review meeting of all the National Highway Projects in Kerala State was conducted by
Honble Minister of Ministry of Shipping, Road Transport & Highways, Govt. of India at
Thiruvananthapura on 17.07.2006, where it was declared this is the only stretch of road where
4-laning work is allowed to be done in 30m ROW as a special case. 4-laning work by NHAI
will be done where ROW of 60m is available.
A meeting was conducted by Member (Technical) & CGM NHAI at
Thiruvananthapuram on 17.07.2006 for this project road and the final decision for
length of packages was taken, which are as follows:
Package-I : Km. 379.100 to Km. 465.000 (ch. 379.100 to ch. 462.700)
Package-II : Km. 465.000 to Km. 551.900 (ch. 462.700 to ch. 548.050)
The Member Technical BOT and GM BOT had visited the project site on 16.12.2006
and had given certain suggestion to be incorporated in draft PPR.
Accordingly the Draft Preliminary Project Report (DPPR) for Package-I has been prepared
incorporating the various decisions taken in the board by Client
The broad features of the Draft Preliminary Project Report submitted earlier for Package-I,
are as under:
i) The Section of the project road in Stage-I shall be from km 379.100 (Thiruvoor Junction)
NH-49 : Bodimettu-Kundannoor
NH-47A : Kundannoor-Willington Island
NH-208 : Kollam-Aryankavu
NH-212 : Kozikode-Muthanga
NH-213 : Palakkad-Kozikode
NH-202 : Kollam-Kumily
Out of 8 National Highways, NH-47 is the busiest highway in the State. NH-47 starts at
Salem in Tamilnadu and passes through Kerala and ends at Kanyakumari in Tamilnadu, the
southern most tip of the country. Important Industrial/Commercial Centre located at this NH-
47 are Salem, Erode. Coimbatore, Palaghat, Thrissur, Erunakulam, Alappuzha, Kollam,
Thiruvananthapuram, Nagarcoil and Kanyakumari. This portion of NH-47 in Kerala is
connected to other parts of the country through the following National Highways.
1. NH-17 from Edappally passing through Calicut, Mangalore, Goa and terminating at
Bombay
2. NH-49 from Ernakulam, passing through Moovattupuzha, Munnar, Madurai and
terminating at Rameswaram in Tamilnadu.
3. NH-208 originates at Kollam and passing through Kundara, Kottarakara, Punaloor,
Thenmala, Aryankavu, Kottavasal, Chenkota and Thani.
3.5 Salient Features
The reconnaissance on the project road section from Cherthalai to Thiruvananthapuram was
carried out during 30th September 2005 to 6th October 2005. Subsequently detail survey has
been conducted for Stage-II (Km 465.000 to Km 551.900) in October 2005 to February 2006.
As per our survey, the observed salient features in km 379.100 to km 465.000 are as under.
1. The project road in Stage-I starts from km 379.100 Alappuzha districts and it ends at km
465.000 in Kollam district.
2. The road passes through Cherthalai, Alappuzha, Kalavoor, Punnapara, Ambalapuzha,
Haripad, Kayamkulam, Krishnapuram & Ochira.
3. The construction of Alappuzha (4-lane) from km 408.00 km to km 415.00 of NH-47, 2-
lane bypass is constructed.
4. Ribbon development has been observed throughout the project road, including by pass
and the improvement of the existing road demands provision of service road for main
road, NH-47 and for by pass.
5. Throughout the project road, the land use outside the existing ROW is Built up in major
portion of the project road. In certain section of project road, Commercial area and
Industrial area exist.
6. The project road is the connecting road between the capital city of Thiruvananthapuram
and the Port city of Cochin in the state of Kerala.
7. Major portion of existing road is in Ground level. In certain section the road is in
embankment
8. Condition of existing embankment, in certain parts of the project road, is not in
conformity to the design specifications as it is completely eroded.
9. The project stretch is having 9 bridges, out of which 6 nos. shall be additional 2-lane
bridges and new bridge.
The 83.6 km long project road shall be having 15 nos. underpasses. Out of which 11
underpasses & 4 are existing 2-lane.
10. The project road shall be having 12 no major junctions.
Carriageway Right Side Left Side Right Of Land Use Land Use
Sl. Chainage
Width Open Area Open Area Way Left Side Right Side
No. (Km)
(M) (M) (M) (M) (M) (M)
1 379.100 27.00 1.40 3.60 32.00 BUA+CA BUA+CA
2 380.100 19.80 8.00 4.20 32.00 BUA BUA
3 381.100 19.80 8.20 4.00 32.00 BUA BUA
4 382.100 19.80 4.50 8.20 32.50 BUA+CA BUA+CA
5 383.100 19.80 6.20 4.60 30.60 BUA+CA BUA+CA
6 384.100 19.80 5.30 5.70 30.80 BUA BUA
7 385.100 19.80 4.00 8.20 32.00 BUA BUA
8 386.000 19.80 3.30 6.90 30.50 BUA BUA
9 387.100 19.80 6.20 5.00 31.00 BUA BUA
10 387.300 10.00 900 5.60 24.60 BUA BUA
11 388.000 11.80 9.00 3.60 24.60 BUA BUA
12 389.000 10.30 5.70 8.40 24.60 BUA BUA
13 390.000 10.00 9.00 5.70 24.70 BUA BUA
14 392.700 10.00 9.00 5.60 24.60 BUA BUA
15 392.000 17.60 6.40 6.50 30.50 BUA BUA
16 393.000 10.00 14.50 6.00 30.50 CA CA
17 394.000 10.00 14.20 6.30 30.50 BUA BUA
18 395.000 10.00 5.60 14.90 30.50 BUA BUA
19 396.000 10.00 14.50 6.00 30.50 BUA BUA
20 397.000 10.00 14.50 6.00 30.50 BUA IA
21 398.000 10.00 13.10 7.40 30.50 BUA+CA BUA
22 399.000 15.30 7.70 7.50 30.50 BUA+CA BUA+CA
23 400.000 10.00 11.30 9.20 30.50 BUA+CA BUA+CA
24 401.000 10.00 7.50 13.00 30.50 BUA BUA
25 402.000 10.00 8.50 12.00 30.50 BUA BUA
26 403.000 10.00 15.00 5.50 30.50 BUA+AG BUA+AG
27 404.000 10.00 9.50 11.00 30.50 BUA BUA
Introduction
Carriageway Right Side Left Side Right Of Land Use Land Use
Sl. Chainage
Width Open Area Open Area Way Left Side Right Side
No. (Km)
(M) (M) (M) (M) (M) (M)
28 405.000 10.00 10.50 10.00 30.50 BUA+IA BUA+IA
29 406.000 10.00 11.00 9.60 30.60 IA IA
30 407.000 10.00 15.60 7.10 32.70 IA+CA IA+CA
31 408.000 10.00 4.95 16.50 31.45 CA CA
32 409.000 10.00 9.30 13.50 32.80 BUA+CA BUA+CA
33 ALAPUZHA BY PASS
34 000.100 7.00 24.50 13.50 45.00 BUA BUA
35 000.200 7.00 24.50 13.50 45.00 BUA BUA
36 000.300 7.00 24.50 13.50 45.00 BUA BUA
37 000.400 7.00 24.50 13.50 45.00 BUA BUA
38 000.500 7.00 24.50 13.50 45.00 BUA BUA
39 000.600 7.00 24.50 13.50 45.00 BUA BUA
40 000.700 7.00 24.50 13.50 45.00 BUA BUA
41 000.800 7.00 24.50 13.50 45.00 BUA BUA
42 000.900 7.00 24.50 13.50 45.00 BUA BUA
43 001.000 7.00 24.50 13.50 45.00 BUA BUA
44 001.100 7.00 24.50 13.50 45.00 BUA BUA
45 001.200 7.00 24.50 13.50 45.00 BUA BUA
46 001.300 7.00 24.50 13.50 45.00 BUA BUA
47 001.400 7.00 24.50 13.50 45.00 BUA BUA
48 001.500 7.00 24.50 13.50 45.00 BUA BUA
49 001.600 7.00 23.50 14.50 45.00 BUA BUA
001.600 to Pavement not
50
006.000 constructed
51 006.100 7.00 24.50 13.50 45.00 BUA BUA
52 006.200 7.00 24.50 13.50 45.00 BUA BUA
53 006.300 7.00 24.50 13.50 45.00 BUA BUA
54 006.400 7.00 24.50 13.50 45.00 BUA BUA
55 006.500 7.00 24.50 13.50 45.00 BUA BUA
56 006.600 7.00 24.50 13.50 45.00 BUA BUA
57 006.700 7.00 24.50 13.50 45.00 BUA BUA
58 006.800 7.00 24.50 13.50 45.00 BUA BUA
59 006.900 7.00 24.50 13.50 45.00 BUA BUA
Carriageway Right Side Left Side Right Of Land Use Land Use
Sl. Chainage
Width Open Area Open Area Way Left Side Right Side
No. (Km)
(M) (M) (M) (M) (M) (M)
Marshy + Marshy +
89 438.000 10.00 15.50 5.00 30.50
BUA BUA
90 439.000 10.00 15.00 5.50 30.50 BUA BUA
91 440.000 10.00 12.50 8.00 30.50 BUA+CA BUA+CA
92 441.000 10.00 8.50 12.00 30.50 BUA BUA
93 442.000 10.00 16.50 4.00 30.50 BUA BUA
94 443.000 9.00 7.50 14.00 30.50 BUA BUA
95 444.000 10.00 7.50 13.00 30.50 BUA+CA BUA+CA
RES+BU RES+BUA
96 445.000 24.00 3.00 3.50 30.50
A+CA +CA
97 446.000 10.00 5.00 15.50 30.50 BUA+CA BUA+CA
98 447.000 10.00 6.00 14.50 30.50 BUA+CA BUA+CA
99 448.000 10.00 7.50 13.00 30.50 BUA+CA BUA+CA
BUA+OP BUA+OPE
100 449.000 10.00 7.00 13.50 30.50
EN AREA N AREA
BUA+OP BUA+OPE
101 450.000 10.00 6.00 14.50 30.50
EN AREA N AREA
BUA+OP BUA+OPE
102 451.000 10.00 15.00 5.50 30.50
EN AREA N AREA
103 452.000 10.00 15.00 5.50 30.50 BUA BUA
104 453.000 10.00 16.00 4.50 30.50 BUA+CA BUA+CA
105 454.000 10.00 10.00 5.50 30.50 BUA BUA
106 455.000 10.00 13.00 7.50 30.50 BUA BUA
107 456.000 10.00 16.00 4.50 30.50 BUA BUA
108 457.000 10.00 15.00 5.50 30.50 BUA+CA BUA+CA
109 458.000 11.50 12.00 7.00 30.50 BUA+CA BUA+CA
110 459.000 10.00 16.00 4.50 30.50 BUA+CA BUA+CA
111 460.000 10.00 7.00 13.50 31.00 BUA BUA
112 461.000 9.50 6.50 14.50 31.00 BUA+CA BUA+CA
113 462.000 10.00 5.00 15.50 30.50 BUA+CA BUA+CA
114 463.000 10.00 5.00 15.50 30.50 BUA+CA BUA+CA
115 464.000 10.00 6.50 14.00 30.50 BUA+CA BUA+CA
116 465.000 10.00 5.50 15.00 30.50 BUA BUA
* 433.500 to 435.000 River / Marshy
3.6 Existing Road
The existing NH-47 is the busiest highway in the State of Kerala. The alignment of the
project road, under Stage-I, i.e. from Km 379.100 (Thiruvoor) to Km 465.000 (Ochira), is
Monthly Progress Report
1 - 10
straight in major portion of the road.
The of project road is in Plain terrain. The horizontal and vertical alignment are generally
satisfactory except in a few reaches. However the Geo-metrics of the existing road is subject
to further review and analysis, in conformity to the proposed design standard of Geo-metrics
and in line with improvement option.
In major portion of the section, width of carriageway is 10m, including 1.5m paved shoulder
on both side of main carriageway. Most of the stretch of road passes through built-up areas,
commercial areas and Industrial areas.
In some urban areas/ city areas the section of project road is locally developed, having 4-lane
divided carriageway. The approximate width of each carriageway is 8.5m –9.0m including
paved shoulder. Width of median varies from 1.5m to 3m.
From ch 408.00 to ch. 415.00 there is a 2-lane bypass at Alappuzha.
3.7 Carriageway Width (Pavement Width)
Carriageway width including Paved shoulder of the existing project road is furnished in Table
2.
Table 2: Carriageway Width
Main Paved
Sl Chainage Length
Road formation Carriageway Shoulder
No (Km) (Km)
(m) (m)
01 379.100-379.500 0.40 4 lane divided carriageway 7.25+8.50 2 x 1.50
02 379.500-387.100 7.60 4 lane divided carriageway 7.25+7.25 2 x 1.50
03 387.100-387.500 0.40 2 lane undivided c’ way 7.30 2 x 1.50
04 392.685-393.200 5.185 2 lane undivided c’ way 7.00 2 x 1.50
05 393.685-393.200 0.515 2 lane undivided c’ way 7.00 2 x 1.20
06 393.200-393.700 0.50 2 lane undivided c’ way 7.00 2 x 1.50
07 393.700-394.700 1.00 2 lane undivided c’ way 7.00 2 x 1.50
08 394.700-397.200 2.50 2 lane undivided c’ way 7.00 2 x 1.50
09 397.200-397.500 0.30 2 lane undivided c’ way 7.00 2 x 1.50
10 397.500-398.000 0.50 4 lane divided carriageway 7.00 2 x 1.50
11 398.000-400.700 2.70 2 lane undivided c’ way 7.00 2 x 1.50
12 400.700-401.200 0.50 2 lane undivided c’ way 7.50 2 x 1.50
13 401.200-408.000 6.80 2 lane undivided c’ way 7.00 2 x 1.50
14 408.000-411.000 3.0 2 lane undivided c’ way 7.00 Nil
15 411.000-412.000 1.00 2 lane undivided c’ way 7.00 Nil
16 412.000-412.500 0.50 2 lane undivided c’ way 7.00 Nil
17 412.500-413.000 0.50 2 lane undivided c’ way 7.00 Nil
18 413.000-414.000 1.00 2 lane undivided c’ way 7.00 Nil
19 414.000-415.000 1.00 2 lane undivided c’ way 7.00 Nil
20 415.000-429.765 14.765 2 lane undivided c’ way 7.00 2 x 1.50
21 429.765-430.264 0.499 4 lane undivided c’ way 2x7 Nil
Introduction
Main Paved
Sl Chainage Length
Road formation Carriageway Shoulder
No (Km) (Km)
(m) (m)
22 430.264-432.706 2.442 2 lane undivided c’ way 7 2x1.5
23 432.706-433.153 0.447 4 lane undivided c’ way 2x6.5 Nil
24 433.153-437.124 3.971 2 lane undivided c’ way 7 2x1.5
25 437.124-437.604 0.480 2 lane undivided c’ way 7 2x2
26 437.604-441.582 3.978 2 lane undivided c’ way 7 2x1.5
27 441.582-442.207 0.625 2 lane undivided c’ way 7 2x1
28 442.207-443.560 1.353 2 lane undivided c’ way 7 2x1.5
29 443.560-444.060 0.500 4 lane undivided c’ way 2x7.5 2x3.0
30 444.060-446.059 1.999 2 lane undivided c’ way 7 2x1.5
31 446.059-446.558 0.499 4 lane undivided c’ way 2x7 2x1.5
32 446.558-456.059 9.501 2 lane undivided c’ way 7 2x1.5
33 456.059-456.559 0.500 2 lane undivided c’ way 7.5 Nil
34 456.559-457.060 0.501 2 lane undivided c’ way 7 2x2.25
35 457.060-459.056 1.996 2 lane undivided c’ way 7 2x1.5
36 459.056-459.920 0.864 2 lane undivided c’ way 7 2x1.25
37 459.920-460.642 0.722 2 lane undivided c’ way 7 2x1.5
38 460.642-461.001 0.360 2 lane undivided c’ way 7 2x2
39 461.002-462.718 1.716 2 lane undivided c’ way 7 2x1.5
Total (km) 83.618
Height of
Total Length
Embankment in Stretch
(Km)
(m)
< = 0.50 418.5-419.0; 422.0-422.5; 1.00
380.0-381.0; 385.5-386.0; 386.5-387.1; 421.0-
> 0.50- < = 1.00 4.10
421.5; 422.5-423.0; 426.0-427.0;
381.0-383.0; 385.0-385.5; 386.0-386.5; 401.0-
> 1.00- <= 2.00 5.00
401.5; 421.5-422.0; 427.0-428.0
> 2.00- <= 3.00 424.0-424.5 0.50
Total 9.60
3.11 Junctions
The details of existing junction are given in Table 5.
Table 5 : Existing Major Junctions
Sl. Design Status of
Side Description Category
No. Chainage Cross Road
X-Ray Jn. Road to
1 390.550 LHS Cherthalai town in East MDR
direction
Thiruvala Jn. Road to
2 394.800 RHS ODR
Thiruvitha in East direction
S.L. Puram Jn. Road to
3 397.800 LHS Morhomma Village in East MDR
direction
Kalavoor Jn. Road to
Cross Monachery in East (left)
4 402.100 MDR
Road and to Kalur village in
West (Right)
Alappuzha Bypass (North
5 408.500 LHS end Jn.) Alappuzha bypass NH-47
in west direction
Alappuzha bypass (South
6 414.500 LHS NH-47
end Jn.)
Ambalapuzha Jn. Road to
7 424.380 LHS Thiruvalla town in East SH-12
direction
8 432.875 RHS Thottapally bride south jn. MDR
Introduction
4.1 Corrugation
allowed to become severe. The Consultant has not observed any measurable
corrugation, in the project road.
4.2 Rutting
Rutting is a longitudinal depression or groove in the wheel tracks. The ruts are usually
of the width of a wheel path. Swerving from a rutted wheel path at high speed can be
dangerous.
The depth of rut is measured by keeping the straight edge placing transversely across
the wheel tracks and using graduated measuring wedge. The mean value for the
wheel tracks is worked out.
Potholes are bowl shaped holes of varying sizes in a surface layer or extended into
base layer, caused by the localized disintegrations of the usually thin bituminous
surfacing material.
The area affected by major potholes was measured and the percentage area was
worked out.
4.4 Ravelling
4.5 Cracking
A common defect in bituminous surface is the formation of cracks. The area affected by
cracking was measured by encircling and the extent of cracking was assessed visually at
500m intervals or the places of defects.
4.6 Patching
During field inspection, patching was observed.
4.7 Edge Breaking
Irregular breakage of pavement edge was noticed in some portion of road.
4.8 Edge Drop
The edge drop is the vertical difference in levels between the edge of the carriageway and
abutting shoulders.
4.9 Inventory of all Road Side Facilities
The details of the road side amenities and facilities like school, dhabas, telephone booths, bus
stop, hospital, hotel, repair shops etc.
5. ROAD MEASUREMENT DATA ACQUISITION SYSTEM (ROMDAS)
ROMDAS works as a response type road roughness measuring system. The system has been
calibrated by recording its response (RAW values) and comparing the same with that of a
ROMDAS Z-250 Reference Profiler. ROMDAS Z-250 reference Profiler has been developed
by Data Collection Ltd (DCL). The Calibration sections called standard sections have been
divided into a number of smaller subsections of 100m lengths each. A total of 12 such
“standard” points have been collected consisting of 400 lengths each. “Standard” sections
vary from “very smooth” to “very poor” and at each section the Z-250 has been run along the
selected lane and roughness has been noted in terms of IRI (m/km).
ROMDAS vehicle has been run at Constant Speed of 32+2 km/hr on the “standard” section
along the same selected lanes and ROMDAS response (RAW values) have been recorded.
Using the software-NLREG the calibration equation has been developed between ROMDAS
Response (RAW/km) and IRI (m/km).
Calibration equation at 32km/hr:
IRI Roughness values have been converted into Bump Integrator Index (BI) by means
of the equation given in HDM-III:
Introduction
Field data collected and analyzed subsequently along each lane of the stretch have
been expressed in terms of IRI (m/km) and BI (mm/km) and have been presented in
both tabular and graphical forms in the following pages.
The following guidelines for road roughness in terms of IRI (m/km) and BI (mm/km)
for different surface types have been considered for assessing the road condition.
As per World Bank Technical Publication No. 46 the minimum and maximum
range of BI and IRI for new pavements is as follows, but the type of surface has
not been mentioned.
5.4 Observations
Based on the Roughness Measurement Studies the km-wise average roughness in IRI
and BI Units of various lanes have been summarized. The detailed 100m-wise
Roughness Measurement Studies have been provided.
Total
Proposed Proposed Proposed
Sl. Design Type of length of
structural Structure span
No. Chainage Underpass the
configuration type arrangement
structure
New 4-lane RCC box
1 384.025 Vehicular 1x15.0x5.0 19.00
structure structure
RCC T
New 4-lane
2 389.130 Vehicular beam 1x15.0x5.0 19.00
structure
structure
New 4-lane RCC box
3 395.650 Vehicular 1x15.0x5.0 19.00
structure structure
New 4-lane RCC box
4 402.090 Vehicular 1x15.0x5.0 19.00
structure structure
New 2-lane RCC box
5 409.565 Vehicular 1x8.0x4.5 12.00
structure structure
New 2-lane RCC box
6 409.685 Vehicular 1x8.0x4.5 12.00
structure structure
New 2-lane RCC box
7 413.600 Vehicular 1x8.0x4.5 12.00
structure structure
8 418.200 Pedestrian New 4-lane RCC box 1x15.0x3.5 19.00
Introduction
Total
Proposed Proposed Proposed
Sl. Design Type of length of
structural Structure span
No. Chainage Underpass the
configuration type arrangement
structure
structure structure
New 4 RCC box
9 433.100 Vehicular 1x15x5.0 19.00
structure structure
New 4 RCC box
10 439.000 Pedestrian 1x15x3.5 19.00
structure structure
Existing
New 4 RCC box
11 441.765 Underpass 6x5 12.00
structure structure
(6x5)
New 4 RCC box
12 442.900 Vehicular 1x15x5 19.00
structure structure
New 4 RCC box
13 445.900 Vehicular 1x15x5 19.00
structure structure
New 4 RCC box
14 456.265 Vehicular 1x15x5 19.00
structure structure
New 4 RCC box
15 461.600 Vehicular 1x15x5 19.00
structure structure
Due to constraint in available land width, the approach road towards the underpass shall be
restrained by providing RE wall on both side. The proposed vehicular underpass shall have
clear opening as 5.5m x 15.0m, and pedestrian underpass shall have clear opening of 3.5m x
12.0m in main road.
7.2 Median Opening
Median opening shall be provided at approximately 2km interval along the project highway.
Length of opening shall be 30m. On the two sides of median opening, steel railing is proposed
to be provided on precast blocks. In between service road and main carriageway, to restrict
the pedestrian crossing through the designated road marking only. The details of median
opening are summarized in Table 9.
Table 9 : Details of Median Opening
Sl. No. Design Chainage Sl. No. Design Chainage
1 381.165 21 425.000
2 383.100 22 426.900
3 385.500 23 428.400
4 388.500 24 430.400
5 391.500 25 432.000
6 392.150 26 434.000
7 393.300 27 435.600
8 396.300 28 437.400
9 397.500 29 439.400
10 399.500 30 441.200
9. HYDROLOGY OF BRIDGES
9.1 General
• This section deals with Hydrological and Hydraulic study of Bridges from Existing Km
379.100 to km 465.000 of NH-47.
• There are 4 existing Bridges in the existing road stretch. One number bypass has been
proposed to be bypass Alappuzha town.
• The hydrological study, computations and methodology adopted for discharge and other
hydrological computations have been discussed in this report.
9.2 Study Objective
These investigations are primarily intended for evaluating the adequacy of waterways of the
existing bridges for the design flood flow. The hydrological study has been done based on the
field investigations and survey data. This report describes the method of evaluation of
performance of existing bridges on the existing highways for widening proposals, and design
discharges, waterway required, scour depth and afflux etc for the new bridges.
10. BRIDGES AND STRUCTURES
10.1 General
Introduction
In all there are 14 nos. bridges and structures existing in the stretch from km 379.100 to km
465.000 of NH-47 as below in Table 11:
Table 11: Details of Structures
Partially completed
Description Main NH Total
Alappuzha Bypass
Major bridges 435/1 ---- 1
383/1, 386/1, 389.90, 435/2, 437/1,
Minor bridges ---- 8
444/1, 458/1, 462/1
ROBs 424/1 ---- 1
Ch. 409.565, ch.
Underpasses 444/2 4
409.685, ch. 413.600
TOTAL 14
The bridge at Thotapally is 366m long with 40 spans of 9.14m each having RC beam
and slab type superstructure resting over stone masonry wall type substructure
supported on piles. The bridge has 6.7 m wide carriageway which is less than 7.5m
required for a 2-lane bridge. Further extensive repairs in the form of gunniting to
superstructure and substructure have been carried out by the PWD. In view of the
inadequate carriageway width, and poor structural condition, the bridge is proposed to
be replaced
Generally all of the bridges have deck level at considerable height above ground.
There is no report of any submergence. Further the bridges are across lake, canals
and rivers having very little velocity due to being near to sea. Therefore, no adverse
effect of water current has been noted and the bridges appear to have adequate
waterway.
Thus only Thotappally bridge no. 435/1 which is old, weak and narrow, is proposed to
be replaced and all of the remaining bridges are proposed to be retained.
Out of exiting 14 bridges/structures 2 bridges viz bridge no. 383/1 and 386/1 are 4-
lane facility. Out of remaining 12 structures only one bridge namely Br. No. 435/1 is
proposed to be replaced and remaining 11 bridges/structures are proposed to be
Introduction
retained.
In case of Alappuzha bypass, the alignment crosses railway line at two locations,
where 4-lane ROBs comprising 2 units of 2-lane capacity each are proposed.
10.5 Underpass
Thus in the project stretch a total of 27 bridges / structures have been proposed as
detailed below Table 13.
Alappuzha
Main NH
Description Bypass Total Remarks
Major Minor Major Minor
* four
6 (Addl. 2 laning
1 (4L) 7
Bridges Lane) - - already
---- 2*
(2 *) (4 lane) carried
out
Underpass 1 (2-lane)
3 (2-lane) 12
(vehicular) 8 (4lane)
Underpass
3 (4-lane) ----- 3
(pedestrian)
Total 27
Location
Median
Because of habitation developed all along the National Highway, there is scarcity of
land. Accordingly the new bridges are proposed to be constructed adjacent to existing
bridges. 4.5m wide median is proposed in the entire length except the reaches where
elevated road has been proposed.
Span Arrangement
In case of additional two lane bridges proposed to be constructed by the side of the
existing bridges span lengths have been proposed equal to or in multiples of those of
existing bridge so that the new piers are inline with the existing ones to achieve
streamline flow. Where altogether new bridges are proposed span lengths have been
chosen from practical considerations.
There is only 30m wide ROW available which is proposed to be widened to 45m. In
this width 4-lane road alongwith service roads on either side have been proposed.
Since traffic projections indicate need for 6-laning of road within 10 years of
completion of 4-laning, the bridges have been proposed with deck configuration
shown in NHAI’s circular no NHAI/PH-II/NHDP/ADB/GM (NS)-1/108 dated
11.8.2004 i.e. each new unit will have cross section of a 2-lane bridge with scope for
widening to 3-lane in future. In the case of major bridges, 8-lane bridges are proposed
to account for the service road traffic as well.
Type of Superstructure
Types of superstructure have been proposed as per site requirement and ease of
construction. Normally following types of superstructure have been adopted :-
span length
Introduction
Loading
Since the proposed deck configuration for each 2-lane bridge unit has scope for widening to
3-lane capacity in future, each unit shall be designed for 3-lanes of IRC Class “A” or one lane
of IRC class 70R +one lane of IRC Class-A loading whichever governs.
Seismic Force
As per modified seismic map of India the project road lies in Seismic Zone - III. According to
modified clause 222.1, of IRC 6-2000, in Seismic Zone - III, only those bridges having span
length more than 15m or bridge length more than 60m are to be designed for seismic force.
Therefore seismic force shall be considered in the design of bridges according to their overall
length / span length.
Bearings
For RC Solid slab type superstructure : Tar paper
For spans > 10m <20m : Elastomeric bearings
For spans >20m : POT bearings
Crash Barriers
Crash barriers have been proposed for all new bridges as per provision of IRC:5-1998.
Expansion Joints
Filler / Strip seal type expansion joints have been proposed.
Wearing Coat
65mm thick wearing course comprising of 50mm thick bituminous concrete (laid in 2 layers
of 25mm thick each) laid over 15mm thick layer of mastic asphalt, has been proposed in
accordance with section 500 of MOSRTH specifications.
Design Concrete Strength
For Foundations M-35
Severe exposure condition
For RCC Substructure M-35 considered as Arabian Sea is very
For RCC superstructure M-35 near.
- Foundations 2.5m
Protective Coating
Since the proposed bridges / structures are in proximity of Arabian sea it is proposed
to provide protective coating to all exposed concrete surfaces.
Design Standards
Designs for various components of bridges shall be carried out as per following IRC
codes of practice:
(ii) Foundations
IRC:6-2000
IRC:21-2000
IRC:78-2000
(iii) Substructure
IRC:6-2000
IRC:21-2000
IRC:78-2000
(iv) Superstructure
IRC:21-2000
IRC:18-2000
IRC:22-1986
IRC:SP:64-2005
(v) Bearings
IRC:83-1987 (Part-II) for Elasomeric bearings (with amendments in 2000)
IRC:83-2000 (Part-III) for POT/PTFE bearings
(vi) Expansion Joints
IRC: SP-69
(vii) Protection Works
IRC: 89-1997
Based on the above stipulations General Arrangement Drawings for all of the bridges and
structures in Package-I have been prepared.
10.7 Right of Way (ROW)
On the insistence of the State Govt. of Kerala during the meeting taken by the Hon’ble Chief
Minister at Thiruvananthapuram on 08.11.2005, NHAI/ICT were constrained to develop the
X-sections for 4 laning within the existing Right of Way (ROW) width of 30m. This had the
following inherent drawbacks:
i) Non availability of space for 4.5m wide Median as per Ministry’s / NHAI guidelines
ii) Non Provision of 1m wide earthen shoulders on both sides of the 4-lane road
iii) Only 5.5m width of service roads including 1.5m width for side drain and 0.5m for utility
services
iv) No space for stacking lane for turning traffic in medium opening for safety
v) Non availability of adequate space for utility services
vi) No space for bus bays, bus shelters, parking areas etc.
vii) No scope of future expansion
11. REPORTS SUBMITTED
Feasibility Report of the project was submitted to NHAI on 29.12.2005.
Draft Preliminary Project Report for Package I i.e. km 379.100 to km 465.000 was submitted
to NHAI on 20.01.2007. These reports were based on the earlier decision of 4 laning in the
existing 30m Right of way (ROW) width.
• Due to change in ROW width from 30m to 45m new cross-sections for 4-laning
were developed and sent to NHAI for approval on 31.05.2007 and 06.07.2007.
• NHAI was informed that the change would involve additional inputs of survey,
extensive Land Acquisition Plans, Resettlement Plans, Environmental
Management Plans and preparation of entire design and drawings afresh.
• Case for additional cost of Rs. 94.31 Lakhs (excluding service tax) as Variation
was submitted to NHAI vide ICT letter no. ICT:436:TL:4447 dated 31.05.2007.
• NHAI was also informed on 31.05.2007 that fresh exercise would require
Extension of Time (EOT) of 8 months for preparing DPR.
13. PRESENT STATUS
• Approval in principle for the modified 4-lane cross-section has been received
from NHAI vide their letter no. NHAI/BOT/11012/67/2005 dated 15.11.2007.
• Extension of Time (EOT) upto 31st Jan 2008 has been approved by NHAI vide
their letter of 15.11.2007 referred to above.
• Meeting of the variation committee has been held in NHAI on 14.03.2008.
Approval for additional cost as variation is awaited from NHAI.
14. SITE VISIT
A site visit was undertaken by Team Leader accompanied by Senior Surveyor from
4th December 2007 to 10th December 2007. After the approval of the modified X-
sections of 4 laning by NHAI, widening schedule was finalized keeping in view the
ground situation. The abstract of widening is indicated as under:
* Bypass at Alappuzha
Based on above, the modified alignment plans have been prepared and sent to NHAI
Introduction
15. PACKAGING
16.1 General
The following necessary traffic surveys have been carried out as stipulated in the terms of
reference in order to obtain data for efficient design, reliable economic analysis and to depict
the reality scenarios.
• Classified Traffic Volume counts for seven days.
• Intersection Turning Movement Surveys for 24 hours.
• Origin - Destination and Commodity Movement Surveys for 24 hours
• Axle load surveys for 2 normal days (24 hours)
• Speed and Delay surveys
• Toll rate surveys
• Pedestrian and animal cross traffic counts
• Truck terminal surveys
To get consequence, to the above requirements, the project road was considered for:
These above features facilitated a framework for carrying out the necessary count surveys in
accordance with the guidelines specified in IRC codes of practice. The various survey
locations have been selected with careful assessment of the traffic characteristics including
entry and exit point along the NH 47 corridor. These points were further refined jointly at site
as required by the NHAI. The final locations of various surveys were carried out are furnished
in Fig 1. The approach and methodology employed for carrying out the traffic surveys in the
Monthly Progress Report
1 - 36
project is described in the following paragraphs.
16.2 Classified Traffic Volume Counts
Manual traffic counts have been conducted between November 8, 2005 and December 3,
2005 The counts have been carried out in both directions, for successive 15-minute periods,
24 hours a day for 7 consecutive days. Table 15 provides a summary of the Average Daily
Traffic (ADT). Various types of vehicles were converted into PCU using the respective PCU
factors.
Introduction
Location of Survey
Non Motorized
Chainage (km)
With Trailer
ADT (PCU)
3-Wheelere
Station No.
2-Wheeler
Vehicle
Trucks
Car
VC1 380 Thuravoor 9133 1605 5889 1800 2415 1776 107 1488 29375
VC2 419 Punnapra 4806 1657 7416 1704 1805 1224 66 2461 23228
VC3 459 Kayamkulam 5052 2294 7987 1617 1450 1258 71 2070 35361
Homogeneous section
Based on the character, composition, traffic movements at different intersections and from the
results of the traffic volume counts, two homogenous sections are considered for the stretch
from km 379.100 to km 429.000 which are as follows:
• Section - I: Km 379.100 to Km 408.00 (start of Alappuzha Bypass)
• Section - II: Km 408.00 to Km 435.00
• Section - III : Km 435.00 to Km 465.00
The ADT percentage composition of the traffic Volume counts at each location is given in
Table 16.
Table 16: Average Percentage Composition of Traffic
Percentage Composition
Chainage (Km)
Mini Buses)
Buses (incl.
Station
Wheelers
Vehicles
Vehicles
No.
Cars
survey crew was organized into 3 groups by 8-hour shifts with sufficient enumerators in each
traffic direction as well as in groups. Classroom training were given to the enumerators in
order to get acquainted the work and in the use of standard interview sheets. Police help was
sought to ensure smooth flow of traffic and stoppage of randomly selected vehicles. Engineers
supervised the whole survey activities. The sample size varied about from 10% to 15% for
different types of vehicles. The results of the survey are in the process of calculation and will
be furnished in the feasibility report later.
16.4 Axle Load Surveys
Generally a tendency on the part of commercial vehicle operators to overload goods vehicles
exists in India despite legislation and the existence of an enforcement agency. The Axle load
survey provides necessary data to enable the assessment of the damaging effect of these
heavily loaded vehicles. The survey was carried out for 2 days for 24-hour period on each day
using the Axle weighing pad as stipulated in the terms of reference. The locations where axle
load survey is carried out are given in Table 17.
Station
Chainage (Km) Name / Reference Location
No.
1 431.000 Ambalapuzha
The traffic census and the axle load surveys have been conducted simultaneously. In traffic
census surveys, all types of vehicles traveling in both directions have been counted
throughout the axle load survey period to provide the actual break down of the traffic
composition at the particular location. It was not possible to weigh all the commercial
vehicles because of the requirement of stopping a vehicle for weighing, nevertheless, a
attempt was made to capture large amount of commercial vehicles passing through survey site
to know the pattern of loading. About 10% of commercial vehicles have been weighed in the
24 hours duration.
The major proportion of the total number of vehicles selected in this survey comprised of two
axle trucks and light goods vehicles because of its presence in high percentage in the total
traffic flow. The Vehicle Damage Factor (VDF) is an important index factor in characterizing
the traffic loading for a road. It is a multiplier for converting the number of commercial
vehicles of different axle loads, to the number of standard Axle load repetitions. The VDF
calculated for all commercial vehicles on the basis of Axle load survey carried out on the
project road is given in Table 18.
Table 18: Vehicle Damage Factor (VDF) for Commercial Vehicles
Chainage
Location Type of Vehicle VDF
(Km)
2 – Axle truck 4.712
3 – Axle truck 4.873
Ambalappuzha 430.00
Multi – Axle vehicle 2.219
LGV 0.841
Cross pedestrian counts have been carried out at designated locations of all major
intersections where required along the project road. The analysed survey results did
not signify the requirements for separate pedestrian facilities at these intersections.
The OD survey analysis and survey of truck parking facilities did not reveal the
requirements of truck parking terminal on the section of the project road.
Approach
The returns from transport sector depend on the agricultural and industries economy of the
country. This is especially true in the case of developing nations, where transport is the
catalyst for all round development and one of the basic infrastructures. When the capital
available is scarce for such and has competing demands, the investments in a road project
require carefulness in planning and keeping in view not only the present demand but also the
requirements for a reasonable period in future. Thus the need for estimating the future traffic
as accurate is mandatory either for the construction of a new facility or for the improvement
of existing facilities. The accurate estimate of future traffic projection will significantly
influence the engineering design and in the decision to take of the project or not.
Introduction
Year
Mode Beyond
2007 2012 2017 2022
2022
Cars 1.20 1.35 1.22 1.10 0.99
Buses 1.50 1.67 1.50 1.35 1.22
Trucks 0.80 0.86 0.77 0.70 0.63
Motorized two wheelers 1.80 1.97 1.77 1.59 1.43
3 wheeler 1.10 1.26 1.19 1.02 0.92
Growth in population and per-capita income are the principal parameters for forecasting
future passenger traffic demands. The following formula combines these parameters with the
passenger vehicle elasticity:
Annual growth rate = [(1 + P/100) (1 + I/100) – 1] x 100 x E
Where:
P = annual population growth rate
I = annual per-capita income growth rate
E = elasticity coefficient.
For goods vehicles, the principal parameters are agriculture, mining, industry, trade and
commerce, which are combined and averaged before applying the elasticity coefficient to
obtain the growth rate.
Future patterns of change in various parameters such as population, NSDP, primary and
secondary industries, trade and commerce, fuel consumption and etc could only be estimated
with limited accuracy. Three scenarios related to future socio-economic trends in the form of
‘most probable’, ‘pessimistic’ and ‘optimistic’ are thus adopted for comparison with the
growth rates determined from the analyses of category wise growth of motor vehicles in
Kerala state. The growth rate obtained from elasticity method is named as ‘most probable’.
Other two considerations of 10% lower and 10% higher growth rates in comparison with most
probable case are named as ‘pessimistic’ and ‘optimistic’ respectively. The growth rates
developed for each of these scenarios are summarised in Table 22.
Year
Mode Beyond
2007 2012 2017 2022 2027
2027
Scenario-1: Projected Most Probable Traffic Growth Rate
Cars 7.1 7.8 7.0 6.3 5.7 5.7
Buses 8.7 9.6 8.7 7.8 7.0 7.0
Trucks 4.5 4.9 4.5 4.0 3.6 3.6
Motorised Two-
10.3 11.3 10.2 9.2 8.3 8.3
wheelers
3 wheeler 6.6 7.3 6.5 5.9 5.3 5.3
Scenario-2: Projected Pessimistic Traffic Growth Rate
Cars 6.4 7.0 6.3 5.7 5.1 5.1
Buses 7.9 8.7 7.8 7.0 6.3 6.3
Trucks 4.0 4.5 4.0 3.6 3.2 3.2
Motorised Two-
9.3 10.2 9.2 8.3 7.4 7.4
wheelers
3 wheeler 5.9 6.5 5.9 5.3 4.8 4.8
Scenario-3: Projected Optimistic Traffic Growth Rate
Cars 7.8 8.6 7.7 6.9 6.2 6.2
Buses 9.6 10.6 9.5 8.6 7.7 7.7
Trucks 4.9 5.4 4.9 4.4 4.0 4.0
Motorised Two-
11.3 12.5 11.2 10.1 9.1 9.1
wheelers
3 wheeler 7.3 8.0 7.2 6.5 5.8 5.8
These growth rates have been calculated with detailed study of economic indicators of Kerala
state and from the guidelines of World Bank for the calculation of elasticity for different
vehicles. The above growth rates have been used for the economic evaluation of the project
road.
16.12 Traffic Projections
The traffic projections based on category wise growth of motor vehicles in Kerala state have
been computed. Of the 3 scenarios developed by the Elasticity of transport demand approach,
the most probable scenario give the closest comparison with the projections computed by
category wise growth of motor vehicles in Kerala, thus the same have been adopted for design
and economic analysis.
Comparison of different method of forecast
The traffic fore cast comparison of different method is given in Tabled 23. The most probable
case gives a reasonable comparison with category wise growth of vehicles. The elasticity
demand takes into account of different socio – economic profile factors and thus the future
growth may not perfectly depicted .In such a circumstances, the traffic forecast computed by
most probable method have been adopted for design and economic analysis.
Introduction
16.13 Inference
Two scenarios were examined here namely
• Do nothing option
• Widening the existing road to four/ six lane capacity
The impact of speed for various links is considered in this option. The speed flow analysis
using the following Road User Cost Study equations is carried out. Substituting the normal
growth of traffic for the required period the average speed of different modes with base year
flow are computed and the details are furnished in Table 24
Two lane carriageway speed equations (with earthen shoulders)
Vc = 85.45 – 0.017Q
Vb = 66.79 – 0.013Q
Vt = 58.96 – 0.008Q
Vtw = 51.58 – 0.007Q
Four lane carriageway speed equations (with paved shoulders)
Vc = 92.79 – 0.0075Q
Vb = 74.48 – 0.0042Q
Vt = 63.25 – 0.0047Q
Vtw = 57.21 – 0.0062Q
Where,
Q: Traffic flow in PCU
Vc, Vb, Vt, and Vtw: Speeds of cars, buses, trucks and motorized two wheelers respectively.
Table 24 Speed flow analysis at km 380.000 & 419.000
The entire project road stretch passes through plain terrain barring about 15 km stretch which
is between plain and rolling. Thus Plain terrain with curvature (degree/kilometer) 0 to 50 is
considered. Design service volume as reveal in IRC 64: 1990, recommend for two-lane road
that has 7 m wide blacktop carriageway with reasonably good earthen shoulders with peak
hour traffic in the range of 8% and level of service ‘B’ is 15000 PCU/day and for four lane
dual roads is 40000 PCU/day. From the projected traffic different carriageway requirement
options are considered and the details are given Table 25.
Table 25: Carriageway Requirement Options
Km 380.000 Km 419.000
Sl. No. Year
PCU Requirement PCU Requirement
1 2005 29375 4L -PS 23228 4L -PS
2 2006 31451 24879
3 2007 33695 26672
From the above table, it is obvious that the project road is already exceeded the capacity
requirements of two lane. The peak hour factors obtained from count stations at km 380.00
and at km 419.00 are 6.72% and 6.29% respectively, which are comparatively lower than the
peak hour factors of 8%, which are referred in the IRC guidelines. Thus about 20% capacity
may be increased and accordingly the requirement and go beyond of four laning facilities are
calculated.
Introduction
It is evident from the traffic studies that the project road from km 379.100 to km 431.000 is
already exceed its capacity and warrant four lane facilities right at the moment.
16.14 Design for Major Road Junction
Four major road junctions exist on this stretch of the project road. Turning movement count
for consecutive15 minute’s intervals for a period of 24 hours are carried out. The base year
flow for the year 2005 and predicted peak hour flow in the years 2017 and 2027 for all these
junctions are exemplified in Table 26.
Table 26: Predicted Peak flow at major junction
Highway grade separators are envisaged at intersection of divided rural road if the ADT (fast
vehicles only) on the cross road within the next 5 years is likely to exceed 5000 and otherwise
the need for such facilities could be kept in view for future consideration/construction. An
interchange may be justified when an at-grade intersection fails to handle the volume of
traffic resulting in serious congestion and frequent choking of the intersection. This situation
may arise when the total traffic of all the arms of the intersection is in excess of 10,000 PCU/
hours. These above cases do not arise in none of the four junctions till the year 2027. In the
year 2027, the junction at km 392.100 marginally exceeds the limit. The project road is
bypassing the Alappuzha town thus the junction at km 411.200 too does not considered for
such facilities. Based on the peak hour flow the at-grade junctions will be designed as per
MOSRT &H standards. The type of intersections proposed are given in Table 27.
Table 27: Types of intersections proposed.
Design CBR : 8%
Pavement Composition
New Pavement:
Bituminous Concrete : 50mm
Dense Bituminous Macadam (DBM) : 140mm
Wet Mix Macadam (WMM) : 250mm
Granular Subbase (GSB) : 200mm
Overlay:
Bituminous Concrete : 50mm
Dense Bituminous Macadam (DBM) : 140mm
Profile Correction with DBM : 50mm
Service Road:
Bituminous Concrete : 40mm
Dense Bituminous Macadam (DBM) : 60mm
Wet Mix Macadam (WMM) : 250mm
Granular Subbase (GSB) : 200mm
19.1 General
Improvement of surface connectivity through construction of new roads or strengthening/
upgradation of existing roads is generally undertaken to improve the economic and social
welfare of those using the road or served by it. The need for faster growth in the economic
and social sectors has propelled the Government of India to invest liberally in infrastructure
development program and strengthening the road network of the country has got a focus.
There is a realization that improved connectivity goes a long way in integrating the markets in
the country and providing a level playing field for the manufacturers and producers located in
different regions. The project of 4-laning of Cherthalai Thiruvananthapuram section (km
379.10 to km551.90) of National Highway NO. 47 in the state of Kerala is a part of the
National Highway Development Program. The project involves rehabilitation and upgrading
of the existing 2-lane road and widening it to 4-lane dual carriageway. The project road has
been divided into two packages. Package-I starts at Cherthalai (km 379.100) and ends at
Ochira (km 465.000) is primarily confined within the district of Alappuzha known all over the
world for its backwaters and the popular boat race and terminates after entering the Kollam
district a center for cashew processing industries. Kollam has also the second largest estuary
of Kerala in Ashtamudi lake which in the recent past has been declared as a Ramsar site.
Introduction
Monitoring of environmental quality during construction and during operation reflects the
success of implementation of the mitigation measures. Monitoring will be conducted by the
project authority with the help of an independent monitoring organisation Monitoring
parameters, locations and frequency for air, water, noise quality have been suggested.
Monitoring of survival rates of plantations also has been suggested.
A budgetary estimate of Rs. 500.00 lacs for environmental management activities has been
prepared. This includes cost of mitigation measures, enhancement and monitoring.
Environmental mitigation measures, which are part of engineering activities such as slope
stabilization, sediment/ silt control, provision of cross-drainage etc. have not been included in
this estimate.
20.1 General
The Resettlement Action Plan (RAP) is based on social impact assessment of the
potentially affected owners of houses, shops, hotels, tea stalls, business and
agricultural land including impact on local community infrastructures due to widening
of National Highway – 47. In view of the human involved, the possible social
impacts have been integrated into the improved alternative engineering designs to
minimize resettlement and forced displacement. This task has been achieved by
adopting road engineering techniques in terms of the provision of Alappuzha bypass,
realignment, widening and reduction in median width at congested settlements. The
RAP provides details to implement provisions of the policy framework, including
institutional arrangements and budgets based on enumeration of project-affected
people with entitlements under the framework.
20.2 Budget
The estimated budget for R&R is Rs.344.70 crores including land acquisition. The
item wise detailed indicative budget of the R&R component of the project will be
presented in the stand along RAP document, which will be sent along with the revised
PPR.
The estimated cost (civil cost) of this package based on 2006-07 rates works out to
Rs. 956.28 crores. This has been updated to Rs. 1054.30 crores after adding
escalation for 2 years @ 5% per annum i.e. Rs. 12.61 crores per km (Total Length =
Km 83.60). After adding contingency and supervision charges and cost of shifting
utility services, environmental mitigation measures, land acquisition and resettlement
and rehabilitation charges, the cost comes to Rs. 1600.00 crores i.e. Rs. 19.14 crores
per km.
22.1 Introduction
This chapter presents the economic analysis for the project road section from km 379.100 to
km 465.000 of NH-47 in the state of Kerala. The economic analysis is carried out within the
broad framework of social cost-benefit analysis. The appraisal compares the total transport
costs in situations of “with” the project and “without” the project alternatively called the
“base case” or the “do minimum case” for the project highway.
Introduction
The underlying objective of economic analysis is to maximize the returns on the investment.
The concept behind the economic appraisal of the project is that if it is implemented, the
resulting benefits will be the decreased road users costs when compared to the costs of the
‘base’ situation.
The total transport costs comprise two basic components (Table28), viz. road supplier costs
and road user costs.
Table 28: Total Transport Costs
Road Supplier Costs Road User Costs
Construction Costs Vehicle Operating Costs (VOC)
Maintenance Costs Travel Time Costs
Replacement Costs: Costs of Environmental Impact
Mitigation Measures, Costs of Rehabilitation and
Resettlement (R&R) measures
22.2 Methodology
All costs considered in the analysis are valued in money terms at the market prices. For
economic analysis, these are expressed as economic costs for avoiding distortions in the
prices of inputs such as labour, materials, equipment, and machinery i.e. market prices net of
transfer payments such as taxes and subsidies arising due to market imperfections. The
transport costs are estimated for the ‘Do nothing’ and ‘With Project’ scenarios. The reduction
in these costs under ‘With Project’ scenario, alternatively called the savings, are treated as
economic benefits corresponding to the incremental investment estimated over the life of
project.
The economic appraisal is carried out by using the ‘Highway Development and Management
(HDM 4) Model’. The model is used to generate cash flow streams of VOCs and travel time
costs to compute the net economic benefits, as inputs for the estimation of the IRRs and NPVs
for project evaluation.
22.3 Project Option
Economic evaluation for the project road from km 379.100 to km 465.000 has been carried
out. The project option considered is:
Widening and strengthening of existing 2-lane (partly 4-lane) National Highway to four lane
carriageway configuration with 7m wide service lane on either side.
22.4 Basic Input Data
The basic input data used for the application of HDM-4 have been grouped into following
categories:
General
Traffic
Road Condition and Pavement design
General Data
Pavement Option : Flexible Pavement has been considered for proposed four lane
carriageway configuration of existing 2-lane highway
The foreign exchange component in the total capital cost is insignificant and has been
considered to be zero, as all material, machinery and labour are available in India. Standard
Conversion factor of 0.90 has been used for converting market prices of road construction and
maintenance inputs into economic costs.
Traffic Volume and Composition
The traffic volume data has been taken from Traffic Analysis & Forecast chapter as per
Traffic Surveys conducted in the year 2005.
Summary of Annual Average Daily Traffic (AADT) along with percentage composition of
vehicles at km 380.00, km 419.00 and km 459.00 is given in Table 30.
Table 30: AADT & Percentage Composition of Vehicles
Percentage Composition (Motorised)
AADT ( Motorized
Vehicles) in Nos.
Two Wheelers
Car/Jeep/Van
(Passenger)
LGV
Bus
380.00 22723 40.19 2.61 5.31 7.06 25.92 7.82 8.85 1.77 0.47
Introduction
AADT ( Motorized
Vehicles) in Nos.
Two Wheelers
Car/Jeep/Van
(Passenger)
LGV
Bus
419.00 18676 25.73 3.24 5.88 8.87 39.71 6.55 8.01 1.65 0.36
459.00 21621 30.59 2.25 6.76 10.61 36.93 5.82 5.65 1.06 0.33
Estimated growth rates used for projection of traffic to horizon years are given in
Table 31.
Table 31: Estimated Traffic Growth Rates (%)
Year
Mode 2005 - 2008 - 2013 - 2018 - 2023 - 2027
2007 2012 2017 2022 2027 onwards
Cars 7.1 7.8 7.0 6.3 5.7 5.7
Buses 8.7 9.6 8.7 7.8 7.0 7.0
Trucks 4.5 4.9 4.5 4.0 3.6 3.6
Motorized two
10.3 11.3 10.2 9.2 8.3 8.3
wheelers
3 wheeler 6.6 7.3 6.5 5.9 5.3 5.3
Existing Road Condition: Other parameters like pavement condition data, roughness
Pavement Deflection (BBD) of various sections have been taken from respective chapter and
are summarized in the Table 32 and Table 33.
Table 32: Existing Roughness (m/Km) of various sections
Chainage (km.)
Sl. No. Length (km) Roughness (m/km)
From To
1 379.100 387.000 7.9 2.54
2 387.000 408.000 21 2.59
3 408.000 465.000 57.0 3.02
Table 33: Pavement Condition Survey data
Patching
Cracking Potholes (% Ravelling Rut Depth
Chainage area
area (%) area) area (%) (mm)
(%)
379.100-
3.71 0.42 - - 0.64
387.000
408.000-
9.28 1.54 4.75 1.11 1.68
465.000
Economic and Sensitivity Analysis results show that project road section from km 379.100 to
km 465.000 is economically viable by all means. Thereby project may be taken up for
improvement to 4-lane configuration.
22.7 Financial Analysis
The base objective of the financial analysis is to determine whether the Build Operate
and Transfer (BOT) model is workable for the stretch Cherthalai to Ochira (km
379.100 to km. 465.00) and if so, under what conditions
Financial Analysis has been carried out for the following scenarios.
23.2 The memorandum for Public Private Partnership Appraisal Committee (for ‘Final’
approval) has also been prepared and is sent herewith as Annex III together with brief
particulars of the Concession Agreement (Annex III-Appendix ‘A’).
The economic with sensitivity analysis and financial analysis results show that the
project is economically and financially viable even without any grant from NHAI.
The project is therefore recommended to be taken up on priority for 4 laning under
BOT (Toll).
•••
EXECUTIVE SUMMARY
0.1 INTRODUCTION
M/s Intercontinental Consultants and Technocrats Pvt. Ltd., New Delhi have been appointed
as Consultants to carryout the Feasibility Study and preparation of Detailed Project Report
(DPR) for 4/6-laning of Cherthalai to Thiruvananthapuram section of
0.2 CONTRACT
The Contract for Consultancy Services between M/s. ICT Pvt Ltd. and NHAI was entered
into on 08.09.2005 with the amount of consultancy contract being Rs. 2,21,69,400/-
(excluding service tax) for the entire length of proposed 4 laning in the Cherthalai-
Thiruvananthapuram section of NH-47 in the State of Kerala. Length has been divided in two
parts. Package I deals from Cherthalai (km 379.100) to Ochira (km 465.000) section of NH-
47.
• Case for additional cost of Rs. 94.31 Lakhs (excluding service tax) as Variation
was submitted to NHAI vide ICT letter no. ICT:436:TL:4447 dated 31.05.2007.
• NHAI was also informed on 31.05.2007 that fresh exercise would require
Extension of Time (EOT) of 8 months for preparing DPR.
0.4 PRESENT STATUS
• Approval in principle for the modified 4-lane cross-section has been received
from NHAI vide their letter no. NHAI/BOT/11012/67/2005 dated 15.11.2007.
• Extension of Time (EOT) upto 31st Jan 2008 has been approved by NHAI vide
their letter of 15.11.2007 referred to above.
• Approval for additional cost as variation is awaited from NHAI.
0.5 SITE VISIT
A site visit was undertaken by Team Leader accompanied by Senior Surveyor from
4th December 2007 to 10th December 2007. After the approval of the modified X-
sections of 4 laning by NHAI, widening schedule was finalized keeping in view the
ground situation. The abstract of widening is indicated as under:
Package
38.850 27.600 10.450 6.700 83.600
I
* Bypass at Alappuzha
Based on above, the modified alignment plans have been prepared and sent to NHAI
vide letter no. ICT: 436: TL: 1523 dated 18.02.2008.
0.6 TRAFFIC
The traffic in the base year i.e. December 2005 varies from 29,375 PCU to 35,361
PCUs. The pavement has been designed for 20 years design life.
0.7 DESIGN OF PAVEMENT
Design Life : 20 Years (Flexible)
Design Traffic : 100 msa for main carriageway; 10msa for service road
Design CBR : 8%
Pavement Composition
New Pavement:
Bituminous Concrete : 50mm
Dense Bituminous Macadam (DBM) : 140mm
Wet Mix Macadam (WMM) : 250mm
Granular Subbase (GSB) : 200mm
Overlay:
Bituminous Concrete : 50mm
NPV (Rs.
Option EIRR %
Million)
Four lane carriageway 35.90 18121.33
configuration of existing 2-lane
carriageway of NH-47 (With
time saving)
Sensitivity Analysis
Condition – I : 15% increase in project cost, traffic remains unchanged
Condition – II : 15 % decrease in traffic, project cost remains unchanged
Condition – III: 15 % increase in project cost & 15% decrease in traffic
Results (With Time Saving)
Condition IRR (%) NPV (Rs. Million)
I 32.30 16987.34
Introduction
II 32.50 16788.84
III 29.30 15654.85
0.11.2 Financial Analysis
The base objective of the financial analysis is to determine whether the Build Operate
and Transfer (BOT) model is workable for the stretch Cherthalai to Ochira (km
379.100 to km. 465.00) and if so, under what conditions
Financial Analysis has been carried out for the following scenarios.
iii) Base case with no NHAI grant
iv) With 20% equity support and 20% O&M support during the concession
period, the results are indicated as under;
Post-
Equity
Sl Tax
Description FIRR NPV
No. FIRR
(%)
(%)
Concession Period: 25 Years
1 Base case with 15.00 12.98 99.89
no grant Crores
2 With 20% 27.25 19.62 700.81
equity support + Crores
20% O&M
support
0.12 MEMORANDUM FOR PPP APPRAISAL COMMITTEE
0.12.1 Memorandum for consideration of Public Private Partnership Appraisal Committee
(for ‘In Principle’ approval) has been prepared in the format prescribed by NHAI and
is sent separately as document (Annex II) along with the Term Sheet of the proposed
Concession Agreement (Appendix A).
0.12.2 The memorandum for Public Private Partnership Appraisal Committee (for ‘Final’
approval) has also been prepared and is sent herewith as Annex III together with brief
particulars of the Concession Agreement (Annex III-Appendix ‘A’).
0.13 CONCLUSION AND RECOMMENDATION
The economic with sensitivity analysis and financial analysis results show that the
project is economically and financially viable even without any grant from NHAI.
The project is therefore recommended to be taken up on priority for 4 laning under
BOT (Toll).
•••