Workover Operations Manual
Workover Operations Manual
Workover Operations Manual
Operations Manual
Work over and Testing
Procedures
Version 1.0
Contents
1. Rig Moving and Installation
2. Well Killing Operation
3. Swabbing Operation
Introduction:
This comprehensive manual has been compiled for the main purpose of
serving as a guide to Work over Operations personnel and a reference to Work
over Engineers. And it has been considered the main work over and testing
operations as well killing, cementing, drilling, wire line.etc. This manual is
written in such a way that it is clear, easy to follow, and simple to achieve
benefits for Asawer company personnel. So this Manual has been arranged as
versions to be updated annually.
Swabbing Procedure
Preparation:
1. The ID of swabbing string should be of same specification.
2. The drift check with standard drift gauge for tubing should be conducted
before RIH swabbing string.
3. The total length of stuffing box and lubricators should be at least 2
meters more than the length from rope socket to swab cup, which should
be safe and reliable to prevent blowout.
Operation Procedures:
1. Link braided line, rope socket and sinker bar, and connect lubricators.
2. Connect swab mandrel without swabbing cup to sinker bar to check the
ID of tubing and 6 marks shall be made on the swab line (3 marks when
the in lubricator, 2 marks after 50m and one marks after 100m from first
marks).
3. Link swab cup after POOH sink bar, then put into swabbing head.
Continue RIH swab after connecting lubricators with the speed no more
than 150m per min. The submergence should be controlled within 200m.
4. It should not be run too deep when unclear of liquid depth and be tried
gradually to deepen.
5. Check the lubricators once every 5 times swabbing and make sure the
packing of lubricators in good condition.
6. If blowout is observed while swabbing then POOH until swab enters into
lubricators and then close swab valve.
7. The pressure difference should not be too large when swabbing for sand
produced formation and the uplifting speed should be reduced.
Squeezing Cement Procedures
1. RIH squeezing string to designed depth.
2. Connect and flush surface lines, then pressure test 15-20MPa without
leakage in 5-10 minutes to be qualified.
3. Circulate down hole fluid, and check whether the surface system in good
condition or not and to decrease down hole temperature.
4. Conduct trivial squeezing with clean water to test water absorbing index
and casing expansion rate (injective test to determine the feed rate).
5. Mix cementing slurry according to design.
6. Normally displace designed volume of cementing slurry according to
design requirement.
7. Normally displace specific volume of displacement fluid according to
design requirement and the displacement rate should be controlled to
0.5m3/min.
8. POOH string to the position for reverse circulation.
9. Reversely circulate to wash out extra cementing slurry.
10. POOH string to designed depth, and assemble stopcock and pressure
gauge at the top of tubing string.
11. Multi-squeeze until the pressure stable, then close the casing valve to
wait on cement.
Sand Flushing Procedure
1. RIH sand flushing string to tag sand level with one bevel edge at the
bottom of the string.
2. Uplift sand flushing bevel edge 3m above sand level. Lower down string
slowly and smoothly after normal circulation with pump and the pump
rate should meet the demand of working plan.
3. Full circulation should be conducted for each joint with flushing time no
less than 15 min.
4. Each duty should cooperate with each other closely to control RIH speed
according to pump pressure and outlet pump rate.
5. When over 5 joints are flushed continuously, the RIH could be continued
only after flushing one round.
6. When malfunction happens to pump and the pump must be stopped to
dispose, the string should be uplifted to 10m above initial sand level and
trip up and down repeatedly.
7. Normal circulation must be kept when troubles happen to uplifting
equipment.
8. When serious leakage of formation and no sand flushing fluid returning
to surface are found during sand flushing operation, the flushing should
be stopped. Uplift flushing string above initial sand level and trip up and
down repeatedly. The job could be continued with methods such as wax
ball plug-off, sand flush with united large rate pumps, and sand flush
with gasified fluidand so on.
9. The outlet pump rate should be controlled for the sand flush of high
pressure flowing wells to be balanced with inlet pump rate so as to
prevent blowout.
10. After sand flushing to designed depth or bottom hole which is the top
surface of cement plug the pump rate should be kept above 400L per min
to continue circulation. It is qualified after sand cut less than 0.2 percent.
Then uplift string more than 20 m, then detect sand level repeatedly after
waiting for sand settlement 4 hours later and record the depth.
2.4.2 Pipe thread must be painted by pipe dope, the thread torque is in the range
of the pipe required.
2.4.3 Be sure that there is no junk on top of cement plug level.
2.4.4 If use downhole screw driller, the drill fluid must be clean to meet the
requirement of downhole screw driller.
2.4.5 Make a short trip every 3-5m of footage.
2.4.6 Avoid the casing damage.
2.4.7 The drill fluid must be compatible with the formation.
2.4.8 To the designed depth, RIH casing tool gauge or scraper to Drilled
designed depth, and clean the wellbore with 1.5-2.0 times of wellbore
volume fluid.
2.3.3 Drill out the BP, WOB: 10-20KN, the rotary torque is no more than the
string required torque.
2.3.4 After released the BP, pushed it to PBTD. If the PBTD is not required to
leave junks, then RIH fishing tool to take out all junks.
2.4 Quality requirement
2.4.1 If there is junks on top of the BP, it must be fished and make the BP level
clean.
2.4.2 The milling fluid must be compatible with the formation.
2.4.3 Before POOH, make a round circulation.
2.4.4 If no obvious footage, cannot put more weights on bit in order not to
damage the casing.
Remarks
Its length should be
more than rotor
length
Adjust the polished rod
1 set pony rod
which have different
length
Fall the rotor to the desired depth, transfer Determine the total
the torque
length according to
the pump hanger
Fall one set every 6-10 sucker rods
Use according to the
well conditions
Connect sucker rod and rotor
over tighten.
4.6 Connect the power cable with motor and control.
5 Commissioning
5.1 Open the production valve and oil pipeline valve.
5.2 Start up the motor and observe the current and volatage changes at the same
time.
5.3 When oil flows from the flowline, shut off the producing valve then observe
the well head pressure. If the pressure rises and no abnormal changes emerge,
PCP system is proven to be all right and could be put into production.
Tubing Conveyed Perforating Procedures
Tubing Conveyed Perforating is running the perforation gun with tubing.
Procedure :
1. Get the well information from well operation program;
2. Get the perforation request from the well operation program;
3. Draw the Gun String sketch for the operation;
4. Prepare the Gun on surface;
5. Double check the Gun String before sent to wellsite;
6. Confirm the Gun String is well-assembled;
7. Make sure all the safety regulations are well performed;
8. Safety meeting is necessary before lifting the gun;
9. The Safety Space Gun must be long enough to ensure the gun under surface
when make up the Fire Head;
10.Gun must be RIH with smoothly and keep the RIH speed in 10-15stands;
11.The Tubing and Annular must be well covered to protect something
unexpected drop in;
12.The fluid height both in Tubing and in Annular are enough to keep the gun
fire safely;
13.GR/CCL depth correlation logging must be done for confirm the gun face the
planning information;
14.BOP is well installed on the wellhead, function and pressure test must be
done on the BOP facilities;
15.Drop bar or Pump to fire the gun with observing on the wellhead and casing
gauge to detect the perforation on surface.
16.POOH perforated gun with smoothly.
Wireline Conveyed Perforating Procedures
Wireline Conveyed Perforating is running the perforation gun with wireline.
Operation Procedures:
1. Confirm there is no potential blow out;
2. Get the well information from well operation program;
3. Get the perforation request from the well operation program;
4. Draw the Gun String sketch for the operation;
34567-
Unset procedures:1- Reach to setting depth and circulate above the fishing Neck of the RBP.
2- Apply down weight between(10-15) Tons depend on the Size of casing
(7,9 5/8).
3- Over pull the same weight above depend on the size of casing.
4- Repeat the step No (2 &3) one time more to confirm that you catch the
RBP.
5- Over pull the 2 Ton and start turn to the right until the weight is release.
6- Wait Five Minutes until the elements relax.
7- Continue turn 15 Turns.
8- Go up and go down passing the setting depth to confirm the tool is free
Setting Procedures
1- Reach to the setting depth put a mark above the holding slips
Of the tubing and it will be a reference point.
2- Pick up 60 CM
3- Turn to the right between (one turn to three turns)depend on depth
4- Apply down weight between(10.15) Tons depend on size of Packer.
Unset Procedures
1- Take out the weight
2- Wait Five Minutes until the element is relax.
3- Start pull one Join and monitor the weight indicator
If the J slot it is manual position you need to turn to the lift
While pulling the one Join
4- Go down passing the setting depth to confirm the Packer is free.
Conclusion:
Finally I hope that I have managed to cover the major work over & testing
operations. And I hope to benefit for all. I ask my god to enjoy everyone with
health and wellness till meet you in the next version.