Using Prince2 and MSP Together Oct 2010
Using Prince2 and MSP Together Oct 2010
White Paper
October 2010
2
Using PRINCE2 and MSP Together
Contents
1
3.1 Themes
3.2 Processes
Appendix A Roles
Appendix B References
10
10
Acknowledgements 10
Trademarks and statements
10
Further information
10
It is a project
Being managed
as a project
Being managed
as a programme
Optimized
Over-complicated
Over-governed
No clear boundaries, e.g. scope
It is a programme
Optimized
4
Using PRINCE2 and MSP Together
3.1 Themes
The structure of MSP is very similar to that of PRINCE2; both
have a set of themes. Table 3.1 maps the relationship between
the MSP governance themes and the PRINCE2 themes.
As shown in Table 3.1, the MSP governance themes often
reflect the themes in PRINCE2, so many of the disciplines can
be consolidated at the programme level to reduce duplication at
project level and improve consistency.
3 Approach to integrating
PRINCE2 and MSP
Projects
Characteristics
Driven by deliverables
Finite defined start and finish
Bounded and scoped deliverables
Delivers product or outcome
Benefits usually realized after
project closure
Shorter timescale
Management focus
Programmes
Driven by vision of end state
No predefined path
Delivers changes to the
business capability
Coordination of products/outcomes
Benefits realized during the
programme and afterwards
Longer timescale
High-level specification
(of why/what)
Stakeholder management
Benefit realization
Dependency management
Transition management/change
acceptance
Integration with
corporate strategies
Organization
Organization
Vision
Organization
Plans; progress
Business Case
Risk; change
Quality management
Quality
3.1.2 Organization
Projects and programmes are a people thing. No amount of
good planning or control will overcome not having the right
people involved in the project and programme in the first place.
MSP organization structure
MSP defines a programme organization structure, shown in
Figure 3.1. This comprises a Sponsoring Group, Programme
Board, Senior Responsible Owner (SRO), programme manager,
one or more business change managers, representatives of
corporate functions as necessary (for example, human resources,
finance), the lead supplier and the Project Executives of the
projects within the programme. See Appendix A for details of
each of these roles.
Duplication is avoided
The Stationery Office 2010
6
Using PRINCE2 and MSP Together
Sponsoring Group
focus on investment and
strategic alignment
Senior
Responsible
Owner
Programme Board
focus on driving
the programme
forward
Senior business
management
Business
Change
Manager(s)
Programme
Manager
Supporting
functions
Projects
Figure 3.1 Programme organization structure
Senior User
Executive
Senior Supplier
Project Board
Change
Authority
Project
Manager
Project
Assurance
Project
Support
Team
Manager
Team
Manager
Team
Manager
Senior
Responsible
Owner
Business Change
Manager
A
Business Change
Manager
B
Programme
Support
Programme
Manager
Design
Authority
Programme Board
Senior
User
Senior
Supplier
Executive
Project Board
Combined
Role
Change
Authority
Project
Manager
Senior
Supplier
Combined
Role
Combined
Role
Project
Assurance
Team
Manager
Team
Manager
Team
Manager
3.1.3 Quality
The projects quality management strategy is derived from that
of the programme.
Quality assurance and quality control activities may be carried
out by members of the programme management team.
The programmes design authority may provide advice and
guidance to the Project Manager on any quality methods to
be used.
The Stationery Office 2010
8
Using PRINCE2 and MSP Together
3.1.4 Plans
Any specific standards that the project planners should use will
be described in the programme monitoring and control strategy.
The project planning activity in the Design the Plan process will
ensure that such standards and tools are adopted by the project.
The programme office may have dedicated planners that can
help the Project Manager prepare and maintain the Project Plan
and Stage Plans.
The programme dependency network will detail how each
projects deliverables are being used by other projects within
the programme. Any dependencies to or from the project
should be incorporated into the projects plans.
3.1.5 Risk
The projects Risk Management Strategy will be derived from
that of the programme.
This will include defining a common set of risk categories, risk
scales (for probability, impact and proximity), any risk evaluation
techniques (such as expected monetary value), the projectlevel risk tolerance and the mechanisms to escalate risks to the
Programme Board.
A key consideration here is that project personnel may identify
programme-level risks and programme personnel may identify
project-level risks. It is important that risks are documented in
the risk register at the level in the extended organization that is
most capable of managing them.
3.1.6 Change
The Projects Configuration Management Strategy will be
derived from the programmes information management
strategy. The information management strategy defines how
interfaces between projects should be maintained (for example,
so that any changes within this project that may affect one or
more other projects are captured and escalated).
The projects change control procedure will be derived from
the programmes issue resolution strategy. This will define how
scope or delivery changes that take the project out of tolerance
or affect the programme benefits or programme plan are
escalated to the Programme Board.
The programmes design authority may be the projects Change
Authority, or a member of it.
3.1.7 Progress
The programmes monitoring and control strategy may influence
the formality, frequency and content of the projects reviews
and reports, and any project management standards that are to
be complied with.
Project-level time and cost tolerances will be defined by
the programme.
The number and length of management stages will be
influenced by the programme plan so that end stage
assessments align to other programme-level milestones (for
The Stationery Office 2010
3.2 Processes
Within MSP, the Delivering the Capability process within
Managing the Tranches is entirely focused on starting,
monitoring and closing projects within the programme. This
process does not need to be tailored when working with PRINCE2.
The PRINCE2 process most affected by working in a programme
will be Starting Up a Project. The Starting Up a Project process
will be undertaken almost entirely by the programme. The
programme will appoint the Project Executive and Project
Manager, review previous lessons, design and appoint the
Project Management Team and probably prepare the Project
Brief. The Project Manager, however, will be responsible for
preparing the initiation Stage Plan. In this context, it is not so
much that the Starting Up a Project process is not done, just
that it is mainly done by the programme.
The Directing a Project process will be affected if the
integrated organization structure collapses Project Boards
into the Programme Board. It may be that some of the Direct
a Project processes are run for multiple projects by a common
Project Board.
The Managing a Stage Boundary and Closing a Project
processes may be affected if the programme is undertaking the
responsibilities for benefits reviews.
Appendix A Roles
Programme management roles
The Sponsoring Group is the driving force behind the
programme and appoints the Senior Responsible Owner
(SRO). It is the group of senior managers responsible for the
investment decision, for interpreting the strategic direction of
the business, and for ensuring the ongoing alignment of the
programme to that strategic direction.
The SRO is the single individual with overall responsibility for
ensuring that a programme meets its objectives and delivers
the projected benefits. It is likely that the SRO will appoint the
Project Executive.
The Programme Boards prime purpose is to drive the
programme forward and deliver the outcomes and benefits.
Members will provide resource and specific commitment to
support the Senior Responsible Owner who is accountable for the
successful delivery of the programme. The Programme Board is
appointed by, and reports to, the Senior Responsible Owner.
Programme Assurance is responsible for building confidence
in the sponsoring organization(s) by ensuring that all aspects of
the programme are being managed properly.
The Programme Manager is responsible for the set-up and
day-to-day management and delivery of the programme on
behalf of the SRO.
The Business Change Manager is responsible for benefits
management, from identification through to realization. The
aim is to ensure that the new capabilities delivered by the
projects in the programme are properly implemented and
embedded in the sponsoring organization(s), so Business
Change Managers often have long-term line management
responsibilities for realizing benefits. Usually, there will be more
than one business change manager for a programme in order
to manage impacts in different parts of the organization (or in
different organizations). It is sometimes advisable to establish a
change team to support the Business Change Managers and
contribute specialist business change skills.
A programme office is the information hub and standards
custodian for the programme and its delivery objectives.
Programme offices take different forms depending on the
programmes and organizations that they support.
Programmes vary considerably in terms of scale and complexity
and MSP suggests that a number of other governance roles
should be considered and established, if necessary. These may
or may not be included as members of the Programme Board:
10
Using PRINCE2 and MSP Together
Acknowledgements
Appendix B References
Further information
Further information is available at:
www.best-management-practice.com
www.ogc.gov.uk
www.outperform.co.uk