Contracts and Specifications: Contracts. Construction Contract Is A Formal Agreement For Construction
Contracts and Specifications: Contracts. Construction Contract Is A Formal Agreement For Construction
CE 5-2
(a) Lump sum - This is the most basic form of agreement between a supplier
of services and a customer. The supplier or contractor agrees to provide
specified services for a specific price. The owner then agrees to pay the price
upon completion of the work or according to a negotiated payment schedule.
In developing a lump sum bid, the builder will estimate the costs of labor and
materials and add to it a standard amount for overhead and the desired
amount of profit.
(b) Unit price - In this contract, the work to be performed is broken into
various parts, usually by construction trade, and a fixed price is established
for each unit of work. For example, painting is typically done on a square foot
basis. Unit price contracts are seldom used for an entire major construction
project, but they are frequently used for agreements with sub-contractors. In
a unit price contract, like a lump sum contract, the contractor is paid the
agreed upon price, regardless of the actual cost to do the work.
Project management, where the owner engages a project manager
to act as its agent with control over the whole project, which may
or may not be divided into discrete parts.
EPCM (Engineering, Procurement, and Construction Management),
in which the contractor designs, procures and as agent for the
owner manages the construction.
Construction management, in which
the
owner
engages
how the component must function after installation. The general concept
behind the performance specification is for the architect or engineer to
describe what they need, and the contractor to determine the best way to
get there. The performance specification focuses on the outcome and shifts
the selection of materials and methods, as well as a portion of the design
work, onto the shoulders of the contractor. This approach can provide
incentives for innovation and flexibility in the construction approach, but also
reduces the amount of control that the architect or engineer has over the
project.
b. Prescriptive Specifications
Prescriptive specifications convey the requirements of a project through a
detailed explanation of the materials that the contractor must use, and the
means of installing those materials. This type of specification will typically be
formatted in a manner similar to the following sections:
1.
2.
3.
Execution: This section will explain how to prepare the materials and
conduct the installation, including the testing requirements to be
followed.
Prescriptive specifications shift more of the project design control onto the
shoulders of the architect or engineer and away from the contractor by
establishing a set of rules that is to be followed for each project component.
This type of specification provides more certainty regarding the final product
composition than the performance specification, and is very frequently used
for highly complex portions of a project.
c. Proprietary Specifications
Proprietary specifications are those that require the use of a single approved
product type for any particular installation. Proprietary specifications are
often used in cases where there is existing equipment or installations already
on site. In these cases the owner may want to maintain consistency of
materials or possibly simply prefers a specific type of product. Also, in highly
complex installations where there is only one specific piece of equipment
that will accomplish a specified task, a proprietary specification is required.
Architects and engineers typically try to avoid utilizing proprietary
specifications except when absolutely necessary, and will usually allow the
Define the Project and all of its significant activities or tasks. The
Project (made up of several tasks) should have only a single start
activity and a single finish activity.
II.
III.
Draw the "Network" connecting all the activities. Each Activity should
have unique event numbers. Dummy arrows are used where required
to avoid giving the same numbering to two activities.
IV.
V.
Compute the longest time path through the network. This is called the
critical path.
VI.
Use the Network to help plan, schedule, monitor and control the
project.
The Key Concept used by CPM/PERT is that a small set of activities, which
make up the longest path through the activity network control the entire
project. If these "critical" activities could be identified and assigned to
responsible persons, management resources could be optimally used by
concentrating on the few activities which determine the fate of the entire
project.
Non-critical activities can be replanned, rescheduled and resources for them
can be reallocated flexibly, without affecting the whole project.
Five useful questions to ask when preparing an activity network are:
Some activities are serially linked. The second activity can begin only after
the first activity is completed. In certain cases, the activities are concurrent,
because they are independent of each other and can start simultaneously.
This is especially the case in organizations which have supervisory resources
so that work can be delegated to various departments which will be
responsible for the activities and their completion as planned. When work is
delegated like this, the need for constant feedback and co-ordination
becomes an important senior management pre-occupation.