Section C7: Program: 1. Schedule

The document outlines a proposed schedule for a piping supply and installation project for a ferroalloys smelter complex. It lists key activities and their proposed start and completion dates, including enquiry adjudication, contract finalization, submission of required documents, equipment manufacturing, testing, delivery, and full delivery to the site. The supplier is asked to accept the proposed dates or provide alternate dates in the "Supplier's Guaranteed Schedule" columns. Accepting dates does not imply automatic acceptance of the purchaser's proposed dates.

Uploaded by

Thiruvengadam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views2 pages

Section C7: Program: 1. Schedule

The document outlines a proposed schedule for a piping supply and installation project for a ferroalloys smelter complex. It lists key activities and their proposed start and completion dates, including enquiry adjudication, contract finalization, submission of required documents, equipment manufacturing, testing, delivery, and full delivery to the site. The supplier is asked to accept the proposed dates or provide alternate dates in the "Supplier's Guaranteed Schedule" columns. Accepting dates does not imply automatic acceptance of the purchaser's proposed dates.

Uploaded by

Thiruvengadam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

CLIENT:

SAKURA FERROALLOYS

PROJECT:

SAKURA HCFeMn AND SiMn SMELTER COMPLEX

DOCUMENT:

ENQUIRY SECTION C7: PROGRAM

ENQUIRY NO.:

MM001-5001 PIPING SUPPLY AND INSTALL

SECTION C7: PROGRAM

1.

SCHEDULE
The following are the latest scheduled dates on the Project. The Supplier must accept the
scheduled completion dates or state in this Contract, other dates for the performance of the
work. Earlier dates are preferred.
No dates filled into the Suppliers guaranteed schedule columns will imply automatic
acceptance of the Proposed by Purchaser dates.
Day duration as indicated below, shall be expressed as calendar days and not working days.
See Attached Programme. Supplier to provide his acceptance of the program dates.

Activity

Suppliers Guaranteed
Schedule

Proposed Schedule
Start

Completion

Duration

Start

Completion

Enquiry
Adjudication
Order placement, Contract
finalisation
Effective date of Contract
Submission of Bond within
10 days from Contract start
(if applicable)
Submission of program and
required information
documents within 14 days
from effective date of
Contract/Purchase order
Submission of engineering
documents incl. joint review
(drawings, analyses, lists)
Proof of Malaysian DOSH
approval submitted to
Purchaser
Site Establishment
All equipment
manufacturing (Engineer to
specify)

Printed on: 18 June 2014

Page 1 of 2

S:\Engineering\MC363 Sakura\CONTRACTS\MM\MM001-5001 Piping\Enquiry\SECTION C\C7 PROGRAM\C7 Program.docx

CLIENT:

SAKURA FERROALLOYS

PROJECT:

SAKURA HCFeMn AND SiMn SMELTER COMPLEX

DOCUMENT:

ENQUIRY SECTION C7: PROGRAM

ENQUIRY NO.:

MM001-5001 PIPING SUPPLY AND INSTALL

Activity

Suppliers Guaranteed
Schedule

Proposed Schedule
Start

Completion

Duration

Start

Completion

Testing of electrical /
mechanical equipment at
Suppliers Works

Disassembly & packaging


Ex works collection
Delivery to Port FOB (if
applicable)
Full delivery to site of
piping and fittings as per
BOQ

Printed on: 18 June 2014

Page 2 of 2

S:\Engineering\MC363 Sakura\CONTRACTS\MM\MM001-5001 Piping\Enquiry\SECTION C\C7 PROGRAM\C7 Program.docx