Typical FEED Schedule

This document outlines the typical engineering schedule for a Front End Engineering Design (FEED) project. It shows the timeline over 12 months for key activities including process simulations, piping and instrumentation diagrams, equipment selection and specifications, civil works like foundations, and development of cost estimates. Major milestones include hazard reviews, engineering issues of the diagrams, material selection reports, and mechanical, instrumentation, electrical, and civil work packages. The schedule provides guidance on sequencing interdependent tasks to complete the FEED within one year.

Uploaded by

Vinh Do Thanh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (7 votes)
6K views1 page

Typical FEED Schedule

This document outlines the typical engineering schedule for a Front End Engineering Design (FEED) project. It shows the timeline over 12 months for key activities including process simulations, piping and instrumentation diagrams, equipment selection and specifications, civil works like foundations, and development of cost estimates. Major milestones include hazard reviews, engineering issues of the diagrams, material selection reports, and mechanical, instrumentation, electrical, and civil work packages. The schedule provides guidance on sequencing interdependent tasks to complete the FEED within one year.

Uploaded by

Vinh Do Thanh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Front End Engineering Design (FEED) - Typical Engineering schedule

Activity
Contract Effective Date
Process simulations
PFD
H&MB
Equipment list
Fluids list
P&IDs preparation and 1st issue (IFR)
PR
P&ID review with COMPANY
P&IDs 2nd issue (IFH)
HAZOP review
P&IDs IFD
Process equipment sizing & data sheets
Equipment Mechanical design, dwgs, data sheets
EQT Equipment Material Requisitions
Equipment Technical Bid Tabulations
PRT Inquiries to Equipment Vendors
Material selection report
PM
Piping classes summary & specifications
Plot plan - 1st issue (IFR)
HAZID + Plot Plan review with COMPANY
PL
Plot Plan IFD
Piping routing
PI
Piping MTO
Instrument list
System architecture drawing
I&C
Main cable routing drawings
MTO
Load list
Single line diagram
Equipment sizing
EL
Sub-station arangement drawings
Main cable routing drawings
MTO
HSE Fire Protection drawing
Building architectural drawings
General Underground Networks drawing
Foundation guide drawings
CIV
Pipe-racks and Steel structures outline drawings
Civil MTO
SUB Inquiries to Construction contractors
COST Cost estimate

Project Month
4 5 6 7 8 9 10 11 12

(c) The Oil & Gas Engineering Guide, Herv Baron, Eidtions Technip, 2005