Project Construction Management
Data Sheet
Activities
1-2 Demolition and clearing
2-3 Excavation
2-5 Underground installation
3-4 Foundation and columns
4-5 Dummy
4-6 Construction of second floor
4-7 Roof framing and flooring
5-7 Ground floor slab
5-8 Mech. & Elect services
6-7 Construction of exterior walls
7-8 Dummy
7-9 Construction of interior
partitions
8-9 Mech. & Elect. Equip. &
fixtures
9-10 Painting and finishing work
Time Duration in
Weeks
8
14
6
5
0
6
6
4
12
12
0
10
12
8
Network Diagram
6
6
8
1
12
14
3
4
6
0
4
6
5
10
12
1
2
1
0
Network Diagram
6
33
1
0
14
12
22
08
27
27
45
10
33
4
27
0
45
5
14
12
8
57
31
6
55
12
8
39
65
1
0
Project Construction Management
Data Sheet
Activities
1-2 Demolition and clearing
2-3 Excavation
2-5 Underground installation
3-4 Foundation and columns
4-5 Dummy
4-6 Construction of second floor
4-7 Roof framing and flooring
5-7 Ground floor slab
5-8 Mech. & Elect services
6-7 Construction of exterior walls
7-8 Dummy
7-9 Construction of interior
partitions
8-9 Mech. & Elect. Equip. &
fixtures
*ESPainting
- Early and
Startfinishing work
9-10
*EF - Early Finish
Tim
e
8
14
6
5
0
6
6
4
12
12
0
10
12
8
ES
EF
0 + 8
8 + 14
8 + 6
22 + 5
27 + 0
27 + 6
28 + 6
27 + 4
29 + 12
33 + 12
45 +
0
45 + 10
45 + 12
57 + 8
=
=
=
=
=
=
=
=
=
=
=
=
=
=
8
22
14
27
27
33
33
31
39
45
45
55
57
65
Network Diagram
6
33
45-12=33
6
88=0
0
33-6=27
14
2
27
336=27
08
12
27
22
39 45-6=39
33
22-14=8 27-5=22
57-10=47
33-0=33
47
7
10
45
45-4=41
41
12
5
33 45-
12=33
450=45
1
2
8
45 57-
658=57
57
12=45
65
1
0
Project Construction Management
Data Sheet
Activities
9-10 Painting and finishing work
8-9 Mech. & Elect. Equip. &
fixtures
7-9 Construction of interior
partitions
7-8 Dummy
6-7 Construction of exterior walls
5-8 Mech. & Elect services
5-7 Ground floor slab
4-7 Roof framing and flooring
4-6 Construction of second floor
4-5 Dummy
3-4 Foundation and columns
2-5 Underground installation
2-3 Excavation
1-2*Latest
Demolition
Finish and
LF clearing
*Latest Start LS
Tim
e
8
12
10
0
12
12
4
6
6
0
5
6
14
8
LF
LS
65
57
57
45
45
45
45
45
33
46
27
47
22
8
8
12
10
10
12
12
4
6
6
0
5
6
14
8
=
=
=
=
=
=
=
=
=
=
=
=
=
=
57
45
47
35
33
33
41
39
27
33
22
27
8
0
Total Float
is the span of time an activity can be delayed after its Earliest
Start time without delaying the project time of completion. It is
numerically equal to the Total Time for the activity minus the
Activity Duration.
Free Float
is the span of time an activity can be delayed after its Earliest
Start without delaying the Earliest Start of any succeeding real
activity.
Project Construction Management
Activit
y
1-2
2-3
2-5
3-4
4-5
4-6
4-7
5-7
5-8
6-7
7-8
7-9
8-9
9-10
(LF EF) =
Total Float
8 - 8
22 - 22
33 - 33
27 - 27
33 - 27
33 - 33
45 - 33
45 - 31
45 - 39
45 - 45
45 - 45
57 - 55
57 - 57
65 - 65
= 0
= 0
= 19
= 0
= 6
= 0
= 12
= 14
= 6
= 0
= 0
= 2
= 0
= 0
Activity
1-2
2-3
2-5
3-4
4-5
4-6
4-7
5-7
5-8
6-7
7-8
7-9
8-9
9-10
(LF D) - LF =
Free Float
(8 - 8) - 0 = 0
(22 - 14) 8 = 0
(33 - 6) - 8 = 19
(27 - 5) - 22 = 0
(27 - 0) - 33 = -6 =
0
(33 - 6) - 27 = 0
(45 - 6) - 27 = 12
(45 - 4) - 33 = 8
(45 - 12) - 33 = 0
(47 - 12) - 33 = 0
(45 - 0) - 45 = 0
(57 - 10) 45 = 2
(57 - 12) 45 = 0
(65 - 8) - 57 = 0