Project Construction Management: Data Sheet

The document provides information on the activities, time durations, early start and finish dates, late start and finish dates, total float, and free float for a construction project. There are 14 activities including demolition, excavation, underground installation, foundation work, construction of floors and walls, mechanical and electrical work, and finishing. The total project duration is 65 weeks based on the late finish date of the last activity.

Uploaded by

yfcbrandon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
515 views8 pages

Project Construction Management: Data Sheet

The document provides information on the activities, time durations, early start and finish dates, late start and finish dates, total float, and free float for a construction project. There are 14 activities including demolition, excavation, underground installation, foundation work, construction of floors and walls, mechanical and electrical work, and finishing. The total project duration is 65 weeks based on the late finish date of the last activity.

Uploaded by

yfcbrandon
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Project Construction Management

Data Sheet

Activities
1-2 Demolition and clearing
2-3 Excavation
2-5 Underground installation
3-4 Foundation and columns
4-5 Dummy
4-6 Construction of second floor
4-7 Roof framing and flooring
5-7 Ground floor slab
5-8 Mech. & Elect services
6-7 Construction of exterior walls
7-8 Dummy
7-9 Construction of interior
partitions
8-9 Mech. & Elect. Equip. &
fixtures
9-10 Painting and finishing work

Time Duration in
Weeks
8
14
6
5
0
6
6
4
12
12
0
10
12
8

Network Diagram
6
6
8
1

12

14
3

4
6
0

4
6
5

10

12

1
2

1
0

Network Diagram
6

33

1
0

14

12

22

08

27
27

45

10

33
4

27

0
45

5
14

12

8
57

31
6

55

12
8
39

65
1
0

Project Construction Management


Data Sheet

Activities
1-2 Demolition and clearing
2-3 Excavation
2-5 Underground installation
3-4 Foundation and columns
4-5 Dummy
4-6 Construction of second floor
4-7 Roof framing and flooring
5-7 Ground floor slab
5-8 Mech. & Elect services
6-7 Construction of exterior walls
7-8 Dummy
7-9 Construction of interior
partitions
8-9 Mech. & Elect. Equip. &
fixtures
*ESPainting
- Early and
Startfinishing work
9-10
*EF - Early Finish

Tim
e
8
14
6
5
0
6
6
4
12
12
0
10
12
8

ES
EF
0 + 8
8 + 14
8 + 6
22 + 5
27 + 0
27 + 6
28 + 6
27 + 4
29 + 12
33 + 12
45 +
0
45 + 10
45 + 12
57 + 8

=
=
=
=
=
=
=
=
=
=
=
=
=
=

8
22
14
27
27
33
33
31
39
45
45
55
57
65

Network Diagram
6

33

45-12=33

6
88=0
0

33-6=27

14

2
27

336=27

08

12

27

22

39 45-6=39
33

22-14=8 27-5=22

57-10=47

33-0=33

47
7

10

45
45-4=41

41
12

5
33 45-

12=33

450=45

1
2

8
45 57-

658=57
57

12=45

65
1
0

Project Construction Management


Data Sheet

Activities
9-10 Painting and finishing work
8-9 Mech. & Elect. Equip. &
fixtures
7-9 Construction of interior
partitions
7-8 Dummy
6-7 Construction of exterior walls
5-8 Mech. & Elect services
5-7 Ground floor slab
4-7 Roof framing and flooring
4-6 Construction of second floor
4-5 Dummy
3-4 Foundation and columns
2-5 Underground installation
2-3 Excavation
1-2*Latest
Demolition
Finish and
LF clearing
*Latest Start LS

Tim
e
8
12
10
0
12
12
4
6
6
0
5
6
14
8

LF
LS
65
57
57
45
45
45
45
45
33
46
27
47
22
8

8
12
10
10
12
12
4
6
6
0
5
6
14
8

=
=
=
=
=
=
=
=
=
=
=
=
=
=

57
45
47
35
33
33
41
39
27
33
22
27
8
0

Total Float
is the span of time an activity can be delayed after its Earliest
Start time without delaying the project time of completion. It is
numerically equal to the Total Time for the activity minus the
Activity Duration.
Free Float
is the span of time an activity can be delayed after its Earliest
Start without delaying the Earliest Start of any succeeding real
activity.

Project Construction Management


Activit
y
1-2
2-3
2-5
3-4
4-5
4-6
4-7
5-7
5-8
6-7
7-8
7-9
8-9
9-10

(LF EF) =
Total Float
8 - 8
22 - 22
33 - 33
27 - 27
33 - 27
33 - 33
45 - 33
45 - 31
45 - 39
45 - 45
45 - 45
57 - 55
57 - 57
65 - 65

= 0
= 0
= 19
= 0
= 6
= 0
= 12
= 14
= 6
= 0
= 0
= 2
= 0
= 0

Activity
1-2
2-3
2-5
3-4
4-5
4-6
4-7
5-7
5-8
6-7
7-8
7-9
8-9
9-10

(LF D) - LF =
Free Float
(8 - 8) - 0 = 0
(22 - 14) 8 = 0
(33 - 6) - 8 = 19
(27 - 5) - 22 = 0
(27 - 0) - 33 = -6 =
0
(33 - 6) - 27 = 0
(45 - 6) - 27 = 12
(45 - 4) - 33 = 8
(45 - 12) - 33 = 0
(47 - 12) - 33 = 0
(45 - 0) - 45 = 0
(57 - 10) 45 = 2
(57 - 12) 45 = 0
(65 - 8) - 57 = 0