Chapter Four: Relay Coodination
Chapter Four: Relay Coodination
Chapter Four: Relay Coodination
RELAY COODINATION
1.0 INTRODUCTION
Co-ordination of relays is an integral part of the overall system
protection and is absolutely necessary to:
(a)
(b)
(c)
(d)
2.0
58
3.0
Co-ordination Procedure
3.1
59
3.2
(a) Whenever and wherever possible, use relays with the same
characteristics in series with each other.
(b) Set the relay farthest from the source at the minimum current settings.
(c) For succeeding relays approaching the source, increase the current
setting or retain the same current setting. That is the primary current
required to operate the relay in front is always equal to or less than the
primary current required to operate the relay behind it.
3.3
60
61
3.4
3.4.1 This principle is based on the fact that the fault current varies with the
position of the fault because of the difference in impedance values
between the source and the fault. The relays are set to pick up at
progressively higher currents towards the source. This current grading
is achieved by high set over current relays and with different current
tap positions in the over current relays. Since their selectivity is based
solely on the magnitude of the current, there must be a substantial
difference (preferably a ratio of 3:1) in the short circuit currents
between two relay points to make them selective.
3.4.2 A simple current graded scheme applied to the system as shown in fig
1 above will consist of high set over current relays at S, A, B and C
such that the relay at S would operate for faults between S and A; the
relay at A would operate for faults between A and B and so on.
3.4.3 In practice the following difficulties are experienced with the
application of purely current graded systems:
(a) The relay cannot differentiate between faults that are very close to,
but are on each side of B, since the difference in current would be very
small.
(b) The magnitude of the fault current cannot be accurately determined
since all the circuit parameters may not be known exactly and
accurately.
62
(c) There may be variations in the fault level depending upon the source
generation, thereby necessitating the frequent change in the settings
of the relay.
3.4.4
3.5
63
3.5.3 There are two basic adjustable settings on all inverse time (IDMT)
relays. One is the TMS (Time Multiplier Setting) and the other is the
current setting, which is usually called the PSM (Current Plug Setting
Multiplier)
Time Multiplier Setting (TMS) =
Where
TM
T
=
T
TM
= 1.
Plug Setting Multiplier (PSM) =
Primary Current________________
Relay operating current x C.T. ratio
3.5.4 As per B.S., there are two types of IDMT relays, namely 3.0 secs and
1.3 secs relays. This only means that with TMS = 1.0 and PSM = 10,
the relay operates at the time of 3.0 secs or 1.3 secs as the case may
be.
3.5.5 The time interval of operation between two adjacent relays depends
upon a number of factors. These are:
(a) The fault current interrupting time of the circuit breaker.
(b) The overshoot time of the relay.
(c) Variation in measuring devices - Errors.
(d) Factor of Safety.
3.5.6 Circuit breaker interruption time
64
It is the total time taken by the circuit breaker from the opening of the
contacts to the final extinction of the arc and energization of the relay.
Modern circuit breakers have an operating time or tripping time of 3 to
5 cycles in the EHV ranges and up to 8 cycles in the H.V and M.V
ranges.
3.5.7 Overshoot
When the relay is de-energised, operation may continue for a little
longer until any stored energy has been dissipated. This is
predominant only in electromagnetic relays but not in static relays.
3.5.8 Errors
All devices such as relays, CTs etc are subject to some degree of error.
Relay grading is carried out by assuming the accuracy of the
measuring device or by allowing a margin for errors.
3.5.9 Factor of Safety
Some safety margin is intentionally introduced to account for errors
and delays in breaker operating time.
The Phase-to-Phase fault current should be considered for phase fault
relays and the phase to earth fault current for earth fault relays.
The setting for phase fault element (OCR) may be kept as high as 150
to 200% of full load current. Normally the minimum operating current
is set not to exceed 130% of the setting i.e.
I setting
65
4.1
SOLUTION
Secondary value of short circuit current
=
=
8000 x 5
400
100 A
=
With 100% current setting IR =
Therefore Plug setting =
400 x 5
400
5A
5A
5.0
100
5
= 20
66
Looking into the relay characteristic curve, the time of operation for this
value is 2.2 seconds at Unity TMS. If the relay is to operate in 2.0 sec., then
TMS = 2.0
2.2
i.e. from formulae
= 0.9
Tu
= To
TMS
Or TO = TU x TMS
Alternatively:
relays
4.2
TO
0.14
MPS0.02 - 1
Data: Given a radial feeder with fault current and C.T. ratios at
substations A, B, and C as indicated. Full load current at C = 100A.
Available relay is 1DMT 3 secs. Relay.
Find out the current setting P.S and TMS at each substation.
SOLUTION
We proceed from the farthest station towards the source.
67
Substation C
Secondary value of fault current
50A
=100 x 5 _ =
200
2.5A
100A
2000 x 5 _ =
200
2.5A =
IR
At C:
0.1 + 0.16 =
TMS =
0.26 =
2.2
P.S
2.5
TMS =
0.26 secs
0.12
0.12
Substation B
The relays at B must act at a time grading higher than that of relays at
C.
Therefore we assume a time grading of 0.35 secs. (in our own case)
68
0.26 + 0.35=
0.61 secs
1.3 x 2.5
3.25
2000 x 5 =
300
33.33A
=
33.33 =
3.75
8.88
The time of operation of the relay at MPS = 8.88 with TMS = 1 is 3.2
secs (from the relay characteristic curve)
TMS at 0.61 secs. =
0.61 =
3.2
0.19
3000 x 5__
300
50A
3.75
50
=
3.75
13.33
69
The time of operation of the relay at MPS = 13.33 with TMS = 1 is 2.6
secs (from the relay characteristic curve)
But TMS chosen for the relay at B is 0.19
Actual operating time of the relay at B for a fault current of 3000A (a
fault very close to B) is equal to:
To
Tu x TMS
0.19 x 2.6
0.49 secs.
Substation at A
Required operating time for relay at A for a fault current at B is:
=
0.49 + 0.35
0.84sec
3000 x 5__
300
50A
=
50 _
3.75
13.33
With TMS = 1, operating time for this value of MPS = 13.33 is given as
2.6 sec.
TMS for the operating time of 0.84 secs
70
TMS at A
0.84 =
2.6
0.32
0.32
MPS
5000 x 5_
300
83.33
3.75
22.22
83.33A
0.7 secs
SUBSTATION
CTR
P.S
A
B
C
300/5
300/3
200/5
3.75
3.75
2.50
Actual
Operating time
of relays
0.7 secs
0.49 secs
0.26 secs
71
4.3
37.17MVA
ZO
SOLUTION
Assume base MVA = 100
Source impedance at station A
Zs
=
=
=
Base MVA
Fault MVA
100__
37.17
2.69 p.u
72
[(19.58) 2 + (12.86) 2 ]
23.43 ohms
Zp.u =
Z0
Zp.u
Z1 x MVA
(KV) 2
23.43 x 100
(33) 2
2.15 p.u
[(23.89) 2 + (38.37) 2 ]
45.19 ohms
45.19 x 100
332
4.15 p.u
Zt
%Z x base MVA_______
Transformer MVA
6.5 x 100
100 5
1.3 p.u
Zs + Z1 + Zt
73
6.14 p.u.
Base MVA
Zf
100
6.14
16.29MVA
Fault current
=
16.29 x 106
3 x 11 x 103
855A
100/5
855 x 5__
100
42.75A
100 x 5__
100
74
IR
5A
0.1 + 0.16 =
0.26 secs.
Where 0.1sec
0.16sec
TMS =
0.26
3.25
0.08
TMS =
5.0
0.08
300/5
855 x 5__
300
14.25A
5 x 106 ____
3 x 11 x 103
75
262.5A
262.5 x 5__
300
4.375A
0.26 + 0.35
delay
TMS =
=0.61 secs
0.61
6.29
0.096 =
0.10
5.0
TMS =
0.1
855 A
3
76
285 A
CTR =100/5
Secondary value of fault current
=
285 x 5_
100
14.25 A
5 x 106 _____
3 x 33 x 103
87.5A
87.5 x 5__
100
4.375A
We choose a P.S = 5A
MPS =
14.25
5
2.85
77
0.61 + 0.3
0.91 secs.
TMS =
0.91
6.29
0.1446
0.15
TMS =
STATION B
11KV main breaker
5.0
0.15
P.S
5.0
5.0
TMS
0.10
0.08
CTR
300/5
100/5
RELAY
OCR
OCR
5.0
0.15
100/5
OCR
11KV feeder
breaker
STATION A
33KV line breaker
Earth Fault Relay Co-ordination
For transmission line and transformer Z1 = Z2
Z0 of transmission line = 4.15 p.u
Z1
Z0 of transformer = 80% of Zt
= 0.8 x 1.3 =
Z0
4.15 + 1.04 =
1.04 p.u
5.19 p.u
Zs + Z1 + Z2 + Z0
3
2.69 + 12.09
3
6.72 p.u
Base MVA
Zf
100
6.72
14.88 MVA
=
14.88 x 106
3 x 11 x 103
781 A
781 x 5
79
100
=
39.05A
For earth fault the P.S is kept at the lowest setting for the feeder and so
also the operating time at the minimum say, 0.1 sec.
Therefore, P.S = 1.0
A fault current of 39.05 A corresponds to an MPS of 39.05 = 39.05
which
1.0
operating time at Unity TMS is given as 1.84 secs.
TMS =
0.1
1.84
0.05
Earth Fault Relay setting for the 11KV feeder is given as:
P.S
TMS =
Transformer breaker CTR
1.0
0.05
=
300/5
781 x 5__
300
13.02 A
80
0.4
2.66
0.15
TMS =
1.0
0.15
781 x 5__
100
39.05 A
39.05
3
0.7
2.66
81
0.26
Therefore Earth Fault Relay setting of 33KV line panel at station A is:
P.S
TMS =
STATION B
11KV Feeder
11KV Transformer
breaker
STATION A
33KV Line breaker
1.0
0.26
P.S
1.0
TMS
0.05
CTR
100/5
RELAY
EFR
1.0
0.15
300/5
EFR
1.0
0.26
100/5
EFR
82