This document outlines the commissioning process for a 90 MW simple cycle power plant in Nigeria. It includes individual testing of pumps, compressors, measurement equipment, control systems and fire protection. Complex testing involves a 3-day trial run of the power plant, performance testing and training of operating personnel. Prior to commissioning, test protocols will be prepared for equipment and fittings will be checked for operation in local/remote manual and automatic modes. Cables will be tested to international standards.

Uploaded by

Jaroslav Kuruc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
26 views1 page

JK Version 299

This document outlines the commissioning process for a 90 MW simple cycle power plant in Nigeria. It includes individual testing of pumps, compressors, measurement equipment, control systems and fire protection. Complex testing involves a 3-day trial run of the power plant, performance testing and training of operating personnel. Prior to commissioning, test protocols will be prepared for equipment and fittings will be checked for operation in local/remote manual and automatic modes. Cables will be tested to international standards.

Uploaded by

Jaroslav Kuruc
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

page #1

lEC

90 MW Simple Cycle Power Plant Magboro, Nigeria

Project name:

Document

name:

Appendix A: Technical Specification


Contract Agreement

No.:

EPC-1312-32-ERT-001

to Onshore

Project No.:

EPC-1312-2011

Rev:

Date:

B
22-05-2015

Individual tests pumps local / remote operation


Individual tests connection measurement equipments TIR, PIR, FIR
Individual tests compressor local / remote operation
Individual tests signals in DCS
Individual tests C02 Fire Protection System
Individual tests High Voltage System,
Test interlocks simulation
Preparation on the first start gas turbine
The first start gas turbine
Training operation personal
Pre - complex

test s :

Checks of control, interlocks, alerting, measuring and regulation


Function tests automatic operation (all algorithms)
Dynamic Testing/Setting
Combustor Mapping
Preparation on the complex tests
Training operation personal
Complex

tests:

Start of 3daysTrial run of Power Plant


Performance tests
Final take - over

This phase contains also practicai instruction of the Cliens

operating

personnel

as a part of

personnel training.
Prior to commissioning,

protocols on individual test runs of relevant equipment as for its function

will be prepared.
Fittings operated electrically will be checked as for stop/start location, proper connection to driving
media and control system, possibility of being controlled either locally or remotely in manual of
automatic mode.
Electric cabling and control cabling will be asked and tested according to relevant international
standards. Based on these checks, relevant protocols and certifications will be issued.