Work Programme (Project Management)

This work programme outlines the timeline for a construction project over 80 periods. It includes tasks such as land surveying, engineering, permitting, site planning, utilities installation, foundation work, framing, exterior and interior finishes, landscaping, and final acceptance. The project is 70% complete overall with some tasks like cabinetry and countertops only 50% finished. The timeline shows the planned start and duration for each task against the actual start and duration.

Uploaded by

Quah Qiu Yu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
164 views1 page

Work Programme (Project Management)

This work programme outlines the timeline for a construction project over 80 periods. It includes tasks such as land surveying, engineering, permitting, site planning, utilities installation, foundation work, framing, exterior and interior finishes, landscaping, and final acceptance. The project is 70% complete overall with some tasks like cabinetry and countertops only 50% finished. The timeline shows the planned start and duration for each task against the actual start and duration.

Uploaded by

Quah Qiu Yu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Work Programme

TASK

Period Highlight:
2

3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
35
42
47
51
55
60
63
64

Actual

% Complete

Actual (beyond plan)

% Complete (beyond plan)

PLAN
PLAN ACTUAL ACTUAL PERCENT
START DURATION START DURATIONCOMPLETE PERIODS (WEEK)

1 2
1 Development
2
Land Survey

Plan

Plan design
2
Engineering
2
Bidding
3
Permits
7
Site Planning
Grading
8
Excavation
10
Install drain tile and grav 12
Backfilling
14
Final grading
18
Utilities
Rough in main sewer
20
Rough in water main
21
Rough in electrical main 22
Foundation
Set forms for foundation 23
Set steel for foundation 26
Pour foundation
29
Strip foundation
30
Framing
Set sill plates
31
Sheath first floor
33
Build first floor walls (except
35
Set 2nd floor joists
37
Sheath 2nd floor
39
Build 2nd floor walls (except
41
Dry In
43
Exterior Finishes
51
Interior Finishes
Cabinetry & Countertops 67
Interior Trim & Stairs
68
Tile & Ceramics
70
Wall Finishes
73
Door & Closet Hardware 77
Bath Hardware
78
Appliances
79
Landscaping and Grounds80Work
Final Acceptance
80

11

13

15

19

20

21

22

23

27

30

31

31

33

35

37

39

41

43

16

51

20

67

68

70

4
1
1
1
1
2

100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
100%
70%
50%
50%
50%
0%
0%
0%
0%
0%
0%

9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80