Construction Cost Management: Learnings From Case Studies by Keith Potts
Construction Cost Management: Learnings From Case Studies by Keith Potts
Keith Potts
AN EXAMPLE OF OPERATIONAL METHOD OF ESTIMATING
The question relates to the construction of a reinforced concrete basement (size 50
m 30 m 10 m deep) built below ground on a green field site. The contractors
estimator is required to calculate an appropriate BofQ rate. E326 Excavation for
foundations, material other than topsoil, rock or artificial hard material maximum
depth 510 m 15,000 m3
Approach: Consider two alternative construction methods.
Method A open cut with battered sides (assume total volume of excavation
equals 2.5 net volume) the open-cut method will require additional working space
to allow for erect and strip shutter to the outer face;
Method B steel cofferdam built around net perimeter of basement.
Assume the following net costs (based on quotations from subcontractors):
Solutions
There are two solutions; costs involved as described in method A (open cut) and
costs
involved in method B (steel cofferdam) (see Figs 6.2 and 6.3); both are discussed in
detail in
the following sections.
Costs of method A (open cut)
Excavating in open cut 15,000 2.5 m3 37,500 m3 @ 10/m3 375,000
Disposal on site 37,50015,000 22,500 m3 @ 1/m3 22,500
Bring back and fill 22,500 m3 @ 2/m3 45,000
Total net cost 442,500
It is up to the contractor to select the most economic method of working. The
additional
excavation required is dependent on the nature of the ground and the natural slope
of
inclination generally the harder the material the steeper the slope.
Costs of method B (steel cofferdam)
Sheet piling mobilization/demob 2 5,000 10,000
Sheet piling 160 15 2,400 m2 @ 35/m2 84,000
Excavate within cofferdam 15,000 m3 @ 25/m3 375,000
Extract cofferdam 5,000
Total net cost 474,000