Physical Demo

The document outlines two identical activities with 10 tasks labeled A-K. It includes information on early start and finish dates, predecessors, estimated task durations, late start and finish dates, and slack for each task. The activities both start at time 0 and must finish by time 37.

Uploaded by

spectrum_48
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Activity

A
B
C
D
E
F
G
H
I
J
K
End

Activity
A
B
C
D
E
F
G
H
I
J
K
End

Early
Start
0
15
27
27
33
0
8
8
16
17
31
37
Projec
t

Immediate
Predecessor

A
B
B
C

F
F
G
H
J
D, E, I, K

Early
Finish
15
27
33
32
36
8
16
17
23
31
37
37
37

Estimated Time (days)


15
12
6
5
3
8
8
9
7
14
6

Late
Start
1
16
28
32
34
0
22
8
30
17
31
37

Late
Finish
16
28
34
37
37
8
30
17
37
31
37
37

Slack
1
1
1
5
1
0
14
0
14
0
0
0