Mining Engineering
Mining Engineering
Platinum Concentrator
Development of a Management Tool to Measure and Monitor
OEE and Process Pain
Master of Science Thesis in Quality and Operations Management, Mechanical Engineering
ANTON KULLH
JOSEFINE LMEGRAN
Department of Product and Production Development
CHALMERS UNIVERS ITY OF TECHNOLOGY
Gothenburg, Sweden, 2013
ANTON KULLH
JOSEFINE LMEGRAN
II
ANTON KULLH
JOSEFINE LMEGRAN
Abstract
The current low platinum price has put
high pressure on the industry and forced
companies to introduce cost cutting efforts
as well as productivity increasing actions.
Increasing the productivity can be done
either by increasing the output or
decreasing the amount of consumed
resources. This project has focused on the
latter. There are several productivity
increasing methods, such as Total
Productivity Maintenance (TPM) and Lean,
to utilise. In the mining industry these
methods have not been used to the same
extent as in, for instance, the automobile
industry to improve productivity. Existing
research in mining mostly deals with the
technical aspects of the process, such as
optimising single units.
III
IV
ACKNOWLEDGEMENTS
A number of people have been highly
valuable to us in this Masters thesis project.
We would like to mention them here and
send them our deepest gratitude for
assisting us throughout the project.
TABLE OF CONTENTS
.
VII
APPENDIX
APPENDIX I
Process Maps
APPENDIX II
Lynxx Cameras Map
APPENDIX III
Job Card Inspections and Maintenance Map
APPENDIX IV
OPT Print Screens
APPENDIX V
OPT Manual
OPT Meeting Procedure
OPT Action List
Organisational Chart
VIII
CHAPTER ONE
INTRODUCTION
This chapter will introduce the Masters Thesis project by presenting a background of the
problem, a company introduction, earlier efforts in the area, the project aim and finally the
research questions
CHAPTER 1 - Introduction
refined platinum produced by their own
mines amounted to about 44 tons in 2011.
1.3 BACKGROUND
South Africa accounts for nearly 80% of
the global platinum production, which
makes the platinum price highly influenced
by the economy of the country.
CHAPTER 1 - Introduction
profitable operations during recent years.
(Mail & Guardian, 2011)
improve.
CHAPTER 1 - Introduction
Define a calculation
model for OEE &
other equipment
performance metrics
in a single stream
process
Design a method
describing how to use
the tool output in the
organisation with
primary focus on
finding root causes
1.7 DELIMITATIONS
The decision to limit the project to a subset of the plant is supported by Idhammar
(2010) who argues that implementing OEE
in a part of the plant will facilitate an
implementation throughout the plant at a
later stage. Idhammar also states that an
early pilot can eliminate issues and provide
useful training and experience for staff
members.
CHAPTER TWO
THEORETICAL FRAMEWORK
This chapter will present the theoretical framework used for the Masters thesis project.
The theoretical framework shall act to facilitate understanding for readers with no or little
former experience of the industry and the methodologies used in the project.
However, the targeted readers of the report are assumed to already possess a basic knowledge
in the area. Some basic definitions are therefore left out.
2.1 PRODUCTIVITY
A general definition is that productivity is
the amount of output per unit of consumed
resources or total costs incurred. Thus,
productivity is defined as how efficiently
the resources are being utilised in the
production of goods or services. Increasing
the productivity can hence be done by
increasing the output, in terms of volume
and quality, or decreasing the amount of
consumed resources with a constant or
increased output. (Prokopenko, 1992)
Productivity =
Output
Input
Equation 1
Equation 2
Equation 3
Availability
Performance
Quality
Operating Time
Gross Operating Time
Total Pieces
Equation 4
Equation 5
Figure: Freely after Method and a system for improving the operability of a production plant
The
Anglo
American
Equipment
Performance Metrics (a company internal
standard) offers another way of calculating
the OEE, which will be presented in this
section.
The metric corresponding to the general
OEE calculations availability is titled
Overall Utilisation (see Equation 6). This
Figure: Freely after Anglo American Equipment Performance Metrics Time Model
Overall Utilisation
Equation 6
Performance
Quality
Actual Quality
Target Quality
Equation 7
Equation 8
10
Equation 9
11
2.5 PERFORMANCE
MEASUREMENTS
Equation 10
Equation 11
MTTR
13
Person A
Person B
Decision A
Decision B
Decision C
14
Person C
Person D
Person E
2.8 PLATINUM
Platinum was discovered in 1735 in South
America by Ulloa and can be found
occurring naturally, accompanied by small
quantities of iridium, osmium, palladium,
ruthenium and rhodium, all of which
belong to the same group of metals, the
Platinum Group Metals (PGM) (The PGM
Database, 2012). Platinum is one of the
rarest elements in the Earth's crust and has
an
average
abundance
of
approximately
platinum
5g/kg.
Other
precious metals like
gold, copper and
nickel
denote
concentration in ores
in percentages, but
platinum
denotes
this in parts per
million. Based on a Figure 5 Platinum in
typical
conversion the periodic system
rate of 25%, 14 tons
of ore are required to produce 10 grams of
platinum. (Probert, 2012)
78
Pt
195.08
Platinum Gold
Chemical Symbol
Atomic number
Pt
78
Au
79
Atomic weight
195.084
196.967
Density (g/cm )
Melting point (C)
21.45
1769
19.30
1064
Vickers hardness
(MPa)
Electrical resistivity
(nohm-cm at 20C)
549
216
105
22.14
Tensile strength
(MPa)
125-240
120
15
2.9 EXTRACTION OF
PLATINUM-GROUP METALS
(PGMS)
16
CHAPTER THREE
METHODOLOGY
In this chapter the methodology of the thesis will be presented and analysed in order for the
reader to better understand the approach leading up to answering the research questions and
fulfil the project scope. First, the research strategy and approach are presented. Next, details
are given regarding the data collection methods used in the thesis project. Finally, reliability,
validity and ethical aspects of the study are discussed.
17
CHAPTER 3 Methodology
GROUNDED THEORY
A proper methodology when conducting
action research is to use Grounded theory,
which is defined as theory that is derived
from data, systematically gathered and
analysed through the research process.
(Strauss & Corbin, 1998, pp.12). This
implies that data collection, analysis and
eventual theory are closely related in an
iterative process.
Strauss and Corbin
(1998) claim that grounded theories, since
they are drawn from data, are likely to
offer insight, enhance understanding and
act as a meaningful guide.
3.3 THEORY
Before travelling down to South Africa the
pre-study was initiated in order for the
researchers to gain the basic knowledge
needed to understand the problem, become
familiar with the available process data and
the available theories in the area. Since
Anglo American Platinum already used
18
CHAPTER 3 Methodology
OEE as a measure, the study of OEE and
therefore also TPM became a natural part
of the studies. TPM also led the path to
studies of other maintenance fields, such as
Lean maintenance, which is closely linked
to improving productivity. The studies of
OEE were broadened by studying the
economic factors associated with improving
OEE numbers, which also provided
arguments for working with OEE
improvements.
INTERVIEWS
A major part of the qualitative data was
collected through numerous interviews with
persons involved in the production process
as well as management. The character of
the interview was dependent on the
position of the interviewee and the type of
information
sought
(qualitative
or
quantitative). The basic approach was an
unstructured interview in order for the
interviewee to further elaborate on the
questions asked. In
an
unstructured
interview, the interviewers do not follow
a strict structure of questions, but instead
might have only one or a few questions to
answer. The interview therefore resembles
a conversation. (Bryman & Bell, 2011)
SECONDARY DATA
The major part of the data is secondary in
the sense that it stems from information
from metallurgists and specialists, and that
no long-term observations beside the
machines have been conducted. Still, the
data is in most cases measured over a long
period of time, which in a sense increases
its accuracy. This gathering of data also
limited the cost of the project, though the
information might be difficult to
understand and interpret and there is
always a risk that some important
information may be left out of the material
handed to the researchers (Bryman and
Bell, 2011). The process data used for
calculation can also be seen as secondary
data. The process data comes from the PI
database were more than hundreds of
thousands of different measurement points
are logged.
OBSERVATIONS
In order for the researchers to acquire their
own understanding of the situation,
observations were conducted on site. This
helped with the understanding of the
specific steps in the production process as
19
CHAPTER 3 Methodology
3.4 RELIABILITY
3.5 VALIDITY
20
CHAPTER 3 Methodology
just because they are being studied. Due to
the long time period and the size of the
production system this has to be considered
as a low risk, but should still be kept in
mind in projects of this kind.
21
22
CHAPTER FOUR
DATA
This chapter will first present how the quantitative and qualitative data has been gathered.
Next, the empirical data, including a process map, presentation of the units included in the
project as well as some remarkable facts about the comminuting units, are presented. The
quantitative and qualitative data has, together with the empirical data, served as input to the
obtained results of this Masters thesis project.
23
CHAPTER 4 - Data
To provide a picture of how the developed
tool (called the Overall Productivity Tool
(OPT)) uses tags from the PI-database to
calculate the required metrics, see Table 3.
The table displays the measures used for
process area 406 to perform the required
calculations.
Table 3 The data extracted from the PI-database in order to calculate the OEE measures for area 406
UNIT
MEASURE
UNIT
MEASURE
HPGR Crusher
406-CR-001
Power [kW]
Conveyor
406-CV-003
Running [ON/OFF]
HPGR Screen 1
406-SC-001
Running [ON/OFF]
Conveyor
406-CV-004
Running [ON/OFF]
HPGR Screen 2
406-SC-002
Running [ON/OFF]
Conveyor
406-CV-005
Running [ON/OFF]
Conveyor
406-CV-006
Conveyor
406-CV-007
Belt scale
406-WT-010B
Speed [%]
Belt scale
406-WT-402
Belt scale
406-WT-416
Belt scale
406-WT-433
Lynxx camera
(placed at 406-CV-007)
Speed [%]
Speed [%]
Speed [%]
Running [ON/OFF]
Running [ON/OFF]
24
Running [ON/OFF]
Running [ON/OFF]
Mass [t]
Mass [t]
Mass [t]
Mass [t]
Size [mm]
CHAPTER 4 - Data
Plant Manager
Technical Manager
Operators
Planners
Head of R&D
Head of Engineering
Control Engineer
Production Leaders
Engineering Specialists
During
the
pre-study
in
Sweden
unstructured interviews were held with the
following persons at Chalmers University
of Technology from August 15th until
September 10th:
25
CHAPTER 4 - Data
COMMINUTION
Figure 6 - Process map displaying area 102-408 at MNC (For more detailed maps, see
Appendix I)
CONVEYOR
A conveyor is a unit which has the purpose
of moving or transporting bulk material or
26
CHAPTER 4 - Data
objects in a path predetermined by the
design of the conveyor. The conveyor can
be horizontal, inclined or vertical in its
design. At MNC, all bulk transports are
performed by conveyors and the total
length of all conveyors is approximately
9000 metres.
FEEDER
A feeder is a unit that puts material in
motion. Its purpose is to regulate the
amount of material that, for example, is fed
into a crusher or from a storage silo onto a
conveyor.
CLASSIFIER
AREA 102
Table 4 The name and number of units in process area 102
TYPE OF UNIT
Comminution unit
Feeder
Conveyor
Classifier
NO. OF
UNITS
1
2
2
0
NAME
102-CR-001 Primary crusher
102-FE-001 & 102-FE-002
102-CV-001 & 102-CV-002
-
AREA 401
Table 5 - The name and number of units in process area 401
TYPE OF UNIT
Comminution unit
Feeder
Conveyor
Classifier
NO. OF
UNITS
0
6
1
1
NAME
401-FE-001 - 401-FE-006
401-CV-001
401-GY-001 Grizzly
AREA 405
Table 6 - The name and number of units in process area 405
TYPE OF UNIT
Comminution unit
NO. OF
UNITS
3
Feeder
Conveyor
Classifier
5
6
2
NAME
405-CR-001 405-CR-003 Secondary Crushers
1,2,3
405-FE-001 405-FE-005
405-CV-001 405-CV-006
405-SC-001 & 405-SC-002 Secondary Screen 1 & 2
27
CHAPTER 4 - Data
AREA 406
Table 7 - The name and number of units in process area 406
TYPE OF UNIT
Comminution unit
Feeder
Conveyor
Classifier
NO. OF
UNITS
1
6
7
2
NAME
406-CR-001 HPGR Crusher
406-FE-001 406-FE-006
406-CV-001 406-CV-007
406-SC-001 & 406-SC-002 HPGR Screen 1 & 2
AREA 407
Table 8 - The name and number of units in process area 407
TYPE OF UNIT
Comminution unit
Feeder
Conveyor
Classifier
NO. OF
UNITS
0
2
2
0
NAME
407-FE-001 & 407-FE-002
407-CV-001 & 407-CV-003
-
IN TOTAL
Table 9 - The total number of units in process included in this project
TYPE OF UNIT
Comminution unit
Feeder
Conveyor
Classifier
NO. OF
UNITS
5
21
15
5
28
CHAPTER 4 - Data
CRUSHERS
LYNXX CAMERAS
MILLS
The primary and secondary mills are the
two first gearless mill drives (GMD) at
29
CHAPTER 4 - Data
30
CHAPTER FIVE
RESULTS
This chapter will present the results that have been obtained in the project. The results are
presented in three distinct sections Define, Develop and Design. The same sections are used
in the discussion and conclusions in order for the reader to more easily follow the red thread.
31
CHAPTER 5 - Results
Define a calculation
model for OEE &
other equipment
performance metrics
in a single stream
process
Design a method
describing how to use
the tool output in the
organisation with
primary focus on
finding root causes
Define a
model
32
CHAPTER 5 - Results
OEE
Utilised
Uptime
Availability
Overall
Utilisation
Performance
MTBF
&
MTTR
Process
Pain
Quality
OVERALL UTILISATION
PERFORMANCE
Primary Production
Total time
Equation 12
Equation 13
33
Equation 14
CHAPTER 5 - Results
Figure: Freely after Anglo American Equipment Performance Metrics Time Model
QUALITY
The method to calculate the product
Quality was developed by the Masters
thesis writers. The Quality looks at the
particle size and shows to what extent the
particle size is below the targeted size. The
target and actual particle size concerns the
P80 value, which is a commonly used value
in the comminution industry. P80 is defined
as the size where 80 percent of the material
passes a certain upper size limit. The
Quality 1
Target Size
n
n
Target Size
34
Equation 15
CHAPTER 5 - Results
deviation, an average deviation is
computed. This average deviation is then
divided by the Target Size and subtracted
from 1 to get a percentage between 0 and
100.
Oversized
particles
[mm]
Figure 11 - Example size distribution of P80 with target size marked
5.1.2 AVAILABILITY
OEE and its components is the first metric
in the calculation model. The second metric
is Availability.
In some cases, the Overall Utilisation
equation is not sufficient and/or applicable,
for instance when there is a lack of data. In
that case, Availability (see Equation 16) is
used. The Availability shows the
percentage uptime of the unit and is
defined as the ratio between Uptime and
Total Time.
35
CHAPTER 5 - Results
Availability
Uptime
Total Time
Utilised Uptime
Equation 16
Overall Utilisation
Availability
Equation 17
MTBF
Uptime
Number of stops
Equation 18
MTTR
Equation 19
Equation 20
i 1
36
CHAPTER 5 - Results
Along with the Pain equation, the Masters
thesis writers have developed the Pain
diagram which displays the errors with the
top 6 highest Pains, sorted in ascending
order (see Figure 12). This diagram gives a
clear view of the currently most alarming
errors in the process.
To facilitate the drilling down in stop
reasons, the frequency and downtime can
be displayed and analysed in a pyramid
diagram (see Figure 13).
37
CHAPTER 5 - Results
should therefore be taken into account
when setting target production rates.
PERFORMANCE
When calculating Performance, a Target
Production Rate is used for comparison
with the Actual Production Rate. The
Anglo American Equipment Performance
Metrics describes three ways of setting the
Target Production Rate, these ways are as
follows:
QUALITY
When calculating Quality, a Target Particle
Size is used for comparison with the Actual
Particle Size. The Target Particle Size at
different points in the process has been set
with advice from production experts at
MNC. The target is based on the particle
size demands of the downstream
comminuting unit.
5.1.7 CLASSIFICATION
Classification
Equipment
Circuits
Comminution
units
Supporting
equipment
(with available
measures)
Details
OEE
Overall
Utilisation
Performance
Quality
Availability
Utilised Uptime
OEE
Overall
Utilisation
Performance
Availability
Utilised Uptime
MTBF
MTTR
Pain
Overall
Utilisation
Availability
Utilised
Uptime
Supporting
equipment
(without
available
measures)
Availability
38
CHAPTER 5 - Results
The program extracts real time data from
the PI-database and computes the defined
metrics from the calculation model defined
in the first phase of the project.
Develop a
tool
CHAPTER 5 - Results
40
CHAPTER 5 - Results
CHAPTER 5 - Results
At the top of the sheet, above the charts,
Mean Time Between Failures (MTBF) and
Mean Time To Repair (MTTR) are
displayed for the crushing unit in the area.
42
CHAPTER 5 - Results
successful
combination.
The
group
members different backgrounds help to
create a broader view of the OPT output. If
a cross functional group is used, it also
helps to increase the collaboration between
departments and limits dual work. The
OPT Methods incorporated action list
facilitates tracking of issued actions, which
has been seen necessary in large
organisations.
Another positive effect is
that cross-functionality unites the users
among a common systematic problem
solving technique.
Design a
method
Figure 25 Project
phase three - Design
OPT Manual
OPT MANUAL
The OPT Manual is a complete guide on
how to use the tool. It provides a step-by43
CHAPTER 5 - Results
step guide on how to run the OPT software,
explanations of the sheets in OPT (OEE,
OEE Table and Pain and Stop Table),
definitions of the metrics displayed and
examples of how to interpret the output
values. The OPT Manual shall be used to
facilitate the usage of OPT for both
experienced users and beginners.
ACTION
1. Meeting Preparations
a. Update OPT
b. Review Action List from previous
meeting
DATE
OUTCOME
3. Running OPT
a. Review outcome
b. Analyse outcome
c. Use the 5 WHYs to find root
causes of encountered issues
44
CHAPTER 5 - Results
Uptime
Total Time
Availability
Performance
Quality 1
Equation 21
Equation 22
Target Size
Equation 23
i
n
Target Size
45
CHAPTER 5 - Results
preparation to get it to a stage where it
could be analysed. Therefore, a new system
that allows all the crusher and mill stops
data to be recorded and reported daily in
electronic format has been developed and
implemented at MNC by the Masters
thesis writers. This procedure has
eliminated the manual work involved when
creating the crusher and mill stop reports
and also reduced the risk for manual data
entry errors. A map of the new procedure
46
CHAPTER SIX
47
CHAPTER 6 - INTRODUCTION
TO DISCUSSION
6.1 CALCULATION
MODEL
Define a
model
Define a calculation
model for OEE &
other equipment
performance metrics
in a single stream
process
Design a method
describing how to use
the tool output in the
organisation with
primary focus on
finding root causes
OVERALL UTILISATION
The metric Overall Utilisation shows the
units time distribution as the percentage of
time the unit is used for primary production.
This is the metric which represents the time
usage in OEE. However, it will not show
the percentage of time the unit has been
available for production, merely the time it
has been utilised. By looking at the Overall
Utilisation one cannot tell whether the unit
has been utilised all the available time or if
there is more available time to utilise. That
is, one cannot tell if the available time has
to be increased in order to increase the
utilisation or if the utilisation can be
increased without increasing the availability
of the unit. To be able to determine this,
OPT presents both Availability and Overall
Utilisation (see section 6.1.2) for all
possible units. Displaying of both the
Overall Utilisation and the Availability
facilitates the understanding of the
distribution of the equipments total time.
To clarify the relation between Overall
Utilisation and Availability, the Masters
thesis writers defined a metric referred to
as Utilised uptime (see section 6.1.3), which
is the ratio between Overall Utilisation and
Availability.
49
Equation 24
PERFORMANCE
The Performance of a unit has two
components, Target Production Rate and
Actual Production Rate, and is computed
as the ratio between the two. This means
that the Performance is as affected by the
Actual rate as the Target rate. The Actual
rate is determined by data extracted from
the PI-database and is only dependant on
the performance of the process unit. The
Target rate is set by the organisation
following certain guidelines (see section
5.1.6 Setting Filters & Target Values). This
in turn means that a rate set by the
organisation has a huge part in deciding the
Performance rate of a unit. Therefore, the
setting of the Target Production Rate needs
to be done very carefully, otherwise
Performance can turn out to be a
misleading metric.
QUALITY
The new definition of Quality (see
Equation 25) combined with the method of
how to, in practice, determine quality in a
single stream comminution process has not
been seen before. The development of a
quality metric makes the OEE calculation
complete and provides a more accurate
OEE value than previously when the
quality most often was assumed to be 100%
in a process such as this one. It is a wellworking method, however it could be
refined. It does not take into account the
magnitude of the deviations below target
size but assumes all sizes below target to
have a quality of 100%. The method could
be refined to take those variations into
account, which would result in a more
accurate quality measure. At MNC, there
was no need for lower particle size limits
since all particles smaller than target size
were accepted.
Quality 1
Target Size
Equation 25
n
Target Size
51
6.1.2 AVAILABILITY
52
Utilised Uptime
Overall Utilisation
Availability
Equation 26
53
54
Classification
Equipment
Circuits
Comminution
units
Supporting
equipment
(with available
measures)
Supporting
equipment
(without
available
measures)
Details
OEE
Overall
Utilisation
Performance
Quality
Availability
Utilised Uptime
OEE
Overall
Utilisation
Performance
Availability
Utilised Uptime
MTBF
MTTR
Pain
Overall
Utilisation
Availability
Utilised
Uptime
Availability
56
Develop a
tool
Design a
method
59
60
6.7 OBSERVATIONS
One of the reasons for spending a
considerable period of time on site was for
the researchers to observe the day-to-day
activities and gain a greater understanding
of the operations. Various observations
have been made during the time spent on
site. Only those that were deemed
important for plant productivity are
reported here.
FOLLOW-UP
The plant has done well in following up on
most of the issues that have arisen. It is
commendable for a plant with such a large
capacity to carry out most of the follow-up
tasks as they do. However, the
documentation and formal report back on
the actual effects of performed process
changes targeted for follow-up on tasks that
need a review is not stringent. This leads to
failure to attend to some of the cases
targeted for follow-up. If the records and
report backs do not capture the follow-up
information and the effects of the change,
the plant would take it for granted that
follow-ups are done continuously even
though some of the key matters are not
getting any attention. This can be the case
PROBLEM SOLVING
Observations have been made regarding
the problem solving procedures in the
operations. Although many tasks in the
operations involve problem solving, there
seem to be no defined structure and
documentation of procedures used in
recurring tasks. Granted, while most of the
employees have many years of experience,
62
JOB CARDS
The current system for maintenance relies
on the SAP to generate job cards which in
most cases works well. However, some
areas in the process do not have access to
job cards because some tasks lack a
dedicated functional code in the system.
The problem that arises from this is that
some jobs are performed without job cards
and therefore cannot be easily tracked.
Further, all existing job cards should be
continuously reviewed to keep them
aligned with the continuously changing
process.
INTER-DIVISIONAL
COMMUNICATION & COOPERATION
Throughout the organisation there is a
common drive to produce concentrate as
effectively as possible and to maintain the
plant in a good operational state. This is
clearly visible even for external observers
like the researchers who prepared this
report. However, the plant is fairly large
and it takes a long time for information to
reach all the relevant people in various
sections of the operations. There is an
opportunity to implement information
structures that can help visualise
information between divisions of the
operation. This will also reduce duplication
GOVERNANCE
MNC has a defined structure in terms of
the
sections
of
engineering,
technical/metallurgy and production which
is commendable. It is also evident that
63
6.8 RECOMMENDATIONS
Recommendations for the outcome of this
project mainly concern the usage and
future development of the Overall
Productivity Tool (OPT). The development
of OPT should continue before the new
platform is completed, it is highly
recommended that the current users of
OPT continue to provide feedback on how
the tool is used and how it can be improved
by suggestions for improvements can be
incorporated in the follow up version. The
users are encouraged to thoroughly test the
different methods suggested by the
Masters thesis writers since these have not
been fully evaluated on a production plant.
Another important aspect of the methods is
that they should be tested by several
different users and not only the main users
to provide information on how user
friendly the tool is. It is crucial to do this in
order to receive feedback from experienced,
as well as new, users before further
development options proposed.
64
65
REFERENCES
REFERENCES
Ahlmann, H., (2002). From traditional practice to the new understanding: the significance of the
Life Cycle Profit concept in the management of industrial enterprises. In: IFRIM (International
Foundation for Research in Maintenance), Maintenance Management & Modelling conference.
Vxj 2002, Vxj, Sweden: International Foundation for Research in Maintenance
Anglo Platinium webpage (updated 2011), About Anglo Platinum (Electronic). Available at:
http://www.angloplatinum.com/about/about_sub/comp_profile.asp [Accessed August 15, 2012]
Bryman, A., and Bell, E., (2011). Business Research Methods (3rd ed.). Oxford: Oxford
University Press.
Crundwell, F., Moats, M., Ramachandran, V., Robinson, T., Davenport, W.G., (2011),
Extractive Metallurgy of Nickel, Cobalt and Platinum Group Metals, Elsevier, ISBN 978-008096-809-4
Dressler, S., (2004), Strategy, Organization and Performance Management. From Basics to Best
Practices, Universal-Publishers, ISBN 978-1-58112-532-0
Gulati, R., (2009), Maintenance and Reliability Best Practices, Industrial Press, Inc., ISBN: 9780-83112-211-5
Halachmi, A., "IntroductionPerformance Measurement is Only One Way of Managing
Performance" International Journal of Productivity and Performance Management:
Performance Measurement and Performance Management, Volume 54, Number 7,
2005. Emerald Group Publishing 2005.
http://common.books24x7.com.proxy.lib.chalmers.se/toc.aspx?bookid=13077
[Accessed November 2, 2012]
Hansen, R C., (2001). Overall Equipment Effectiveness A Powerful Production / Maintenance
Tool for Increased Profits. New York, Industrial Press, Inc. ISBN 0-8311-3138-1
Idhammar Systems Ltd., (2010), Implementing OEE Systems. [online] Bristol: Idhammar
Systems Ltd., Available at:
http://www.idhammarsystems.com/resource%20library/overview/whitepapers/ [Accessed
September 13, 2012]
Kato, I. and Smalley, A., (2011), Toyota Kaizen Methods: Six Steps to Improvement. Taylor and
Francis Group, Productivity Press. ISBN: 978-1-4398-3854-9
Kitco webpage (updated 2012), Live Charts (Electronic), Available at:
http://www.kitco.com/charts/livegold.html [Accessed October 25, 2012]
Lesshammar, M., (1999), Evaluation and improvement of manufacturing performance
measurement systems the role of OEE, International Journal of Operations and Production
Management, vol. 19, no. 1, pp. 55-78
Liker, J. K. and Convis, G. L., (2012). The Toyota Way to Lean Leadership: Achieving and
Sustaining Excellence through Leadership Development. McGraw-Hill. ISBN: 9780071780780
66
REFERENCES
Liker, J. K., and Franz, J. K., (2011), The Toyota Way to Continuous Improvement: Linking
Strategy and Operational Excellence to Achieve Superior Performance. McGraw-Hill USA.
ISBN: 978-0-07-176215-1
Ljungberg, ., (2000), TPM Vgen till stndiga frbttringar. Lund: Studentlitteratur. ISBN:
978-91-44-00837-0
Luotojarvi, M., 2009-04-09, Method and a system for improving the operability of a production
plant, US 2009/00940880 A1, United States of America.
Mahadevan, B., (2009), Operation Management: Theory and Practice, Prentice Hall, ISBN:
978-8-17758-564-3
Mail & Guardian webpage (updated 2011), Platinum's pluses and minuses (Electronic),
Available at: http://mg.co.za/article/2011-11-25-platinums-pluses-and-minuses [Accessed
October 25, 2012]
Maran M., Manikandan G., and Thiagarajan, K., (2012). Overall Equipment Effectiveness
Measurement By Weighted Approach Method. In: IMECS (International MultiConference of
Engineers and Computer Scientists), International MultiConference of Engineers and
Computer Scientists 2012. Hong Kong, 14-16 March 2012.
Merriam-Webster, Opt Definition (Electronic) Available at:
http://www.merriam-webster.com/dictionary/opt [Accessed November 30, 2012]
Mining Weekly webpage (updated March 14, 2008), Biggest platinum concentrator achieves
safety milestone at PPRust, Available at: http://www.miningweekly.com/article/biggestplatinum-concentrator-achieves-safety-milestone-at-pprust-2008-03-14 [Accessed November
30, 2012]
Nadler, D, Tushman, M., (1997) Implementing New Designs: Managing Organisational Change.
Managing Strategic Innovation and Change: A collection of readings, First edition, pp 596-606.
Oxford University Press, New York.
Nakajima, S., (1989). Introduction to TPM. Cambridge, Mass.: Productivity Press
Oxford Dictionaries, Definition of comminution (Electronic) Available at:
http://oxforddictionaries.com/definition/english/comminution [Accessed November 30, 2012]
Oxford Dictionaries, Definition of kaizen (Electronic) Available at:
http://oxforddictionaries.com/definition/english/kaizen [Accessed December 11, 2012]
Perrin, R., (2008), Real World Project Management: Beyond Conventional Wisdom, Best
Practices and Project Methodologies, John Wiley & Sons, ISBN: 9780470170793
The PGM Database, Metals Data (Electronic) Available at:
http://www.pgmdatabase.com/jmpgm/index.jsp [Accessed August 15, 2012]
Probert, T., (2011). Rocking around the clock in SA. African Review of Business and
Technology, February 2012, pp.56-57.
67
REFERENCES
Platinum Today webpage (updated 2012), Properties of platinum group metals (Electronic),
Available at: http://www.platinum.matthey.com/applications/properties-of-pgm/ (2012-08-15)
Prokopenko, J., (1987). Productivity management: A practical handbook. International Labour
Office, ISBN: 92-2-105901-4
Rich, N., Esain, A., Bateman, N., Massey, L., Samuel, D., (2006). Lean Evolution: Lessons
from the Workplace. Cambridge University Press.
Scheinberg, S. (2009). From Inner to Outer Integration of Refugees and Immigrants in
the Swedish Society: A Gestalt Intervention in Joseph Melnick and Edvin C. Nevis eds.
Mending the World: Social Healing Interventions by Gestalt Practitioners Worldwide, A
Gestalt International Study Center Publication, p. 206-240
Smith, R. and Hawkins, B., (2004). Lean Maintenance, Butterworth Heinemann ISBN: 978-07506-7779-0
Strauss, A., and Corbin J.M., (1998). Basics of Qualitative Research: Techniques and
Procedures for Developing Grounded Theory. Thousand Oaks, California: Sage.
Taylor Fitz-Gibbon, C., (1990). "Performance indicators", BERA Dialogues (2), ISBN 978-185359-092-4
68
II
III
IV
VI
II
II
II
III
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
OPT MANUAL
GUIDELINES TO THE OVERALL PRODUCTIVITY TOOL (OPT)
IV
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
3. To update the OEE calculations for the previous month, click the grey button named Previous
Month and wait until a dialogue box opens and confirms the update.
4. To update the Pain analysis for the previous month, go to the sheet named Pain and click the
grey button named Previous Month and wait until a dialogue box opens and confirms the
update.
Note that the Pain analysis for the previous month has to be updated before updating the
previous 7 days in order to display the stop table for the previous 7 days under OEE Table sheet.
5. To update the Pain analysis for the previous seven days, go to the sheet named Pain and
click the grey button named 7 days and wait until a dialogue box opens and confirms the
update.
6. OPT is now updated according to the dates displayed on top of each sheet under Start and
End.
Note that the document shall be saved before closing down.
OEE CALCULATIONS
Two sheets in the Overall Productivity Tool (OPT) concern OEE calculations; those are named
OEE and OEE Table.
OEE SHEET
The OEE sheet displays charts with the OEE for the circuit and the crushing unit in the
monitored area. It also displays charts with the Overall Utilisation, Performance, Quality,
Availability, and Utilised Uptime for all units included in the monitored area.
The charts are sorted in ascending order to visualise what units that currently have the lowest
Overall Utilisation, Availability and Utilised Uptime. The abbreviations of the units are explained
in the OEE Table sheet.
To the right of the charts boxes with explanations of the charts and their metrics are provided.
At top of the sheet, the monitored time intervals are displayed. For information on how to
update these and the tables to the current end time, see section How to Update Calculations.
VI
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
The definition of any displayed component can be viewed by hovering over the component name
(see Figure 3, where the pointer is hovered over Availability).
Poor
Alarming
The colour limits for the different units can be seen at the bottom of the sheet. The limits shall be
set based on the business targets of those values and should only be changed by the
administrator of OPT.
The cells with a grey background colour are target values which shall be changed if process
changes resulting in target changes are performed. The target values should be changed only by
the administrator of OPT.
All set targets shall be reviewed if the process has been changed in such way that the current
target parameters are invalid.
Parameters to be reviewed:
VII
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
At top of the sheet, the monitored time intervals are displayed. For information on how to
update these and the tables to the current end time, see section How to Update Calculations.
PAIN ANALYSIS
Two sheets in the Overall Productivity Tool (OPT)concern the Pain analysis; those are named
Pain and Stop Table.
PAIN SHEET
Pain is a way of visualising the combination of frequency and downtime of stops occurred in the
monitored area. The Pain sheet displays charts with the top 6 Pains in the monitored area.
The charts are sorted in descending order to visualise what stop reasons that currently are
causing the largest Pain. The stop reasons are labelled below each bar in the chart. The unit for
the y-axis is thousand minutes, however, pain is displayed as a unitless metric.
At the top of the sheet, above the charts, Mean Time Between Failures (MTBF) and Mean Time
To Repair (MTTR) are displayed for the units.
At the top of the sheet, the monitored time intervals are displayed. For information on how to
update these and the tables to the current end time, see section How to Update Calculations.
More detailed stop information, such as stop time, start-up time, duration of stop, comment and
downtime codes, can be found in the Stop Table sheet.
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
DEFINITIONS OF METRICS
The following metrics are used in OPT and has to be understood in order to utilise OPT as
effectively and correctly as possible.
OVERALL UTILISATION
The Overall Utilisation is the percentage of the total time that the unit is utilised for primary
production. It is the ultimate performance indicator of how total calendar time is utilised.
Overall Utilisation = Direct Operating Time / Total time
Direct Operating Time (T300): Time the unit is performing primary production activities
Total time (T000): Total time in chosen time interval (24/7)
PERFORMANCE
The Performance is the production rate at which the operation runs as a percentage of its
targeted rate.
Performance = Actual Production Rate / Target Production Rate
Actual Production Rate = Actual Production Achieved / Primary Production
Actual Production Achieved: Actual tonnes produced during chosen time interval
Primary Production (P200): Time equipment is utilised for production.
For time definitions, see Figure 4.
QUALITY
The Quality looks at the P80 particle size and shows to what extent the particles size is below the
targeted size. It compares the Actual Particle Size at a certain point in the process to the Target
Particle Size. The Quality is defined as the mean deviation above Target Size as a percentage of
the Target Size. This implies that all particles below target size results in zero in deviation. To
get the Quality and not the deviation, the ratio is subtracted from 1.
n
Quality = 1
AVAILABILITY
IX
i 1
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
The Availability is the percentage of the total time that the unit is available for production
activities.
Availability = Uptime / Total time
Uptime (T200): Time the unit is available for production activities
Total time (T000): Total time in chosen time interval (24/7)
For time definitions, see Figure 4.
UTILISED UPTIME
The Utilised Uptime is the percentage of the available time that the unit is being utilised for
primary production.
Utilised Uptime = Direct Operating Time / Uptime
PAIN
Pain is calculated as the product of frequency of the error and total stop time caused by the
error.
Pain = Frequency of error x Total stop time caused by error
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
5 WHYS
OEE
OEE is not just a number; it can be up to four numbers the OEE, Overall
Utilisation, Performance and Quality. It is important to look into all the
factors when analysing an OEE number. If an OEE number found in the
OEE sheet is found to be of interest, it can be viewed in more detail in the
OEE Table sheet. There, all components of the OEE can be seen and
analysed individually.
XI
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
LOW
OEE
HIGH
OEE
OVERALL
UTILISATION
LOW
OVERALL
UTILISATION
HIGH
OVERALL
UTILISATION
The Performance shows the production rate at which the unit or circuit
runs as a percentage of its targeted rate. This means that the targeted
PERFORMANCE rate has a large influence on the achieved Performance; therefore, it is
highly important that the Target rate is carefully determined. Otherwise,
the Performance measure will be misleading.
A low Performance indicates a Production Rate far below the targeted
rate during the primary production time. This can be due to either a very
LOW
long production time or low production achieved. To increase the
PERFORMANCE
Performance, a higher achieved production has to be reached during the
production time or the same amount of production has to be reached in
shorter time.
A high Performance indicates that the production rate is close to the
HIGH
targeted Production Rate. A unit or circuit with high Performance can
PERFORMANCE provide useful information on how this can be achieved. The user should
learn from this and apply it on other units and circuits.
The Performance can exceed 100%. This will occur when the Production
PERFORMANCE Rate is greater than the Target Rate. This indicates that the target rate
>100%
has to be reviewed. If process changes have been made in such way that
XII
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
the current target parameters are invalid, the Target Rate shall be
adjusted accordingly.
QUALITY
The Quality looks at the P80 particle size and shows to what extent the
particles size is below the targeted size. It looks at the mean particle size
deviation above the targeted size. This implies that all particles below
target size results in zero in deviation, hence 100% in Quality.
LOW
QUALITY
A low quality indicates that the mean particle size is far above the Target
Size. The actual particle size and mean deviation are displayed in the
sheet OEE Table. If the Quality is low, the downstream process might be
affected and it should be beneficial to look at the performance of the
downstream units.
HIGH
QUALITY
AVAILABILITY
A high Quality indicates a mean particle size below the Target Size. If all
particle sizes are below the targeted size, the Quality will be 100%. The
actual particle size and mean deviation are displayed in the sheet OEE
Table.
The Availability shows to what extend the unit has been available for
production. It does not have to be used during that time; however, it has
to be available. Availability has a strong connection to Overall Utilisation.
Those two metrics are complementary since they present the unit
running time in two different aspects. The Availability is in most cases a
larger number since it is including a broader span of time, i.e. all the time
the unit has been switched on, whereas the Overall Utilisation only
includes the time the unit has been performing production.
A low Availability indicates a large proportion of non-running time. The
LOW
Availability can be increased by extending the unit Uptime, which implies
AVAILABILITY reducing the unit downtime. For the crushing units, the downtimes can
be seen in the Stop Table sheet.
A high Availability indicates a large proportion of running time. This
HIGH
implies that the downtime and non-controllable time both are low. A unit
AVAILABILITY with high Availability can provide useful information on how this can be
achieved. The user should learn from this and apply it on other units.
UTILISED
UPTIME
LOW
UTILISED
UPTIME
To show the ratio between Availability and Utilised Uptime, a rate called
Utilised Uptime is displayed in OPT. The Utilised Uptime is the proportion
of the Available time that has been utilised for production.
A low Utilised Uptime indicates a low utilisation of the time the unit
actually has been available for production. This shows a possibility to
increase the production of the unit by only increasing the utilised time,
without increasing the available time of the unit or reducing the unit stop
time. In fact, if the availability increases and the production time is
constant, the Utilised Uptime will decrease.
XIII
OPT Manual
Developed by: Anton Kullh & Josefine lmegran, 2012
HIGH
UTILISED
UPTIME
PAIN
A high Utilised Uptime indicates a high utilisation of the time the unit has
been available for production. An Utilised Uptime of 100% indicates that
all available time has been utilised for production. This means that both
the available time and the utilised time have to be increased in order to
increase production. A unit with high Utilised Uptime can provide useful
information on how this can be achieved. The user should learn from this
and apply it on other units.
The Pain charts show the top 6 highest Pains for the crushing unit.
A high Pain of a failure indicates one of the following:
HIGH
PAIN
MTBF
LOW
MTBF
A low MTBF indicates that the unit fails frequently. The aim is to
maximise the MTBF. Actions should be taken to investigate how to solve
the problem.
HIGH
MTBF
A high MTBF indicates that the unit does not fail frequently. A unit with
high MTBF can provide useful information on how this can be achieved.
The user should learn from this and apply it on other units.
MTTR
Mean Time To Repair (MTTR) shows the average time required to repair
the failed unit.
HIGH
MTTR
LOW
MTTR
A high MTTR indicates that the downtime per failure is long. The aim is to
minimise the MTTR. Actions should be taken to investigate how to solve
the problem.
A low MTTR indicates that the downtime per failure is short. A unit with
low MTTR can provide useful information on how this can be achieved.
The user should learn from this and apply it on other units.
XIV
XV
3
RESPONSIBILITY ROLES
ACTION
Completed? Action
Responsible
Accountable
Consulted
DATE
Informed
Due date
OUTCOME
Completion date
Result
Conclusions
Natalie
Albert
Natalie
Dane
Dane
-
Ellie, Natalie
2012-12-01
2012-12-10
2012-11-30
John
Phillemon
Philip
Natalie
Dane, John
Dane
2012-12-01
2012-12-30
2012-12-02
No
Dane
Natalie
John, Philip
2013-01-14
Yes
Felix
Dane
Herman
2012-11-25
2012-11-23
Yes
No
Yes
No
XVI