Foundation For A Commercial Complex

The document discusses the foundation project for a commercial complex near Villivakkam, Chennai with an estimated cost of 1.75 crores. The foundation involved 53 bored piles of varying diameters from 900-1200mm and depths from 35-41m. The main contractor is CCCL and subcontractor for pile foundation is Geo Foundation and Structures. Approximately 35 people are employed daily including 5 rig operators, 20 helpers, 1 welder, 8 bar benders and 1 mechanic. Materials consumed so far include 9826 cement bags, 1.03 million kg of sand and 2.06 million kg of stone. Labour rates range from Rs. 180-250 and material costs are Rs. 220/bag for cement, Rs

Uploaded by

Umar Saba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
69 views2 pages

Foundation For A Commercial Complex

The document discusses the foundation project for a commercial complex near Villivakkam, Chennai with an estimated cost of 1.75 crores. The foundation involved 53 bored piles of varying diameters from 900-1200mm and depths from 35-41m. The main contractor is CCCL and subcontractor for pile foundation is Geo Foundation and Structures. Approximately 35 people are employed daily including 5 rig operators, 20 helpers, 1 welder, 8 bar benders and 1 mechanic. Materials consumed so far include 9826 cement bags, 1.03 million kg of sand and 2.06 million kg of stone. Labour rates range from Rs. 180-250 and material costs are Rs. 220/bag for cement, Rs

Uploaded by

Umar Saba
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

INTRODUCTION

FOUNDATION FOR A COMMERCIAL COMPLEX


The topic we undertaken for our project is a foundation for a commercial complex
near Villivakkam (Chennai) at an estimated cost of nearly 1.75crores.The work has been
awarded to M/S CCCL . Foundations are made as bored (DMC-Direct Mud Centering)
pile. There are about 53 piles of varying dia (900, 1200 mm ) and the total depth varies
from 35m - 41m.The site had been dug up to 2.5m below GL and total no of rigs operated
are 5 nos. and the minimum saw cut length is 3m.

Persons Employed
Main contractor

: CCCL

Sub contractor
(pile foundation)

: Geo Foundation and Structures

Approximate Man power employed per day


RIG operators

: 5 Nos

Helpers

: 20 Nos

Welder

: 1 No

Bar Bender

: 8 Nos

Mechanic

: 1 No

Material consumption for 90% completion of project

Cement

: 9826 bags

Sand

: 1.03x10^6 kg

HBG broken Stone

: 2.06 x10^6 kg

Rates of Labour and Material involved


Labour
1. RIG operators

: 250

2. Helpers

: 180

3. Welder

: 200

4. Bar Bender

: 180

5. Mechanic

: 200

Material

Cement

: Rs. 220/bag

Sand

: Rs. 9/cft

HBG broken Stone

: Rs. 25/cft