Cyclone Project

The document presents a network diagram and Gantt chart for the CyClon Project. The network diagram shows the 13 activities in the project, their durations, dependencies, and the critical path. The critical path runs through activities 2-3-5-6-7-8-10-11-12-13 and has a total duration of 80 days. The Gantt chart further illustrates the start and end dates of each activity to visualize the project schedule over the 80 day period.

Uploaded by

Anusha Javaid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
351 views8 pages

Cyclone Project

The document presents a network diagram and Gantt chart for the CyClon Project. The network diagram shows the 13 activities in the project, their durations, dependencies, and the critical path. The critical path runs through activities 2-3-5-6-7-8-10-11-12-13 and has a total duration of 80 days. The Gantt chart further illustrates the start and end dates of each activity to visualize the project schedule over the 80 day period.

Uploaded by

Anusha Javaid
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

Prepared By:

Sajal Faheem
Hashaam Ahmed
Yasir Ali
Ahmad Arbab

CyClon Project Network diagram

10
0
10
0

Design

10

20

Procure
prototype
Parts

10

20

10

20
0

10

20
10
2
12

Legend

24

Assemble
Prototype

24

18

Fabricate
parts

20

The project will take 80 days


The critical path is shown
It is 2-3-5-6-7-8-10-11-12-13

ES
ID
EF
SL Description
LS DUR LF

Gantt Chart
Activity
2
3

Description
Design
Procure prototype parts

4
5
6
7
8
9
10
11
12
13

Fabricate parts
Assemble Prototype
Laboratory test
Field Test
Adjust Design
Order stock components
Order custom components
Assemble test production uni
Test unit
Document results

CyClone Pro
10-May
Design
Procure prototype parts
Fabricate parts
Assemble Prototype
Laboratory test
Field Test
Adjust Design
Order stock components
Order custom components
Assemble test production unit
Test unit
Document results

15-May

20-May

25-May

30-May

4-Jun

9-Jun

24
0
24

31

31

Laboratory
test

31

31

41

Field Test

10

41

41
0
41

47

Adjust
Design

47

oject will take 80 days to complete


critical path is shown in the above network diagram with red arrows.
-5-6-7-8-10-11-12-13

Start Date

Duration

10-May
20-May

10
10

Note: For the purpose of making the Gantt chart I h

20-May
30-May
3-Jun
10-Jun
20-Jun
26-Jun
26-Jun
11-Jul
21-Jul
26-Jul

Note: For the purpose of making the Gantt chart I h


and the weekends or other holidays are already ac

8
4
7
10
6
10
15
10
5
3

CyClone Project Gantt Chart

May

4-Jun

9-Jun

14-Jun

19-Jun

24-Jun

29-Jun

4-Jul

9-Jul

14-Jul

19-Jul

24-Jul

29-Jul

47
5
52

57

Order stock
components

10

62
62
0
62

47
0
47

10

11

72

72

Assemble test
production
unit

10

72

0
72

62

Order custom
components

15

62

aking the Gantt chart I have assumed that the project Started on 10th May 2015

12

77

Test unit
5

77

er holidays are already accounted for in duration

9-Jul

24-Jul

29-Jul

3-Aug

77
0
77

13
80
Document
results
3
80