JKR 203W
JKR 203W
1/2008)
KERAJAAN MALAYSIA
JABATAN KERJA RAYA
PERAKUAN PENDUDUKAN SEPARA
Refferences .............................
Company Address .........................................
.........................................
.........................................
.........................................
Date .........................................
To .....................................
..........................................
..........................................
(Contractor)
Registered with PKK Class ................
Cotract No ...................................................................................................................................
Contract For ................................................................................................................................
.....................................................................................................................................................
.....................................................................................................................................................
Description of the part of the works occupied :
.....................................................................................................................................................
In accordance with Clause 42 of the Condition of Contract, the Goverment is desirous
Of taking possession and occupying the part of the Works as mentioned above (hereinafter reffered to
as the relevant Part) before the Practical Completion of the whole of the works, and with your written
consent dated ................................ to the same, it is hereby certified that the relevant Part has been
satisfactorily complete on .................................... and taken into possession and occupied
on ................................ and that the Defects Liability Period in respect of the relevant Part shall
commence on ................................ and the end on ..............................
2. The estimated value of the relevant Part completed and taken into possession and occupied is
RM .....................................
3. The relevant Part having been completed and taken into possession and occupied, the
Liquidated and Ascertained Damages as stated in the Appendix to the Conditions of Contract is hereby
reduced from RM ................................. per .................................. to RM .............................
RM ............................... per .................................... in accordance with Clause 42(d) of the Condition of
Contract.
...........................................................
Superintending Officer/SO Rep.
Name in Full ...................................................
Designation ....................................................