Hitung Volume Galian Dan Timbunan Untuk Daerah

The document discusses methods for calculating excavation and fill volumes for an area using the four average corner method. It then provides an example calculation and presents the volume calculations. It also provides specifications for a CAT 769C dump truck, including its capacities, weights, and traction calculation. Finally, it outlines tasks for earthworks including excavation and transportation of soil from a quarry area to a construction site, and provides data on loaders and dump trucks used, including their cycle times and costs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
88 views9 pages

Hitung Volume Galian Dan Timbunan Untuk Daerah

The document discusses methods for calculating excavation and fill volumes for an area using the four average corner method. It then provides an example calculation and presents the volume calculations. It also provides specifications for a CAT 769C dump truck, including its capacities, weights, and traction calculation. Finally, it outlines tasks for earthworks including excavation and transportation of soil from a quarry area to a construction site, and provides data on loaders and dump trucks used, including their cycle times and costs.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

1.

Hitung volume galian dan timbunan untuk daerah

Dengan menggunakan metode four average corner, diasumsikan nilai


kanan bawah untuk kotak no.VII = 258 dan nilai kanan bawah untuk kotak
no.VIII = 259

Four Average Corner


Vc = (L2 x Hc2) / 4(Hc + Hf)
Vf = (L2 x Hf2) / 4(Hc + Hf)
Sehingga didapat :

Contoh Perhitungan :
No. I
Hc = 0 (karena di kotak I tidak terjadi proses penggalian)
Hf = (255 250) + (255 252) + (255 251) + (255 253)
= 14
Vc = (L2 x Hc2) / 4(Hc + Hf)
= (L2 x 0) / 4(0+14)
=0
Vf = (L2 x Hf2) / 4(Hc + Hf)
= (L2 x 142) / 4(0+14)
= 3,5 L2
No. II
Hc = 255 257 = -2
Hf = (255 252) + (255 253) + (255 253)
=7
Vc = (L2 x Hc2) / 4(Hc + Hf)
= (L2 x - 22) / 4(-2+14)
= 0,2 L2
Vf = (L2 x Hf2) / 4(Hc + Hf)
= (L2 x 72) / 4(0+14)
= 2,45 L2
Sehingga didapat :
Vc = Vc I + Vc II + Vc III + Vc VI + Vc VII + Vc VIII
= 0 + 0,2 L2 + (-2,3) L2 + 0,8 L2 + (-2,5) L2 + (-3,3) L2
= -7 L2
Vf = Vf I + Vf II + Vf III + Vf VI + Vf VII + Vf VIII
= 3,5 L2 + 2,45 L2 + (-0,25) L2 + 3 L2 + (-0,2) L2 + 0
= 8,5 L2
2. Dump truck CAT 769C

Max capacity 17.5 m3 (struck) and 23.6 m3 (heaped)


Max load 36.1 tons
Soil density = 1.65 tons/B m3
% swell = 15%
Loaded distribution (rear : front = 67% : 33%)
Coefficient of traction = 0.55
Find tractive effort
Answer :
Operating weight (empty) : 31.178 kg
Top Speed (loaded)
: 75 km/hr
Max Gross Vehicle Weight : 67.586 kg
Weight Distribution
Empty- Front:
50 %
- Rear :
50 %
Loaded
- Front:
33 %
- Rear :
67 %
i.

Payload (Hauled Load)


Volume
Dry density (bank)
: 1.650 Kg/m3
% Swell
: 15%
Dry density (loose)
:

% swell
0,15

Dry density (loose)


Swell factor
SF

Dry density ( bank )Dry density (loose)


Dry density (loose)
1650Dry density (loose)
Dry density (loose)
=

= 1.435 Kg/m3
:
=
=

Dry density (loose)


Dry density (bank )
1435
Kg/m3 x 100%
1650

= 87 %
Payload
Max Payload
kg (struck)

= 27.5 m3 = 27.5 m3 x 1.435 Kg/m3 = 25112,5


= 33.6 m3 = 33.6 m3 x 1.435 Kg/m3 = 33.866 Kg

(heaped)
Heaped load exceed rated load (36100) !
Use max payload = 36.100 Kg / 1.435 Kg/m3
Payload = 25.16 Lm3
ii. Check Traction
a.

Haul:
Total Weight = 31.178 Kg + 36.100 Kg
= 67.278 Kg
Weight on Driving Wheels = 33% x 67.278 Kg
= 22.201,74 Kg
Available Traction = 0.55 * 22.201,74 Kg
= 12.210,96 Kg
b. Return:

Total Weight =
= 31.178 Kg
Weight on Driving Wheels = 50% x 31.178 Kg
= 15.589 Kg
Available Traction = 0.55 x 15.589 Kg
= 8.573,95 Kg
3. Tugas Pekerjaan Tanah
BAGIAN A
Sebuah proyek

persiapan

lahan

konstruksi

mencakup

pekerjaan

penimbunan, perataan dan pemadatan tanah. Lahan yang akan disiapkan


mempunyai ukuran 300 m x 150 m. Tanah untuk galian akan diperoleh
dari suatu lokasi penggalian A (quarry) yang terletak 80 m lebih tinggi dan
berjarak 8 km dari lokasi lahan yang dipersiapkan (C).

Dimensi galian

(quarry) 100 m x 75 m x 8 m. Penggalian akan dikerjakan oleh dua (2)


buah loader E-1, sementara untuk pengangkutan akan menggunakan
sejumlah dumptruck DT-X
Data yang terkait dengan trayek pengangkutan adalah sebagai berikut:
N

Posis

Kegiatan

Jar

Gra

RR

CoT

Kecepa

ak

de

(kg/to

(kg/To

tan

(k

(%)

n)

n)

(km/ja

Keterangan

m)
1

A-B

B-C

C-B

B-A

Penggalian
Pengangku
tan
Pengangku
tan
Penimbuna
n
Kembali

m)

+2

2.4

Penggalian

0.35

140

0.35

5.6

-4%

135

0.40

135

0.55

+4

5.6

Kembali

125

135

0.40

2.4

-2%

140

0.35

125

0.35

Data LOADER E-1

18
km/jam
22
km/jam
-

RR

=
rolling

resistant
CoT = coeff.
of

20

traction
Driving

km/jam

wheel of DT

24

at rear

km/jam
-

Data DUMP-TRUCK DT-X

Bucket capacity

= 1,2 m3

kg
Operating weight

= 22.400 kg

27,3 ton
Lifting capacity (front)

= 3,320 kg

Operating weight empty = 22.400


Maximum capacity

Heaped volume

= 18.6 m3
Lifting capacity (side) = 2,310 kg

Struck volume

= 16.5 m3
Optimum depth of cut
= 3,25 m

DT load distribution (front :

rear) :
Average depth of cut = 3,00 m
a) empty = 50%:50%;
Angel of swing
= 125o
b) loaded = 33%:67%
DT Fixed time (position, dump) = 2,3 menit
Correction factor for swing & depth of cut = 0,85
Bucket fill factor
= 85%
Fixed time loader (cut, raise, swing, dump) = 1,7 menit
Mgt. Condition correction factor = 0,80; Job Efficiency= 50 minute-hour;
Working hours =8 hours/day
Massa jenis kering, bank, B = 2.100 kg/m3 ; swell factor = 80%; dan
shrinkage factor = 75%.
Bagian A1
1) Hitung payload untuk setiap dumptruk, DT-X (m3)

2) Hitung jumlah dumptruck yang dapat dilayani (optimum) oleh 2 Loaded


(E-1)
Bagian A2
Biaya operasi (termasuk sewa alat, operator, bahan bakar dan pelumas):
Loader, E-1 = Rp 210.000,- / mesin-jam
Dumptruck DT-X = Rp
115.500,- mesin-jam
Biaya tidak langsung adalah Rp. 321.600,- / hari
3) Hitung biaya penggalian dan pengangkutan tanah (Rp /Bm 3)

Jawab :
A1
1. Payload
Volume
Dry density (bank)
Swell factor
Dry density (loose)

: 2.100 Kg/m3
: 80%
:

Dry density (loose)


Dry density (bank )
Dry density (loose)
80%
=
Kg/m3 x 100%
2100
loose
) = 1680 Kg/m3
Dry density
SF =

% swell

% swell
=

Dry density ( bank )Dry density (loose)


Dry density (loose)
21001680
x 100%
1680
=

= 25%
Payload
Max Payload
(struck)

= 16.5 m3 = 16.5 m3 x 1.680 Kg/m3 = 27.720 kg


= 18.6 m3 = 18.6 m3 x 1.680 Kg/m3 = 31.248 Kg

(heaped)
Heaped load exceed rated load (27300) !
Use max payload = 27.300 Kg / 1.680 Kg/m3
Payload = 16.25 Lm3
2. Jumlah dumptruck yang dapat dilayani (optimum) oleh 2 Loaded (E-1)

Check Traction
a. Haul:

Posisi A-B
Total Weight = 22.400 Kg + 27.300 Kg
= 49.700 Kg
Weight on Driving Wheels = 67% x 49.700 Kg
= 33.299 Kg
Available Traction = 0.35 * 33.299 Kg
= 11.654,65 Kg
Rolling Resistance Coeff= 140 kg/ton

Grade Resistance

= +2%

Total Resistance = (140/1000 + 2%) x 49700 Kg


Traction > Total Resistance OK

Posisi B-C
Total Weight = 22.400 Kg + 27.300 Kg
= 49.700 Kg
Weight on Driving Wheels = 67% x 49.700 Kg
= 33.299 Kg
Available Traction = 0.4 * 33.299 Kg
= 13.319,6 Kg
Rolling Resistance Coeff= 135 kg/ton

= 7.952 Kg

Grade Resistance

= -4%

Total Resistance = (135/1000 - 4%) x 49700 Kg


Traction > Total Resistance OK

= 7.952 Kg

b. Return:
Posisi C-B
a.
b.
c.

d.
e.

Total Weight =
= 22.400 Kg
Weight on Driving Wheels = 50% x 22.400 Kg
= 11.200 Kg
Available Traction = 0.4 x 11.200 Kg
= 4.480 Kg

Rolling Resistance Coeff= 135 kg/ton

Grade Resistance

= +4%

Total Resistance = (135/1000 + 4%) x 22.400 Kg


Traction > Total Resistance OK

= 3.920 Kg

Posisi B-A
c.
a.
b.

c.
d.

Total Weight =

= 22.400 Kg

Weight on Driving Wheels = 50% x 22.400 Kg


Available Traction = 0.35 x 11.200 Kg

Rolling Resistance Coeff= 140 kg/ton

Grade Resistance

= -2%

Total Resistance = (140/1000 - 2%) x 22.400 Kg


Traction > Total Resistance OK
Cycle Time
a. Haul:
Posisi A-B

= 11.200 Kg
= 3.920 Kg

= 2.688 Kg

Total Weight = 22.400 Kg + 27.300 Kg

= 49.700 Kg

Speed Rimpull Curve for TR = 16 %


Max Speed (loaded)
Haul Time = 2400 m / 11 Km/hr

Posisi B-C
Total Weight = 22.400 Kg + 27.300 Kg
= 49.700 Kg
Speed Rimpull Curve for TR = 9,5 %
= 22 Km/hr
Max Speed (loaded)
= 22 Km/hr
Haul Time = 5600 m / 22 Km/hr
= 0.255 hr

= 11 Km/hr
= 18 Km/hr
= 0.218 hr

Return:
Posisi C-B
Total Weight
= 22.400 Kg
Speed Rimpull Curve for TR = 17.5%
= 25 Km/hr
Max Speed (empty)
= 20 Km/hr
Haul Time = 5.600 m / 20 Km/hr
= 0.28 hr
Posisi B-A
Total Weight
= 22.400 Kg
Speed Rimpull Curve for TR = 12%
= 27 Km/hr
Max Speed (empty)
= 24 Km/hr
Haul Time = 2.400 m / 24 Km/hr
= 0.1 hr
Fixed Time:
Fixed Time (position,dump)= 2.3 minutes
= 0,038 hr
Loaded Time = 1,7 x 15
= 0,425 hr
Total Cycle Time = 0,218 hr + 0,255 hr + 0,28 hr + 0.1 hr + 0,038
hr + 0,425 hr
= 1,316 hr
Productivity = 16,25 Lm3 / 1,316 hr x 50/60 (eff.)

= 10,29 Lm3/hr

Jumlah dumptruck yang dapat dilayani (optimum) oleh 2 Loaded (E1

Nd = (1,316 hr / 0,425 hr) = 3,09 3 dumptruck


For 2 Loaded E-1 2 * 3 DT = 6 DT
Bagian A2
Biaya operasi (termasuk sewa alat, operator, bahan bakar dan pelumas):
Loader, E-1 = Rp 210.000,- / mesin-jam
Dumptruck DT-X = Rp
115.500,- mesin-jam
Biaya tidak langsung adalah Rp. 321.600,- / hari
3) Hitung biaya penggalian dan pengangkutan tanah (Rp /Bm 3)

A2

a. Penggalian Tanah

Volume penggalian = 100 m x 75 m x 8 m

= 60.000 m3

Load Capacity (m3/bucket) = 1,2 m3 x 85%

1,02

m /bucket

3,25 m
x 100
3m

% optimum depth of cut =

Cycle time / bucket = fixed time = 1,7 menit

Probable production / bucket =

= 108,3%
= 102 secon

1,2 m3 x 85 50 min
x
1,7 min
60 min
60 min

30

m3/hr

Probable Production / day = 8 hr/day x 30 m3/hr

Production time / loader = =

= 240 m3/day

60.000
2 x 240 m 3/day

125

hari

Loader E-1,

= Rp 210.000/mesin-

jam

Operation Cost 2 loader= Rp 210.000/mesin-jam x 125 hari x 8


jam/hari x 2
= Rp 420.000.000,00

b. Pengangkatan tanah

Jumlah

bucket

16,25 m 3
1,2 m3 x 0,85

Load time

Payload
bucket capacity x bucket fill factor

= 15,93 = 15
= jumlah bucket x fixed time bucket = 15 x 1,7 menit

= 15,5 menit

Haul time

= 0,573 hr

Return time = 0,38 hr

Fixed time

= 2,3 menit

Cycle time

= load time + haul time + fixed time + return time


= 1,25 jam

50
60

Productivity/DT

= 1,25 jam x

= 1,04 jam / DT

Productivity/DT

= 1,04 jam/ DT x 8 jam / hari x 125 hari

= 1040 jam / DT
Dumptruck DT-x= Rp 115.500/mesin-jam

Operation Cost

= Rp 115.500/mesin-jam x 1040 jam/DT x 6 DT

= Rp 720720000
Biaya tak langsung = Rp 321.600 / hari x 125 hari = Rp
40.187.500,00