Project Report

This project report is for Balaji Plastic proposing a PVC granules production unit with a capacity of 5 tons per month. The total capital investment will be approximately Rs. 398,900. The main raw material needed is 5 tons of fresh PVC per month. The manufacturing process involves cutting, mixing, extruding, and cooling PVC scrap and waste to produce plastic dana granules. Water consumption is 300 liters per day, mostly for cooling which will be fully recycled. Wastewater discharge is only 60 liters per day for domestic use. Air pollution controls like hoods and filters will be installed on machines. There is no water or noise pollution expected from the process.

Uploaded by

Arti Maggo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
602 views5 pages

Project Report

This project report is for Balaji Plastic proposing a PVC granules production unit with a capacity of 5 tons per month. The total capital investment will be approximately Rs. 398,900. The main raw material needed is 5 tons of fresh PVC per month. The manufacturing process involves cutting, mixing, extruding, and cooling PVC scrap and waste to produce plastic dana granules. Water consumption is 300 liters per day, mostly for cooling which will be fully recycled. Wastewater discharge is only 60 liters per day for domestic use. Air pollution controls like hoods and filters will be installed on machines. There is no water or noise pollution expected from the process.

Uploaded by

Arti Maggo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

PROJECT REPORT

For

M/S.
BALAJI PLASTIC
H-1404, DISDC, NARELA
INDL AREA DELHI-110040
1.0 INTRODUCTION
M/s BALAJI PLASTIC ARE PROPOSED PVC Granauler by using Sole/
Scrab and old Rexne West Uniton Reprocessing without washing
H-1404, DSIDC, NARELA INDL. AREA, DELHI-110040
Capacity of the PVC Grenus shall be 5 Tons Per Month. The Unit
has acquired 350 Sq. Mtr. Area on rent at aforesaid address.

Industrial Activity

PVC GRANULES

Name of Product

FRESH PVC DANA

Production Capacity :

5 Tons Day

By Product

Nil

2.0 TOTAL CAPITAL INVESTMENT


The Proposed total Capital Investment of the Unit Shall be about
Rs. 398900.00 Three Lakh Ninty Eight Thousand Nine Hundred
Only)

Including Land and Building Plant and Machinery without


Depreciation.

3.0 RAW MATERIAL REQUIREMENT


The following raw material shall be required at the time of
production

ITEMS

QUANTITITY

Fresh PVC (Dana)


PVC Granvles
____________

5 tons Month (PVC) Dona


____________/Day

4.0 MANUFACTURING PROCESS:


Manufacturing process First of all we are purchase PVC Sole/
Scrap and old Rxine fresh waste ASA Raw Material. Then it is
going to cutte and mixer machine. Then going to do water is used
for the purpose of calling of cose water used for colling purposes
It will be Recycled or Recycle and tank is used and then cutter
These are Plastic Dana Ready.

5.0

FLOW CHART OF MANUFACTURIN GPROCESS


RAW MATERIAL

CUTTER

MIXER

EXTRUDER

COOLING

CUTTING PLASTIC DANA READY

PACKING

DISPATCH

6.0 DETAILS OF WATER CONSUMPTION


Total 300 Lt/Day water are consumed by the Unit. The break up of the
Consumption of
water are as under:

Cooling

Domestic Use

Process

Others

200 Ltr Cooling water on Completely Recycled


:

100 Ltr/Day)

Nil
:

Nil

7.0 SOURCE & VOLUME OF WASTE WATER DISCHARGE

The break up to waster discharge from the difference sources are as under:

A.
B.

Cooling
Domestic Use

C.
D.
E.

Process
Other
Other

:
:
:

200 Ltr/Cooling Water on Complectly Recyeled


:
60 Lt/Day
(Discharge in Sewar)
NIL
NIL
NIL

8.0 PROPOSED POLLUTION CONTROL SYSTEM

8.4 AIR POLLUTION:


There will be Air Pollution from the process exhaust Gas from
Stock attached to extrude, Cutter, Mixer & Filter Machine provided
hood & channelization. Proper complete photograph attach.

8.5 WATER POLLUTION WASTE WATER DISCHARGE:


There will be No Source of water pollution. Only Water will be used
for Domestic Purpose Domestic effluent water will be discharged
in the public sewer.

8.6 D.G. SET:


There would be no source of Noise Pollution from the process,
However if required necessary control measured shall be taken to
meet the ambient noise standards.