Application Exercise 6 Washing Machine For PLC
Application Exercise 6 Washing Machine For PLC
PLC Output
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Function Switch/Button
StartBTN
HalfLoadSW
SpinSW
CoolWashSW
HotWashSW
TubFullBTN
TubHalfFullBTN
DoorClosedSW
VibrationBTN
PLC Input
1
2
3
4
5
6
7
8
9
Where SW, Stands for Switch and BTN, stands for Button in the Input Table.
Now click on the Serial Port Setup button above. The following window appears:
Click on Controller and select Program transfer to PLC. The following window is
opened:
Now type in 01 in the Detect ID box and click on Memorize Username &
Password to clear the Tick sign. This means the PLC should not be set with a
username and password.
Note: you must not set a Password for any other subsequent experiment or
project. Username can be ignored and left alone as samples.
Therefore the window should appear as shown below before you proceed to the next
step.
The i-Trilogi software will now compile the Ladder logic to machine code. If the code
contains errors, then the PLC will display an error message that the compilation is
not successful. You must then go back to editing and correcting your errors.
If the compilation is successful, you will see the message Success! In the
Compilation window shown above.
Click on Controller and select On-Line Monitoring. The following example window
appears: