Estimation Notes
Estimation Notes
ii)
iii)
iv)
v)
vi)
Report
Specification
detail drawing showing plan, section etc.
design ,data and calculation
Basis for rates adopted in the estimate
3
Bay method
This is an estimated cost of all items which are related to the work
in addition to the main contractor to the detailed estimate. One may
think that an estimate of the structure includes only the cost of land
and the cost of the main contracts or labor, materials and
supervision, In addition there are many other cost items to be
included.
8. Annual maintenance or repair estimate
After completion of wok it is necessary to maintained the same for its
proper function and for the same, an estimate is prepared for the items
which required renewal replacement repaired in the form of detail
estimate.
An idea if the amount to be prepared is taken from the actual figure
of expenditure incurred during the last year. The total estimated
cost for maintenance of the structure is generally kept within the
prescribed limit so on percentage basis of the cost of construction of
the structure and its importance .
b. Current rate per bay should worked out from the previous
recorded rate.
c. The location, specification and drawing should be same.
Or,
Or,
Or,
Or,
0.5x = 2000
X = 4000 sq. m
Now, ground floor 4000 sq. m cost @ Rs 9000 per sq. m = Rs
36,000,000
1st, 2nd & 3rd floor 3 x 4000 sq. m cost @ Rs 9000 per sq. m = Rs
108,000,000
Total cost for super structure = Rs 144, 000, 000
Extra for deep foundation = Rs 2,160,000
Extra for especial architectural treatment = Rs 4,320,000
Extra for sanitation & water supply installation = Rs 11,520,000
Extra for internal electricity installation = Rs 11,520,000
Overall cost = Rs 173,520,000
Add contingency chares @ 5% of overall cost = Rs 8, 676,000
Add supervision charge @ 10% of overall cost = Rs 17,352,000
Ground total of estimated cost = Rs 199,548,000
Q. 5. How are the following terms measured and write the unit of
measurement and payment. Write also the coefficient, rule for the
deduction in measurement sketch the figure if necessary.
a) Earthworks in excavation:
Earthworks for the following conditions shall be measured
separately
i)
ii)
iii)
iv)
Work
Work
Work
Work
in or under water
in or under foul position
under tides and
in show
i)
ii)
iii)
iv)
v)
vi)
vii)
viii)
ix)
ii)
iii)
iv)
v)
vi)
unless otherwise stated, forming opening and flues for which no deduction
is made, leaving chases of sections for exceeding 50cm in girth, forming
reveals to jambs where face cutting on exposed faces is not involved,
bedding wall plates, lintels, sills, corrugated sheets, roof tiles, etc. in or
wall if not covered in respective trade.
Following categories of brickwork includes in general brickworks
i)
ii)
iii)
iv)
v)
Foorings
Eaves or beam fillings, no decuction being made for joists,
farters, etc.
Plain copings, sills and plasters
Battered, battened surfaces.
Brickwork in chimney breasts, chimney stades, airflues.
iv)
v)
vi)
Mixing
Preparation of base
Laying
Curing
Alternatively, the damp proof coarse may also be of 2cm thick layer of
cement mortar (1:2) mixed with water-proofing compound of with 5 %
of pullo by weight of cement. In this case only specification should be
given of sand and cement.
e) RCC, PCC for RCC slabs and lintels:
f) Painting:
Painging unless otherwise mentioned shall be measured in sq m stating
the number of coats. The item of work shall fully describe materials and
truly represent the work to be done. Preparatory work such as stopping,
knotting, rubbing down, and burning after stripping shall be stated.
Work on different surfaces as absorbent surfaces (plaster, concrete, brick,
stone, etc) semi-absorbent surfaces ( wood, fibre-board) and nonabsorbent surfaces ( steel and other metals) shall be stated and measured
under separate item.
No deduction shall be made for openings upto 0.5 sq m each, and no
addition shall be made for painting to jambs, soffits, sills, edges,
mouldings, etc. of such openings.
12
Priming coat of paing for fabricated structural steel and iron work shall be
included with fabrication. But subsequent coats of paing shall be
measured separately on the basis of, width of steel work and iron work or
in sq m. In case rivet heads, bolt heads, nuts are picked out in a tint
different from that of adjacent work, these shall be enumerated and
measured as extra over.
Painting work or surfaces not exceeding 10cm in width or in girth and not
in conjunction with similar painted work shall be measured in running
meters and cutting to line if required shall be included in the item. Cutting
to line, where not included in the item, shall be measured separately in
running meters.
Small particles up to 0.1 sq m of painted surfaces, where not in
conjunction with painted stork, shall be enumerated.
Corrugated sheet surface and initial pattern roof surfaces shall be
measured flat in sq m after increasing their areas by the same percentage
as that of white working, distempering work.
Painting on rainwater pipes, soil and ventilating pipes, steel poles and
eaves gutters shall be measured in running meters stating the size or
girth. All pipe fittings such as bends, branches, heads, shoes, etc. shall be
included in the length.
Painting on small articles, such as metal ceiling roses, metal switch-blocks,
heads and nuts or bolts, turn straps, articles of builders hardware and the
like when painted separately in a different colour or not in conjunction
with similar painted work shall be enumerated.
Painting is repair work not exceeding 1 sq m shall be enumerated in the
following categories:
i)
ii)
iii)
Upto 1 sq m
Exceeding 0.1 sq m and upto 0.1 sq m
Exceeding 0.5 sq m and upto 1.0 sq m
k) Site clearance:
Clearing of shrubs, bush, wood and small trees is done in sq m and the
clearing not exceed 30cm girth is included in the item.
The cutting of trees (exceeding 30 cm girth), its measurement is done in
number and girth shall be measured one meter above GL.
l) Apron and apron drain
15
ii.
Work in liquid mud
iii.
Work in or under foul position
iv.
Work under tides and
v.
Work in snow.
d. Items of work for bills of quantities shall fully describe the materials
and workmanship and accurately represent the work to be
executed.
e. Some work done under different conditions or stages shall be
measured separately stating the condition, the height or depth or
distance whichever is applicable.
xi) Preparation of site plan or Index plan for a building project and in
case of a road or irrigation project preparation of key map, index
map, detailed location, survey plan and longitudinal sections,
detailed cross-section for building, rest houses, etc
xii)
Quantity estimated of different items of work involved
in the project from the working drawing
xiii)
Collecting data required for preparing estimate from
sponsoring departments.
xiv)
Preparation of detailed specifications for the items of
works which are not provided in the department schedule.
xv)
Calculations of quantities for road and irrigation works,
the detailed calculations of earth works calculation for each item of
works.
xvi)
Preparation of detailed estimate and abstract of cost for
different sub head of items.
xvii)
Preparation of general abstract of cost. This includes the name
of the project and cost of different sub-heads along with
contingency work changes, Tool and plants, Operation and
maintenance during construction, etc
xviii)
Working out the cost benefit ratio specially for irrigation
project.
xix)
Purchase of different material and equipments. The particulars
of different materials for the projects as bricks, stone chips, bitumen
M.S rounds, cement, spun, pipes, etc and equipments required to be
purchased and supplied departmentally to contractors.
xx)
Accommodation of field staff. This includes temporary
accommodation of staff quarters, site office ,arrangement for water
supply ,sanitation, electrification, approach road etc.
xxi)
Project report or general report and report as estimate.
xxii)
Bar-chart showing the phasing, the physical and financial
performance for the entire plan period of the project.
18
X x 20
100
X x 20
100
= 5200 m2
Total cost of plinth = 6500 x 40,000
= 260000000/Cost of water supply = 260000000 x
5
100
1
100
12
100
31200000/-
3
100
= 7800000/Cost of building = 260000000/- + 13000000/- + 2600000/- + 31200000/+ 7800000/= 314600000/Contingency established = 5% of 314600000
= 15730000/Work charge establishment =
5
2
% of 314600000
Descripti
on or
particular
s
No.
Length
Breadth
Height/dep
th
Content
or
quantity
S.No
Descripti
on or
particular
Quantity
Unit
Rate
Unit of
rate
Amount
Q. 10 When and where the following terms are used :1)approximate estimate
it is an estimate to find out an approximate cost in a short time and thus
enables the authority concerned to under the financial aspect of the
scheme for according sanction to the same . such an estimate is framed
after knowing the rate of similar works and ----practical knowledge in
various ways for types of works such as
i) Plinth area or square meter method
ii) Cubic rate or cubic meter method
iii) Service unit or unit rate method
IV) Bay method
v) Approximate quantities with bill method
vi) cost comparison method
vii) Cost from materials and labor
2)detail estimate
it includes the detailed particulars for the quantities rates and costs of all
the items involved for satisfactory completion of a project.
22
4) Supplementary Estimate:23
Plinth Area Built up area, covered area measured at the floor level
of the basement or of any story of a building.
Floor area the plinth area less the area of the walls. In the
calculation of wall area the thickness of the wall shall be inclusive of
finishing and dado if the height of such finish is more than 1m from
floor finish.
Carpet area-floor area less the area of the following portion
verandah, corridor and passage, entrance hall and porch, staircase
and stair cover, bathroom and lavatory and unusable are for living,
kitchen and pantry, store, canteen, shaft and machine room for lift,
air conditioning duct and plant room, shaft for sanitary piping
Rentable area for residential buildings the area shall be the carpet
area along with the carpet are o f kitchen, pantry, store, lavatory,
bathroom, 50% of carpet area of unglazed and 1005 of glazed
verandah. Following shall not be considered rentable area: storage
space on the top, landing of staircase, under first landing and waist
slab on floor are and 50% of the area of balconies.
Circulation area or free space area- A certain amount of free space
area is required for movement and access to different room, sitting
room, kitchen, etc for those who use buildings. This includes
verandah, balconies, passages, corridors, porches, entrance hall,
and staircase. Circulation area may be horizontal or vertical (4% 5%
of
whole
area
of
building)
estimated cost = plinth area of building x plinth area rate of the
locality for similar building constructed recently.
24
6) Annual repair and maintenance estimateAfter completion of a work it is necessary to maintain the same for its
proper function and for the same, an estimate is prepared for the items
which require renewal, replacement, repairs,etc in the form of a detailed
estimate.
For buildings, such items of work like white washing, color washing and
painting of doors and windows etc quantities are based on the previous
measurements recorded in the measurement book as standard
measurement books. For petty works such as replacement of glass
panes, repairs of floors, patch repairs to cement plaster to walls and
changing of roof tiles or similar nature of work whose repairs cannot be
estimated in the beginning, only lump sum provision is made for different
items in the estimate. An idea of the amount to be provided is taken from
the actual figures of expenditure incurred
During the last year.
The total estimated cost of maintenance of a structure is generally kept
within the prescribed limits on percentage basis of the cost of the
construction of the structure and its importance.
26
0.468
7
= 0.06685 m3)
1.54
7
1.54
7
x 2 = 0.44 m3
1.54
7
x 4 = 0.88 m3
29
1.54
4
S 0.385 m3 .962
A 0.77m3 1078
w = 346.1 lit = 34.6
L 1 x Rs. 350
4 x Rs. 200
ii)
iii)
iv)
v)
vi)
Principles of Valuation
When resorting to valuation of any property or value must be expert in the
trade. He must have sound knowledge of planning designing and
construction of property. He should be quite aware of administrative laws
like town planning laws, rent restriction act, local taxes, etc.
Following principles should be observed at the time of evaluating a fair
and reasonable value of property:
i)
ii)
iii)
iv)
v)
vi)
vii)
Solution:
Plinth area of building = 20 x 15 = 300 sq m
Cost of building = 300 x 40,000
= Rs. 12000,000/The depreciated value of building, D= P(
100rd
)n
100
33
50,000 x 10
100
= Rs. 5,000
34
Y.P =
but
Sc=
R
n
(1+ R) 1
0.06
30
(1+0.06) 1
= 0.0034
1
0.06+0.0034
Y.P =
= 15.77
100rd n
D=P(
) ,
100
Where,
D = depreciated value
P = cost at present market rate
Rd = fixed percentage of depreciation
r = rate of depreciation
d = depreciation
n = no. of years the building had been constructed.
The value of rd may be taken as below:
35
Net return:
i)
ii)
On cost of construction =
On value of land =
3,50,000
100
x8
= Rs. 3037.5
Net return = Rs. (28000 + 3037.5)
= Rs. 31037.5
Outgoings = Rs. 10,000/Gross income = Rs. 31037.5 + 10,000
= Rs. 41037.5
36
41037.5
12
80
= 0.0018
37
38