Atc BPO PEP
Atc BPO PEP
Atc BPO PEP
Muntinlupa City
MDC COG:
PROJECT
EXECUTION
PLAN
JM EBERO NP MICALLER
Risk Management
Table of Organization
EHS Plan
Procurement
QA Plan
Asset Management
Contract Management
Design Production
Operating Budget
Construction Methods
PROJECT INFORMATION
RESOURCE
ASSIGNMENT
CONTRACT DETAILS
Contract Package : Fixed Lump Sum/PS
FLS Amount
: Php. 819,790,177.57
June 2, 2015
Completion Date :
Oct. 1, 2015
Duration :
16 months
DESIGN
CONSULTANTS
Lead Architect : Aidea Philippines Inc.
Structural : TandeM Engineering
Mechanical : Westrim Inc.
Electrical : EB Cruz & Partners
Plumbing/Sanitary : NBF Consulting Inc.
Fire Pro : NBF Consulting Inc.
PROJECT INFORMATION
VICINITY MAP
PROJECT
SITE
MA
DR
IGA
L
MOLITO
AV
EN
UE
AVIDA
TOWERS
ALABANG
COM
M
AL
AB
AN
GZ
AP
OT
ER
OA
D
ALA
BAN
G
CEN TOW
N
TER
MA
LL
ERIC
AL A
VEN
UE
PROPOSED
OFF SITE
TEMFACIL
PROJECT INFORMATION
LOCATION MAP
PARKING
AREA
Mc Donalds
ATC
ATC BPO1
PARKING
AREA
ALABANG
TOWN CENTER
PROJECT INFORMATION
PROJECT DESRIPTION
ZONE 3
9
ZONE 2
ZONE 1
5
PPER RDECK
MACHINE ROOM LEVEL
RDECK
10THFLOOR
9TH FLOOR
7 LEVELS OF MULTI TENANT
OFFICES
8TH FLOOR
7TH FLOOR
6TH FLOOR
5TH
4TH FLOOR
3RD FLOOR
MADGRIGAL
SIDE
SERVICE
ROAD SIDE
PROPOSEDM BRIDGE
BRIDGE
LINK
LINK TO
MALL
TO MALL
OPENING
ND
OPENING
OPENING
OPENING
OPENING
OPENING
OPENING
FLOOR
GROUND FLOOR RETAIL OFFICES
OPENING
UG FLOOR
RAMP FROM LG TO
2ND FLR,.
OPENING
DROP
OFF
DROP-OFF
OPENING
OPENING
OPENING
LG
OPENING
OPENING
OPENING
OPENING
OPENING
PROJECT INFORMATION
PROJECT BRIEF
PLAN
ELEVATION
PROPOSED
TUNNEL
FUTURE
BASMENT
PARKING
RETAIL
EXPANSION
PROPOSED
TUNNEL
FUTURE
BASMENT
PARKING
RETAIL
EXPANSION
TO
OF
TO
PROJECT DESCRIPTION
OF
PROJECT INFORMATION
PROJECT BRIEF
PROPOSED
TUNNEL
FUTURE
BASMENT
PARKING
RETAIL
EXPANSION
PLAN
PROPOSED
TUNNEL
FUTURE
BASMENT
PARKING
4
3
2
RETAIL
EXPANSION
RDEC
K
Floor
OF
TO
OF
MACHINE ROOM
LEVEL
RDECK
TO
Heigh Elevati
t
on
PARKIN
G
area
UPPER
ROOF DECK
6.7
44.3
ROOF DECK
40.3
76.68
10TH
FLOOR
36.3
6 Offices
2280.17
439.41
143.07
2862.6
5
9TH FLOOR
4.4
31.9
6 Offices
2280.17
439.41
143.07
2862.6
5
8TH FLOOR
27.9
6 Offices
2280.17
439.41
143.07
2862.6
5
7TH FLOOR
23.9
6 Offices
2280.17
439.41
143.07
2862.6
5
6TH FLOOR
19.9
6 Offices
2280.17
439.41
143.07
2862.6
5
5TH FLOOR
15.9
6 Offices
2280.17
439.41
143.07
2862.6
5
4TH FLOOR
11.9
6 Offices
2280.17
450.39
132.09
2862.6
5
3RD FLOOR
3.2
8.7
1092.5
1559.27
131.89
2783.6
6
2ND FLOOR
3.2
5.5
1044.5
1456.98
314.3
2815.7
8
UPPER
GROUND
5.5
1576.74
1151.17
24.6
2752.5
1
LOWER
GROUND
-5
1068.5
1248.51
824.68
3141.6
9
108.14
604.06 680.74
10TH
9TH
7 LEVELS OF MULTI
TENANT OFFICES
8TH
7TH
6TH
5TH
4TH
3RD
2ND
SERVICE
ROAD SIDE
PROPOSEDM
BRIDGE LINK
MALL
BRIDGETOLINK
TO MALL
OPENING
OPENING
OPENING
RAMP FROM
LG TO 2ND
FLR,.
OPENING
OPENING
LG
OPENING
OPENING
OPENING
OPENING
OPENING
OPENING
UG
OPENING
OPENING
OPENING
OPENING
LOWER GROUND
PARKING LVL,
ELEVATION
OPENING
OPENING
DROP
DROP-OFF
OFF
TOTAL CFA :
322
13
RISK MANAGEMENT
Item
1
Risk Description
Project Execution Risk
Complaints/Mall business affected
(cause - pedestrian flows disrupted,
noise/dust puts off Mall users)
Sources
Risk
Mall business
impact.
Dissatisfaction.
carpentry works, Tenants seek
concrete
reimbursement.
pouring,operation Received Notice of
of equipments violation from the
owner. Work
stoppage
Excavation work Flooding. Service
interruption. Road
settlement, closure.
Additional Measures
Needed
D
2
S
4
R
24
S/NS
S Close communication
with mall
administrator.
Planning of activities
during night time.
Setting guidelines on
dust and noise.
18
NS
NS
NS
20
45
Excavation work
Provide protective
system such as blue
sack, polytylene and
proper sloping.
Removal of spoil on
top of excavation
S/NS
EHS PLAN
EMERGENCY RESPONSE TEAM
JM EBERO
PROJECT
MANAGER
EMERGENCY
MARSHALL
DI TOMANENG
PROJECT-INCHARGE
DEPUTY
EMERGENCY MARSHALL
TBN
SAFETY
SUPERVISOR
ERT
LEADER
FIRE
Officer
MDC Safety
Team Leader
Contact #: ________
EVACUATION
MDC MEFPS
Supervisor Team
Leader
Contact #: ________
References:
DOLE OSHS/D.O. 13
OHSAS 18001:2007
ISO 14001:2004
MDC Project
Nurse
Team
Leader
Admin Officer
Team Leader
Contact #: ________
RESEARCH AND
RESCUE
MEDICAL TEAM
ALARM/COMMUNICA
TION
MDC
MDC QA/QC
Supervisor
Team Leader
Contact #: ________
Contact #: ________
EQUIPMENT
Equipment Engineer
Team Leader
Contact #:
________
SECURITY AND
CROWD CONTROL
Site
Security Officer
Team Leader
Contact #:
________
EHS PLAN
DRIVEWAY AND PEDESTRIAN OVERHEAD
PROTECTION
Gate 2
EXISTING CANOPY
AND FENCE @
SUPERMARKET DRIVE
PROPOSED DRIVEWAY
SAFETY CANOPY
SUPERMARKET
DRIVE
DP
DP
CATW ALK
CATWALK
DP
S HIP
LADDER
MADRIGAL
AVENUE
S HIP
LADDER
S HIP
LA DDER
S HIP
LA DDER
DP
CATW ALK
DP
CATWALK
DP
PROPERTY LINE
ATC MALL
PARKING
SERVICE ROAD
Gate 1
Gate 3
LEGEND:
EXISTING FENCE
PROPOSED EXTENSI
FENCE
PROPOSED BARRICA
FOR FALL PROTECTIO
IN EXCAVATION
PROPOSED BARRICA
FOR FALL PROTECTIO
IN (1.5M FROM THE
2ND FLOOR AND ABO
AUGUST 2013
APRIL 2014
05 APRIL 2014
21 APRIL 2014
:
02 JUNE 2014
:
30 JUNE
2014
24 JULY
2014
29 MAR
2015
22 MAY
2015
15 SEPT 2014
15 JUNE
2015
:
15 APRIL 2015 to 01 OCT. 2015
:
01 OCT. 2015
01 OCT. 2015
:
01 OCT. 2015
Legend:
Subject for excavation
Exit Point
Item
No.
1
Stockpile Area
2
3
Description
Backhoe (PC
200)
Bulldozer
Loader
No. Of Units
1
1
1
ZONE 3
STRUCTURE
FOOTING
PEDESTAL
COLUMN (1ST
LIFT)
RC WALL (1ST
LIFT)
SOG
STRUCTURE
ZONE 1
ZONE 2
FOOTING
PEDESTAL
COLUMN (1ST
LIFT)
RC WALL (1ST
LIFT)
SOG
STRUCTURE
FOOTING
PEDESTAL
COLUMN (1ST
LIFT)
RC WALL (1ST
LIFT)
SOG
11-Jul-14
25-Jul-14
01-Aug-14
24-Jul-14
31-Jul-14
06-Aug-14
DUR
(DAY
S)
14
7
6
01-Aug-14
07-Aug-14
26-Aug-14
ZONE
207-Sep-14
START
FINISH
13
21-Jul-14
04-Aug-14
11-Aug-14
03-Aug-14
10-Aug-14
16-Aug-14
DUR
(DAY
S)
14
7
6
11-Aug-14
17-Aug-14
START
FINISH
31-Aug-14
ZONE 310-Sep-14
11
31-Jul-14
13-Aug-14
22-Aug-14
12-Aug-14
20-Aug-14
28-Aug-14
DUR
(DAY
S)
13
8
7
22-Aug-14
29-Aug-14
05-Sep-14
13-Sep-14
START
FINISH
ZONE
1
ZONE
2
ZONE
3
Item
No.
1
2
Description
BULK EXCAVATION
STRUCTURAL
EXCAVATION
Zone 1
Zone 2
Zone 3
FOOTING
Zone 1
Zone 2
Zone 3
PEDESTAL
Zone 1
Zone 2
Zone 3
Zone 1
Zone 2
Zone 3
Start
End
02-Jun-14 30-Jun-14
Dur
JULY - 2014
AUGUST - 2014
SEPTEMBER - 2014
3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30
29
st
Col.
1 Lift
Ret.
Wall
1st Lift
01-Jul-14
19-Jul-14
26-Jul-14
11-Jul-14
21-Jul-14
31-Jul-14
25-Jul-14
4-Aug-14
13-Aug14
1-Aug-14
11-Aug14
22-Aug14
18-Jul-14
25-Jul-14
02-Aug-14
24-Jul-14
3-Aug-14
12-Aug-14
31-Jul-14
10-Aug-14
18
7
8
14
14
13
7
7
Footing
Pedestal
20-Aug-14
6-Aug-14
16-Aug-14
28-Aug-14
LIFT
Zone 1
1-Aug-14
11-Aug
Zone 2
14
22-Aug
Zone 3
14
RETAINING WALL 2ND
LIFT
Zone 1
8-Aug-14
18-Aug
Zone 2
14
29-Aug
Zone 3
14
BACKFILLING
11-Aug
Zone 1
14
16-Aug
Zone 2
14
23-Aug
Zone 3
14
Wall
2nd
Lift
Ret.
7-Aug-14
17-Aug-14
29-Aug-14
Backfilling
Slab-on-Grade
14-Aug-14
26-Aug-14
4-Sep-14
24-Aug-14
14
nd
Column
2 Lift
30-Aug-14
15
4-Sep-14
13
ZONE
1
ZONE
2
ZONE
3
Description
UPPER GROUND
Zone 1
Zone 2
Zone 3
SECOND FLOOR
Zone 1
Zone 2
Zone 3
THIRD FLOOR
Zone 1
Zone 2
Zone 3
FOURTH FLOOR
Zone 1
Zone 2
Zone 3
FIFTH FLOOR
Zone 1
Zone 2
Zone 3
SIXTH FLOOR
Zone 1
Start
End
Dur
8-Sep14
11-Sep14
14-Sep14
24-Sep14
27-Sep14
30-Sep14
10-Oct14
13-Oct14
16-Oct14
26-Oct14
29-Oct14
3-Nov14
13-Nov14
16-Nov14
19-Nov14
29-Nov14
19-Sep14
22-Sep14
25-Sep14
SEPTEMBER
OCTOBER
NOVEMBER
DECEMBER
1 1 1 2 2 2 3
1 1 1 2 2 2 3
1 1 1 2 2 2 3
1 1 1 2 2 2
3 6 9
3 6 9
3 6 9
3 6 9
30
2 5 8 1 4 7 0
2 5 8 1 4 7 0
2 5 8 1 4 7 0
2 5 8 1 4 7
5-Oct-14
12
8-Oct-14
12
12
12
12
4F
12
12
12
12
12
12
12
12
8-Nov-14
11-Nov14
14-Nov14
24-Nov14
27-Nov14
30-Nov14
10-Dec14
12
12
UG
11-Oct14
21-Oct14
24-Oct14
27-Oct14
12
2F
3F
5F
6F
ZONE
1
ZONE
2
ZONE
3
Zone 1
Zone 2
Zone 3
EIGHT FLOOR
Zone 1
Zone 2
Zone 3
NINTH FLOOR
Zone 1
Zone 2
Zone 3
TENTH FLOOR
Zone 1
Zone 2
Zone 3
ROOF DECK
Zone 1
Zone 2
Zone 3
MACHINE ROOM
Zone 1
Zone 2
Start
End
15-Dec- 29-Dec14
14
18-Dec4-Jan-15
14
21-Dec7-Jan-15
14
6-Jan-15 17-Jan-15
9-Jan-15 20-Jan-15
12-Jan23-Jan-15
15
22-Jan2-Feb-15
15
25-Jan5-Feb-15
15
28-Jan8-Feb-15
15
7-Feb-15 18-Feb-15
10-Feb22-Feb-15
15
13-Feb25-Feb-15
15
24-Feb7-Mar-15
15
27-Feb10-Mar-15
15
2-Mar-15 13-Mar-15
15-Mar26-Mar-15
15
18-Mar29-Mar-15
15
Dur
DECEMBER
JANUARY
FEBRUARY
MARCH
3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21 24 28 3 6 9 12 15 18 21 24 27 30
12
12
CONCRETE
TOPPING OFF :
MARCH
29,
2015
12
12
12
UG
12
12
12
12
12
12
12
UG
12
12
12
RL
12
12
UG
UG
UG
FLOOR FORMWORK
ZONE AREA S NEEDED
(SQM)
(SQM)
1
950
1113.82
925
1376.88
949
1466.48
TOTAL
ZONE
1
ZONE
2
3957.18
FORMWORKS
NEEDED
5,264 SQM
ZONE
3
ACTIVITIES
Survey and Lay-out
Installation of Column Rebars
Column Formworks
Column Concreting
Preparation of Beam Bottom
and Shoring
Beam Rebar Installation
Installation of Translab
Beam Siding
Installation of PC Wall
Installation of Top Bars
Electro-Mechanical
Embedments
Clean
up/Inspection/Concreting
DUR
13 14 15 16 17 18
.
1 2 3 4 5 6 7 8 9 10 11 12
(day
Start: ZONE 2
s)
1
2
2
2
Start: ZONE
3
2
4
4
4
4
4
Vertical
Structure
Concreting
Horizontal Structure
START
END
DURATION
FW
AREA
UGF
2F
3F
4F
5F
6F
7F
8F
9F
10F
RD
08-Sep-14
24-Sep-14
10-Oct-14
26-Oct-14
13-Nov-14
29-Nov-14
15-Dec-14
06-Jan-15
22-Jan-15
07-Feb-15
24-Feb-15
25-Sep-14
11-Oct-14
27-Oct-14
14-Nov-14
30-Nov-14
16-Dec-14
07-Jan-15
23-Jan-15
08-Feb-15
25-Feb-15
13-Mar-15
18
18
18
18
18
18
18
18
18
18
18
4973.11
5936.9
4890.88
5083.19
5261.64
5267.67
5267.67
5267.67
5268.09
5287.59
5445.15
RL
15-Mar-15
29-Mar-15
15
1439.80
FLOOR CYCLE:
18 DAYS PER
FLOOR
AVERAGE AREA = 5268.14 SQM
AVERAGE (output/day) = 293 SQM/DAY
AVERAGE (carpenter/day) = 147 carpenters
FORMWO
RKS SET 4
FORMWOR
KS SET 3
FORMWO
RKS SET 2
FORMWO
RKS SET 1
FORMWO
RKS SET 2
FORMWO
RKS SET 3
R
L
R
D
1
0
F
9
F
8
F
7
F
6
F
5
F
4
F
3
F
2
F
U
G
L
G
ZONE 3
Mar. 26,
2015
Mar. 07,
2015
Feb. 18,
2015
Feb. 02,
2015
Jan. 17,
2015
Dec. 29,
2014
Dec. 10,
2014
Nov. 24,
2014
Nov. 08,
2014
Oct. 21,
2014
Oct. 05,
2014
ZONE 2
ZONE 1
FW4
FW1
Sept. 19,
2014 Sept.
08, 2014
Mar. 10,
2015
Feb. 22,
2015
Feb. 05,
2015
Jan. 20,
2015
Jan. 04,
2015
Dec. 13,
2014
Nov. 27,
2014
Nov. 11,
2014
Oct. 24,
2014
Oct. 08,
2014
Sept. 22,
2014
FW2
Mar. 13,
2015
Feb. 25,
2015
Feb. 08,
2015
Jan. 23,
2015
Jan. 7,
2015
Dec. 16,
2014
Nov. 30,
2014
Nov. 14,
2014
Oct. 27,
2014
Oct. 11,
2014
Sept. 25,
2014
FW3
PRELIMS/TEMPORARY
FACILITIES
CLEARING AND
GRUBBING/BULK
EXCAVATION
STRUCTURAL
EXCAVATION
2015
2-Jun-14 30-Jun14
1-Jul-14 30-Jul-14
Topping-Off
(March 29, 2015)
CONCRETE
FORMWORKS
25-Jul14
29-Mar15
CONCRETE
REINFORCEMENT
11-Jul14
29-Mar15
CAST-IN-PLACE
CONCRETE
2-Aug14
29-Mar15
ARCHITECTURAL
WORKS
17-Oct- 1-Oct-15
14
12
ELECTRO-MECHANICAL
WORKS
3-Nov- 1-Oct-15
14
11
TESTING AND
COMMISSIONING
15-Apr- 1-Oct-15
15
Watertighness
Energization
(June
15,
2015)
C
O
N
C
R
E
T
E
1600
V
O
L
U
M
E
600
1783
1750
1847
1870
1670
1579
1366
1400
1137
1200
1000
800
400
286
200
0
1
May
Jun
Jul
Aug
10
11
Sept
Oct
Nov
Dec
Jan
Feb
Mar
406119
398698
400000
404101
409006
365567
359648
350000
300541
300000
259061
R
E 250000
B
A 200000
R
S
150000
(KGS)
65029
100000
50000
0
1
10
11
May
Jun
Jul
Aug
Sept
Oct
Nov
Dec
Jan
Feb
Mar
10706
10012
10000
9298
8000
7543
7085
F
O 6000
R
M
W 4000
O
R
K 2000
S
(SQM)
10094
6629
4721
314
0
1
May
Jun
Jul
Aug
Sept
10
11
Oct
Nov
Dec
Jan
Feb
Mar
STEELMAN
29
4
200
180
160
29
9
29
4
160
22
1
140
27
8
27
7
172
167
166
MASON
159
16
8
19
117
1
120
100
97
92
80
84 80
95
95
89
96
88
78
60
55
40
20
0
19
JULY
54
18
27
AUGUST
26
SEPTEMBER
31
32
32
29
30
18
OCTOBER
NOVEMBER
DECEMBER
JANUARY
FEBRUARY
MARCH
MAJOR EQUIPMENT
UNITS
START
FINISH
2014
PEAK
2015
(mos.)
May Jun Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun July Aug Sept oct
10
MOS.
30-Jun-14
30-Apr-15
2.6
MOS.
30-Jun-14
15-Sep-14
3.1
MOS.
15-Jun-14
15-Sep-14
MOS.
24-Jul-14
29-Mar-15
Stake Truck
4.00
MOS.
19-Sep-14
17-Jan-15
Submersible Pump
9.97
MOS.
5-Jul-14
30-Apr-15
Mini-Dumptruck
3.00
MOS.
1-Jul-14
8-Jan-15
Skid Loader
1.10
MOS.
11-Aug-14
13-Sep-14
1.10
MOS.
11-Aug-14
13-Sep-14
10 Plate Compactor
1.10
MOS.
11-Aug-14
13-Sep-14
2.00
MOS.
1-Jul-14
8-Jan-15
12 Gondola (rental)
4.07
MOS.
15-Apr-15
15-Aug-15
Sub-Total
1
1
2
3
6
3
0
11
11
3
3
3
3
3
3
3
3
3
3
ACTIVITIES
7 AM to
8 AM Rebar Fabrication
8 AM to
9 AM Rebar Fabrication
Rebar Fabrication/Formwork
9 AM to 10 AM Installation/Stripping
10 AM to 11 AM Rebar Fabrication/Formwork Installation
11 AM to 12 NN Rebar Fabrication/Formwork Installation
12 NN to 13 PM BREAK TIME
13 PM to 14 PM Formworks/Rebar Fabrication
14 PM to 15 PM Rebar Fabrication/ MEPFS Insert
15 PM to 16 PM Rebar Fabrication/ MEPFS Insert
16 PM to 17 PM Clean - Up
17 PM to 18 PM Inspection
18 PM to 19 PM Concrete Pouring
19 PM to 20 PM Concrete Pouring
20 PM to 21 PM Curing Time
21 PM to 22 PM Curing Time
22 PM to 23 PM Curing Time
23 PM to 24 AM Curing Time
24 PM to
1 AM Curing Time
1 AM to
2 AM Curing Time
2 AM to
3 AM Curing Time
3 AM to
4 AM Curing Time
4 AM to
5 AM Curing Time
5 AM to
6 AM Curing Time
6 AM to
7 AM Curing Time
TRANSLAB
FABRICATI
ON AREA
(ON-SITE)
(6.0m x 25.5m
CAPACITY:
= 14 PANELS/DA
ACTIVE FLOOR
ROOF DECK
ZONE 2
Active Floor
RDECK
10TH
3 Flrs.
9TH FLOOR
8TH FLOOR
ZONE 1
1.
2.
3.
4.
5.
6.
7.
Rubcon
Instln of Arty Wall
Instln of Steel Doors
Waterproofing
Conc. Topping/Tiling Works
Instln of Ceiling Frame
Initial Paint Application
1.
2.
1.
2.
3.
4.
5.
Drywall/Ceiling Works
Metals
Tiling Works/Granite
Specialty Works
Final Painting
7TH FLOOR
3 Flrs.
6TH FLOOR
Building Envelope
5TH FLOOR
2 Flrs.
4TH FLOOR
3RD FLOOR
2ND FLOOR
UG FLOOR
CONSTRUCTION
SCHEDULE
FLOOR LEVEL
ROOFDECK
ARCHITECT
8
7
URAL
WET
Apr. 29 May
WORKS
20, 2015
BUILDING
5
ENVELOPE
ARCHITECTUR
3
2
1
AL DRY
WORKS
Sept. 12 Sept.
27, 2015
Apr. 12 May
12, 2015
Aug. 22 Sept.
26, 2015
Aug. 01 Sept.
05, 2015
Jul. 11 Aug. 15
2015
Feb. 18 Mar.
20, 2015
Feb. 02 Mar.
12, 2015
Jan. 17 Feb. 21,
2015
Feb. 13 Feb.
27, 2015
UPPER GROUND
Feb. 02 Feb.
16, 2015
Jan. 22 Feb. 05,
2015
Jan. 05 Jan. 25,
2015
LOWER GROUND
Oct. 21 Dec.
05, 2015
TENTH FLOOR
NINTH FLOOR
EIGHT FLOOR
SEVENTH FLOOR
SIXTH FLOOR
FIFTH FLOOR
FOURTH FLOOR
THIRD FLOOR
BRIDGE LINK
TO MALL
OPENING
SECOND FLOOR
OPENING
OPENING
OPENING
OPENING
OPENING
OPENING
GLASS
/CURTAIN
WALL
Zipper area
May 15 May 22, 2015
DROP-OFF
OPENING
OPENING
OPENING
OPENING
OPENING
OPENING
OPENING
Use of MDC reinforced concrete precast panels for all exterior walls for
greater efficiency in construction, minimization of unsightly result of poor
plastering works, and elimination of leaks coming from walls.
Use of ARTY Wall for interior non-load bearing masonry works for finer
interior wall finishes, efficiency in erecting interior partitions, and
minimization of construction debris.
Coring shall be done instead of installing pipe sleeves to minimize chipping,
and superior precision in installing building utilities.
VIII. CONSTRUCTION
METHODS
CONSTRUCTION METHODOLOGY
EXCAVATION
CONSTRUCTION METHODS
EXCAVATION
CONSTRUCTION METHODS
STRUCTURAL WORKS (REBARS AND
FORMWORKS)
Spacer Block
Modeler
CONSTRUCTION METHODS
STRUCTURAL WORKS (REBARS AND
FORMWORKS)
CONSTRUCTION METHODS
STRUCTURAL WORKS (CONCRETING)
CONSTRUCTION METHODS
TRANSLAB/HALF SLAB SYSTEM
CONSTRUCTION METHODS
TRANSLAB/HALF SLAB SYSTEM
CONSTRUCTION METHODS
TRANSLAB/HALF SLAB SYSTEM
CONSTRUCTION METHODS
FORMWORKS SYSTEM (COLUMNS)
Column Form:
1. Gand Set.
2. Crane assisted form.
CONSTRUCTION METHODS
FORMWORKS
LAYOUT
FORMWORKS
LAYOUT
BLOW-UP A
CONSTRUCTION METHODS
FORMWORKS FLY OUT AREA
LEGEND:
2
8300
3
8000
4
8000
8000
64600
6
8000
7
8000
8
8000
9
8300
8250
LP2
TOWER CRANE
5000
2750
LP1
B
41600
9600
F
G
2750
5000
FLY OUT AREA IN SIDE OF ATC MALL PARKING (NOTE: CONSIDER SAFETY PRECAUTIONS
FOR PARKING TENANTS OF MALL)
8250
AREA WITH
OUT
PRECAST
LOADING
PLATFORM
CONSTRUCTION METHODS
PC Wall Installation Method
CONSTRUCTION METHODS
PC Wall Installation Method
CONSTRUCTION METHODS
PC Wall Joint Details
LEGEND:
ACCES ROAD FOR SITE
PROPERTY LINE
MA
D
AV RIGAL
EN
UE
AL
A
COM
M
BA
NG
RO ZAP
AD
OT
E
ALA
BAN
G
CEN TOW
N
TER
MA
LL
ERIC
AL
AVE
NUE
MA
DR
IGA
LA
VE
.
PARKING
AREA
SU
PE
RM
ATC BPO1
PARKING
AREA
AR
KE
T
DR
IVE
ALABANG TOWN
CENTER MALL
PROPOSED
OFF SITE TEMFACIL
(2,625 SQ. M)
COM
M
ERC
E
AVE.
PUMPCRETE STN. 1
PUMPCRETE STN. 2
Gate 1
Gate 3
GENSET
FORMWORKS FABRICATION AND
STAGING AREA
TRANS
LAB
FABRIC
ATION
AREA
Gate 2
TOWER CRANE
FORM
WORKS
HOLDIN
G AREA
TRANS
LAB
STOCK
PILE
AREA
(Zone
1)
SATELLITE OFFICE
CONSTRUCTION
ACCESS
REBARS
STOCKPILE AREA
A
MERALCO POST 2
MERALCO POST 1
SUPERMARKET DRIVE
DP
CATW ALK
CATW ALK
DP
S HIP
LADDER
SHIP
LA DDER
TOWER CRANE
30 MTS. 6.3T
LEGEND:
SHIP
LA DDER
S HIP
LADDER
DP
CATW ALK
DP
40 MTS. 5.0T
CATW ALK
DP
PROPERTY LINE
50 MTS. 3.6T
109
0
-7.45
-7.85
-8.50
52.7M
Extended level of
mast for Tower crane
RD LVL.
+46700
Upper Roof Deck
40.3M
Roof Deck
+40300
10 Roof Deck
+35900
9 10TH FLOOR
+31900
8 9TH F LO OR
+27900
7 8TH F LO OR
+23900
6 7TH
+19900
5 6TH
+15900
4 5TH
+11900
3 4TH F LO OR
+8700
2 3RD FLOOR
BRIDGE LINK
TO MALL
+5500
1 2ND FLOOR
ARCADE
0
G RO UND FLOOR
-5000
LO WE R GROUND
-7.565m BOTTOM
footing of tower
crane foundation
NOTE:
7TH FLOOR
1465
MERALCO6
POST 1
6TH FLOOR
5TH FLOOR
1229
6
MERALCO POST 2
4TH FLOOR
3RD FLOOR
ATC MALL
PARKING
SUPERMARKET
DRIVE
ARCADE
ATC MALL
PARKING
DISTANCE OF TC TO
ATC MALL
7TH FLOOR
6TH FLOOR
5TH FLOOR
4TH FLOOR
3RD FLOOR
DROP OFF
ATC MALL
SERVICE DRIVEWAY
X. TABLE OF ORGANIZATION
TABLE OF ORGANIZATION
NP MICALLER
OPCEN HEAD
IT CASING
PROJECT MGMT.
COOR.
D ARAGO
EHS OPCEN
HEAD
CNC RAMOS
OPCEN ADMIN
OFFICER
BM TRIMIDAL
ASSET MGT
SUPERVISOR
JM CABINGAS
OPCEN
SURVEYOR
JM EBERO
PROJECT
MANAGER
FL DELOS REYES
MEPFS
CONSULTANT
IB FABRO
OPCEN QA
AUDITOR
MQ VILLONGCO
OPCEN
TSD
MS REAMICO
OPCEN
QS
DI TOMANENG
PROJECT-INCHARGE
TBN
SAFETY
SUPERVISO
R
SAFETY
OFFICER (4)
TBN
PROJ.
PHYSICIAN
TBN
PROJ.
NURSE
SHARED
R OCAMPO
PROJECT
SUPERINTENDEN
T
CN MARFIL
ADMIN OFFICER
TBN
TIMEKEEPER
TBN
ASSET MGT.
SPECIALIST
TBN
SURVEYOR
TBN
(C) FIELD
ENGINEER
TBN
ARCHI.
SUPERVISO
R
TBN
EXPEDITER
TBN
WAREHOUS
E AIDE (2)
TBN
INSTRUMEN
TMAN
TBN
(F) FIELD
ENGINEER
TBN
FIELD ARCHI.
TBN
FIELD
CHECKER
TBN
SURVEY
AIDE (2)
CJ
FERNANDEZ
QA AUDITOR
TBN
MEPFS
SUPERVISO
R
TBN
FIELD ENGR.
ELECL
TBN
(R) FIELD
ENGINEER
TBN
FIELD ENGR.
MECHL
TBN
FOREMAN
TBN
F. ENGR.
PL/FP.
TBN
ASST QA
AUDITOR (2)
TBN
DOC
CONTROLLE
R
MP
MALIGAT
TSD
SUPERVISOR
ML CAPOY
COST
ENGINEER
MC
MACAHILO
TSD COOR.
TBN
Q.S.
TBN
CADD
OPERATOR
(2)
C.A.Y
ADDURU
ASST. Q.S.
(2)
TBN
PLANNER
XI. PROCUREMENT
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY
Usage of alternative/other way that helps minimize the Debris on site, including Usage of Precast and
Undergo Cut and Bend Process for Rebar.
Avoid rework as it costs money , waste of time and materials.
Paperless reporting using yahoo groups and owa (mdc email)
Minimize the use of plastic materials and chemical treatments.
Placing silt protection on drains to prevent them from clogging
Implementation of Material Recovery Facility
Using non-compliant, non-standard or inappropriate materials can increase costs, off cuts and wastage.
Ensuring public transports is used when possible and limit car travel.
Using glasses/Mugs in office instead of disposable plastic cups
Ensuring that monitors and IT equipment are switched off when not in use
End of Presentation