Sustainable Reclamation
Initiatives and Geotechnical Issues on Land Supply for Future Development
K K Yin
Ove Arup & Partners Hong Kong Limited
Reclamation History in Hong Kong
Total reclaimed area
6824ha
Reclamation
The Good Old Days..
Fully Dredged Reclamation Method
Existing Profile
Sea
Marine Deposits
Alluvium/CDG
Dredging of Marine Deposit at Seawall and Main Reclamation Area
Sea
Original seabed
profile
Dredged Level
Marine Deposits
Marine Deposits
Alluvium/CDG
Construction of Seawall and Filling at Main Reclamation Area
Seawall
Reclamation Area
Sea
Marine Deposits
Sandfill/ Rockfill
Sandfill/ Rockfill
Alluvium/CDG
Sea
Reclamation Fill
Marine Deposits
Fully Dredged Reclamation Methods
MD within the reclamation area was dredged
Sandfill was used to fill the dredged trench and
reclamation filling
Vibro-compaction of sandfill
Dredging and Disposal of Marine Sediment
Dredging
Disposal
A) Open Sea Disposal of Dredged Sediment
Sea floor disposal areas at South Cheung Chau and East
Ninepin or other empty marine borrow pits have been used
for disposal of uncontaminated mud.
B) Confined Disposal of Dredged Contaminated
Sediment
Contaminated mud is being disposed of at East Sha
Chau.
Compliance on environmental monitoring and until 2
years after closure of all the pits to ensure that there is no
adverse impact on the environment.
Guide Boat Leading the
Barge to the Target Area
for Contaminated Mud
Disposal
Sandfilling
Vibro-compaction of Sandfill
Compaction of granular soils by depth vibrators.
Reclaimed sands can be compacted to a depth of
70m and the intensity of compaction can be varied
to meet need of various projects.
Its improvement effect includes reduction of creep
settlement, increase of shear strength of soils and
reduction of permeability of soils.
Penetration
Compaction
Completion
The Vibroproble
penetrates by vibration
and aid of compressed
air or water to the
required depth.
The Vibroproble is
retracted from the
maximum depth in
0.5m intervals. The insitu sand or gravel is
flowing towards the
Vibroproble
After compaction, the
working platform needs
to be levelled and
eventually roller
compacted.
Historical Projects with Dredged Reclamation
Hong Kong International Airport Reclamation
Area of reclamation is approx. 950 hectare
Dredging volume is approx. 70 million m3
West Kowloon Reclamation
Area of reclamation is approx. 330 hectare
Dredging volume is approx. 32 million m3
Container Terminal No. 9 Reclamation
Area of reclamation is approx. 120 hectare
Dredging volume is approx. 18 million m3
Pennys Bay Reclamation Stage 1
Area of reclamation is approx. 200 hectare
Dredging volume is approx. 42 million m3
Fully Dredged Reclamation
Advantages
Good for fast tracking
Settlement risk is lower
Disadvantages
Large amount of marine deposits to be disposed
Large amount of sandfill and rockfill is required
Adverse environmental impact due to dredging work and filling works
10
Reclamation
Not too long ago
11
Reclamation with Fully Dredged Seawall
Existing Profile
Sea
Marine Deposits
Alluvium/CDG
Dredging of Marine Deposit at Seawall Area
Dredged Level
Sea
Marine Deposits
Marine Deposits
Original seabed
profile
Dredged Level
Marine Deposits
Alluvium/CDG
Construction of Seawall and Filling at Main Reclamation Area
Seawall
Reclamation Area
Reclamation Fill
Sea
Marine Deposits
Sandfill/
Rockfill
Sandfill/
Rockfill
Marine Deposits
Alluvium/CDG
12
Sea
Sandfill/
Sandfill/Rockfill
Rockfill
Band drains
Marine Deposits
Reclamation with Fully Dredged Seawall
Only MD under seawall is dredged
Sandfill is used to fill the dredged trench for seawall
No dredging is required for main reclamation
Sandfill is used for main reclamation filling
Ground treatment (mainly band drain and surcharging) is applied to accelerate the leftin-situ soft marine deposit and reduce long term settlement
13
Dredging would still be significant particularly when the area of reclamation is small
Band
Drain
and
Surcharge
Typically used in soft ground to accelerate
consolidation of the compressible soils for the
drained reclamation.
Marine-based Band Drain Installation
In reclamation areas with thick soft marine
clay/silt, long term consolidation under
reclamation loads can continue for many years.
With band drains and surcharge load, the soft
compressible soils can be pre-consolidated prior
to development in a matter of weeks or months.
Land-based Wick Drain Installation
Band Drain
14
Past Reclamation with Fully Dredged Seawall
Pennys Bay Reclamation Stage 2 (for Disneyland Theme
Park)
Area of reclamation is approx. 60 hectare
15
Siu Ho Wan MTR Depot
gin
g
Dr
ed
lace
s
p
s
t
n
ud i
nen
o
m
p
he
t
pro
t
g
c
e
epin
e
proj e
k
of
h
t
n
n
o
i
o
mpt
u
s
as
fo
r
the
tio
na
le
lan
p
l
l
ha
c ts
e
j
o
ir pr
Ra
The Change
ge
Dumping at Sea Ordinance Cap. 466 (DASO)
ne
con ric
osals
p
o
wa side guide
r
p
r
vation
a
c
x
e
sel ste c ing w lines
/
ging
d
ha
e
e
r
f
a
d
o
c
f
rac ste
ass tio
r
ted
val o
a
o
v
r
a
p
n
c
p
t
m
x
a
e
e
riza an
op ssm ,
ged/e
d
e
r
d
a
tion
f
tion ge
and
sal o
o
p
s
s, p ent o
m
i
d
,
en
du
arine
erm f po
m
t
m
p s opti
ent.
it is tent
m
i
d
e
o
s
i
te
ns,
sue ial e
an ffec
d m ts
on of d
itor isp
ing osa
l
16
Diver of Change - Increased Environmental Concerns
Enforcement of Environmental Impact Assessment
Ordinance (1 April 1998)
Air Quality
Water Quality
Noise Control
Waste Management
Nature Conservation
Marine habitats & associated fauna e.g. marine mammals, fish,
corals, & others
Increased Public Concerns
17
Driver of Change - Lack of Contaminated Sediment Disposal Facilities
Sha Chau
Existing disposal facilities
The Brothers
Proposed disposal facilities
(last mud pit)
Hong Kong
International Airport
18
Driver of Change - Lack of Sand Borrow Area in HK
Legend:
Borrow areas worked out
Borrow areas sand remaining
Tap Shek Kok
Brothers
South of
Tsing Yi
East of Tung
Lung Chau
East Lamma
Channel
Po Toi
19
South of
Victor Rock
And the Mitigation.
Systematically manage impacts that our works may have on
the environment for the benefit of community
20
Available of Advanced Technology
Advanced technology of ground treatment methods have been developed overseas in
recent years
Successful application of various ground treatment method for reclamation in overseas
projects
21
Innovative seawall schemes have been developed in overseas projects in recent years
Recent Implementation of
Innovative Ideas
22
Stone Column
23
Stone Column
Typically used in soft soil applications in order to accelerate consolidation of the
compressible soils for the drained reclamation
Increase the shear strength of the soil dealing
Achieved by the use of vibro-displacement or vibro-replacement method
Involve the installation of gravel compacted piles commonly referred to as stone
columns
24
Stone Column Installation Process
25
Vibroprobe
252 384
23mm
amplitude
26
Sand Compaction Pile
27
Use of Sand Compaction Pile
Install large diameter compacted sand piles in soft clay/ mud. Diameter of sand piles is
1.2m to 2.0m
Non-dredged method for seawall base
Improve bearing capacity, slope stability and consolidation settlement by replacing the
soft clay/ mud by the compacted sand piles
Widely adopted in Japan and Korea
SCP at Busan
Visit
Reclamation
Sea Wall
Sea
Soft Marine Mud
SCP
Provide drain path for
consolidation
settlement
Stiff Soil
28
Soft Marine
Clay
Improve slope
stability
Improve bearing capacity
Installation cycle of SCP
Step 1
Step 2
Step 3
Step 4
Step 5
Sand fill
Step 6
Step 1 -
Casing driving
Step 2 -
Pour the sand inside the
casing
Step 3 -
Drive the casing to the
required level
Step 4 -
Extract the casing by a fixed
distance and fill up the bored
hole by sand
Step 5 -
Re-drive the casing to
compress the sand pile.
Supply the sand continuously
Step 6 -
Repeat Steps 4 and 5 until the
sand pile is built
Sand fill
29
Operation of SCP plant
1 Delivery and store the sand on SCP barge
Sand Transportation
Barge
Sand Storage Tank
2 Conveyor to send the sand to travelling
bucket
30
Operation of SCP plant
3 Travelling bucket to send the sand in
vertical direction
4 Load the sand to the hopper at top of
casing
2
3
31
Hopper
Operation of SCP plant
5 Discharge of sand into ground via the
casing
2
3
32
Casing Driving
Vibrator
Hopper
33
Installation Control
Top and bottom level of SCP piles measured by Auto-electronic Sand Level System
Casing Toe Level
Actual Sand Top
Level
Desired Sand Top
Level
Water Pressure Meter
Auto-electronic Sand Level System
Pressure inside the casing controlled
by Pressure Control System
Casing Pile Pressure
Pressure Control System
34
Up-heaving of Soil after SCP Installation
In case of marine mud 20 to 25m thick, specialist contractor advised based
on their experience that the thickness of up-heaved soil after SCP
installation could be:
1) For SCP replacement ratio of 70%
Thickness of up-heaved soil could
be 7 to 8m
2) For SCP replacement ratio of 40%
35
Thickness of up-heaved soil could
be 4 to 5m
Height of SCP Plant
Surely the minimum height of the SCP plant is based on the envisage
maximum thickness of marine mud, depth of water plus a bit
Xm
Soft Marine
Deposits
36
Xm
Soft Marine
Deposits (to be
treated)
Original Height of SCP Plant
Original Height
~50 60m advised
by Specialist
Contractor
37
Reduced Height of SCP Plant
Spec
ia
SCP list cont
racto
pla n
t
r
o ut t
op fr can be m advised
that
ame
odifi
if h e
ight ed by cut
is a p
t
roble ing
Rem
m
ov
40m
(Min height that could be reduced
by specialist contractor)
Mean Water Level
~ +1.7 mPD
38
Possible SCP Application for Seawalls in Recent Large Scale Reclamation
Project Airport Height Restriction Constraint
Legends
AHR above
+45mPD
Seawall w/o
restriction on the
use of SCP due
to AHR
Remaining Phase of HKBCF
AHR in mPD
HKBCF
39
Possible SCP Application for Seawalls in Recent Large Scale Reclamation
Project Soil Up-heaving Constraint
Use SCP at seawalls with sufficient water depth. Also use low replacement
ratio of SCP + surcharge to reduce the thickness of up-heaved soil
-4.5
40
Possible SCP Application for Seawalls in Recent Large Scale Reclamation
Project Hong Kong Boundary Crossing Facilities
Legend
-10.
5
5
-6.
Seawall w/o
restriction on the
use of SCP due
to up-heave &
AHR
-7.0
-8.0
-6.0
Seabed Level in
mPD
-6.0
Remaining Phase of HKBCF
-4.5
HKBCF
-3.5
AHR in mPD
-3.5
-4.0
-4.5
-4.0
-6.0
AHR above
+45mPD
-5.0
-4.5
-2.8
-3.0
About 25% of seawall (temporary + permanent) without
restriction on the use of SCP due to up-heave and AHR
41
Deep Cement Mixing
42
Typical DCM Barge Setup
3
1
2
4
Mixing
Shafts
Operation
Room
1
Cement Slurry Mixing Plant
Grout Pump
Mixing Blades (under sea water)
43
2
4
Mixing Blades
Illustrative Details of Mixing Blade
Mixing Blades
44
Mixing Plant
45
Marine Based DCM Equipment
Control System of DCM method
Land Based DCM Equipment
Land Based DCM Equipment
Land Based DCM Equipment
DCM Plants
Previous Development of DCM in Hong Kong
46
Port Works Manual Part 4 Guide to Design of Seawalls and Breakwaters introduced
this for the use of supporting seawall
DCM has been mentioned in many proposals in last 20 years but never been adopted in
Hong Kong
Relevant authorities has no objection in principle on the use of DCM as long as proposer
illustrate previous experience in Hong Kong
---meaning a Trial!
Why there is no DCM Trial in HK previously?
Not possible for a Government project to do a field trial before going forward i.e. no
gazetted land, no fundingetc
Lengthy process to carry out field trial due to:
Gazetting under Foreshore and Seabed (Reclamation) Ordinance
Long mobilization period of the plant from overseas i.e. over 4 months (excluding
ordering which depends on how busy the DCM industry is)
47
High mobilization cost
Why DCM have not been adopted in Hong
Kong?
1.
Field trial demonstrate strength and environmental performance?
2.
Residual ground settlement any precedent case?
3.
Ground heave during treatment would this impose any constraint?
4.
Leachability of contaminants from mud (if contaminated) would the
contaminants or contaminated pore water still be leached after treatment?
5.
Environmental impact during construction - what measures were done in
previous projects?
48
Ground Heave during Installation
Ground heave = ~ 70% of injected slurry volume
Yokohama Port
-11m
-15m
For 20m thick mud (DCM replacement ratio of 50%), estimated ground heave = 1.5m
MLLW
+0.55mPD
1.5m Sand Blanket
Seabed
-5.5mPD
Heave
Min. underkeel clearance = 1m
Max barge draft = 2m
Marine Mud
DCM
Columns
49
Water Depth ~ 3.0m
Draft of common DCM plants = 1.5m to 3.3m (impose constraint if shallow water + heaving)
Height of common DCM plants = 35.7 to 72.7m (impose constraint if Height Restriction)
50
Key Environmental Concerns -Marine
51
Possible cement slurry leakage from the preparation plant / slurry pump and
mixing shaft
Possible seepage during soft soil and cement slurry mixing
Undefined heat emission during the chemical reaction
Long term deterioration of soil/cement mix and dissolution into seawater is not
well defined
Possible Mitigation
52
Heaving i) dredge and dispose of upheaved soil; ii) improve the upheaved soil
up to surface
Possible seepage during soft soil and cement slurry mixing DCM operation
will stop some distance below the seabed level (i.e. 1 to 2m)
Possible cement slurry leakage from mixing shaft during extracting the
blades from the mud Place a layer of sand / stone blanket above sea bed in
advance for washing the mixing shaft and blades while passing through this
layer
Cofferdam Type Seawall
53
Use of Cofferdam Type Seawall
A series of circular or rectangular cell formed by interlocking of steel sheet piles / pipe
piles
Directly vibrated into existing seabed without dredging
Act as a massive gravity retaining structure when backfilled to its top level
Used for overseas maritime structures in South Korea, Japan, Singapore, Egypt, Chile,
Canada, U.S, etc
54
Reclamation with Non-Dredged Seawall
1. Existing Profile:
Sea
Marine Deposits
Alluvium/CDG
2a. Ground Improvement (e.g. Stone Column, Deep Cement Mixing), Construction of Seawall and Filling at
Reclamation Area
Seawall
Reclamation Area
Reclamation Fill
Sea
Marine Deposits
Sandfill/ Rockfill
Marine Deposits
Alluvium/CDG
Ground Improvement
Sea
Marine Deposits
Sandfill/ Rockfill
Vertical drains
2b. Cofferdam Type Seawall with Ground Improvement , Filling at Reclamation Area
Seawall
Reclamation Area
Sea
Marine Deposits
Ground Improvement
55
Fill
Fill
ReclamationFill
Fill
Reclamation
Marine Deposits
Alluvium/CDG
Sea
Marine Deposits
Vertical drains
Design Consideration of Non-dredged Seawall
Overall stability:
Internal stability:
Tension failure of sheet pile
when subjected to hoop force
Log-spiral
curve
Failure of interlocks between
sheet piles
Log-spiral
curve
Combined tension and
bending failure of sheet piles
56
Benefit of Non-dredged Seawall
57
Eliminates dredging and disposal of marine sediment
Largely reduce the amount of fill materials for dredged trench
Reduce marine risk by reduce number of barge trip for fill materials logistic
Environmental Friendly
Other Overseas Use of Non-dredged Seawall
Montgomery Point Lock and Dam, Arkansas, USA
Collision Protection Structures for the Inchon Bridge, South
Korea
Artificial Island for
Trans Tokyo-bay Highway
Ohio River , USA
Port at Voiseys Bay, Labrador, Canada
58
Quay Construction at Anping Port, Taiwan
Comparison
59
Comparison
Method
Fully-dredged
Pros
Cons
Good for fast tracking
Large amount of marine deposits to be disposed
Settlement risk is lower
Large amount of sandfill and rockfill is required
Adverse environmental impact due to dredging work and
filling works (especially if rainbowing of sand is adopted)
Non-dredged:
Stone Column
No dredging is required
Large amount of rockfill is required
Environmental friendly
No preferable if strength of surrounding soil is very low
Non-dredged:
Sand Compaction
Pile (SCP)
No dredging is required
Special plant required from overseas and long booking
period required
Environmental friendly
Require lesser rockfill/
sandfill
No track record in HK
Up-heaving of soil
Working height limit
Non-dredged:
Deep Cement
Mixing (DCM)
No dredging is required
Similar to the Cons of SCP except up-heaving of soil
Require lesser rockfill/
sandfill
Significant environmental impacts: grout leakage
Expensive
Slow construction rate
Non-dredged:
Cofferdam Type
Seawall
60
No dredging is required
Require considerable amount of steel
Reduced Marine Traffic
Less track record in HK
Use for disposal of public fill
Working height limit
Newer Attributes
61
Reclamation along Original Coastline
Original Coastline
Proposed
Reclamation
Configuration
A 2-D hydrodynamic modeling can be carried out to develop an optimum offshore reclamation
configuration such that sufficient tidal flushing can be maintained during ebb and flood tide for
control of water quality in the development area.
62
Creation of Eco-shoreline
Eco-shoreline
Tidal Water Level
63
Tidal Basin Cross-section
Disposal Area for Public Fill
64
Cell of cofferdam type seawall can be filled by public fill
Treated as alternative disposal site for public fill
Today
Dawning of a new era.
65
First Fully Non-dredged Reclamation in HK
Non-dredged cellular steel sheetpile seawall with a
diameter of 26.9m to 31.2m
Formed by straight web sheetpile
Penetrate through over 25m thick of marine deposits
into underlying alluvium.
Stone column installed to strengthen the soft marine
deposit providing lateral support to the cellular seawall
cell.
Approx. 30m
/
94m
31.1
SchematicLayoutofNondredgedSeawall
66
0m
26.9
IsometricViewofSimilarSeawallConstruction
Airport Height Restriction
t li
h
g
i
He
mi
mPD
0
3
t=+
+50 +40 +30
+40
67
+30
+20
+20
Conclusions
Advocate Sustainability onto Reclamation
Innovate the best solution for Reclamation
Nothing is generic as far as todays Reclamation is concerned
68
Principles of Sustainability For Reclamation
Strive to reduce burden on existing mud pits
Strive to reduce potential sites as borrow pits
Strive to reuse public fills
Strive to meet environmental restrictions
Strive to reduce cost of construction
Strive to achieve quality reclamation
These guiding principles itself, though not exhaustive, set the major
challenge to implement sustainable reclamation in Hong Kong.
69
Thank You
70