RRRP 7200 Ebean 011 A
RRRP 7200 Ebean 011 A
RRRP 7200 Ebean 011 A
Revision: A
Prepared By
Australian Nuclear Science and Technology Organisation
18 May 2006
Page 1 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
ANSTO
Replacement Reactor Project
Document N: RRRP-7200-EBEAN-011-A
Revision: A
Document Title: OPAL CONSTRUCTION AND
STAGE A COMMISSIONING EXECUTIVE
SUMMARY REPORT
Ref No:
REVISION SHEET
Revision
Letter
0
Description of Revision
Prepared
AFX
GDW
MSX
RMX
Notes: 1. Revision must be verified in accordance with the Quality Plan for the job.
RRRP-7200-EBEAN-011-A
Page 2 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
TABLE OF CONTENTS
1
2
2.1
2.2
2.3
2.4
3
3.1
INTRODUCTION ....................................................................................................................4
SUMMARY OF VERIFICATION PROCESSES .....................................................................4
Detailed Engineering Phase ................................................................................................4
Construction Phase..............................................................................................................5
Pre-Commissioning Phase ..................................................................................................6
Stage A Commissioning Phase ..........................................................................................6
SUMMARY OF KEY ACTIVITIES AND EVENTS .................................................................7
Construction Phase..............................................................................................................7
3.1.1
Civil Works ......................................................................................................................8
3.1.2
Mechanical / Process Systems.......................................................................................9
3.1.3
Electrical Systems.........................................................................................................10
3.1.4
Instrumentation and Control Systems...........................................................................10
3.2
Pre-Commissioning Phase ................................................................................................10
3.2.1
Electrical Systems.........................................................................................................11
3.2.2
Building Service Systems .............................................................................................11
3.2.3
Process Systems ..........................................................................................................11
3.2.4
Instrumentation, Control and Shutdown Systems ........................................................12
3.2.5
Containment Systems...................................................................................................13
3.2.6
Radioisotope Handling and Neutron Beam Systems ...................................................13
3.3
Stage A Commissioning Phase ........................................................................................14
3.3.1
Instrumentation and Control Systems Tests.................................................................14
3.3.2
Reactor State Tests ......................................................................................................14
3.3.3
Containment Systems Tests.........................................................................................15
3.3.4
Control Rooms & Emergency Preparedness Tests......................................................15
3.3.5
Electrical Power System Tests .....................................................................................15
3.3.6
Other Stage A Commissioning Tests............................................................................16
4
FINAL CONCLUSIONS .......................................................................................................16
RRRP-7200-EBEAN-011-A
Page 3 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
INTRODUCTION
The ARPANSA Construction Authorisation for the OPAL Reactor covers four project phases:
1. Detailed Engineering Phase
2. Construction Phase (including civil construction, procurement, manufacture and
installation works)
3. Pre-Commissioning Phase
4. Stage A Commissioning Phase
This report summarises the activities conducted under the Construction Authorisation and
consists of two substantive sections: Section 2, which summarises the verification processes
which were applied to ensure the reactor was constructed in accordance with specified
requirements and which have produced the documentation that allows ANSTO to demonstrate
this; and Section 3, which summarises the major activities and events which occurred under the
Construction Authorisation. Full details of the verification processes and all activities and events
are contained in the OPAL Construction Report (RRRP-7033-EBEAN-001) and the OPAL
Stage A Commissioning Report (RRRP-7311-EDEIN-004).
Page 4 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
made which had significant implications for safety, ARPANSA approval was also obtained in
accordance with ARPANS Regulation 51 prior to implementing the change.
Page 5 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
001). This documentation demonstrates that the reactor has been constructed in accordance
with all specified codes and standards, and design, safety and regulatory requirements.
Page 6 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
These plans were prepared by INVAP and reviewed, verified and accepted by ANSTO in
accordance with project procedures prior to commencement of Stage A Commissioning.
In June 2004, a request for approval relating to Stage A Commissioning of items important to
safety was submitted to ARPANSA to meet the requirements of Facility Licence: Construction
Authorisation, License Condition 4.7. This request for approval was based on the above
commissioning plans, although it also covered the final commissioning testing of a number of
safety-related systems to be undertaken during the Pre-commissioning Phase. In January 2005,
the CEO of ARPANSA revised License Condition 4.7 so that it required ARPANSA approval of
the Stage A Commissioning program as a whole, rather than requiring separate approvals for
the commissioning of the various safety-related items of plant. He also approved the Stage A
Commissioning program for items important to safety, provided certain conditions were met
during implementation of the program, including a number of ARPANSA control points imposed
on specific commissioning activities.
Stage A Commissioning activities were controlled through the preparation and implementation of
commissioning procedures for the various systems and subsystems of the OPAL Reactor and
overseen by the Commissioning Management Group. Commissioning procedures were
prepared in accordance with the commissioning plans, and described in detail the
commissioning activities, including the objective of the activities, acceptance criteria, reference
documentation, responsibilities, prerequisites, step by step instructions and requirements for
records generation. Those commissioning procedures were reviewed, verified and accepted by
ANSTO in accordance with project procedures prior to commencement of the relevant
commissioning activities. Stage A Commissioning activities were controlled by INVAP, but
involved significant participation by ANSTO. This included ANSTO reactor operators performing
all plant operations under the direction of INVAP.
During Stage A Commissioning, the Commissioning Quality Assurance Group conducted quality
assurance audits of the various commissioning activities, while the Commissioning Safety
Review Committee conducted reviews and provided advice on safety issues as requested by the
Commissioning Management Group.
A total of 47 commissioning test procedures were implemented during the Stage A
Commissioning Phase. Upon completion of all Stage A Commissioning procedures, a Stage A
Commissioning report was prepared, providing the final record of the Stage A Commissioning.
This report was prepared in accordance with the commissioning plan, and includes a summary
of the tests carried out, including reference to the relevant Stage A Commissioning procedures,
a description of the limitations, problems or deficiencies observed during commissioning and
their resolution; references to data collected, analyses and deviations, and the conclusions and
recommendations drawn from the testing. The Stage A Commissioning report signified the
completion of Stage A Commissioning, and has been approved by both INVAP and ANSTO.
Page 7 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
security measures. On 10 April 2002, the Minister for Environment and Heritage advised the
Minister for Science that he was satisfied with the arrangements covered by the conditions
arising from the EIS process relating to the design and construction of the reactor. These
approvals allowed construction to commence. Excavation works on the OPAL site commenced
on 10 April 2002.
The following subsections provide a summary of the key activities and events relevant to works
in the areas of civil works, mechanical systems, electrical systems and instrumentation / control
systems during the Construction Phase.
3.1.1
Civil Works
The civil works program commenced with bulk excavation works in April 2002. On 20 June
2002, this work was suspended following the discovery of two geological faults during bulk
excavation. A significant geological investigation was undertaken by independent consultants
with expertise in fault dating and structural geology, and involved several hundred metres of
deep trenching in rock in the immediate vicinity of the excavated site. Those investigations
revealed that the faults were not significant in terms of any future seismic events. The
suspension of site construction work was revoked on 23 October 2002 following the CEO of
ARPANSAs decision that the faulting on the site was not capable of resulting in surface
displacement and that there was no change in the basis for his earlier conclusions on the
reactors seismic design.
Construction of the Reactor Building, including construction of the Reactor Building concrete
structure and the high density concrete Reactor Block which surrounds the Reactor and Service
Pools, took place over the period between November 2002 and February 2005. Concrete
pouring activities were strictly controlled, and concrete testing carried out in accordance with
relevant codes and standards. The aircraft impact grillage was assembled and mounted on top
of the Reactor Building in July 2004. Fit-out and installation of building services proceeded in
parallel with and following completion of the Reactor Building structure, including installation of
cranes, fire systems, water supply systems, compressed air and gas supply systems and
communications systems. Civil works activities were strictly controlled in accordance with the
SITP process described in Section 2.2 to ensure compliance with relevant codes and standards,
design, safety and regulatory requirements. ANSTO fully participated in this verification process
by witnessing key activities, conducting inspections and reviews, and providing final acceptance
of the works.
Other facility buildings, including the Neutron Guide Hall and the Main Entry Building, were
constructed in parallel with the Reactor Building.
During September 2003, waterproofing problems were encountered at levels -7 and -5 of the
Reactor Building due to cracking in the concrete wall and floor slabs. The cracking was caused
by concrete shrinkage, coupled with stress concentrations and restraint formed by the
foundation rock. Upon detection of the problem, investigations were performed and
comprehensive remedial measures were devised and implemented to seal all detected leaks. All
remedial works were undertaken in accordance with approved procedures and SITPs. Remedial
works have been completed in a significant portion of the affected area with all leaks
successfully sealed and released. However, work in a small number of areas has not yet been
completed. Whilst waterproofing works in some areas of the Reactor Building are ongoing, the
works have no significant effect on the building structure and INVAP and ANSTO have accepted
it as fit for purpose.
Page 8 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
3.1.2
Page 9 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
3.1.3
Electrical Systems
3.1.4
Construction of instrumentation and control systems included manufacture and installation of the
First and Second Reactor Protection Systems (FRPS/SRPS), Post Accident Monitoring System
(PAM), Reactor and Facilities Control and Monitoring Systems (RCMS/FCMS), nucleonics
instrumentation, radiation monitoring instrumentation and control room consoles, as well as
installation of cabling, cable raceways and field instruments throughout the facility.
Instrumentation and control systems, particularly those involving software based digital systems,
were subject to rigorous verification and validation programs by both the manufacturer and
INVAP. These activities culminated in the integrated instrumentation and control factory
acceptance test conducted by INVAP in Argentina during 2004. In that test, the FRPS, SRPS,
RCMS, FCMS, nucleonics instrumentation and control room consoles were fully integrated and
tested before being delivered to the OPAL Reactor site. Radiation monitoring instrumentation
was also subject to factory acceptance testing in Argentina prior to shipment. Where necessary,
instrumentation was subject to qualification testing to ensure compliance with IEEE standards for
qualification of safety-related instrumentation.
Manufacture and installation of all instrumentation and control components was strictly controlled
in accordance with the SITP process described in Section 2.2 to ensure compliance with
relevant codes, standards, design, safety and regulatory requirements. ANSTO fully participated
in this verification process by witnessing key activities such as factory acceptance tests,
conducting inspections and reviews, and providing final acceptance of the manufacture and
installation of systems and components.
Page 10 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
handling and neutron beam systems. The order of sections follows approximately the order in
which pre-commissioning activities were undertaken during the Pre-Commissioning Phase.
3.2.1
Electrical Systems
Electrical pre-commissioning activities commenced in June 2004 with testing of the electrical
earthing system and subsequent energisation and testing of the facilitys high voltage
switchboard and six electrical power transformers. This was followed by energisation and noload testing of the six Main Distribution Switchboards and the downstream distribution system,
including safety-related standby switchboards, motor control centres and distribution boards. Noload pre-commissioning of the distribution system included full functional testing, verification of
electrical protective devices and electrical inspections/tests required by Australian Standards
and the electrical power supplier, Energy Australia.
Pre-commissioning of the diesel generators commenced in November 2004, and comprised a
comprehensive set of starting and loading tests to verify the capability and reliability of the diesel
generator units, including a 24 hour full load run test. The tests revealed some problems
relating to priming of the diesel generator fuel supply lines, which were rectified by modifying the
lines to prevent the occurrence of air pockets in the lines. Following pre-commissioning of the
diesel generators, a no-load integration test of the standby power system (SPS) was performed
to verify the automatic operation of the SPS to connect the diesel generators on loss of normal
power supply (NPS).
Uninterruptible power supplies, including those which supply the FRPS, SRPS, RCMS and
FCMS were also subject to full functional testing including loading tests and mains failure
simulation tests.
Pre-commissioning of the electrical system culminated in a series of full load system tests
conducted in December 2005 once sufficient electrical equipment was available to provide
electrical load. These tests verified the operation of both the NPS and the SPS while supplying
the full facility electrical load.
3.2.2
Building service systems include the radioactive liquid waste management system, compressed
and breathing air systems, gas supply systems, water supply systems, fire detection and
suppression systems, ventilation and air conditioning systems, cranes and hoists,
communications systems, lifts, surveillance CCTV systems and security systems. Each of these
systems was subject to one or more pre-commissioning procedures to demonstrate that the
operation of the system is in accordance with design specifications and relevant codes and
standards. In addition, ASIO T4 will conduct inspections and a performance demonstration of
the integrated security system to demonstrate that it meets the specified performance
requirements. The ASIO T4 report on security system performance will be transmitted to ASNO
and if deemed satisfactory, ASNO will issue a report to the CEO of ARPANSA that confirms the
security system is suitable for reactor operation.
3.2.3
Process Systems
Process systems include the primary cooling system (PCS), the reactor and service pools
cooling system, the reflector cooling and purification system, the emergency make-up water
system, the hot water layer system, the reactor water purification systems and associated resins
handling system, the secondary cooling system and the demineralised water supply system.
Page 11 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
3.2.4
Pre-commissioning of instrumentation and control systems included testing of the FRPS, SRPS,
PAM, RCMS, FCMS, nucleonics instrumentation systems and radiation monitoring systems.
Pre-commissioning of these systems involved testing of the main system functions and
verification of all field and control room connections by testing every system input and output for
correct operation. In addition, for radiation monitoring systems, radiation sources were used to
simulate high radiation conditions in order to verify correct system operation.
Pre-commissioning of shutdown systems included testing of both the First Shutdown System
(FSS), designed to shutdown the reactor by rapid insertion of control rods, and the Second
Shutdown System (SSS), designed to shutdown the reactor by rapid draining of the heavy water
reflector. Pre-commissioning of the FSS involved testing of the control rod withdrawal and
insertion times, as well as trip tests including measurement of the control rods insertion time
following a reactor trip for various system conditions. The testing also included verification of the
operation of the control rod movement protection interlock, which prevents the simultaneous
movement of more than one control rod and limits the control rod withdrawal speed. Precommissioning of the SSS included performance tests to measure the rate of drainage of the
heavy water reflector following a reactor trip for various system conditions. Acceptance criteria
associated with these tests of both the FSS and SSS were satisfied.
An event of note which occurred during pre-commissioning testing of the FRPS and the FSS
was a number of spurious actuations of the SRPS and SSS. Investigations determined that this
was caused by the control rods bouncing slightly when they were dropped, which in turn resulted
in the control rod bottom position indication incorrectly showing that more than one control rod
was not fully inserted in the period immediately following the trip. This condition is interpreted by
File Name: RRRP-7200-EBEAN-011-A.DOCRRRP-7200-EBEAN-011-A
Revision: A
Page 12 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
the SRPS as a failure of the FRPS and thus actuates the SSS. To prevent this spurious
actuation of the SRPS and SSS, modifications were made to the SRPS instrumentation.
3.2.5
Containment Systems
3.2.6
Page 13 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
3.3.1
3.3.2
The OPAL reactor has four defined operating states, known as the Power State, Physics Test
State, Shutdown State and Re-fuelling State. Each state defines a particular reactor operating
environment, with specific rules, interlocks and alarms, as well as requirements relating to
configuration of plant systems in order to either allow or preclude the performance of certain
tasks.
The bulk of the Stage A Commissioning test procedures involved testing to demonstrate the
correct operation of the reactors safety and plant systems for each of the four reactor operating
states. This included verification of the operation of reactor cooling systems, hot water layer
system, electrical system, instrumentation and control systems and reactor shutdown systems.
As there was no nuclear fuel in the core during Stage A Commissioning, fuel assembly dummies
were used to simulate the presence of the core, and nucleonic signals were simulated where
necessary. For each reactor operating state, the systems were operated and configured
accordingly in order to verify that the reactors systems are able to perform their assigned
File Name: RRRP-7200-EBEAN-011-A.DOCRRRP-7200-EBEAN-011-A
Revision: A
Page 14 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
functions and that plant parameters remain within acceptable limits. Trial tests of plant operation
manual procedures, including those for transitions between the various reactor operating states,
were included in this series of tests.
Reactor state tests included coolant flow distribution measurements which demonstrated that the
coolant flow rates within the reactor core and irradiation rig positions comply with the specified
acceptance criteria. Also, a blocked fuel assembly simulation which demonstrated that this
occurrence would be detected by the FRPS instrumentation was performed.
The operation of the PCS flap valves to initiate the transition from forced to natural convection
cooling of the reactor core following a reactor shutdown was also tested and found to comply
with the specified acceptance criteria.
3.3.3
Stage A Commissioning included tests of the reactor containment and associated containment
ventilation systems in both normal mode and containment isolated mode. The test for normal
mode verified that containment conditions, including pressure, temperature and humidity,
remained within acceptable limits and that system instrumentation and interlocks relevant to
normal mode were functional. The test for containment isolated mode verified the triggering of
the various groups of containment isolation closures, the correct operation of containment
systems (including the CERS and RCVS) during and following containment isolation, that
containment conditions remained within acceptable limits and that system instrumentation and
interlocks relevant to isolated mode were functional. The tests demonstrated that the reactor
containment and associated containment ventilation systems function correctly.
3.3.4
Stage A Commissioning included testing of procedures for evacuation of the Main Control Room
to the Emergency Control Centre (ECC) and tests of the operation of the ECC Ventilation and
Pressurisation System, which is designed to protect reactor operators from radiation during
occupancy of the ECC. An emergency drill was also conducted in order to verify emergency
preparedness, including the effectiveness of the reactor systems, emergency plans and
procedures, and reactor operations staff in responding to simulated accident scenarios. The
results of these tests demonstrated an adequate level of emergency preparedness within the
reactor and its operating organisation.
3.3.5
Stage A Commissioning included tests to verify the behaviour of the facility following a loss of
NPS and to verify the ability of the SPS to provide power to the various reactor systems
following loss of normal electrical power. The tests included verification of the effect of loss of
NPS on the reactor protection systems, shutdown systems, reactor control and monitoring
system, control room consoles and wall panels, heat removal systems, containment and
ventilation systems and CNS systems. Also verified was the automatic operation of the SPS in
response to loss of the NPS and its ability to supply essential loads including the containment
systems, emergency lighting and ventilation, reactor cooling systems and instrumentation and
control systems.
Page 15 of 16
INVAP
ANSTO
Australian Nuclear Science and Technology Organisation
3.3.6
Other Stage A Commissioning Tests consisted of an entire facility cold run test, CNS tests and
health physics tests.
The entire facility cold run test involved the reactor being operated in Power State at simulated
full power for a period of 36 hours, with dummy fuel assemblies in the core, irradiation rigs
loaded with dummy irradiation targets, and the CNS and hot cells facilities in operation. The test
also trialled procedures for control room shift arrangements and hand-overs, as well as
procedures for plant surveillance and in-service inspections. The tests demonstrated that the
reactor facility is capable of operating with high availability over an extended period and the
plant operating documentation is appropriate. Some tests originally planned for the cold run test
relating to operation of irradiation facilities could not be completed due to incomplete installation
of some items. However, this did not prevent the tests ability to demonstrate operation of the
reactor systems.
CNS tests involved CNS instrumentation and controls systems functionality verification, system
manoeuvring tests, and integrated functional tests, similar to those conducted during precommissioning, but with deuterium loaded.
Health physics tests conducted during Stage A Commissioning consisted of a health physics
walk-through and conducting radiological measurements to provide a baseline on radiation
levels prior to fuel loading. The result of the health physics walk-through was that health physics
provisions, including radiation shielding, signage, monitoring equipment, personal protective
equipment and decontamination facilities are in place and adequate.
4 FINAL CONCLUSIONS
This report has outlined the activities conducted under the Construction Authorisation, including
the verification processes applied to ensure the reactor was constructed in accordance with
specified requirements and the major activities and events which occurred under the
Construction Authorisation. The activities and verification processes completed during the
Construction Authorisation have demonstrated that the OPAL Reactor has been constructed in
accordance with design, safety, quality assurance and regulatory requirements, and that the
facility is in a state suitable for commencement of Stage B Commissioning activities.
Page 16 of 16