E.G Infra Pvt. LTD: Tinkune, Kathmandu Nepal

1) This report provides a daily construction progress update for Emero Plaza Hotel project in Kathmandu, Nepal on Chaitra 2071 (March/April 2014). 2) On this date, 57 total staff were working including 28 pile workers and 27 laborers. The laborers worked between 5-8 hours. 3) Work performed on this date included line and layout of columns and walls, earthwork excavation and backfilling, and reinforcing of shear walls and columns. Formwork installation of shear walls also began. 4) Work forecast for the following day includes continuing earthwork excavation and backfilling and reinforcing of columns and shear walls, along with beginning waterproofing works.

Uploaded by

dipesh_dmd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
673 views

E.G Infra Pvt. LTD: Tinkune, Kathmandu Nepal

1) This report provides a daily construction progress update for Emero Plaza Hotel project in Kathmandu, Nepal on Chaitra 2071 (March/April 2014). 2) On this date, 57 total staff were working including 28 pile workers and 27 laborers. The laborers worked between 5-8 hours. 3) Work performed on this date included line and layout of columns and walls, earthwork excavation and backfilling, and reinforcing of shear walls and columns. Formwork installation of shear walls also began. 4) Work forecast for the following day includes continuing earthwork excavation and backfilling and reinforcing of columns and shear walls, along with beginning waterproofing works.

Uploaded by

dipesh_dmd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

E.G INFRA PVT.

LTD
TINKUNE, KATHMANDU NEPAL
PHONE: 2229500
Contract:

Emero Plaza Hotel

Report No:
Date:

Weather:

21 C

Temperature: .
( ) Clear

( ) Rainy

( ) Windy

( ) P-Cloudy

S.NO

Type of Emp.

Staffs

Total Staff

36
Chaitra
2071

BF from previous day


Project Manager
Project Engineer
Engineer
Site Supervisor
Procurement
Runners
Operator
Driver
Store Keeper
Mechanic
of the day
Total
BF from previous day

( ) Cloudy

Nos of
Emp.
18
1
1
1
1
1
1

Working
hours
183
10
11
11
11

1
1
1
1
10

10
10
10
10
11
11
105

28
30

288
266

Pile Workers
Mason
Electrician
Plumber
Welder

0
0
0
0
0

0
0
0
0
0

Labor

27
27
57

183

Remarks

Remarks

Worker

Total of the day


Total

11 labors worked for 5


hours, rest 16 labors for 8
hours

183
449

Work Performed this day (include definable features/phase, demo, construction materials and % complete)
1
Line and layout works of columns and walls
2 Earthwork excavation and backfilling
3 Reinforcing works of shear walls and columns
4 Formworks installation of shear walls
Others:
Work Forecast for the following day
1 Earthwork excavation and backfilling
2 Reinforcing works of column and shear walls
3 Water proofing works
Changes, Comments, Conflicts, Delays & Remarks.

Delay in delivery of manpower due to miscommunication among supervisors


Tests & Test Results:
N/A
Quality Remarks: (Include rework items, substandard conditions)
Prepared by:

Dipesh Dhimal

Approved by:

Manoj Pant