Focl Newlsetter April2012 Final Color
Focl Newlsetter April2012 Final Color
Focl Newlsetter April2012 Final Color
FOCL POINTS
Friends of Colorado Lagoon is a coalition of concerned citizens working to preserve and restore Colorado Lagoon
Presidents Letter
April 2012
As I walk and run near the lagoon, I can almost see past the cloth hanging on the fences around Colorado
Lagoon, but not quite! I see neighbors, visitors, bikers, and other also craning their necks to see past the fence and into
the construction zone. We all ask the same questions: What is going on in there? Where is all that mud going? The
Friends of Colorado Lagoon thought this would be an excellent time to update you about the construction progress at
the lagoon; consider it your glimpse through the fence!
The goal of this phase of the restoration project is to remove 75,000 cubic yards of contaminated sediment from
throughout the lagoon. This sediment has accumulated over the last 80+ years, brought to the lagoon by storm runoff
along with pollutants like lead. The dredging is mandated by the State Water Board who recently set very strict limits
for pollutants in the lagoon.
In order to accomplish this, AIS Construction has mobilized several large barges each with its own excavator
on top. On any given morning, you can see these excavators slowly crawling through the lagoon, moving the barges
into place to begin dredging for the day. Working Monday through Saturday, AIS is dredging approximately 1,000
cubic yards of sediment a day on average. This sediment includes thousands of golf balls and at least one car (so far).
Once the material is removed from the lagoon, it is staged and, if needed, treated on site. Then trucks haul away the
dredged material, which raises the next question, Where does the sediment go once it leaves the lagoon?
The treated sediment leaving the lagoon is headed for the Port of Long Beach, to be used as fill in the Middle
Harbor Project. The port has given AIS a specific window of time in which to bring the sediment, and this has driven
the schedule and has necessitated the extended working hours. By accepting the sediment, the port has saved the
lagoon project significant trucking costs that would have been incurred if the material had to be trucked to another site.
(Presidents Letter - continued on page 2)
Page 1
April 2012
Photo on previous page: the AIS dredge on the water at the Lagoon
with FOCLs East Bank Restoration in the background; Photo above: the
staging area for the dredged sediment before it is taken to the Port of
Long Beach; Photo below: an automobile engine pulled up from depths
of the Lagoon. All photos from Dave Pirazzi.
April 2012
Native Trees
Some may recall the first article I wrote in April 2007 entitled
A Salt Marsh Unseen. In this communication I challenged
Lagoon visitors to take some time to look a little closer
andsee a whole new world at your feet. At that time it was
challenging to find the small remnants of salt marsh habitat
that existed. This was before FOCLs education and
community-based restoration programs had been established
at the WAMSEC and well before FOCL began its first
restoration project on the East Bank in November 2008. In
fact, so much has changed at Colorado Lagoon since that time.
This was before the storm drains were diverted and tons of
trash trapped from entering the lagoon. This was before the
culvert was cleaned and the tidal regime improved. This was
before FOCL created the beach garden that runs from the
WAMSEC to the Playgroup and before the Termino Avenue
Drain Project steamed through the Appian Way parking lot.
And of course this was before 4 excavators and an army of
trucks were unleashed on the Lagoon to remove its
contaminated sediments.
While all of these achievements have been of importance, the
biggest milestone for Friends Of Colorado Lagoon was
reached on March 26th, 2012 when the Rivers and Mountains
Conservancy voted unanimously support of FOCLs grant
application for $500,000 to revegetate 5 acres of habitat in the
Lagoons western arm, along with the installation of trails and
interpretive elements (see page 4 for more info). This new
project will make the Lagoons salt marsh and associated plant
communities more visible than ever before, but will only be
possible with the support of community volunteers. FOCL
plans to host over 200 public restoration events over the next 2
years to accomplish this work.
So as this conservation effort moves forward I now ask you,
the supporters of Colorado Lagoon, to take some time to get
a little closer involved and create a whole new world at your
feet. Together we will build new habitats and restore
Colorado Lagoons salt marsh ecosystem to be seen by future
generations to come.
Page 3
April 2012
Editors
Contributors
Whitney Graves
Taylor Parker
Dave Pirazzi
Dr. Christine Whitcraft
Eric Zahn
Page 4