Steam Temp. Required Steam Temp. Initial Steam Pressure. Final Steam Pressure. Added Water Temp
Steam Temp. Required Steam Temp. Initial Steam Pressure. Final Steam Pressure. Added Water Temp
Attempterator
Texmaco Boiler
At PRDS Station
IJT Boiler
5 Exhaust Steam
A) At PRDS Station
Calculation
Capacity of boiler 50 ton/ Hr.
Total heat at 440 Deg cel. = 793.5 * 50000 Kcal/Hr.
= 39675000 Kcal/Hr.
Total heat at 415 Deg cel. = 774.16 * 50000 Kcal/Hr.
= 38708000 Kcal/Hr.
Required quantity of water
Mw = (39675000 - 38708000) / (774.16 - 95)
Referance.
From (45Kg/cm2 , 440
Deg cel to (45 Kg/cm2,
415 Deg cel.
From steam table.
Water temp. 95 Deg cel.
Plant capacity 280 T/Hr.
Mw = 1.4 Ton / Hr
Mw = 0.65 Ton / Hr
Mw = 4.7 Ton / Hr
Mw = 3.3 Ton / Hr
Mw = 1.0 Ton / Hr
Sno.
Place
Calculation
Referance.
Mw = 0.4 Ton / Hr
Mw = 4.0 Ton / Hr
15.5 Ton/Hr.