Earned Value Management Tutorial Module 1: Introduction To Earned Value Management
Earned Value Management Tutorial Module 1: Introduction To Earned Value Management
Prepared by:
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
Current Department of Energy policy, DOE Order 413.3, Program and Project
Management for the Acquisition of Capital Assets, states the requirements for
contractors project management system
The industry standard for project control systems described in American
National Standards Institute (ANSI) EIA-748, Earned Value Management
Systems, must be implemented on all projects with a total project cost (TPC)
greater than $20M for control of project performance during the project
execution phase.
Finally, below lets look at some Best Practice guidance currently in the DOE.
The Office of Field Management has issued a series of 33 Good Practice Guides.
Though they are not official guidance, each guide describes the good practices
used throughout DOE and industry for specific topic including Earned Value
Management, and provides examples of performance objectives, criteria, and
measures.
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
With the understanding of what Earned Value is and why it used, lets take a brief look at
the history of Earned Value.
1960s - Earned value-based performance management began in the 60s, based initially
on Department of Defense (DOD) Cost/Schedule Control Systems Criteria (C/SCSC).
Earned Value was used as an objective measure for progress, i.e., physical
accomplishment
1970s-80s The DOD continued the use of Earned Value in response to bearing cost
and schedule risk in cost-plus contracting.
Contractors pushing high tech, newly developed weaponry
Military having critical schedule needs (Arms Race)
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
Traditional Management
In Traditional management, there are two data sources, the budget (or planned) expenditures
and the actual expenditures. The comparison of budget versus actual expenditures merely
indicates what was planned to be spent versus what was actually spent at any given time.
But how much has been produced?
As you can see, with this approach there in no way to determine the physical amount of work
performed. It does not indicate anything about what has actually been produced for the
amount of money spent nor whether it is being produced at the rate, or according to the
schedule, originally planned. In other words, it does not relate the true cost performance of
the project.
Time Now
Budget 5
Actuals 10
10
20
15
30
20
40
25
50
30
60
35
40
45
50
55
60
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
Earned Value takes these three data sources and is able to compare the
budgeted value of work scheduled and compare it to the earned value of
physical work completed and the actual value of work completed.
Lets take a closer look at how earned value appears in a graph.
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
10
Notice the three lines on the graph below. These lines correspond to the three
components of earned value: budget (in red), actual expenditures (in blue),
and the earned value of the production (in black). Note how the budget line is
below both the actual expenditures and the earned value lines. What does
this indicate?
First, it is obvious that the project is expending more (blue line) than it was
150
budgeted to spend, to date
125
(red line). Given the
100
progression of each line, it
75
is also apparent that this
50
trend has occurred since
25
Time Now
the beginning of the
0
J
F
M
A
M
J
J
A
S
O
N
D
project.
Budget
5
10
15
20
25
30
35
40
45
50
55
60
But what else can be
Actuals 10
20
30
40
50
60
Earned
8
15
25
30
35
45
interpreted from the graph? Forecast
70
80
90
100 110 120
Lets take a closer look on
the next page.
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
11
Time Now
J
5
10
8
10
20
15
15
30
25
20
40
30
25
50
35
30
60
45
35
40
45
50
55
60
70
80
90
100 110 120
Module
1 - Introduction
Prepared by: Booz Allen Hamilton
12
There are two conclusions the earned value data will immediately let you make;
they deal with schedule and cost variances.
Schedule Variance - the project is experiencing a schedule variance of 15. This
is derived from comparing the Earned (45) to the Budget (30). Another way of
stating this is that the project is ahead of schedule in comparison to what was
supposed to be done in the frame time measured.
150
125
100
75
50
25
0
Budget
Actuals
Earned
Forecast
Time Now
J
5
10
8
10
20
15
15
30
25
20
40
30
25
50
35
30
60
45
35
40
45
50
55
60
70
80
90
100
110
120
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
13
Time Now
J
5
10
8
10
20
15
15
30
25
20
40
30
25
50
35
30
60
45
35
40
45
50
55
60
70
80
90
100
110
120
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
14
How much money and time a particular job is likely to require prior to starting and once
stated, how much money was spent at any given time.
How much money and time a particular job is likely to require prior to starting and once
stated, how much money was spent at any given time.
Plus
Once started, what work has been accomplished to date for the funds expended (what you
got for what you spent)
Once started, what the total job will cost at completion, and how long it will take to
complete
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
15
Understanding how Earned Value fits into the program and project
management environment is also essential.
On the following page we will discuss and define items such as project vs.
program, project management, program management and the relationship
between them.
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
16
On Time!
Within Budget!
According to Specifications!
With a High Level of Customer Satisfaction
Scope
Quality
Time
Cost/Resources
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
17
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
18
Program Management
Project Management
Budgeting
Cost Proposals/Negotiations
Cost Collection
Change Control
Earned Value Management
Forecasting
Funding
Resource Management
Reporting
Risk Management
Scheduling
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
19
So far, we have discussed what Earned Value is, why to use it, and how it fits
into a program and project management environment. Next, we need to
discuss the framework needed to implement earned value.
The EVMS framework can be divided into three phases:
1. Inputs - what is needed to implement Earned Value
1. Earned Value Methods formulas, metrics and performance measurements used
1.
On the following pages these three phases for developing an Earned Value
Management System (EVMS) will be discussed in more detail.
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
20
If any of these items are not completed or are not completed appropriately, the use of Earned Value will be compromised and your outputs will not
Define/Assign
properly represent the program/project current and future status.
Schedule/Budget
Pl
an
Performance Measurement
Establish Baseline
als
tu
Ac
Accounting
System
$$$
Earned Value
Management
System
Informed Management
Decisions
Corrective Actions
Recovering Planning
g
in
nd
u
F
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
21
WBS/OBS
Project
Schedule
Resource Planning
Once again, if any of these items are not completed or are not completed appropriately,
Define/Assignthe use of Earned Value will be compromised and your outputs
will not properly represent the program/project current and future status.
Schedule/Budget
Pl
an
Performance Measurement
Establish Baseline
s
al
tu
Ac
Accounting
System
$$$
Earned Value
Management
System
Informed Management
Decisions
Corrective Actions
Recovering Planning
g
in
nd
u
F
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
22
The last phase of Earned Value is the outputs. The outputs required for an EVMS include:
Reporting requirements
Proper Analysis of Reports
Correct Action taken
WBS/OBS
Project
Schedule
Resource Planning
Establish Baseline
s
al
tu
Ac
Accounting
System
$$$
Earned Value
Management
System
Informed Management
Decisions
Corrective Actions
Recovering Planning
g
in
nd
u
F
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
23
Review of Module 1
You cannot manage what you cannot measureand what gets measured gets
done.
--- Bill Hewlett, Hewlett Packard
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
24
Summary of Module 1
Module 1 - Introduction
Prepared by: Booz Allen Hamilton
25