Project: MISSION SURE

! "# $%& ' &&(

)%&&

End User Training Manual


for
SAP PP Production Planning & Control

Process Name: Production Execution Production Order Confirmation


(T-code CO11N)

Process No: TRF/O2C/6.0

Control Copy No: TRF/O2C/6.0/

#*
Doc Version

00

+ #

Description

Prepared by

Date

Original

Palani Dorai

24.12.2009 AK Anal,

Reviewed by

Sachin Kumar Rajak,


Minu Singh

Approved by

Project: MISSION SURE

Introduction
The Production Planning and Control functional area in TRF has the following
business processes.
%
%

,
!
"

'

"

"

% &#

"

$$
&#

$
#

For each of the above processes, there are separate End User Training Manuals are
available

This End user Training manual covers from sl. no. 5 of the above list, that is, the
Production Execution (Production Order Confirmation) process.

a) Production order Confirmation - Transaction code CO11N

TRF/O2C/6.0 ' &&(


Page 2 of 12

)%&&

Project: MISSION SURE

1. Production Order Confirmation - Transaction code CO11N


Procedural Steps

Menu Path
To access CO11N, use the following menu path
SAP Easy Access > SAP menu > Logistics > Production > Shop Floor control >
Confirmation > Enter > For Operation > CO11N Time Ticket

Transaction Code
CO11N

Pre-requisite before confirming an operation


All the material that are reserved against a specific Production Order, for which an
operation is being confirmed, needs to be withdrawn from the specific Sales Order stock.

Procedure
Enter the Transaction code CO11N in the command field (as shown in the
below screen)

TRF/O2C/6.0 ' &&(


Page 3 of 12

)%&&

Project: MISSION SURE

Or go as per the navigation shown below and click CO11N Production order
Creation

Press <Enter> key or click on the check mark

icon in the top left side corner of the

Screen, the following screen Project Builder screen appears.


TRF/O2C/6.0 ' &&(
Page 4 of 12

)%&&

Project: MISSION SURE

1) Key-in the Production order Number in the Order field. For our example we have entered
the production order No 906000308.
2) Key-in the operation number to be confirmed.

TRF/O2C/6.0 ' &&(


Page 5 of 12

)%&&

Project: MISSION SURE

In order to select the operation, click once on the Open / activity field, a drop down
button; the
button will appear at the end of the field, and click this drop down
following pop up window showing all the operations for the order will appears.

For our example we have selected the operation 0010.


To select a line, Click once on the line, the colour changes as above, and then click the
check mark

button of the pop up window to get the operation populate on the field.

Note: while creating this confirmation of an operation, the following points are to be
remembered:
a)

Confirmation of operations should be in sequence. That is after confirming


say operation 0010, and then only we can confirm operation 0020.
With out confirming the previous operation we cannot jump to any other
operations.

b)

Similarly while entering the quantity of an operation in the confirmation


screen; it should be in line with the previous operation quantity.
We cannot enter a quantity which is other than the previous operations
quantity. That is we cannot jump the quantity..

Also
c)

Before Inspection, If a Person want to confirm a production order, the system


will automatically launch a Inspection call in the Inspection department.

TRF/O2C/6.0 ' &&(


Page 6 of 12

)%&&

Project: MISSION SURE

The material will go to Quality, they will hold the material, and then if they
clear it, then only the next operation can be confirmed.
And
d)

If we are confirming the Last operation of the Production order, a Inspection


call will be generated.
And
push button, the

Click on the Goods movement


following screen appears,

Click
on
this field

Click on the movement Type field, a drop down


field, and click this drop down
movement type will appear,

button will appear at the end of the

button; the following pop up window showing all the

TRF/O2C/6.0 ' &&(


Page 7 of 12

)%&&

Project: MISSION SURE

Select always movement type 101 for the last operation confirmation.
Also
Enter other required fields like storage location etc.,
3) Key-in the quantity at the Yield field
Note: In order to enter the total Production Order quantity, click on the Actual data
push button, the system will populate in the yield field the total quantity of
the Production order.

TRF/O2C/6.0 ' &&(


Page 8 of 12

)%&&

Project: MISSION SURE

4) Under Activities, In the Std. man Minute field key-in the actual time with units.

5) Enter the employee number of the person who has executed the operation. In the
Personnel No field.
In our example, we have keyed-in check no as 2699.
6) In the Execution Start field, key-in the start Date and time of the operation
And
7) In the Execut. Finish field, key-in the end date and time of the operation
8) In the Posting date field, the system will default todays Date (current date), if required
we can change this date
9) In the Break time field, key-in the total details of the time that was lost due to Machine
Break downs

TRF/O2C/6.0 ' &&(


Page 9 of 12

)%&&

Project: MISSION SURE

10) If required Key-in any textual information of the operation in the Text field.
Once all the fields are keyed-in the screen will look as below

TRF/O2C/6.0 ' &&(


Page 10 of 12

)%&&

Project: MISSION SURE

Click save

button to save the record.

End of document on T-code CO11N Production order Confirmation

End of document on Production order Confirmation - (TRF/O2C/6.0) 001