Explosion and Fire at The Phillips Company Houston Chemical Complex, Pasadena, TX - SACHE Text SECUENCIA

Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

EXPLOSION AND FIRE

AT THE PHILLIPS COMPANY


HOUSTON CHEMICAL COMPLEX, PASADENA, TX
Robert M. Bethea
Chemical Engineering Department
Texas Tech University
Lubbock, TX 79409-3121

In the discussion that follows, it is important to realize that the development


of OSHA standards is a lengthy process and that two standards ostensibly of
particular interest to the Phillips 66/Pasadena event were not yet in place. The
development of the first of these, 29 CFR 1910.147: Control of Hazardous Energy
Source (Lockout/Tagout), began in January 1977, when OSHA issued a Request
for Technical Issues and Notice of Public Meetings. After receipt and evaluation of
many comments from interested parties, OSHA issued an Advanced Notice of
Proposed Rulemaking on June 17, 1980. The preliminary draft of the standard was
issued for comment in July, 1983; was published in the Federal Register as a
proposed standard on April 29, 1988; and became effective on October 31, 1989.
The development of the second of these pertinent standards, 29 CFR
1910.119: Process Safety Management of Highly Hazardous Chemicals, was based
on lessons learned from a series of tragic events, among them Flixborough (1974),
Seveso (1976), and Bhopal (1984) and the fear that unless significant improvements
in chemical process safety occurred, an American Bhopal would probably
happen. The Center for Chemical Process Safety of AIChE was formed in 1985
partly in response to that probability. In 1985, the U.S.E.P.A. initiated a program in
response to the potential for catastrophic releases, followed in 1986 by Title III of
SARA.
A series of serious releases of highly hazardous chemicals from a plant at
Institute, WV, in August, 1985, indicated to OSHA that a program was needed to
examine the industrial practicality for the prevention of disastrous releases and the
mitigation of the effects of non-preventable releases. The primary result of this
program was the determination by OSHA that a comprehensive inspection
approach was needed which would evaluate both physical conditions and
management systems. This result was the genesis of OSHAs process safety
management standard. It was based in part on input from public testimony and
publications by CCPS and many other organizations. Notable among them was
Recommended Practice 750: Management of Process Hazards published by the
American Petroleum Institute in 1990. The OSHA process safety management
standard was formally proposed on July 17, 1990, and became effective on May 26,
1992.

On October 23, 1989, a massive explosion demolished the Phillips 66 Company


polyethylene plant in Pasadena, TX, (a Houston suburb) when more than 85,000 lbm
of flammable material was instantaneously released to the atmosphere. This
massive gas cloud was ignited within less than two min. The initial explosion threw
debris as far away as six miles and registered between 3 and 4 on the Richter scale
on Rice University seismographs. There were many secondary explosions. In all, 23
lives were lost and 314 people were injured. Capital losses were initially estimated
at over $715 million. Business disruption losses were nearly as great, $700 million.
Background
High-density polyethylene is manufactured in Plants IV and V (Figures 1 and 2) of
the Houston Chemical Complex (HCC) at high temperature and pressure. The
reaction is one of condensation polymerization of about 95% ethylene dissolved in
isobutane. Other chemical species (hydrogen, hexane, etc.) are present in the highly
flammable reaction mixture in order to meet product requirements. The resulting
polyethylene particles (fluff) are removed from the settling legs (Figure 3 and 4) of
each reactor through a product take-off valve at the bottom of each leg. In the event
that the settling leg or the product take-off valve becomes clogged with product, the
settling legs can and must be isolated from the reactor by closing a large (8-in.) ball
valve (Figures 5-7, Demco brand) installed where the settling leg joins the reactor.
If the Demco valve were open during any cleaning-out operation, the reactor
contents would be vented directly to the atmosphere. These ball valves are operated
by compressed air. In the case of reactor 6 of Plant V, the compressed-air hoses are
physically disconnected as a safety measure when the valve is closed for
maintenance. Unfortunately, the air connections for opening and closing this valve
were identical. There appears to have been no way for a Phillips 66 employee or
contract employee to tell whether the valve was rotated open or closed.
"A major function of this [8-inch Demco ball] valve is to isolate the settling leg and
other equipment downstream from the reactor for maintenance. The procedure for
maintenance work that was being performed on this settling leg at the time of the
accident required that this valve be closed, locked out, and the air supply that
operated the valve removed. Statements from both hourly and supervisory
personnel who work in this plant confirm that the details of this procedure and the
consequences of not following it were well known and clearly understood.
"It has been established by statement[s from] employees who worked in the
polyethylene Plant V on shifts preceding the October 23 day shift that, according to
procedures, the Demco valve on the No. 4 leg of Plant V, reactor 6, was closed, the
lockout device was properly installed, airline block valves were closed, the air lines
to the cylinder that operated the Demco were disconnected, and the settling leg and
transfer lines to the flash chamber were ready for maintenance. The lockout and air
line disconnection had been performed on the preceding Saturday, but, because of
work priorities, maintenance did not begin on this leg until Monday, October 23
(Silas and Cox, 1990)."

At about 1:00 1:05 pm. on October 23, 1989, an explosion occurred as a


result of a massive gas release from reactor 6: more than 85,000 lbm, or 99% of the
reactor contents were released almost instantaneously. Within 90-120 sec., this gas
mixture "found" a still-unidentified ignition source and exploded with the force of
2.4 tons of TNT. Potential ignition sources were a forklift, a gas-fired catalyst
activator with an open flame, nearby welding and cutting-torch operations, vehicles
near the polyethylene plant office building, and electrical gear in the finishing
building and control rooms. This initial explosion threw debris for about six miles
and, according to seismographic data from Rice University, registered between 3
and 4 on the Richter scale. A pair of secondary explosions occurred about 10-15
min. after the first one when two 20,000 gal. isobutane storage tanks exploded.
About 25-45 min. after the first explosion, another polyethylene reactor failed
catastrophically. There may have been as many as six more explosions in all.
As a result of the initial explosion, two of the six-man contract maintenance crew
and 21 employees of Phillips 66 were killed. Of the fatalities, 22 died at the incident
site, and a 23rd victim died in a local hospital. All those killed were within 250 ft of
the point where the gas was initially released. That release occurred, as determined
by post-incident tests by the FBI, through the open Demco valve at the top of
settling leg number 4 on reactor 6. Those tests also showed that the hoses which
supplied the compressed air to rotate the valve to the "open" or "closed" positions
had been improperly reversed when last re-connected prior to the product
blockage-clearing procedure in progress. As a result, the valve would have been in
the "open" position when the actuator switch in the control room was in the "valve
closed" position.

Cause of the Explosion


According to the Report to the President (Occupational Safety and Health
Administration, 1990), "Established Phillips corporate safety procedures and
standard industry practice require backup protection in the form of a double valve
or blind flange insert whenever a process or chemical line in hydrocarbon service is
opened. Phillips, however, at the local plant level, had implemented a special
procedure for this maintenance operation which did not incorporate the required
backup. Consequently, none was used on October 23.
"Additionally, the following unsafe conditions existed: (1) the DEMCO valve
actuator mechanism did not have its "lockout" device in place, (2) the hoses that
supplied air to the valve actuator mechanism could be connected at any time even
though Phillips's operating procedure stipulated that the hoses should never be
connected during maintenance, (3) the air supply valves for the actuator mechanism
air hoses were in the open position so that air would flow and cause the actuator to
rotate the DEMCO valve when the hoses were connected.
"Field tests have since confirmed that the DEMCO valve involved in the
accidental release was capable of being physically locked in the open as well as in

the closed position. The valve lockout system for this maintenance operation was
inadequate to prevent someone from inadvertently or deliberately opening the
DEMCO valve during a maintenance procedure."
According to the results (Silas and Cox, 1990) of the investigation of this incident by
the Phillips 66 Company, "Examination of the evidence after the accident indicates
that the lockout device had been removed and the air hoses had been reconnected to
the valve operator on the Demco valve of the No. 4 leg. The valve was open, and
the settling leg was open to the atmosphere at the bottom of the leg where a swedge
spool leading to the product take off valve should have been connected. Block valves
to the air lines for the Demco and the piping leading to them had been damaged as a
result of the explosion and moved, making their position meaningless. The evidence
indicates the release occurred through this No. 4 open Demco valve and settling leg.
"The only surviving individuals believed to have been in the immediate area of the
accident were employees of Fish [Engineering and Construction, Inc.]. In interviews
with two of these employees shortly after the accident, one of the Fish employees
placed a P66Co operator at the accident site. Statements made by a P66Co
employee and the location of the body of the operator assigned appear to contradict
this. Neither the HCC team nor the Committee were able to interview the Fish
employees about the accident, making it impossible to determine the exact sequence
of events leading to the release. However, the evidence suggest that either:
1) the lockout device was removed from the Demco, the air lines were
reconnected, and the air line block valve was opened with the leg open to
the atmosphere; or
2) the lockout device was removed from the Demco, the air lines were
reconnected, the air line block valve was opened with the leg closed to the
atmosphere, and the leg subsequently was opened to the atmosphere
without first relocking the Demco, closing the air line block valves, and
removing the air lines.
Either of these actions would have been a serious violation of well established and
well understood procedures and would have created the conditions that permitted
the release and subsequent explosion. "
In addition to the 23 deaths and 314 injuries (185 Phillips 66 and 129 contract
employees), estimates (Mahoney, 1993) of the property damage at the HCC and the
lost income due to disruption of business are $715.5 million and $700 million,
respectively. Phillips 66 Company also agreed (USDoL, 1991) to pay a $4 million
fine and to institute process safety management procedures at four of its facilities.
Another key component of the settlement involves training of on-site contractor
employees as well as Phillips employees about potential hazards. The details of the
settlement agreement between OSHA and Phillips 66 Company are reported in
USDL/OSHA news release 91-416 of August 22, 1991. The settlement agreement
between OSHA and Fish Engineering is described in USDL/OSHA news release 92497 of August 4, 1992, and required payment of a $100,000 fine and implementation
of a corporate-wide safety and health program as detailed in the news release.

Response to the Explosion


Early Response
The initial response was provided by the Phillips 66 Company fire brigade which
was soon joined by members of the Channel Industries Mutual Aid association
(CIMA). This organization had 106 members in the Houston area at the time of the
HCC fire and explosion. The mission of CIMA is to provide emergency assistance
to members with regard to firefighting, search and rescue, first aid, and equipment.
Site command and coordination was vested in the incident commander who was the
Phillips 66 Company fire chief. Technical assistance was provided by a team from
the US EPA. Cooperating governmental agencies were the Texas Air Control
Board, the Harris County Pollution Control Board, the FAA, the U.S. Coast Guard,
and OSHA.
Fire Fighting
The fire-fighting water system at the HCC was part of the process water system.
When the first explosion occurred, some fire hydrants were sheared off at ground
level by the blast. The result was inadequate water pressure for fire fighting. The
shut-off valves which could have been used to prevent the loss of water from
ruptured lines in the plant were out of reach in the burning wreckage. No remotelyoperated fail-safe isolation valves existed in the combined plant/fire-fighting water
system. In addition, the regular-service fire-water pumps were disabled by the fire
which destroyed their electrical power cables. Of the three backup diesel-operated
fire pumps, one had been taken out of service, and one ran out of fuel in about an
hour. Fire-fighting water was brought in by hoses laid to remote sources: settling
ponds, a cooling tower, a water main at a neighboring plant, and even the Ship
Channel. The fire was brought under control within about 10 hr. as a result of the
combined efforts of fire brigades from other nearby companies, local fire
departments, and the Phillips 66 foam trucks and fire brigade.
Search and Rescue
All search and rescue operations were coordinated by the Harris County Medical
Examiner and County Coroner. Search and rescue efforts were delayed until the
fire and heat subsided and all danger of further explosions had passed. These
operations were difficult because of the extensive devastation in the HCC and the
danger of structural collapse on the search and rescue team. The Phillips 66
Company requested, and the FAA approved and implemented, a 1 -mile no-fly zone
around the plant to prevent engine vibration and/or helicopter rotor downwash
from dislodging any of the wreckage. The U.S. Coast Guard and City of Houston
fire boats evacuated over 100 trapped people across the Ship Channel to safety.
OSHA preserved evidence for evaluation regarding the cause of the catastrophe.

Findings of OSHA's Investigation


The findings of OSHA's investigation of the Phillips 66 disaster involve deficiencies
in what we now refer to as process safety management, emergency planning and
response, building or facility egress and escape routes, and employee training. The
most serious of these findings follow.
1) No process hazard analysis had been utilized in the polyethylene plant. As
a result, many serious safety deficiencies were ignored or overlooked.
2) Phillips' own existing safe operating procedures (Silas and Cox, 1990) for
opening lines in hydrocarbon service were not required for maintenance
of the polyethylene plant V settling legs. Rather than rely on a single
block valve (the Demco valve), a double-block-and-bleed valving
arrangement or a blind flange after the single block valve should have
been used.
3) The single block (Demco) valve on the settling leg was not designed to
fail to a safe (closed) position in the event that the air pressure operating
the valve were to be interrupted or to fail.
4) No provision was made for the development, implementation, and
enforcement of an effective permit system for line opening, hot work, or
vehicle entry into an area which could contain hazardous vapors, i.e., a
Class I, Division 1 area.
5) Phillips did not follow adequate procedures such as ANSI Z244.1-1982
for lockout/tagout of equipment in a known hazardous area. Such
procedures are now covered by 29 CFR 1910.147 which was not in effect
at the time of this disaster.
6) No permanent combustible gas detection and alarm system was located in
or near the polyethylene reactors to provide an early warning of leaks or
releases.
7) Ignition sources (open flame on a gas-fired catalyst activator) were
located near or downwind (The prevailing winds at the HCC were from
SE to NW) from large hydrocarbon inventories. In addition, ignition
sources (forklift truck, welding and cutting-torch operations and
vehicles) were introduced into such high-hazard areas without testing for
the presence of flammable gases.
8) Ventilation system intakes for buildings were located in close proximity to
or downwind from hydrocarbon processes or inventories. The ventilation
system for the Plant IV and V finishing building could draw in air
containing flammable gases in the event of a leak or release in the Plant V
reactor area. That situation could have resulted in a confined vapor cloud
explosion.
9) The fire protection system, particularly the fire-fighting water supply and
its associated pumps, both regular and standby, was not maintained in
an adequate state of readiness to provide adequate fire-fighting
capability as already discussed.
Other factors contributed to the extent and severity of this disaster. Four are
especially notable:

1) proximity of high-occupancy structures (control rooms) to hazardous


operations,
2) inadequate separation between buildings,
3) crowded process equipment, and
4) insufficient separation between the reactors and the control room for
emergency shutdown procedures.
Recommended layout criteria and separation distances have been available (Lees,
1980; Mecklenburgh, 1973; Wells, 1980) for many years.
OSHA Citations
The major findings of OSHAs investigation of the incident provided the basis for
the Phillips 66 Company citations (U.S. Department of Labor, 1990a) based on
alleged willful and serious violations of OSHA standards. These deficiencies
included three categories of willful violations as quoted from OSHA news release
90-193 of 4/19/90 and are summarized in the table.
1) Failure to prevent the uncontrolled release of flammable vapors.
2) Failure to minimize or mitigate the consequences of a release of
flammable materials.
3) Failure to provide adequate fire protection
and nine serious violations:
1) Obstacles to safe egress from the facility.
2) No second means of egress.
3) Inappropriate evacuation routes for employees with no alternate routes
established.
4) Inadequate emergency planning for water to fight fire.
5) Failure to provide medical exams to determine employees ability to wear
respirators.
6) Inaudible emergency alarm siren in the finishing building.
7) Failure to inform and train maintenance employees to work safely with
hazardous chemicals.
8) Procedures were not established for emergency escape respirators.
9) Employees were not familiar with emergency evacuation procedures and
hot work permits were not issued for vehicle entry
As a result of the settlement (OSHA news release 91-416 of 8/22/91) between OSHA
and Phillips 66 Company, OSHA agreed to delete the willful characterization of the
citations and the Company agreed to pay a $4 million fine and to institute process
safety management procedures at Pasadena, Sweeny, and Borger, TX and also at its
facilities in Woods Cross, UT. The process safety management procedures include
1) analysis of each process having the potential for an uncontrolled release
of highly hazardous chemicals;
2) evaluation of:
a) safety and hot-work procedures;
b) lockout/tagout procedures;

c) proper electrical classification of hazardous locations and control


over ignition sources introduced into those areas:
d) contingency planning for upset conditions and emergency
response;
e) upset and emergency condition detection systems and systems to
mitigate the scale of hazardous chemical releases;
f) siting, separation, and design and configuration of physical
facilities and equipment to ensure safety;
g) training of operators, technicians and maintenance personnel;
h) safety of existing standard operating procedures and maintenance
procedures; and
i) assignment of authority to plant personnel to identify and correct
hazardous conditions;
3) Phillips will
a. prepare written responses to each process hazard analysis, detailing
action to be taken or justification for not taking action if management
disagrees;
b. promptly implement and document actions taken pursuant to process
hazard analyses;
c. communicate actions to affected employees, including contractors;
and
d. assure that all corrective action is completed.
In addition, the Company will develop and maintain a compilation of written
safety information for employees and contractors. . . and communicate this
information to all affected employees focusing on hazards of chemicals and
information on the equipment and technology involved in the process. Phillips will
also prepare written operating procedures to provide clear instructions for safely
conducting process and maintenance operations. As another part of the agreed
worker education and training, Phillips will provide an overview to each
employee involved in a covered process or maintenance operation of the process . . .
pertinent operating procedures emphasizing safety. Phillips will conduct annual
and refresher safety training or as needed when processes change. Employees will
receive training before assignment to a process or maintenance operation.
Phillips will inform contractors of any known potential fire, explosion or toxic
release hazards of processes on which or near which the contractor[s employees]
will be working. The Company will ensure that contract employees are trained in
necessary work practices and emergency procedures to do the job safely.
OSHA also alleged (U.S. Department of Labor, 1990b) that Fish Engineering and
Construction, Inc. was contributory to the 10/23/89 disaster and that willful and
serious violations of OSHA standards had occurred. The deficiencies listed in the
willful citations follow:

1) Failure to require employees to use hot work permit [and]


2) Failure to obtain hot work permits when cranes were brought into the
polyethylene unit.
Among the serious violations were
1) Failure to determine combustible gas levels and
2) Inadequate hazard communication and emergency procedures training.
As a result of the settlement (OSHA news release 92-497 of 8/04/92), OSHA reduced
the originally proposed fine from $729,000 to $100,000 which Fish agreed to pay.
Fish also agreed to implement a corporate-wide safety and health program to
include
1) all items cited by OSHA and [the] conditions covered by [OSHAs]
general industry and construction standards,
2) other hazards subject to Section 5(a)(l) of the Occupational Safety and
Health Act,
3) management systems already implemented . . . to address safety and
health,
4) an audit program and an action plan, and
5) to correct any potential hazards noted in the audit program.
Learning from the Disaster
As a member of the Channel Industries Mutual Aid association (CIMA) and as a
result of its involvement with the Local Emergency Planning Committee (LEPC),
Phillips met CIMA guidelines for equipment and training and had coordinated its
emergency plans with other responders. After the explosion, representatives of
CIMA, LEPC, the media, and local government began a year-long cooperative
effort to review their emergency plans and to learn from the Phillips explosion
(Richardson, 1991). The results of these efforts are divided into three parts:
findings/critique, accomplishment, and recommendations.
Findings and Critiques
One of the principle findings was that worst-case scenario, such as the massive series
of explosions, had not been considered in developing the emergency plan. Crisis
management planning had been initiated at the corporate level, but was not
complete when the explosion occurred. The incident reinforced the necessity and
value of continuous employee training in emergency-response procedures. Phillips
management found that participation in a cooperative emergency training and
response network such as CIMA and LEPC was essential in providing the necessary
manpower and equipment to the site in response to the emergency. Responders
from the community and other industries were effective, not only because of their
own training, but also because of mutual training in potential problems at each
others sites.

The review revealed that efficient communication was severely hindered or at times
impossible because of insufficient coordination among responders and with the
media. It became obvious that a regional communication plan was needed, perhaps
similar to that developed by the Harris County EMS base station.
The Phillips explosion provided the strongest of incentives for CIMA members,
other industries, and local governments to review and update their emergency
plans. As a result, working committees were established to develop recommended
solutions to problems identified in the review. Four specific findings were
developed. The first was that federal and state officials at the scene did not
coordinate their activities, and in some cases, contradicted each other and plant
officials when talking to the news media.
The second finding concerned critical sites. No backup emergency
operation/command center had been pre-planned. Apparently, no plans had been
made for the location of a triage station. The station was initially set up where some
casualties were located, but had to be moved twice. The first move was caused by
the second explosion in the Houston Chemical Complex. The triage station was relocated to avoid being caught in a kill zone should an even larger explosion occur.
The second move was necessitated by a change in wind direction that sent smoke
from the burning plant over the new triage site. The third critical location was a
series of pre-planned landing zones for helicopters with easy access for ambulances.
The third finding addressed the number of telephone calls jamming the lines for
hours after the incident. Although the public and family members of Phillips
employees were justifiably concerned and needed information, the number of calls
delayed dissemination of that very information. The number of calls also delayed
broadcasts on the Emergency Broadcast System by the staff of the Pasadena
Emergency Operations Center. In addition, many Phillips and emergency personnel
were tied up responding to the public and the media and were thus unavailable for
other essential work (Richardson, 1991). Since the Phillips disaster, procedures for
the development and evaluation of crisis communication plans have been
summarized by Traverso (1993).
The fourth finding was that the warnings from the emergency operations center
omitted information that the smoke and fumes were not toxic (Richardson, 1991).
Accomplishments
Among the accomplishments of the committees, three seem most important to
chemical engineering faculty and their students. The first was the development of a
control contact point for information about victims for use by the community
emergency operations center and the facility involved in the incident. Another was
the development of a checklist for reporting and responding to all types of
emergency off-site incidents. The third was agreement on standard signals for
outdoor warning systems.

Recommendations
The committees recommended that application be made for an emergency
broadcast system transmitter to facilitate information transfer by plant personnel or
the incident/emergency response commander. The committees also recommended
that each site include a backup emergency operations center in its emergency plan.

Implications for Chemical Engineering Curricula


If we as faculty have learned anything from the Phillips 66 Company disaster, it is
that we must teach our students how to behave as professionals. Such a student,
upon graduation and reporting to work, will be able to

understand and use the important safety features and procedures


within a plant environment,

take ownership of all assignments and projects,

promote effective teamwork,

avoid or resolve conflicts within a team,

listen discerningly to instructions,

understand assignments and project objectives,

critically review and assess assignment descriptions for omissions and


redundancies,

ensure that all team members understand their individual as well as


the teams responsibilities,

listen objectively to the concerns of team members,

develop and refine plans for action, and

develop and adhere to a reasonable time schedule for completion of all


assigned or assumed tasks.
Such a young professional seeks opportunities for developing his/her leadership
skills and is fully aware that he/she is accountable for all of his/her actions. To reach
this level, the young engineer will have developed effective communications and
interpersonal skills and will have become a facilitator.
The students/engineers described will be able to function effectively and contribute
their knowledge and skills to any team, whether in a design or unit operations
laboratory course or as a company representative to or participant in a LEPC or a
mutual aid organization such as CIMA. Such people will have had their skills honed
by HAZOPs and other process hazard analysis techniques and will be willing to
consider occurrence of even the most extreme event, e.g., total reactor or process
venting followed by a series of explosions that leapfrog through the plant. These
young engineers will be able to accept criticism, even if not always constructive, of
their designs and analyses and be able to evaluate dispassionately the failures of
their designs or procedures in order to learn from them as was done in the
cooperative review after the Phillips disaster.
The young professional described above will not have at graduation all the chemical
process safety, communications, etc. skills which he/she needs. The concepts of

inherently safer designs (intensification, substitution, attenuation, limitation of


effects, and simplification as described by Kletz (1993)) can be woven into
fundamental chemical engineering courses starting with process principles, unit
operations, and thermodynamics, and reinforced in the process design course.
Students can be exposed to the necessity of and procedures for selecting and sizing
relief valves and safety valves in their basic sophomore fluids and thermodynamics
I courses. Two-phase flow through safety relief valves is too complex for inclusion in
such undergraduate courses.
Many common industrial training requirements can be previewed (Bethea, 1991) in
process control and unit operations laboratory courses. This training can include
lockout/tagout procedures, start-up inspection and start-up of equipment or (unit)
processes, equipment/experiment shutdown, and emergency shutdown and
evacuation procedures. Those laboratory courses can also be used to show the
students how to prepare limited emergency plans and how to conduct at least one
type of hazard analysis. The preparation of multi-part operating directions can be
covered in engineering communications courses. Discussions of well-known
accidents and incidents can be held as part of undergraduate seminars or even
AIChE Student Chapter meetings. Auditing of departmental teaching and research
laboratories, shops, and storage facilities to ensure that adequate procedures are in
place to prevent the occurrence of incidents can be handled by a departmental
safety committee composed of seniors and graduate students, with a faculty member
as team leader. Hopefully, training of undergraduate students in the techniques of
accident and incident investigation and reporting procedures will not be required as
part of their laboratory work.
The Senior process and plant design course(s) can logically include electrical
classifications of areas and the corresponding effects on site layout, distance
requirements between types of facilities or processes, and control room location and
design requirements. Wells (1980) and Lees (1980) are excellent sources of such
supplementary material as is the Dow Fire and Explosion Index (1994). Control
system design including selection of components, fail-safe designs, and hazard
analyses of the resulting PIDs can be, and usually is, included in process control
courses. Such topics as diking and drainage, fire-water distribution and water and
foam deluge systems, while necessary components of the students loss prevention
education, are so specialized that they cannot be incorporated into the
undergraduate chemical engineering curriculum. As part of the design courses(s),
the students must be made to realize the importance of seeking expert assistance
and guidance as necessary as a part of their responsibilities in the design and
operation of safe facilities and plants. Indeed, one of the greatest challenges to the
instructor of such courses is helping the student to recognize when such assistance is
needed.

References
1. Bethea, R.M.: Incorporation of Occupational Safety and Health into Unit
Operations Laboratory Courses, NIOSH Instruction Module, U.S. Dept. of
Health and Human Services, Cincinnati, OH (1991).
2. Cobb, J.T.,Jr.: Essay/Viewgraph Package: Consequences of Operating
Decisions, Center for Chemical Process Safety, Amer. Inst. Chem. Engrs.,
New York, NY (1995).
3. Dows Fire & Explosion Index Hazard Classification Guide, 7th ed., Amer.
Inst. Chem. Engrs., New York, NY (1994).
4. Kletz, T.: Plant Design for Safety: A User-Friendly Approach,
Hemisphere/Taylor and Francis, New York, NY (1993).
5. Lees, F.P.: Loss Prevention in the Process Industries, Vol.1, Ch. 10 (Plant
Siting and Layout), pp. 211-230, Butterworths, London (1980).
6. Mahoney, D.G. (Ed.): Large Property Damage Losses in the HydrocarbonChemical Industries: A Thirty-year Review, 15th ed., M & M Protection
Consultants, New York, NY (1993).
7. Mecklenburgh, J.C. (ed.): Plant Layout, George Godwin, Ltd., London
(1973).
8. Merriman, M.: Emergency Medical Response Teams React Swiftly to
Phillips Plant Tragedy, Occup. Safety & Health 59(3): 32, 33,35,36 (1990).
9. Mihm, J.C.: Principles of Performance, paper presented at the Southwest
Regional Conference of Student Chapters of the American Institute of
Chemical Engineers, Texas Tech Univ., Lubbock, TX (Feb., 1992).
10. Occupational Safety and Health Administration: Phillips 66 Company
Houston Chemical Complex Explosion and Fire: A Report to the President,
U.S. Dept. Of Labor, Washington, DC (1990).
11. Richardson, T.: Learn from the Phillips Explosion, Hydr. Proc. 70(3): 83-84
(1991).

12. Silas, C.J. and G.A. Cox: Phillips 66 Companys Response to OSHA
Citations, Phillips Petroleum Co., Bartlesville, OK (5/09/90).
13. Traverso, D.K.: How to Develop a Crisis Communication Plan, Occup.
Hazards 55(3): 58-61 (1993).
14. U.S. Department of Labor: Citation and Notification of Penalty to Phillips 66
Company, Inspection no. 106612443, Occupational Safety and Health
Administration, Houston, TX (04/19/1990a).
15. U.S. Department of Labor: Citation and Notification of Penalty to Fish
Engineering and Construction, Inc., Inspection no. 107365751, Occupational
Safety and Health Administration, Houston, TX (04/19/1990b).
16. Wells, G.L.: Safety in Process Plant Design, Ch. 8 (Damage Minimization
and Control), pp. 145-178, John Wiley & Sons, New York, NY (1980).

Phillips 66 Disaster
Houston Chemical Complex
Oct. 23-27, 1989
TIME
min:sec:frame

TOPIC

00:00:00

START (Fully rewound)

00:08:12

fireball copyright warning

00:29:10

"Day One 10/23/89" header

00:33:13

home video: fireball

00:49:12

employee describes explosion and its effects on him

01:00:12

elderly couple describe explosion

01:12:04

smoke and initial explanation of probable cause of the disaster

01:35:26

telephoto view of burning plant from helicopter

01:48:27

vertical fire jet plume

01:52:29

Phillips employees describe explosion

02:15:19

emergency vehicles driving toward fire in Unit 5 where initial


explosion occurred

02:27:11

Bill Stolz (Phillips 66 environmental director) gives first official


statement about the disaster

02:37:09

Ben Wilson (Skyeye): description of burning unit, billowing


smoke dispersion indicates scope of multiple fires

02:56:20

description of Rice University seismograph traces with


comments by laboratory director

03:37:13

aerial view of Unit 5 area

03:40:29

ground-level view of explosion, note large debris rising on right


side of screen

03:43:20

second major explosion

03:52:17

aerial overview

03:58:12

Skyeye view, tower in close foreground; description of effect on


workers and delayed alarm

04:46:08

emergency vehicles

04:49:10

ground view of fire through electrical substation; comments


about loss of firefighting water because of the first explosion

04:55:25

employees and members of emergency response teams


watching the disaster unfold

05:01:29

telephoto view of fire from 30 miles away

05:19:18

victim being ferried to hospital by helicopter

05:47:02

relatives trying to locate injured or missing employees

06:43:03

Day Two 10/24/95 leader

06:47:10

Phil Archer describes body search

07:20:15

ground view of fluff section of polyethylene plant, description


of initial survey of plant

07:41:26

Jere Smith (Phillips 66 spokesman) describes initial objective


(put fire out) and efforts during the previous night

08:04:03

Bob Benz (Phillips plant manager) explains the possible


sequence of events leading to the first explosion and what the
Company knows so far

08:16:20

HCC layout (Figure 1) followed by close-up plan view (Figure


2) of initial explosion area (Unit 5 )

08:36:28

scene at HCC followed by burnt-out area (Note: smoke shown


in this area on Day One has been reduced to a light haze as a
result of firefighting efforts, FAA has issued a 1000-ft advisory
caution zone around the HCC)

08:49:14

aerial overview continues and focuses on haze rising from the


area of the initial explosions

09:19:26

wide-angle view of devastated area

09:34:15

Pasadena fire chief (Jay Goyer) gives update on


extinguishment efforts

09:43:09

final knockdown efforts on several small fires

09:48:20

wide-angle aerial view

10:01:16

view straight down into devastated area

10:08:02

Channel Explosion - Damage Survey leader

10:13:16

overview from helicopter

10:26:26

close-up of fire zone

10:32:26

water still being played on two large columns

10:41:23

parking lot showing damage to parked cars (roofs smashed in,


doors blown off) from the unconfined vapor cloud explosion

10:55:10

aerial view (gas holders and other tanks in foreground) from 1


mile away (FAA restriction during body search)

11:08:16

left center of Unit 5 area from 1 mile away

11:24:11

close-up of Unit 5 : smoke and rubble from the explosion

11:31:04

Bob Benz summarizes planned efforts for Day Two: damage


and entry assessments, search for survivors

11:44:02

damage assessment team going in

11:48:27

close-up of Units 4 and 5

11:57:23

reporter explains two-stage plant warning signals and that


employees have reported that the warning signals were
effective and that those employees felt that their safety
training was adequate

12:32:22

aerial view of damaged area (note: Ship Channel has been


re-opened)

12:57:20

Day Three 10/25/89 leader

13:01:04

Channel Explosion Day Three leader and maintenance shop


area where third victim was found

13:10:14

reporter describes arrival of OSHA on site (aerial view of Unit


5 area)

13:21:29

Gil Saulter, OSHA Regional Administrator

13:37:13

Scott Carlberg (Phillips 66) discusses safety record at the HCC

13:58:15

heavy equipment removing debris (fourth body found)

14:15:05

Channel Explosion - Inside look leader followed by groundlevel view of wrecked area

14:20:29
``

wreckage clearing, looking for asbestos and radioisotopes (e.g.


cesium) used in measuring devices

14:41:10

Glenn Cox, Phillips 66 president, explains what the Company


will do

15:25:23

Day Four 10/26/95 leader

15:30:27

News of a leak in the area where the searchers are working

15:38:28

Reporter (Phillip Bruce) quotes a Phillips 66 spokesman


(George Minter) who explains that there is an apparent
hydrocarbon leak near the reactor in plant number 5 where
the searchers are. The area is flooded with water and
employees with hand-held [total hydrocarbon] monitors enter
area to ensure that no small hazardous pockets of gas exist.

16:25:21

George Minter (Phillips 66 spokesman) explains what


happened, what was done, why it was necessary to pull back
from the Unit 5 area

16:41:05

ground shots of disaster area

16:44:29

Day Five 10/27/89 leader

16:50:04

Channel Explosion leader, death toll now 7 as described by


reporter in studio. She describes search and recovery
operations planned for Day Five in the finishing area and the
control room.

16:58:08

clearing away debris near the control room where the 15


missing workers may be buried

17:17:27

Channel Explosion- The Response leader

17:29:18

Pasadena fire chief describes effectiveness of CIMA, Channel


Industries Mutual Aid Association

18:03:00

explanation of need for CIMA and the cooperation with and


support for it by local emergency responders

18:14:17

overview of industrial area along the Ship Channel where


CIMA was developed

18:28:03

CIMA formed in 1947 after the huge Texas City fire

18:33:15

fighting HCC fire at night

18:44:22

END of tape

18:49:09

copyright warning

19:13:28

warning off, STOP tape

You might also like