While entering:
Times of the followings to be logged down:
When vessel enters dock.
When the gate closed
When pumping out commenced.
When vessel sewed
When pump out completed.
1
Class 1 & 2 Oral Answer ( Part 8 )
Procedures:
Arrange a meeting with the heads of departments. Inform them about the dry docking plan.
Inform them about:
The dry dock, particulars of dry dock, if any, expected date of dry dock etc.
Instruct the chief engineer / chief officer to prepare a comprehensive dry docking and repair list.
Arrange another meeting with the head of the departments to go through the repair list
respectively.
Determine which repairs can be done onboard by ship’s personnel.
Check there is no overlapping of repairs between various departments.
Recompile repair list of both departments.
Prepare an official repair list, include proper photocopies of plans or diagrams of parts to repair.
2
Class 1 & 2 Oral Answer ( Part 8 )
Send the repair list to office. Also send the list of repairs to be done by ship’s personnel.
Approved list from head office will be send back to the ship.
Order the necessary stores, materials for repair jobs by ship's crew.
Assign duties for officers and brief them about safety and security of the vessel and maintaining
efficient watch at all times.
For chief officer, overall supervision of deck work list, safety and organization of crew for dry
dock and survey.
For 2nd officer, supervision of hull cleaning and painting and to keep watch under c/o's
instruction.
For 3rd officer, in charge for safety while in dry dock and to keep watch under c/o's instruction.
Designate personnel for fire patrol and gangway watch.
Designate personnel for filling FW and disposal of garbage.
Instruct c/o to brief the crews on general safety requirement, dock and regulations to be followed
and procedures to be taken in case of emergency / accident.
Off-hire time and position to be ascertained and logged (if time chartered).
3
Class 1 & 2 Oral Answer ( Part 8 )
Send the repair list to office. Also send the list of repairs to be done by ship’s personnel.
Approved list from head office will be send back to the ship.
Order the necessary stores, materials for repair jobs by ship's crew.
Assign duties for officers and brief them about safety and security of the vessel and
maintaining efficient watch at all times.
For chief officer, overall supervision of deck work list, safety and organization of crew for dry
dock and survey.
For 2nd officer, supervision of hull cleaning and painting and to keep watch under c/o's
instruction.
For 3rd officer, in charge for safety while in dry dock and to keep watch under c/o's instruction.
4
Class 1 & 2 Oral Answer ( Part 8 )
Additional surveys
5
Class 1 & 2 Oral Answer ( Part 8 )
Stand-by and prepare fire fighting equipments for repair and adjacent areas.
Procedures:
Not possible for normal dry docking.
Damage or repair works in a suitable position.
Possible to pump out some of the dock water sufficient to expose the affected area.
Leave the vessel partly waterborne.
Reduce the reactions on the blocks.
Reduce the tendencies of hogging.
Reduce the tendencies of sagging.
Critical period
The period since the keel first touches the block until the vessel takes blocks overall.
6
Class 1 & 2 Oral Answer ( Part 8 )
MM' = (P X KM)/W
The danger is, due to subsequent loss of GM, the vessel may lose positive stability
and may capsize.
Ship’s stability condition to be kept as close as to that when she is entering in the dry
dock.
Anodes fitted.
While refloating:
7
Class 1 & 2 Oral Answer ( Part 8 )
After refloating:
8
Class 1 & 2 Oral Answer ( Part 8 )