Project Scheduling and Network Techniques
Project Scheduling and Network Techniques
Project Scheduling and Network Techniques
Project Management
Techniques
3-1
PROJECT MANAGEMENT
TECHNIQUES: PERT AND CPM
The Framework of PERT and CPM
Network Diagrams and Approaches
Activity on Node Example
Determining the Project Schedule
Forward Pass
Backward Pass
Calculating Slack Time and
Identifying the Critical Path(s)
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-2
Outline - Continued
Variability in Activity Times
Three Time Estimates in PERT
Probability of Project Completion
3-3
Learning Objectives
When you complete this chapter,
you should be able to :
Identify or Define:
Critical path
AOA and AON Networks
Forward and Backward Passes
Variability in Activity Times
3-4
3-5
Project Scheduling
PERT
Identifying
precedence
relationships
Sequencing
activities
Determining
activity times &
costs
Estimating
material & worker
requirements
Determining
3-6
J
nth
F
Mo
M
A
M
v ity
Acti
ign
Des
d
Buil
t
Tes
Purposes of Project
Scheduling
Project Management
Techniques
Gantt chart
Critical Path Method
(CPM)
Program Evaluation &
Review Technique
(PERT)
3-8
Gantt Chart
Activity
Time Period
J
Design
Build
Test
3-9
3-10
Consider precedence
relationships and
interdependencies
3-12
Each uses a different estimate
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
A Comparison of AON
and AOA Network
Conventions
3-15
Milwaukee General
Hospitals Activities and
Predecessors
Activit
Description
Immediate
y
A
Predecesso
rs
-
Build internal
components
Modify roof and floor
A, B
C
burner
Install pollution control
system
Install air pollution device
D, E
F, G
E
F
3-16
C
F
Star
t
B
H
G
3-17
s
w
o
r
Ar w
sho nc
de
e
c
pre e
hi
s
n
io
t
a
l
e
B
M
ro o
of dif
/ y
r floo
D
umm
y
Activi
ty
4
E
Build burner
A
co in Bu
m ter ild
po n
ne al
nt
s
C
Constru
ct stack
Pour
concrete/
Install frame
3-18
coIn F
ntsta
ro ll
ls
Inspect/T
n
o
est
i
G lut ice
l v
o
e
lpld
l
ta tro
s
In on
c
3-19
EF = ES + Activity time
EF is earliest finish
ES = Maximum EF of all
predecessors for non-starting
activities
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-20
LS = LF - Activity time
LS is latest start
LF = Minimum LS of all
successors for3-21
non-ending
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
ES
EF
Earliest
Finish
Latest
Start
LS
LF
Latest
Finish
Activi
ty
Durati
on
Earliest
Start
3-22
C
F
Star
t
B
H
G
3-23
s
w
o
r
Ar w
sho nc
de
e
c
pre e
hi
s
n
io
t
a
l
e
C
2 H4
2 C4
2
Slack
=0
FF
4 H7
13
1
3
0
E
Slack=6 13H 15
4 H
8
F
H
8
4
13 15
4
2
Slack=0 G
D
Slack=0
3 D7
8 G 13
H
H
8
13
4
8
4
5
Slack=1
Slack=0
3-24
Gantt Chart
Earliest Start and
Finish
A Build internal
components
B Modify roof and
floor
C Construct collection
stack
D Pour concrete and
install frame
E Build hightemperature burner
F Install pollution
control system
G Install
air pollution
PowerPoint presentation
to accompany
Heizer/Render
Principles
of Operations
device
Management, 5e, and Operations
Management, 7e
3-25
Gantt Chart
Latest Start and Finish
Milwaukee General Hospital
1 2 3 4 5 6 7 8 9 10
1112 13 1415 16
A Build internal
components
B Modify roof and
floor
C Construct collection
stack
D Pour concrete and
install frame
E Build hightemperature burner
F Install pollution
control system
G Install
air pollution
PowerPoint presentation
to accompany
Heizer/Render
Principles
of Operations
device
Management, 5e, and Operations
Management, 7e
3-26
Gantt Chart
Latest Start and Finish
Build House Project
Activity
111
123456789012
3-27
3-28
Project Times
Used to obtain
probability of
project
Sum of critical path
completion!
Expected project
time (T)
activity times, t
3-29
PERT Probability
Example
Youre a project
planner for General
Dynamics. A
submarine project
has an expected
completion time of
40 weeks, with a
standard deviation of
5 weeks. What is the
probability of
finishing the sub in
50 weeks or less?
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-30
1995
Corel Corp.
Converting to
Standardized Variable
X - T 50 - 40
=
= 20
Z=
.
s
5
Normal
Distribution
Standardized
Normal Distribution
sZ= 1
s= 5
mz= 0 2.0
T= 40 50 X
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-31
Obtaining the
Probability
Standardized Normal
Probability Table (Portion)
Z .00
.01
.02
s Z= 1
.50399
.50798
0.0.50000
:
.97784
.97831
2.0.97725
.9772
mz= 5
0 2.0
.98257
.98300
2.1.98214
Probabilities in body
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-32
Variability of
Completion Time for
Noncritical Paths
Variability of times for activities
on noncritical paths must be
considered when finding the
probability of finishing in a
specified time.
Variation in noncritical activity
may cause change in critical
path.
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-33
Factors to Consider
when Crashing
The amount by which an
activity is crashed is, in fact,
permissible.
Taken together, the shortened
activity durations will enable
one to finish the project by the
due date.
The total cost of crashing is as
small as possible.
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-34
Steps in Project
Crashing
Compute the crash cost per time period.
For crash costs assumed linear over time:
Crash cost per period =
3-36
3-37
Advantages of
PERT/CPM
Especially useful when scheduling
Limitations of
PERT/CPM
Assumes clearly defined,
independent, & stable activities
Specified precedence
relationships
Activity times (PERT) follow
beta distribution
Subjective time estimates
Over-emphasis on critical path
PowerPoint presentation to accompany
Heizer/Render Principles of Operations
Management, 5e, and Operations
Management, 7e
3-39